PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE-K CENTER AZLE INDEPENDENT SCHOOL DISTRICT ADDENDUM NO. 1 June 18, 2020 The following items modify the Plans and Specifications, and shall become a part of the Contract Documents: ITEM NO. 01 GENERAL ITEMS A. See attached pre-bid sign-in sheet. ITEM NO. 02 MEETING MINUTES FROM PRE-BID MEETING A. All documentation and paper work has to go through Beverly Easter with Azle ISD. All bids and other required documents must be submitted in person. Azle will not accept electronic submissions. B. All questions shall be directed to Beverly Easter with Azle ISD and copy Randy Spiker with Azle ISD and Kyle Sparwasser with RWB. C. It is understood that work in the finger classroom wings of the building will be able to occur during normal working hours even when the building is occupied. The kitchen and the remainder of the scope of work in the main building will need to occur after hours, on weekends, or during breaks. D. Azle ISD finds Trane and Lennox as the two acceptable RTU manufacturers. The basis of design is the Lennox Energence unit with two stage cooling and two stage heating where noted WITHOUT HOT GAS REHEAT. E. Controls scope of work is directly with district and it is Entech controls. The contractor does not need to carry for the controls scope but does need to carry coordination, patching of walls, etc. Refer to drawings for delineation of what is in the contractor’s scope of work. F. RWB noted there is a concurrent project that is occurring at the Pre-K Center and there will need to be coordination between the two projects. The contractor for the other project is Buford Thompson. The majority of their scope is in the north finger wing and several restrooms throughout the school. G. The schedule is currently shown for a substantial completion date of Jan. 4 th , 2021. On the bid form, there is a location to note if the contractor believes they can be substantially complete at an earlier date and this will be considered in evaluating the bids. H. The contingency allowance for the project is $30,000. I. There are three test and balance allowances that need to be carried by the contractor. The base bid TAB allowance for this project is $27,750. The alternate bid TAB allowance for this project is $2,250. The contractor is to include in the base bid a TAB allowance for the concurrent project of $5,800. The contractor will only be responsible for paying the TAB contractor for the concurrent project. All TAB comments regarding the concurrent project will be addressed by Buford Thompson and their sub-contractors. J. All commissioning work will be completed by the owner. K. The district approved fire alarm contractor will be Pro-Action. This will be noted in the addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor

Upload: others

Post on 28-Mar-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the

PARTIAL HVAC SYSTEM REPLACEMENT

FOR

AZLE PRE-K CENTER

AZLE INDEPENDENT SCHOOL DISTRICT

ADDENDUM NO. 1

June 18, 2020

The following items modify the Plans and Specifications, and shall become a part of the Contract Documents:

ITEM NO. 01 GENERAL ITEMS

A. See attached pre-bid sign-in sheet.

ITEM NO. 02 MEETING MINUTES FROM PRE-BID MEETING

A. All documentation and paper work has to go through Beverly Easter with Azle ISD. All

bids and other required documents must be submitted in person. Azle will not accept electronic submissions.

B. All questions shall be directed to Beverly Easter with Azle ISD and copy Randy Spiker

with Azle ISD and Kyle Sparwasser with RWB. C. It is understood that work in the finger classroom wings of the building will be able to

occur during normal working hours even when the building is occupied. The kitchen and

the remainder of the scope of work in the main building will need to occur after hours, on

weekends, or during breaks. D. Azle ISD finds Trane and Lennox as the two acceptable RTU manufacturers. The basis of

design is the Lennox Energence unit with two stage cooling and two stage heating where

noted WITHOUT HOT GAS REHEAT. E. Controls scope of work is directly with district and it is Entech controls. The contractor

does not need to carry for the controls scope but does need to carry coordination,

patching of walls, etc. Refer to drawings for delineation of what is in the contractor’s

scope of work. F. RWB noted there is a concurrent project that is occurring at the Pre-K Center and there

will need to be coordination between the two projects. The contractor for the other

project is Buford Thompson. The majority of their scope is in the north finger wing and several restrooms throughout the school.

