REVIEW MEETING 2012-2013 PED & EPC-Planning & Production HDO-WORKS 1

Upload: parth-k-patel

Post on 17-Aug-2015

13 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Parth Presentation  2012

REVIEW MEETING2012-2013

PED & EPC-Planning & Production

HDO-WORKS

1

Page 2: Parth Presentation  2012

PLANNING DEPARTMENT (PROP)

Prepared By:

Mr. Parth Patel

(Engineer)

2

Page 3: Parth Presentation  2012

ROLES & RESPONSIBILITIES

• Monitoring and controlling all the activities from receiving the P.O copy to

material inward to the completion of final product and dispatch

• Preparing the activity sheet for the jobs.& Arrange Kick off meeting for all

department within 2days after receipt of the order.

• Indenting of the material ( Raw material, BFC, castings & hardware items)

required for a job.(Through Developed Excel software)

• Deciding outsourced jobs in short duration after kick off meeting.

• Release of Plate Cutting & Machining sketches to the Production dept & marking

dept and issuing the material to them.

3

Page 4: Parth Presentation  2012

ROLES & RESPONSIBILITIES

• Identifying the critical items and following them directly with the vendors, if

possible visits the vendors shop.

• Painting specification along with area to be provided to contractor after receipt.

• Packing slip preparation for the Transport activity.

• PROJECT HANDLED: OPAL, Heavy Water Board, Usher Agro, NMDC, NALCO, UCIL,

OMPL, ACC LTD, DCIPS, ISPRL, BPCL , HMEL, JAYSHREE CHEMICAL , DAE,

I.S.S.I,ADITYA BIRLA, IOCL,VEDANTA.

4

Page 5: Parth Presentation  2012

Achievements:

• In Place Of New Forgings ,By Using Non Movable Forgings in OMPL Project

From Forging Yard Save Around 1,60,000 Rs. By reducing Forgings

Inventory.

Apr 18, 2023 5

Page 6: Parth Presentation  2012

Projected Summary for Aug-12 to Nov-12

Sr. No Month No Of Jobs WT in Ton

1 Aug 21 55.5

2 Sep 28 91.8

3 Oct 18 57.4

4 Nov 39 107

Grand Total 106 311.7

6

Page 7: Parth Presentation  2012

Production Plan For Aug-2012Sr. No. Job No. Client CDD ADD QTY. Rs. (Lacs) WT In

Ton REMARKS

1 15116-B HWB Later On Aug 12 1 82.40 17Final inspection offer date planned on 31.08.2012 support required to get internal 1/2" Sparger Pipe & Added 16 nos forging Required.remaining all completed.

2 15121 HWB Later On Aug 12 2 0.00 1 Top dish & btm. dish end connection welding completed. Inspection offer by 30 th Aug. RT Film to be reviewed by HWB representative.

3 15122 HWB Later On Aug 12 2 0.00 1 Top dish & btm. dish end connection welding completed. Inspection offer by 30 th Aug. RT Film to be reviewed by HWB representative.

4 15128 HWB Later On Aug 12 1 6.00 1.5 Fab. Completed .final dimension inspection to be witness by TPI on 21.08

5 15129 HWB Later On Aug 12 1 Awaiting For Dispatch Release note.

6 15130 HWB Later On Aug 12 1 8.12 2.5 Fab. Completed .final dimension inspection to be witness by TPI on 22.08

7 15137 HWB Later On Aug 12 1 9.21 3 Fab. Completed .final dimension inspection to be witness by TPI on 24.08

8 15179 OMPL 31/08/11 Aug 12 1 12.00 7.5 Ready Duly Rubber Lined & To be received from RL(Shreeram Rub-tech).

9 15182 OMPL 31/08/11 Aug 12 1 12.00 4 Ready Duly Rubber Lined & To be received from RL(Shreeram Rub-tech).

10 15229 UCIL 11/01/12 Aug 12 2 2.00 1.5 Ready For dispatch

11 15264 OMPL 31/08/11 Aug 12 1 11.00 5 All Fab. Work Completed & same under Assembly. Only coupling under cutting.

12 15265 OMPL 31/08/11 Aug 12 1 11.00 5 All Fab. Work Completed & same under Assembly. Only coupling under cutting.

13 15284 ACC Ltd Later On Aug 12 2 5.00 5 Shell, dish & Nozzle setup completed. Leg support under progress.

