page i. introduction ii. liability - the options available iii. whom do you...
TRANSCRIPT
I N D E X
VI. CONCLUSIONS
V. PRACTICAL MANAGEMENT OF ISSUES
IV. TYPES OF CLAIMS
II. LIABILITY - THE OPTIONS AVAILABLE
PAGE
1
4
8in 12
18
19
21
2124252627
27
292929303233
35
384348
53
Delay ClaimsExtended Duration CostsImpact CostsAcceleration CostsLost Opportunity
The1.2.3.4.
A.
A. Concurrent Liability in Contract and TortB. Design Professional's Liability to Other Parties
NegligenceC. Conclusions to be Drawn
B. Proof of the Delay Claim
C. Common Claims to be Considered1. By the Owner
(a) In Contract(b) In Tort
2. By the Consultants3. By the Contractor and Subcontractor
A. Steps to Take at .the OutsetB. Production of Documents and DiscoveryC. The Trial
III. WHOM DO YOU SUE?
I. INTRODUCTION
Appendix A - Selected Reading List
Appendix B - The Role of the Consultant as Part of theClaim Team, Stephen V. Revay
Appendix C - Quantifying the Claim - The Accountant's RoleJ.L. Seigel
)
CONSTRUCTION LITIGATION
LEGAL ISSUES AND CASE MANAGEMENT
I. INTRODUCTION
The management of construction litigation is as challenging a task
as the civil litigation lawyer is likely to meet. The underlying
legal principles are uncertain and developing, the parties and
types of claims mUltiple, the factual background and documents
often overwhelming, the sums involved significant and the evidence
often of a very technical or scientific nature. As with any
lawsuit, the key to successful management is proper organization.
Because the demands of construction litigation may be more
intense, deficiencies in planning and systems may become more
obvious and hurt your case more than in other less complex
proceedings.
The theme for my paper is this - The only way to effectively
handle the issues arid evidence in construction litigation or other
complex trials is to have in place systems which permit you to
deal with the legal, factual and evidentiary issues in
identifiable and controlled segments.
Unfortunately, the word "systems" has, in our developing computer
reliant society, the connotation of a rigid, precise, step by step
process that must be followed. The management of lawsuits has
- 2 -
always been and· will remain more suited to individual, flexible
and intuitive systems than such rigid systems and yet some
system or planned approach is essential. In this paper I attempt
to outline my approach and system. There is nothing unique about
it; it largely consists of common sense and the practices of
others that I have borrowed because they suited me or the demands
of cases I was involved in at the time. To speak of it as a
system is somewhat inaccurate since it is more a collection of
suggestions as to possible approaches which I don't necessarily
follow myself in any specific case.
Select what you find appropriate and discard the rest except but
for my overriding theme that some systematic approach and analysis
is essential for proper case management.
The paper barely scratches the surface of the topics which I was
asked to address and I have chosen to eliminate entirely topics
such as quantification of damages because an overview seemed
inappropriate. When I· introduce a topic in this paper the
discussion should not be treated as anything more than an
overview. My purpose is to assist the reader to identify topics
that should be considered further. Because of the paucity of
materials on construction law in Canada I have attached, as
Appendix "A", a selected reading listing which will permit the
)
- 3 -
reader to embark upon a more detailed inquiry into some of the
topics introduced in this paper.
I extend my thanks to stephen Revay and John Seigel for their
permission to use their papers on the roles of the claims
consultant and the accountant in construction litigation. The
concepts discussed in these papers are central to the "claim team"
approach.
- 4
II. LIABILITY - THE OPTIONS AVAILABLE
The complexity of construction litigation is as much a consequence
of the optional approaches to liability as it is of the number of
parties involved. Indeed, the channels of potential liability
form part of the reason why Plaintiffs typically sue a number of
parties who in turn, counter-claim, c'ross-claim and third-party
claim.
As in any litigation, a sound conceptual underpinning is essential
to the proper management of the case. Trite as it may seem, my
message is that case management decisions are really a function of
the quality of your initial conceptual analysis of the case.
Accordingly, I start this paper with a brief overview of
fundamental concepts of liability in construction law.
Unfortunately, there is a distinct shortage of useful texts and
other written material in Canadian legal literature on
construction law. I have attempted to compile a list of reports,
articles and other published materials relevant to the issues I
will address. It is attached as Apendix "A".
Construction litigation is unique in that within one lawsuit you
may address concepts of liability in:
(i) contract,
(ii) quantum meruit, and,
- 5 -
) (iii) tort, in the sUbcategories of negligence, negligent
misrepresentation and economic loss.
The voluminous and detailed contracts that confront counsel in a
construction dispute can overwhelm and distract from consideration
of the quantum meruit and tort avenues of liability.
The first and most essential analysis is, of course, within in the
contractual mode. A detailed review of the contract to identify
all possible breaches or defences to alleged breaches must be
carried out. In this respect construction litigation is no
different than other contractual claims. I do, however, suggest
that in your contractual analysis you also be sure to flag any
waivers directed at relieving parties from liability in either
quantum meruit or tort. It is well established law that parties
may contractually dispense with liability that would otherwise
arise in law.
While perhaps not jurisprudentially correct, my simplistic concept
of quantum meruit is that it was developed with the justification
by the courts that their equitable jurisdiction permitted them to
provide fair compensation for work done where the contract did not
provide for it. This may seem an unjustifiable departure from the
language of the contract in an age when the Courts repeatedly
state that their role is to interpret and apply the contract and
not to rewrite it; but it does continue to exist and is
occasionally invoked. Quantum meruit has been utilized by the)
(iii)
- 6 -
Courts to justify payments to contractors where:
(i) there is no express or implied contract covering the
terms of payment for specific work required to be done,
(ii) where the contractor performed work for a owner in
respect of which there never was an agreement including
cases where the underlining agreement was found to be
void, and,
where the work has been performed even though
circumstances have changed so fundamentally that the
original payment provisions mean nothing or where the
contract has been abandoned.
Generally, a person will be liable to pay on a quantum meruit
basis where there is no contract provision applicable but the work
has been done at the person's request or that person has accepted
the benefit of the work; unless it was clear at the time the work
was done that the parties understood that the person doing the
work did not expect payment for it. As a practical matter,
quantum meruit is not- often resorted to and it will most
frequently arise in circumstances where the need for some
essential, but previously uncontemplated, work arises. Then, if
the contract does not have provisions which accommodate payment or
if the contract has for some reason come to an end the court may
invoke quantum meruit.
Quantum meruit is very narrowly circumscribed and the trend within
)
7 -
construction contracts is to place precise limitations upon
liability. Therefore, the most fertile area for liability
extension lies in tort. Decisions in construction law cases have
been at the forefront of establishing the concept that there can
be concurrent liability in both contract and tort. The craft of
the contractual draftsman will no doubt be brought to bear on the
issue of concurrent liability in contract and tort; but at least
until the forms of contract become explicit on the point, we can
expect to see cases being advanced in both contract and tort.
Concurrent liability opens the option to claim, for example, that
the contractor has a duty of care to the owner and liability in
tort to ensure that the design of the building was appropriate or
to subcontractors to ensure that they are not delayed. It is only
within the tort concepts of duty of care that contractors can
justify claims against design consultants.