G. The schedule is currently shown for a substantial completion date of Jan. 4th, 2021. On

the bid form, there is a location to note if the contractor believes they can be substantially complete at an earlier date and this will be considered in evaluating the bids.

H. The contingency allowance for the project is $30,000.

I. There are three test and balance allowances that need to be carried by the contractor. The

base bid TAB allowance for this project is $27,750. The alternate bid TAB allowance for this project is $2,250. The contractor is to include in the base bid a TAB allowance for

the concurrent project of $5,800. The contractor will only be responsible for paying the

TAB contractor for the concurrent project. All TAB comments regarding the concurrent project will be addressed by Buford Thompson and their sub-contractors.

J. All commissioning work will be completed by the owner.

K. The district approved fire alarm contractor will be Pro-Action. This will be noted in the addendum.

L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor

Page 2: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the

information will be updated in the addendum.

M. The total scope includes 30 RTUs (3 of which are alternates), a high wall ductless split system, and one exhaust fan replacement. There will also be several non-freeze roof

hydrants installed as well as miscellaneous ductwork revisions and electrical work to

accommodate the new RTUs. There will be one ceiling replaced in the northwest

classroom wing as noted on the plans. All other ceilings are to be salvaged and re-used. N. Any power or water shut downs need to be coordinated with the district.

O. All bids are due by 10AM on June 30th, 2020. Late bids will not be able to be considered.

ITEM NO. 03 QUESTIONS ASKED DURING PRE-BID MEETING

A. What is the required percentage for payment and performance bonds? a. In the specifications, it states that the payment and performance shall be in the full

amount of the contract. Refer to specification section 006100 and 006200.

B. Does the condensate drain piping need to be copper or PVC?

a. The specifications call for UV protected PVC on the roof and copper piping below the roof.

DRAWINGS:

ITEM NO. 04 DMPE2.02 - DEMOLITION ROOF PLAN – UNIT B – MPE

A. Added note 7 under ‘Notes by Symbol’.

B. Added note 5 under ‘Electrical Demolition Notes by Symbol’.

C. Revised drawing to show the existing exhaust fan over the gym to be removed.

ITEM NO. 05 MPE2.01 - ROOF PLAN – UNIT A – MPE

A. Added note 10 under ‘Notes by Symbol’.

B. Revised note 15 and added note 17 under ‘General MPE Notes’. C. Revised drawing to show the existing exhaust fan having been removed.

ITEM NO. 06 MPE2.02 - ROOF PLAN – UNIT B – MPE

A. Revised note 15 and added note 17 under ‘General MPE Notes’. B. Revised drawing to show which areas are to have DK Haney be the roofing contractor.

ITEM NO. 07 MPE2.03 - ROOF PLAN – UNIT C – MPE

A. Added note 7 under ‘Notes by Symbol’.

B. Revised note 15 and added note 17 under ‘General MPE Notes’.

C. Revised drawing to show which areas are to have DK Haney be the roofing contractor.

ITEM NO. 08 DM1.02 - DEMOLITION FLOOR PLAN – UNIT B – MECHANICAL

A. Added note 18 under ‘Notes by Symbol’. B. Revised the exhaust fan and associated ductwork and grilles in the gym to be removed.

Page 3: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the

ITEM NO. 09 M1.01 - FLOOR PLAN – UNIT A – MECHANICAL

A. Revised existing condensate drain piping to be 1”.

B. Added note 18 under ‘Notes by Symbol’ and located it on the drawing.

ITEM NO. 10 M1.02 - FLOOR PLAN – UNIT B – MECHANICAL

A. Revised drawing to show the exhaust fan and associated ductwork and grilles in the gym

as having been removed.

End Addendum No. 1

Page 4: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 5: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 6: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 7: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 8: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 9: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 10: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 11: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the
Page 12: PARTIAL HVAC SYSTEM REPLACEMENT FOR AZLE PRE ......addendum. L. Azle ISD noted that some of their roofs are under warranty. The roofing contractor information will be updated in the