14 15343 DCIPS 30/03/12 Aug 12 1 1.00 0.7 All Fab. Work Completed. Only Float valve to be Receipt from D.K.Engg.

15 15344 DCIPS 30/03/12 Aug 12 1 1.00 0.5 All Fab. Work Completed. Only Float valve to be Receipt from D.K.Engg.

16 15358 NALCO Urgent Aug 12 2 0.20 0.3 Under painting.Grand Total 21 160.93 55.5

Page 8: Parth Presentation  2012

Production Plann For Sep-2012Sr. No. Job No. Client CDD ADD QTY. Rs.

(Lacs)WT In Ton REMARKS

1 15116-A HWB Later On Sep 12 1 82.40 17D'end nozzles setup completed. nozzle under welding . Shell to bottom D'end completed. RT completed. Skirt shell Rolled. Internal Sparger Pipe & 16 nos forging material Required

2 15116-C HWB Later On Sep 12 1 82.40 17top D'end nozzle opening comp. Shell to bottom D'end welding completed. Skirt shell under progress. internal Sparger Pipe & 17 nos forging material Required

3 15117 HWB Later On Sep 12 1 19.00 3 Shell to bottom D'end completed. top dish nozzle connection setup under progress. awaiting for sparger pipe(1/2" sch 40) & Support leg pipe (6" sch 40).

4 15118 HWB Later On Sep 12 1 15.69 3 All shell are ready . Remaining under fabrication.2 nos Forging Yet to be rec.

5 15123-A HWB Later On Sep 12 1 0.00 1.5 Shell c/s completed. nozzle setup under progress. Awaiting for sparger pipe and Ammended forging.

6 15123-B HWB Later On Sep 12 1 0.00 1.5 Shell c/s completed. nozzle setup under progress. Awaiting for sparger pipe and Amended forging.

7 15125 HWB Later On Sep 12 1 19.47 6 Shell to dish & C/S welding completed. Nozzle setup on shell completed. Saddle welding completed. 13 Nos Forging & 2" sparger pipe yet to be rec.

8 15126 HWB Later On Sep 12 1 19.47 2 Shell to one side D'end completed. Shell C/S RT under progress. Nozzle setup under progress. Saddle supp. Completed. 7 Nos Forging yet to be Rec.

9 15127 HWB Later On Sep 12 1 12.64 2 D'end under RT. Shell RT clear. C/S setup completed. Nozzle setup to be start.

10 15135 HWB Later On Sep 12 1 0.00 15 SHELL C/S under progress. Dish under RT .15 Nos Forging Yet to be Rec.

11 15284 ACC LTD. Later On Sep 12 2 5.00 5Nozzle set up under progress.

12 15338 NALCO Later On Sep 12 1 25.00 1.5 Nozzle set up & leg support under progress.13 15339 NALCO Later On Sep 12 1 25.00 1.5 Under RT. Nozzle to be Setup.14 15348 NMDC Later On Sep 12 2 4.00 1 Under final internal inspection. To be send for Rubber-lining.15 15349 NMDC Later On Sep 12 2 4.00 1 Under final internal inspection. To be send for Rubber-lining.16 15350 NMDC Later On Sep 12 2 4.00 0.8 Under final internal inspection. To be send for Rubber-lining.

17 15388 OPAL Later On Sep 12 2 24.00 3 GA Drg & BM Rec On 28.05.2012 Which hold is removed on 06.08.12. Shell, top and bottom under marking cutting. Nozzle orientation under hold.

18 15389 OPAL Later On Sep 12 2 24.00 4 GA Drg & BM Rec On 20.06.2012.Shell,top, bottom, baffles under marking cutting. Nozzle orientation under hold.

19 15390 OPAL Later On Sep 12 2 24.00 5 GA Drg & BM Rec On 28.05.2012.Shell,top, bottom, baffles under marking cutting awaiting for TPI.Nozzle orientation under hold.

20 15393 OPAL Later On Sep 12 2 13.00 1 GA Drg & BM Rec On 28.05.2012.Shell,top, bottom, baffles under marking cutting. Nozzle orientation under hold.