- 8 -
A. CONCURRENT LIABILITY IN CONTRACT AND TORT
Initial attempts to found claims in both contract and tort focused
on owner claims against the design professionals. Historically,
actions against professionals were deemed to be actions brought in
contract whether or not a formal agreement existed. For example,
actions against notaries or solicitors are held to be contractual
in nature. See Schwebel v. Telekes (1967) 1 O.R. 541. The
assault on this rule had, as its jurisprudential underpinning, the
argument ,that professional status is a holding out or
representation to the public that the professional in question is
possessed of certain expertise that the pUblic can rely upon. In
the construction industry design professionals hold themselves out
as being solely and uniquely qualified to design structures. The
pUblic and the participants in the industry rely upon the fact
that such design can only be done by the professionals and assume
that the professionals can be relied upon to do a proper job. As
a practical matter,· contractors have no alternative but to rely
upon the design professionals notwithstanding the typical absence
of any contractual relationship.
The concept that where there is a breach of a duty of care which
results in damage to property or person, losses are recoverable
was thought to be limited, in the sphere of commercial activity by
the duty of care issue. In other words, if there was no contract
- 9 -
) to establish a relationship it was concluded no duty was
intended. The famous decision of Hedley Byrne & Co. v. Heller &
Partners Ltd. (1964) A.C. 465, is the origin for the principles
that duties of care can arise in commercial settings absent a
contract by a representation or holding out and that entitlement
to recovery can extend beyond damage to property and person to
recovery for pure economic loss. The Supreme Court of Canada in
The Pas v. Porky Packers Ltd. (1977) 1 S.C.R. 51, reiterated the
principle from Hedley Byrnes as follows:
"The House of Lords has thus expressed the opinion that if in
the ordinary course of business including professional affairs
a person seeks advice or information from another who is not
under any contractual or fiduciary obligation to give it, in
circumstances in which a reasonable man so asked would know
that he was being trusted or that his skill or jUdgement was
being relied upon, and such person then chooses to give the
requested advice or information without clearly disclaiming
any responsibility for it, then he accepts a legal duty to
exercise such care as the circumstances require in making his
reply; for a failure to exercise care that care, an action for
negligence will lie and damage for loss that results."
It is to be noted that The Supreme Court of Canada in The Pas v.
Porky Packers did not limit the duty to the professional
relationship but extended it to relationships arising in the
ordinary course of business. This decision was preceeded by the
Ontario Court of Appeal decisions in Dominion Chain Co. v. Eastern
Construction Co. (1976) 12 O.R.(2d) 201, where Mr. Justice Jessop
stated:
)"I conclude that both Dominion and Dabous the defendant
engineers and architects were tortfeasers· and incurred
- 10 -
liabilities as such to the respective plaintiffs whether or
not they also incurred contractual liabilities for breach of
contractual obligations to take care solely to be implied from
their relation to their clients as members of professions
possessing skills."
Mr. Justice Jessop extended the relationship beyond the
professionals and in respect of the builders stated,
"In any event I think that a contractor or builder who is
negligent in the performance of the contract to build is
liable in tort under the principle of M'Alister v. stevenson
(1932) A.C. 562, to any person SUffering resultant injury to
person or property (without deciding whether he is also liable
for financial loss other than consequential to such injury.)"
The ontario Court of Appeal has reaffirmed its conclusion that
concurrent actions in tort and contract are applicable against
both contractors and design professionals in Consumer Glass Co. v.
Foundation Company of Canada 13 C.L.R. 149. In this case it was
observed that since an action in negligence had not been precluded
by a contract between the parties that the claim could equally be
asserted in both contract and tort. Notwithstanding the principle
that an action may be founded both in contract and tort, the
contract remains of central importance because:
(i) Normally the contract will specifically state the scope
of the duty which has been assumed;
(ii) In the absence of any definition of the scope of the duty
the contract may nonetheless contain provisions which
limit duties of care that might otherwise be implied· by
the law or may restrict the period af time within which
)
- 11 -
the contract may nonetheless contain provisions which
limit duties of care that might otherwise be implied by
the law or may restrict the period of time within which
claims may be brought. Futher, the contract may
specifically address whether the contracting parties can
have resort to negligence principles.
,The fact that the law permits actions in both contract and tort is
of much greater significance to owner actions against the design
professionals than for actions against contractors. The very
essence of being a professional is a holding out of oneself to the
. public that you are possessed of all the requisite skills to
complete the task appropriately. Typically, contracts relating to
the services of professionals do not define standards of
performance because those standards are set by the profession.
Within the construction industry, however, standards of
workmanship and material are not sufficiently defined by custom or
other formula. As a consequence, the contractual terms will play
a greater role and tort analysis will not be as easy to adopt and
apply. Quality is more often than not a function of price, there
are not minimum standards as in design and as a consequence the
contracts frequently specify performance criteria.
While concurrent liability of the design professional to the owner
in tort is helpful; the corallary of the Hedley Byrne's principle
that a design professional owes a duty of care to other
participants in the project - is even more siqnificant.
- 12 -
B. DESIGN PROFESSIONAL'S LIABILITY TO OTHER PARTIES IN NEGLIGENCE
C.E.D. (Western) on Building Contracts, paragraph 131, states with
reference to the design professional that "he is not liable to
third-parties such as contractors or sub-contractors for any
economic loss they suffer as a result of design deficiencies or
inadequate supervision." C. E. D. (Western) does not indicate the
date to which they believe this statement accurately reflects the
law. In my opinion, it does not accurately reflect the present
state of the law.
The most significance aspect of this analysis is economic loss
since typically a third party's claim against a design
professional is not for loss sustained as a result of damage to
property or person but rather is based upon additional costs which
have been incurred in the performance of the work. Such costs may
be the result of:
(i) defects or omissions in the plans and specifications
which a contractor relied upon in making his tender, or
(ii) the design professional having specified particular work
or having permitted work for which he gave no specific
instructions to continue and then sUbsequently rej ecting
it.
(iii) failing to inspect work as it is progressing and later
rejecting.
13 -
As a result of relying upon the design professional's plans,
specifications, instructions or approvals (express or implied) the
contractor may find himself in a situation of having to utilize
different equipment, materials or methods resulting in increased
expenditures of time and money. Occurences of this nature can all
be massaged to fit within the concept of economic loss resulting
from a reliance and thereby fall within the principles set forth
in Hedley Byrne's and The Pas v. Porky Packers.
This concept initially found some resistance in our law. Hudson's
Building and Engineering Contracts, Tenth Edition states the
general principles applicable as between contractor and an owner
in respect of errors in design information as follows:
"An employer (owner) who uses a professional advisor
(designer) does not warrant that completion according to his
advisors plans or design is practicable and even in the
absence of express provisions for the protection of the works,
the risk in regards to the safety of the work remains with the
contractor until they have been reoccupied by the employer and
accordingly a contractor who (as is almost invariably the
case) expressly or impliedly undertakes to complete the work
or project according to the contract drawings and designs
thereby impliedly warrants that he can do so and if he cannot
he will be liable in damages. In consequence, any additional
work necessary to achieve completion must be carried out by
him at his own expense if he is to discharge his liability
under the contract."
- 14 -
An extrapolation of this statement seems to leave little room for
the contractor to make the argument that there was any
representation or holding out to the contractor that the work can
be completed according to the design consultants plans or
specifications. However, in the Supreme Court of Canada's
decision in The Pas v. Porky Packers and in its previous decision
in Rivtow Marine Ltd. v. Washington Iron Works and Walkem
Machinery and Equipment Ltd. (1974) S.C.R. 1189, the door was
opened. The following decisions have confirmed the availability
of a tort claim by the contractor or sub-contractor against design
consultants. They permit recovery for economic loss (e. g. delay
claims or impact costs) which may not be recoverable by the
contractors from the owner:
(i) Trident Construction Ltd. v. W.L. Wardrop and Associates
Ltd. (1979) 6 W.W.R. 481. In this case the information
contained in the design documents was incomplete or in
error as regards soils information and certain
specifications relating to the design of a water stop
were not apt. As a result of this information the
contractor chose a particular method which proved to be
unfeasable. The design consultant raised the usual
defence that there was no warranty that his plans would
be free from defects or that they would be workable. Mr.
Justice Pratt of the Manitoba Court of Appeal concluded
that the contract between the owner and the general
contractor imposed upon the design consultants the
- 15
responsibility to provide the contractor with such advice
as was within the consultants expertise and might be
required to assist the contractor in the proper
performance of the work. Mr. Justice Wilson adopted the
following submission of counsel for Trident namely:
"In the building trade in Manitoba not only does the
owner rely upon a consulting engineer to prepare
competent and reliable structural drawings for the
erection of a building in accordance with those
drawings, but also the contractors who are called
upon to tender for those buildings on the basis of
such drawings and specifications must also rely upon
the accuracy and competency of these drawings. The
normal practice is for the engineers to take months
to research and prepare the plans and specifications
involved in a project for which they are paid
substantial sums and to give the contractors only a
few weeks to prepare and submit competitive bids for
the construction of the building based upon such
plans and specifications. In this time frame, it is
impractical for any building contractor in Winnipeg
to check independently the structural design of the
buildings involved in the plans and specifications
prior to bidding."
He then adopted this statement from Mr. Justice de
Grandpre in Davie Shipbuilding Ltd. v. Cargill Grain Co.
Ltd. :
"It must not be forgotten that the duty of the
engineer and the contractor are different, the
former being a specialist to whom the design and
preparation of plans and specifications are normally
- 16 -
entrusted and the second merely carrying out the
work. If the second is required to do the checking,
which the jUdgment appealed from would imposed upon
him, the precense of the engineer is no longer
useful, for all practical purposes."
(ii) Brown & Huston Ltd. v. The Corporation of the City of
York (1983) 5 C.L.R. 240. This case involved a
(iii)
contractor relying upon soils reports and other tender
documents resulting in an action against the engineers
which alleged that the owner was vicariously responsible
for the faults of its consultant. The Court held, "the
engineers must have known that tenderers would rely upon
the tender package; particularly where the contract
documents did not require the contractor to satisfy
itself about the sub-surface conditions" and later "I
have come to the conclusion that there was a reasonable
reliance on the lack of information concerning a water
condition so as to bring the case within the principles
enunciated in Hedley Byrne & Co. v. Heller & Partners
Ltd."
Cardinal Construction Ltd. v. The City of Brockville
(1984) 4 C.L.R. 149. In this case the contractor relied
upon tender documents prepared by design consultants
which proved not to be correct. Mr. Justice Henry
concluded "in preparing the drawings and specifications
for tender the engineer has a duty to provide information
17 -
that is complete and correct; existing utilities to be
encountered must not be incorrectly described, e.g. a
concrete duct must not be described as cable or conduit"
and later "These findings as to the professional
obligations of the engineer are, in my opinion supported
by, or consistent with, the judicial decisions which I
have referred to above - Hedley Byrne, Haig v. Bamford
and Trident Construction."
In light of the above I believe it can be safely said that there
is a clear avenue for contractors to make claims against design
professionals on the basis of negligent statements contained in
plans and specifications, tender information or background
documents on which the contractors have relied. Whether the
responsibility for this can be passed back to the owner on the
basis of vicariously liability will in large part depend upon the
provisions of the contract with the owner. Presumably, design
consultants are going to react to these decisions by attempting to
insert disclaimers in their documentation; however, this creates
practical problems in the real world. Owners will not feel
comfortable with design consultants insisting upon broad based and
all encompassing disclaimers and it appears probable that there
will be experimentation with various watered down versions.
- 18 -
C. CONCLUSIONS TO BE DRAWN
It is obvious that in every case the potential of framing a claim,
counter-claim or cross-claim in each of contract, quantum meruit
and tort must be analyzed. The potential for actions in either
contract or tort extends right down to the supplier and
sub-contractor levels. All options to avoid the strictures of
privity of contract and the waivers and disclaimers contained in
contracts must be considered. This includes considering product
liability claims against suppliers. No claim or defence can be
properly structured without having analyzed all basis of liability.
\~,
.~
\
o{.J
;'YOwnerQ7!'.~ ~.~: '1/ ".
o{.J : C1 \ '.-y. §..1/ \',
I! :;::;? \'.~. q ,
cS' Cj \ ....:u,. >, ~'.,
Contr~ctor ~ co~su~tant':''\ 1\, '-. ~ ~.. , I \ "oM \',
.' I .Q \.q.:: :IX"~ \Q'\<;\>S; .: I \ H '\~ ~('(. / \; ('( .~~ ~ \~ ~,- ~ \ g \<;\> '~
SUbcontractor~\ '"d ~('( '.~~1\ 8 \ '.~.
/ \ ~ \ .~('(
/ \ " "/ \ \. '.
/ \ :\ .."" ~ ~.Supplier Supplier Subconsultant
- 19 -
III. WHOM DO YOU SUE?
Obviously, the question of whom you sue must be addressed not only
by the plaintiff but also by all other parties in the context of
counterclaims, cross-claims and third party claims. The simple
answer to the question of "whom you sue" is that you sue anyone
who has an economically significant potential liability under any
of the avenues of contract, quantum meruit or tort.
The initial answer to the question is easy but the rider that
directs you into an inquiry of economically significant potential
liability is not. There is, of course, the additional question of
whether there is any economically significant prospect of recovery
if liability complicates matters. Unfortunately, the nature of
the construction industry is such that the party with clear
liability at the outset of litigation may subsequently become or
prove to be insolvent. This "fact" of life reinforces the need to
determine whether arty of. the actors can be made responsible under
any secondary theory of liability. In all of this you must not
forget to address, at the outset, possible direct claims against
bonding companies and/or insurers.
Typically, a bonding company will not pay on a bond if the party
bonded claims not to be in default or to have no liability. In
such instances you will wish to add the bonding company as a party
20
to the action to ensure that, as the litigation drags along, no
limitation periods are missed.
If a party defendant is insolvent you may find that the insurer
does not defend but will lie low in the hope of avoiding having a
claim made on the policy. In such cases you must consider the
option of an appropriate application under The Saskatchewan
Insurance Act· to ensure that the insurer is forced to pay any
proceeds under its policy into court for the benefit of the
jUdgement obtained.
The professional that is the easiest to overlook in the process is
the lawyer. Since lawyers may well have been involved at any
stage from contracting forward the possibility of a negligence
claim against the lawyer involved always exists. Do not fail to
consider this possibility.
Of greater significance than the question of whom to sue is the
question of the nature of or types of claims that can be
advanced. There are many types of claims that are unique to
construction litigation. Once you have identified all possible
parties, the claim should be cast in the broadest formulation
possible.