Grand Total 28 403.06 91.8

Page 9: Parth Presentation  2012

Production plan For Oct-2012Sr. No. Job No. Client CDD ADD QTY. Rs. (Lacs) WT

(MT) REMARKS

1 15124-A HWB Later On Oct 12 1 38.93 7 A.Shell C/S COMPLETED. Dish under RT.44 Nos Forging & Sparger pipe (2" sch 40) yet to be Rec.

2 15124-B HWB Later On Oct 12 1 38.93 7 B.Shell C/S COMPLETED. Dish under RT.44 Nos Forging & Sparger pipe (2" sch 40) yet to be Rec.

3 15124-C HWB Later On Oct 12 1 38.93 7 C. Shell C/S to be start. Dish under RT.44 Nos Forging & Sparger pipe (2" sch 40) yet to be Rec.

4 15136 HWB Later On Oct 12 1 9.82 1 one side D'end setup completed.code-1 Drawign to be recd.

5 15345 NMDC Later On OCT 12 1 4.00 1.2 Under Engineering.

6 15346 NMDC Later On OCT 12 1 4.00 2.5 Under Engineering.

7 15347 NMDC Later On OCT 12 1 4.00 2.8 Under Engineering.

8 15386 OPAL Later On OCT 12 2 106.40 10 Design Pending

9 15387 OPAL Later On Oct 12 2 20.00 5GA Drg & BM Rec. On 28.05.2012. Shell ,top and bottom plate under

Marking Cutting Process with internal quality approval. Nozzle orientation under hold.

10 15391 OPAL Later On OCT 12 2 12.00 4 Design Pending

11 15392 OPAL Later On Oct 12 1 3.00 0.9 GA Drg & BM Rec On 20.06.2012.Shell,top, bottom, baffles under marking cutting awaiting for TPI.Nozzle orientation under hold.

12 15394 OPAL Later On OCT 12 2 10.00 5 Design Pending

13 15395 OPAL Later On OCT 12 2 20.00 4 Design Pending

Grand Total 18 310.01 57.4

Page 10: Parth Presentation  2012

Production plan For Nov-2012Sr. No. Job No. Client CDD ADD QTY. Rs.

(Lacs)WT

(MT) REMARKS

1 15119 HWB Later On Nov 12 1 9.42 5 No detail available from Engg.2 15120 HWB Later On Nov 12 2 146.94 20 No detail available from Engg.3 15335 NMDC Later On NOV 12 2 10.00 7 Under Engineering.

4 15396 OPAL Later On NOV 12 3 75.00 5 Only d'end drg released on 10.07.12. 16 mm Plate For same is not available for further procedure.

5 15397 OPAL Later On NOV 12 2 50.00 5 Only d'end drg released on 11.07.12. 18 mm Plate For same is not available for further procedure.

6 15398 OPAL Later On NOV 12 2 50.00 5Drg rec on 19.07.12. 16 mm Plate for Shell,Top and Bottom Not available.

Orientation under Hold. Outlet Header under hold. Pipe,Forging and Sight Glass To be Procure.

7 15399 OPAL Later On NOV 12 2 60.00 10 Drg rec on 20.07.12. 16 mm Plate for Shell,Top and Bottom Not available. Orientation under Hold. Pipe,Forging and Sight Glass To be Procure.

8 15400 OPAL Later On NOV 12 2 60.00 10 Only d'end drg released on 10.07.12. 16 mm Plate For same is not available for further procedure.

9 15401 OPAL Later On NOV 12 2 24.00 10 Design Pending 10 15402 OPAL Later On NOV 12 2 20.00 10 Design Pending 11 15403 OPAL Later On NOV 12 1 10.00 4 Design Pending 12 15425 OPAL Later On NOV 12 1 7.00 2 Design Pending 13 15415 ISPRL Later On NOV 12 3 8.00 4 Design Pending 14 15416 ISPRL Later On NOV 12 3 8.00 4 Design Pending 15 15417 ISPRL Later On NOV 12 1 2.00 1 Design Pending 16 15418 ISPRL Later On NOV 12 2 2.00 1 Design Pending 17 15419 ISPRL Later On NOV 12 2 2.00 1 Design Pending 18 15420 ISPRL Later On NOV 12 2 2.00 1 Design Pending 19 15421 ISPRL Later On NOV 12 2 2.00 1 Design Pending 20 15422 ISPRL Later On NOV 12 2 2.00 1 Design Pending

Grand Total 39 550.36 107