- 21 -
IV. TYPES OF CLAIM
In this section I will attempt to do little more than to list some
of the various types of claims that may be advanced. This listing
is intended to be no more than a partial checklist and no
discussion of the various types of claims is attempted. An
analysis of the practical considerations behind some of these
categories of claims (for example the contractors delay claim)
could be the sUbject of an entire seminar in itself. As mentioned
in section III above; a consideration of each of these potential
categories of claims should be made, not only from the perspective
.of the plaintiff, but also from the perspective of other parties
for possible counterclaims, cross-claims or third-party claims.
Before my list of common types of claims, I will provide a brief
overview of the delay claim.
A. THE DELAY CLAIM
A significant portion of construction litigation deals not with
straight forward items such as non-payment, inadequate
construction design or who is responsible for what costs under a
proper interpretation of the contract; but rather relates to
claims of economic loss resulting from delay. An owner may suffer
significant financial loss from the failure of the consultants and
contractors to deliver the project in a timely manner. The
- 22 -
quantification of damages in such cases is basically a matter of
proving the increased financing and administrative costs resulting
from the extended duration of the contract and the economic loss
resulting to the owner from the inability to utilize the asset on
the scheduled delivery date. The consequences of delay to the
contractor and the proof of damages for such delays is a more
complicated matter.
Most construction projects and the contracts relating thereto
contemplate a particular scheduling of construction and a
specified completion date. The scheduling itself is an essential
part of the contract and the particular schedule used is vital to
evaluate any delay claim. The simplest, most basic schedule, is a
bar graph which demonstrates graphically for each element of the
building (eg. concrete work, electrical, plumbing) the duration of
each activity and the activities that can be concurrent. It
schedules the flow or sequence of work; however, it does not and
cannot show the inter-relationship between activities. On a well
administered job the bar graph will be amended from time to time
as the circumstances dictate which may assist in proving a delay
claim.
A more sophisticated form of scheduling is the critical Path
Method (C.P.M.) which incorporates the inter-relationship of
activities and records what critical elements must be completed
before another stage of construction can be commenced. By way of
)
- 23 -
simplistic example electrical wiring must be completed before
drywalling can occur.
Any delay claim will involve a comparison of initial job
scheduling with the actual performance on the job site. Essential
to the prosecution or defence of any delay claim will be an
understanding of the project scheduling and how delays in one area
impact other areas. This understanding can only be obtained from
people with experience in this aspect of the industry. This is an
area where you would typically utilize a claims consultant. In
this portion of the paper I will simply outline some basic
concepts that should be considered.
Some delays are of a nature which do not materially disrupt the
sequencing of other work or a particular contractors utilization
of his work forces. Such delays will usually give the contractor
a right to claim extensions of time for completion but not
necessarily a claim for compensation. If the delays are justified
(in the sense of being caused by others or by forces not within
his control), the contractor will be entitled to an extension of
his contract completion period and will be relieved for that
period of time from any damages the owner suffered as a result.
On the other hand, the delay may permit the contractor to claim
both a time extension and compensation. The courts will have to
look to the cause of the delay and the express and implied
provisions of the contract to determine the consequences of any
particular delay.
- 24 -
A delay can have the following costs consequences for a contractor
namely:
(i)
(ii)
( iii)
(iv)
delay or extended duration costs,
impact or efficiency costs,
acceleration costs, and.
lost opportunity to earn profit.
1. Extended Duration Costs
Extended duration costs are those costs which flow from having to
maintain an organization and employees in place for an extended
period of time. In the first instance, these are cost orientated
items and do not include production orientated costs. Examples of
such costs are:
(i)
(ii)
(iii)
(iv)
(v)
administration and supervision costs,
equipment, rental and maintenance costs,
temporary office and facilities costs,
service and utility costs such as light, power, heat,
water, and
insurance bonds and permits
In addition to these overhead costs there are projects specific
costs which arise from the delay including:
( i) increased labour costs - the contract may extend into a
subsequent collective bargaining periods where the labour
rates are higher,
- 25 -
(ii) increased material cost - material costs have a tendancy
of increasing,
(iii) increased cost of winter work including hoarding, heat
and the like, and
(iv) the cost of deterioration to completed work left exposed.
The contractor will of course want to recover all extended
.duration costs from the owner where the option is open to him
under his contract. Where it is not, consider whether such delay
costs can be sought from design consultants or other contractors
on the basis of their fault.
2. Impact Costs
These are costs incurred by a contractor due to loss of efficiency
arising from delay whether it flow from performing a work out of
sequence, at an accelerated pace or for other reasons. Such costs
are the difference between the actual cost of performing the
portion of the project in question and the cost that would have
been incurred for the same portion of the work if it had not been
impacted by the cause alleged. To calculate impact cost you are
essentially trying to figure out the differential between what was
actually spent as opposed to what this contractor, on this
project, doing this work, without interruption would have spent.
For example, what was the loss of productivity of the working
force caused by having to do the work under winter
- 26 -
conditions as opposed to summer construction as initially
scheduled? For an example a case considering impact costs, see
Electric Power Equipment Ltd. v. RCA victor Co. Ltd. (1964) 41
D.L.R. 727.
3. Acceleration Costs
Acceleration costs are increased costs incurred by a contractor in
his effort to compress the work and complete it on time despite
the delays caused by other persons. Especially when a date for
completion is specified it is assumed that a contractor is
entitled to a period of uninterrupted and exclusive possession to
permit him to carry out his work unimpeded.
See Marentette Brothers Ltd. v. Sudbury (1973) 1 O.R. 450 @
462, varied by 45 D.L.R. (3d) 321.
Morrison - Knudsen Co. v. British Columbia Hydro (1978) 85
D.L.R. (3d) 186.
In the Morrison-Knudsen case the British Columbia Court of Appeal
stated at p. 248:
"If Hydro caused the contractor to speed up its work to
overcome owner caused delays, and we think the Trial Judge
properly found that to be the case, then the additional cost
attributable to acceleration can be assessed "
Examples of acceleration costs would be:
(i) increased costs of supervision,
(ii) additional materials,
(iii)
(iv)
(v)
(vi)
(vii)
- 27 -
additional equipment costs,
costs of extra movement of men, equipment and materials,
overtime costs,
costs of overmanning the project, and,
loss of efficiency resulting from overtime work.
4. Lost opportunity
In addition to the actual costs that may be consequent upon a
delay the contractor also suffers the loss of revenue and profit
that he would have earned had he been occupying his time on
another project. The Supreme Court of Canada in Shore & Horwitz
Construction Co. Ltd. v. Franki of Canada Ltd. (1964) S.C.R. 58
utilized the following formula to determine lost revenue, namely:
Total Markup IncludedIn Tender PriceScheduled Length ofJob (in time units)
xLength of Delay AmountIn Time units = Chargeable Due
to Delay
other formulas may b~ more suitable in specific cases.
B. PROOF OF THE DELAY CLAIM
Proof of the delay claim will require adequate contractor
documentation of the actual progress on the job together with the
timekeeping and cost control records appropriate to the claim.
- 28
The delay can only be proven through a comparison of the
contractor's daily records with the initial schedule and some
proof that tne initial scheduling was feaseable. The contractor's
project records will outline particulars such as:
(i) the work being done,
(ii) delays encountered upon specific work and the reasons for,
(lii) records of men and equipment on site and their down time,
(iv) estimates of loss productivity and the reasons for, and,
(v) other pertinent information.
In developing any such claim, the contractor will be the best
initial source to outline the consequences of the delays but the
development of the claim and proof thereof should be supplemented
through the resources of a claims consultant and an accountant
familiar with construction matters. In particular, a qualified
claims consultant will have available to him a broad range of
accumulated industry datas specific to the work in question which
will show average labour and equipment rates and productivity
information for various· types of work which will permit him to
calculate inefficiency and other impact costs.
- 29
C. COMMON CLAIMS TO BE CONSIDERED
1. By The Owner
(a) In Contract
Analyse each contract to which the Owner is a party to identify
all breaches of contract. When doing so'ensure that consideration
is given to all notices that must be given as a prerequisite to a
claim. Such notices are particularily relevant with respect to:
(i) delay claims, and
(ii) bonding claims.
Consider whether the breaches identified are fundamental so as to
give rise to the option to elect to terminate the contract or
whether they sound only in damages. Before making any decisions
to terminate consider all alternatives given the increase cost of
having another contractor complete. Contractors will rarely
takeover another's project except on a cost plus basis or a well
padded fixed price contract - since experience suggests it costs
significantly to complete anothers contract. The mitigation
responsibility must always be borne in mind.
Consider whether there are contractual claims against other
parties such as equipment or material supplier who have been
obligated to provide a warranty for the benefit of the owner.
- 30 -
(i) Against the Design Consultants
- For failure to provide the design on time.
- For failure to design properly.
- For failure to carry out inspections and otherwise supervise
the work.
- For failure to approve shop drawings or deal with other
matters arising ina timely manner resulting in delay
claims from contractors or giving rise to the owners own
delay claims.
(ii) Against the Contractor
Failure to build in accordance with plans and
specifications.
- Failure to meet acceptable standards of workmanship or
materials.
- Failure to comply with National Building Code or other
applicable standards.
- Breach of specific warranty, re: materials, product
performance or. suitability for a particular purpose.
- Failure to complete on time giving rise to an owners delay
claim.
(b) In Tort
Consider whether a tort based claimed will broaden, in any
respect, the claims that can be made against the design
- 31
consultants or contractors. As a matter of precaution it is
probably best to formulate breach of contract claims in negligence
as well.
Claim directly against responsible sub-consultants and
sub-contractors. Do not leave it to the prime consultant or
contractor to third-party them in. They may not for various
reasons and you wish to ensure that all possible resources are
available to cover the Judgement.
Consider whether the consultant failed to perform any function
·that you would normally expect a consultant to do but which is not
particularized in the contract.
Consider whether the contractor failed to do anything which you
would reasonably expect of a competent contractor even if not
particularized in the plans, specifications or contract.
Is there any basis to say that the contractor blindly followed
plans and specifications in ~n area where a reasonably competent
contractor would have picked up an inconsistency or design error.
Claim directly against suppliers where applicable on a product
liability basis.
- 32 -
(c) Quantum Meruit
Owners woulq not have a quantum meruit claim to advance against
anyone. Rather they would be seeking to resist any suggestion of
such a claim.
2. By the Consultants
Typically the design consultants actions are limited to aqtions to
recover fees or resisting allegations of liability for loss. When
sued the consultant must consider all possible cross-claims and
third-party claims available to seek contribution.
Consider whether it is possible to take the position that the
owner so interferred in the consultants role that it can be said
the owner fundamentally breached the contract. This may be
considered if it is considered adviseable to end the consultants
obligation to provide" further contract administration or
supervision.
Cross-claim or third-party other consultants
contribution or indemnity may be sought.
from whom
Consider quantum meruit claims for additional design services,
contract administration or inspections especially for deficiency
- 33 -
investigations. I have never seen such a claim pursued but there
is no reason in logic why its not available.
Do not concede a duty of care is owed to contractors
notwithstanding Trident Construction etc. The position in law is
not rigid. Rely upon all waivers and disclaimers that can be
found in tender documents or contracts.
Plead improper contractor performance whenever possible to counter
allegations of defective design. Cross-claim and third-party
claim other responsible consultants.
Consider third-partying suppliers of proprietory systems whose
systems were incorporated in the design as a result of promotional
representations made regarding its quality or suitability.
3. By the Contractor and Sub-Contractor
Don't forget the option of a debt action where you have a solvent
owner and/or general contractor. Disputes as to who is
responsible may result in a stay of mechanic lien proceedings
pending the conclusion of litigation which settles
responsibility. Sub-contractors and suppliers who are not
involved in this litigation may be well advised to proceed in debt.
~ 34 -
Consider claims in each of contract, tort or quantum meruit to
cover off costs and/or costs and profit for:
(a) Extras,
(b) Increased costs occasioned by changes in site conditions,
design or scope of work,
(c) Extended duration costs caused by:
(i) failure of others to deliver plans, materials or
perform work in accordance with scheduled times,
(ii) change in site conditions, and,
(iii) change in design or scope of work.
(d) Inefficiency or impact costs caused by things such as:
(i) having to wait on others to complete prerequisites,
(ii) having to perform work out of normal sequence,
(iii) having to work around others on site,
(iv) inefficiencies caused by seasonal considerations,
(example, winter construction) or changes in design
or scope of work, and,
(v) any other inefficiencies caused by changes from what
was anticipated at the signing of the contract.
(e) Acceleration Costs - the costs inherent in accelerating
normal work scheduling in an effort to regain lost time
or accommodate changes in the work.
consider claims against the consultants for:
- failure to provide complete or providing inaccurate
information on site conditions in tender information and
reports
- 35 -
- for delays in providing working plans and specifications or
directions
failure to provide or to provide in a timely fashion shop
drawing approvals, supplementary designs or working
instructions
- failure to adequately inspect contractors over as other
contractors work
Consider claims against other contractors for failing to complete
their work in accordance with the contract schedules resulting in
the delay costs consequent upon extended duration, impact or
inefficiency and acceleration.
v. PRACTICAL MANAGEMENT OF ISSUES
Construction litigation is unique in that it combines elements of
actions in both contract and tort with quantum meruit and mechanic
issues thrown in to· boot·. Quite apart from the complexity of the
law, the evidentiary problems are intriguing because much of the
evidence will be the evidence of experts but not in the
traditional sense of an expert who comes in and gives evidence on
the basis of a hypothetical. Rather, you will have experts who
have become inextricably interwoven in the narrative of the case.
Typically, they have either designed the building, built it or
- 36 -
become involved in investigating its failure. The expert becomes
a witness as to both fact and opinion. The money involved is
usually significant, so even minor issues are hotly debated and
the volume of documents is nearly overwhelming.
Because of the complexity of construction litigation it is
essential that counsel adopt a system for managing the
documentation and the investigation of the relevant issues both
legal and factual. Each of us must develop a system that we are
comfortable with and which is sUfficiently flexible to bend to the
damands of the particular case.
There is nothing unique or new in the suggestions I am going to
make - they are simply techniques which others made and I adopted
or wished I had adopted. Utilize them as you see fit.
If I were restricted to a single suggestion as to how to approach
the management of a construction litigation case it would this
it is a false economy not to invest ample time, effort and money
at the front end of the action to organize. As I have fumbled
through major construction actions I found that every time I
decided not to hire an expert or not to research a point because
it might not be needed I was wrong and I wasted a lot of time and
effort on the way to that conclusion.
- 37 -
assembly background information
identify and formulate the factual basis of the claim or
defence
(iii) identify and assemble relevant documents
(iv) undertake and produce the necessary studies and reports
(v) prepare the evidence for trial.
The responsible lawyer orchestrates the group but each member of
the group is expected to assume primary responsibility for his or
her area of responsibility. The team may be as small as the
contractor, an engineer, accountant and the lawyer or may involve
such additional specialists or generalists as the circumstances
may require. In a complex construction case some variation on
this approach becomes virtually essential to ensure that
everything which needs to be absorbed and accomplished is
completed. The role of the scientific or engineering specialists
in such a group is readily apparent. The role that can be played
by a claims consultant and accountant is perhaps not so clear.
Accordingly, I have in Appendix "A" attached stephen G. Revags
excellent paper on "The Role of The Claims Consultant" and in
Appendix "B" John Seigel's paper on "Quantifying the Claim - The
Accountant's Role". The case management team should meet at least
The concept of a case management team should be seriously
cons idered. The concept is to assemble from the outset a team
whose members have specific areas of responsibilities within which
they:
(i)
(ii)
- 38 -
once as a group to be briefed on what the other members have done
or are responsible for, to critique the approaches of one another
and generally to ensure that everyone is on the same wavelength
and that there are no holes in the preparation.
(A) STEPS TO TAKE AT THE OUTSET
Spend time in an analysis of the true nature of your claims and
express them clearly in your pleadings since this sets the course
of only your subsequent decision making, but also for the ultimate
trial. If you're analysis and course is not clear at the
beginning, as you delve into the morass of detail during the
action; your strategy and objectives will become even less clear.
Proof of liability and damages differ depending upon the nature of
the claim advance. Proof of damages in tort and quantum meriut
claims are always more difficult and must be approached
differently than contractual claims. Elements of remoteness are
imposed in addition to the consideration of mitigation.
study the contract(s) and know it (them) inside out. Assemble in
one-three ring binder all contractual materials including:
(i) The invitation to tender and all tender information
including consultants reports available at the time of
tendering
(ii)
(iii)
- 39 -
Correspondence and negotiations between the parties
post-tender, leading to the contract, and
The final form of contract including general and
supplementary conditions, the specifications and all
addendums and change orders.
(ii)
(iv)
(iii)
)
You will have constant reference to this volume(s) throughout the
action. Index and label it appropriately.
If specific issues of design or workmanship are involved engage at
the outsite qualified, capable and local expert (s) and have them
prepare for you written reports in which they:
(i) Identify and describe the deficiencies or alleged
deficiencies,
Relate these deficiencies or alleged deficiencies to
specific requirements of:
(a) the contract,
(b) the plans or specifications,
(c) National BUilding Code or other standards such as
the Canadian standards Association,
(d) engineering standards, and,
(e) workmanship standards
Analyze what was done or what was not done in light of
the above.
Outline what the consequences are.
- 40 -
(V) Outline what can or should have been done and by whom to
remedy the "deficiencies" and if necessary provide a
. remedial design or working instructions.
(vi) Provide a preliminary cost estimate.
Require the experts to quote in their entirety the precise
provisions of the contract, plans, specifications, codes or other
standards they rely upon and attach as an appendix to their report
any relevant extracts from National Building Codes or other
standards and texts not quoted in their entirety within the body
of the report. These are often difficult to obtain otherwise.
The discipline of preparing a report is essential. When you have
meetings to discuss issues people attend with the view that the
objective is to meet and discuss the problems. As a consequence,
no one provides anything concrete and preliminary views only are
obtained.
Most experts are comfortable with preparing written reports. They
do it all the time and they have a standard format for identifying
the terms of their engagement, outlining what they have
investigated, what they found in their investigations, what
conclusions they have reached and outlining the solutions they
see. The experts should be asked to do the reports as if they
were doing it for an owner. If they perceive they are doing it
from the outset as a court document they may be spooked and back
- 41 -
) off from their normal confident approach. They will qualify their
conclusions to death. By asking the expert to deliver a report in
their customary written form for the use of the owner they will
relax and do a professional job.
The report must be commissioned by you as counsel to ensure it is
privileged. The expert must be instructed to provide you in the
intial instance with a draft report only. This will give you the
opportunity to review it in detail and where necessary criticize
style, the adequacy of research or explanations and the use or
lack of back up. If you, as a laymen, cannot understand the
.report the Court won't either. Insist that it be drafted, in its
final form, in such a manner that it is understandable.
As for the choice of your expert, the type of expert you require
should be clear. If there is doubt start with the most general
category of expert you can reasonably identify and have him or her
direct to you into the SUb-specialties. It is necessary to engage
your expert early or th~ best available person may be gone. In
terms of choosing your expert all of the usual criteria and
sources of reference (especially others lawyers) apply. I have
one overriding rule: the homegrown expert will usually do a
better job for you and get a better reception than the import.
I suggest that you have your client review the contract and their
- 42 -
files and provide you with a written report outlining, in detail,
where they see that they or others have breached or met relevant
contractual requirements and have them assemble the documents
which they rely upon in support of their position. They should
also set out their calculations as to the damages they claim if
required. Ask them to identify for you where they feel they could
be criticized and why, together with what, their response to such
criticism would be.
Do not under any circumstances extract documents from your clients
filing system or tear it apart and reorganize it. Leave it as it
is. Get all files both from the project site and head office into
your offices intact and leave them that way. Most design
consultants and construction firms have sophisticated and
well-developed filing systems which are specifically tailored for
the construction industry. Indeed, many construction contracts
are administered under a filing system which everyone from the
architect on down adopts. This form of filing system is keyed to
a numbering system originating in the specifications and the
architect, engineers, contractors and sub-contractors will all
adopt this filing system as it relates to their particular
involvement in the contract. Whether the filing system used is
such a comprehensive system or some other system it is best that
you maintain the integrity of the system. This is of even greater
importance when you realize that others on the case management
- 43 -
team will be requiring frequent access. Learn what the clients
filing system is and use it. When you produce documents produce
the entire block out of the filing system.
If the case justifies it engage a claims consultant. This is
absolutely essential where the claim is for extras, delay costs,
impact costs, acceleration costs or other economic issues. For
the way in which a claims consultant can help you see the paper by
Stephen G. Revay. "The Role of The Consultant as Part of The
Claim Team" which is Appendix "B" to this paper.
(B) PRODUCTION OF DOCUMENTS AND DISCOVERY
Maintaining the integrity of the client's filing system utilize a
numbering machine and within every file number every document or
page, preferrably in the upper left corner, with a sequential
number. This is a pure clerical task which can be accomplished by
office staff since no determination of privilege is needed at this
stage. Presumably the file has already been determined to be
relevant and so that is not a consideration. In the unlikely
event that a claim of privilege exists with respect to a document
in your clients project files then it will be listed as privileged
within the Statement of Documents and extracted from the files and
maintained within a privileged file. The nUmbering system will
- 44 -
clearly record its original location. Personally, it is my
experience, that it is not worth the time and effort to extract
irrelevant documents that may be within an otherwise relevant file.
While the Rules of Court require on a strict interpretation, a
description of each and every document; that is not my practice
unless the other side insists. It is my experience that when you
produce the entire files opposing counsel does not insist. Rather
than wasting secretarial staff time preparing statement as to
Documents detailing thousands of documents simply do a descriptive
disclose such as the following:
Client's file, No. 18-031, entitled "Air Conditioning and
ventilation" containing documents number 18-001 to 18-099.
Do not eliminate multiple copies. At this stage it is to early to
start indexing documents. In fact, your client's filing system is
your rough index.
It is my practice to copy the opponents entire set of disclosed
documents except for obvious major duplications (for example, the
plans and specifications for the building). Again, I maintain
their documents intact. Insist upon the production of the entire
files. Assuming that the opposition has numbered their documents
with a different machine or nUmbering system there should be no
difficulty in identifying the origins. If they have not numbered
- 45
their documents sequentially have this done in another corner of
the document.
Once production of documents has been completed and prior to
discoveries I recommend preparing working volumes. utilize three
ring binders. Take photocopies from the client's files and
opponents documents. A few hundred dollars spent on photocopying
can save a thousands of dollars for the client later on in your
time. Typically, I would extract the pertinent documents from
both sides and arrange them in working document binders as follows
(recall that you already have a separate volume for contract
documents) :
(i) The Chronological File - includes in strict chronological
order all correspondence, memorandum and notes that
beyond being simply relevant appear to be significant.
(ii) Specific topic files such as, for example, "Concrete
Deficiencies" or "Disputed Change Orders" or "Delay
Claims".
(iii)
(iv)
Inspection Reports (broken down by sUb-topic if
appropriate)(i.e~ consultants regular inspection report).
Consultants reports from during the course of the project.
Given that the documents contain a unique numbering you will
always know where to find the documents within the original files
during the course of discovery or Trial. On the working copy, you
(iii)
(iv)
(v)
- 46 -
can highlight points of particular interest and make notes if
appropriate. By utilizing a three ring binder you can add
documents as necessary. You will at this stage begin to develop
some sort of index. Every case will be different and it depends
upon the issues. You may want to consider a computer litigation
support package. At this stage I suggest you begin creating a
Trial Book if you have not already done so. Typically, a Trial
Book would be a three ring binder and have the following tabs:
(i) Pleadings,
(ii) Things To Do - every time an area to be pursued comes to
mind a note is made and remains there until crossed off,
Factual Briefs,
Witness Briefs,
Legal Research - legal issues to be pursued are noted and
when completed a memorandum is inserted,
(vi) Topics to Pursue on Discovery,
(vii) Trial Plan,
(viii) Document Index.
This book becomes the central repository for all ideas, enquiries,
research, briefs and related matters. witness briefs, factual
briefs, legal research, the trial plan and other items are
modified or replaced as circumstances dictate.
The basic rule is that you build up your trial book as you go
along. Ultimately, out of the bits and pieces you develop a
- 47 -
master brief. with respect to witness briefs, be sure that a full
but narrative style of briefing is obtained. There is usually too
much volume to prepare materials in a question and answer format.
If you can coerce them to do it get the principal actors to
prepare their own comprehensive written brief in narrative form.
Organize the trial brief as much as you can; but don't depair
because it is intended as a a repository for random bits of
information which will be sUbsequently organized. If in your
review of the law reports if you see interesting case photocopy it
and insert it in the book.
On Examinations for Discovery it is my practice to leave exhibits
in the client's filing rather than creating a separate volume
containing the exhibits. Since the transcript will refer to the
document number they will be easy to locate. By and large, the
documents exhibited are already in your working documents books.
If not, consider again whether they are significant.
Because of the complexity of the matters you will want to have
accompanying you on examination a knowledgeable person from your
clients to assist you through unexpected developments arising in
the course of the discovery process.
- 48 -
(C) THE TRIAL
For any complex trial I suggest actually putting pen to paper and
preparing a trial plan and strategies. The discipline of
preparing a document will clarify your own thinking and will
assist you in keeping things in perspective and in simplifying the
complex (which is a basis goal for the trial) stated at its
simplest the trial plan is a summary of:
(i) what you need to prove,
(ii) how you will do that,
(iii) what you anticipate your opponent will try to do,
(iv) how you will counter that.
If you have been recording thoughts about trial strategies in the
Trial Plan section of the Trial Book you will have already
recorded a lot of ideas. Now is the time to eliminate and
organize. To my mind the plan is not a detailed listing of items
with which you must deal in the evidence. If you have properly
prepared for trial this is already well in hand. Rather it is a
more general outline of where you are going and specifically it
selects a very limited number of themes for your case. Those
simple propositions or arguments which you have concluded deal
best with the central issues of the case and the evidence of
specific witnesses - your own or anticipated from the opposition.
Choose your theme's carefully but when you have settled upon them
- 49 -
keep coming back to them time and again. These are your best
points and on these the action will probably be won or lost.
During the cpurse of the trial you will become distracted by a lot
of trivia and collateral issues.
themes firmly in mind.
Keep you trial plan and your
The j oint trial exhibits should contain the
The Court, will no doubt, want the parties to agree upon
an exhibit book to be filed. This is not only beneficial to the
Court but counsel.
following parts:
(i) The Contract Book - containing all contract documents,
including invitations to tender invitation, the tender,
the actual contract, general and supplementary conditions
and addendums or change orders as appropriate,
(ii) The plans and specifications for the project,
(iii) TQe Chronology this will contain all relevant
correspondence, minutes, memorandum and other records of
a similiar nature wanted in by any party in absolute
chronological order. The Chronology will be numbered
sequentially in the upper right hand corner (to
distinguish from the production document nUmbering in the
upper left hand corner) • At trial all references to The
Chronology Book can simply be Exhibit 1, Page _.
(iv) Inspection reports and other reports prepared by the
consultants and inspectors during the course of the
project,
- 50 -
(v) The relevant accounting records for the project,
(vi) Such other categories of specific documents as are
relevant.
Again, with each of these categories and documents a sequential
numbering in the upper right hand corner will save time at the
trial.
It will be expected that counsel for all parties agree that the
documents in the joint trial exhibits are:
(i) Authored by whomever purports to be the author,
(ii) Were sent as indicated,
(iii) Were received unless the evidence indicates otherwise,
(iv) Statements contained in such documents which are central
to the issues to be determined are not admitted as
correct but generally speaking collateral records of fact
are to be taken as accurate unless specifically
challenged,
(v) The weight to be given to any document is to be
determined by the Court after having the evidence as a
whole.
There is no point in trying to keep out of these volume documents
which you view as damaging to your case unless you have a winnable
argument at law that the document is not admissible into evidence
in any event. If it is damaging to you the other side will get it
in the Rules of Evidence permitting.
- 51 -
The manner of presentation of expert evidence at trial can be a
difficult matter and where difficulty is anticipated appropriate
briefs of law should be prepared. It is my practice to enter as
an exhibit a written report of my experts which contains his or
her evidence. Often you will be met with a good deal of
opposition to this and various arguments (some with merit) that
this is not a proper way for an experts evidence to be presented.
However, persist in your efforts to have the report filed as an
exhibit. The Court appreciates having the written report since it
greatly assists its ability to follow the evidence and removes the
necessity of taking notes on a very complex area. But, when the
experts final form of report is being prepared for trial
anticipate the possible challenges and have the report prepared in
such a way as to minimize the strength of such challenges. It is
essential that the consultant understand the need to actually do
the work himself or to check others work so that the report and
the evidence contained therein is the experts evidence and not
that of some other person. To the extent to which the expert may
rely upon technicians....to...-do-v.arious tests, (e.g. concrete cylinder
tests) you must ensure that the technician's or actual business
records of the technician performing the tests are available and
entered into the evidence. The consultant must ensure that every
back up piece of information referred to in his report is
available.
- 52 -
When a case involves opposition experts, it is absolutely
essential that your experts be present during the evidence in
chief and your cross-examination of opposing experts. As well
briefed as you may have been by your expert; inevitably in the
course of the evidence in chief or your cross-examination you will
run into matters which have not been previously considered. If
something unexpected develops you can always take the opportunity
to consult with your expert and your expert can feed you questions.
If the case is one which justifies second counsel utilize second
counsel. Responsibility for various aspects of the case should be
divided among counsel. Don't try to do it all yourself. Unless
there are other compelling reasons the lawyer who has done the
background investigation should lead the evidence or conduct the
cross-examination in his or her area of responsibility.
Make use of such demonstrative aids to the evidence as seem apt.
In particular, consider use of the view. The accepted purpose of
a view in Saskatchewan -i,s that it is not evidence but rather an
aid to the trial jUdge to understand the evidence.
Any construction action will benefit from a concerned effort to
make the complex simple. Since construction disputes may involve
opinions and facts about events that occurred over months and
years of construction, planning and activity, you must focus on
reconstructing as simply as possible the relevant sequence of
53 -
events upon which your clients defence or recovery will be based.
It will probably be helpful to the Trial Judge if you prepare a
cast summary which identifies the various parties and the
principal actors for each of these parties including their areas
of responsibility. In addition, some form of chronological
outline would be helpful.
VI. CONCLUSION
In this paper I have attempted to outline an approach to managing,
legal, factual and evidentary issues in construction litigation.
My theme has been organization and the adoption of some system to
manage documents and information at trial. In this I have
probably overlooked the essential prerequisite that counsel
acquire some basic knowledge of the industry itself before getting
very far into a case.
The role of the advocate' is to practise the art of persuasion. It
is not possible to persuade others about matters which we
ourselves do not understand. We as lawyers must first understand
before we can interpret. While certain issues of law are complex
and evolving; do not because preoccupied with the law. The focus
at a trial must be on the facts. In the course of a construction
file some of the most significant facts to be proven may be the
- 54 -
manner in which the industry operates and what the participants in
the industry expect from one another. (Note Mr. Justice Wilson in
Trident Construction). Start your own inquiry at that level and
. understand the various perspectives of the design consultants, the
contractors and the owners. These perspectives may well become
part of your theme for the trial.
DISCLAIMER
In the near future, you can expect to see well advised design
consultants placing a disclaimer of responsibility on all of their
work. With this in mind I put my widest possible disclaimer
forward.
APPENDIX "A"
SELECTED LIST OF CONSTRUCTION LAW MATERIALS
Beyond Hudson's (British) and Goldsmith's (Canadian) texts inconstruction law the following materials are available:
- Reports: the "Construction Law Reports" - cited C.L.R.
the "Professional Negligence" reports - cited P.N.
- Seminar Materials:"Construction Litigation" Continuing LegalEducation Society of British Columbia, October, 1983
"The Prosecution and Defence of ConstructionClaims" -National C.B.A.jC.L.E. Committee Program,April, 1988
Articles and Case Comments:Abraham, J. D., "Concurrent Liability in Contract and Tort Apportionment of Damages: An Update" (1981-82) 3 Adv. Q. 430
Bates, Paul, "ConstructionDisruption and Delay. CaseConstruction (Western) Ltd. v.CLR 48
Litigation: Damages forcomment: ,W.A. Stephenson
Metro Canada Ltd." (1989) 32
Bates, Paul, "Construction Litigation:Disruption and Delay" (1989) 32 CLR 48-55
Damages for
Bristow, David I., "Claims by Owners Against Contractors"(1988), 1 Nat. Property Rev. 89-94
Charles, W.H., "Torts and Contract - Merging Areas?" (1988) 8Advocates Quarterly 222
Doyle, Michael, "Issues in Construction Industry Litigation"(1988) 29 CR 973 .
Elder, P.S., "Kamloops v. Nielsen - Good Result, Unclear Law"(1986), 24 Alta LR 540
Irvine, John, "Case Comment: John Maryon International Ltd.v New Brunswick Telephone Co and Ward v. Dobson ConstructionLtd." (1983), 24 CCLT 213
Irvine, John, "Case Comment:Associates and Toronto-DominionCCLT 266
Surrey v. Carroll-HatchBank v. Guest" (1979),
&10
- 2 -
Irvine, John, "Contract and Tort: Troubles Along the Border"(1979), 10 CCLT 281
Kirsch, Harvey J., Selected Bibliography of Construction LawWritings in Canada (1988) (Carswell, Toronto)
Law Reform Commission of British Columbia, "Report on SharedLiability"· (1986)
MacPherson, Robert W., "A· Lurch Forward in the Law - Doironv. La caisse Populaire d'Inkerman Ltee and Coopers & Lybrandv. H.E. Kane Agencies Ltd." (1986), 35 University of NewBrunswick LJ 197
Plottel, Gordon, "Building Resolutions:Construction Industry" (1988) 26 CLR 48.
Arbitration in the
Rafferty, Nicholas, "Concurrent Liabil i ty and the Running ofLimitation Periods: Central Trust v. Rafuse" (1987) 3 PN 53
Rafferty, Nicholas, "Tai Hing Revisited: Canadian PacificHotels Ltd. v. Bank of Montreal" (1987) 3 PN 193
Rafferty, Nicholas, "Tort Liability of Public Authorities:Anns, Economic Loss and Limitation Periods" (1985) 1 PN 121
Revay, Stephen V., "The Role of the Consultant as Part of theClaim Team" (1989) 31 CLR 18
Rosenburg, Honorable Mr. Justice A.B., "Limitation Periods asthey Apply to Construction Litigation, The Law and SuggestedReform" (1988) 27 CLR 84
Rubin, Robert A. and Barrick, Lisa A., "Contractor Defaultand Practical Advice to Owners" (1988) 28 cLR 61-68
Singleton, John R., "Reversing the Trend Toward ExpandedLiability" (1988) 27 CLR 213
smith, J .C. and Burns, Peter, "The Good Neighbour on Trial:Good . Neighbours Make Bad Law" 17 University 6f BritishColumbia LR 93
Wallace, LN. Duncan, "Excerpts from Correspondence from IanDuncan Wallace, Q.C., to the Mr. Justice A.B. Rosenburg,Supreme Court of ontario" (1988) 29 CLR 239
Wallace, LN. Duncan, "Joint and Several(Construction projects)" (1988) 25 CLR 169-198
Liability
Westeinde, John, "Construction is 'Risky Business' (RiskSharing between Generals and Subcontractors)" (1988) 29 eLR119-123
The Kirsch bibliography noted above while entitled "SelectedBibliography" is for practical purposes comprehensive. The othermaterials noted above are an attempt to update Kirsch with anemphasis upon concurrent liability, delay claims and constructionlitigation.