page 1 of 21 - hpaldc.orghpaldc.org/nrpc_test/11/11_agenda.pdf · 2.1.3.1 at dhauliganga power...

23

Upload: others

Post on 22-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1 of 21

Agenda for 11th

meeting of Telecommunication, SCADA & Telemetry (TeST) Sub- Committee

1. Confirmation of Minutes: The minutes of 10th meeting of TeST sub-committee held on 22.03.2017 were issued on 13.04.2017. Minutes are available on NRPC website (www.nrpc.gov.in). Comments from UPPTCL have been received, Members may discuss and confirm the Minutes.

2.1 OPGW installation under central and state sectors:

2.1.1 Latest status of OPGW installation progress under central sector:

2.1.1.1 In 10th

TeST meeting POWERGRID informed that out of 5203 Kms. of OPGW under central sector, OPGW of 5064 Kms had been completed. The details of balance 139 Kms. of OPGW, which was on under - construction lines are as under:

i) Abdullapur – Dehradun – 54/89 Kms (Balance 35 Kms)- Expected to be completed by April,2017 ii) Kishenpur – Dulhasti – 34/119 Kms (Balance 85 Kms)-Expected by May,2017 iii) Uri-II to Uri-I line - 10Kms. (scope deleted due to sever ROW)

2.1.1.2 Representative of POWERGRID, NR-II confirmed that transmission line

work of Abdullapur-Dehradun line and Kishenpur-Dulhasti was hampered due to sever ROW problems .The lines were targeted for completion by April,17 and May,17, respectively. He informed that same time OPGW would also be laid on both lines.

2.1.1.3 Regarding, Uri-II to Uri-I line , it was informed that due to severe ROW

problems , this part has been deleted from the scope. It was also informed

1. Confirmation of Minutes

2. Telecommunication related issues

Page 2 of 21

that Wagoora connectivity had been established with URI-I, having route length of 96.520 Kms., instead of connectivity of Wagoora with URI-II, having route length of 106.035 Kms., as per approved link. Now, final OPGW connectivity is Kishenpur - Wagoora - URI-I. Tejas communication equipment had been supplied at both URI-I & URI-II and URI-I link would be commissioned in April,17, which was delayed due to ongoing agitation and weather conditions in Kashmir Valley. It was further informed that equipment of URI-II will be diverted to other site as there is no fibre connectivity at Uri-II. OPGW procured for URI-I to URI-II link and balance Wagoora to URI-II link would be used as spare for maintenance purpose.

2.1.1.4 NHPC representative requested PGCIL to consider OPGW connectivity of

Parbati-III in current phase as OPGW work upto Banala had already been covered by PGCIL and Parbati-III Power Station is only approx. 7 Km. from Banala. POWERGRID representative stated that Parbati-III had not been covered in any existing package. However, he added that the work may be taken up by POWERGRID subject to approval by NRPC.

2.1.1.5 In 34th NRPC meeting held on 2nd

POWERGRID may update present status.

May 2017 OPGW for Parbati-III was approved.

2.1.2 Latest status of OPGW installation progress under state sector:

2.1.2.1 In the 10th

TeST meeting POWERGRID informed that they had awarded 3 packages for implementation of OPGW in Northern Region with completion schedule of Mar/April’2017. The progress as updated in the meeting, by POWERGRID, are as under:

Sl. No.

Name of Package Award Date

Completion

schedule

Status

1 OPGW for State sector (Package-V) M/s ZTT/ECI/Steel Product

July, 2015 July’2017 • Out of total 1664 Kms, installation has been completed for 1560 Kms. Balance OPGW work would be completed shortly.

• FAT of communication

Page 3 of 21

equipment had been done.

• Equipment installation would be completed by July,17 for whole package.

2 OPGW for State sector additional requirement (Package-I a) M/s SDGI-Offshore contract

Oct, 2015 Apr,2017 (supply Pkg)

Out of 2922 Kms. Supply of 950 Kms. Completed. Balance supply would be done in April’17.

3 OPGW for Additional

requirement for CS and SS (Package-III a) M/s Prem Power

Sept’ 2015 Sep,17 Total scope 726 Kms under central sector lines only. Supply completed. Installation work would be completed by Sept, 2017.

2.1.2.2 Regarding Package-I a, POWERGRID representative stated that this is

only offshore supply. Installation package had been awarded by respective Region of POWERGRID i.e New Delhi and Jammu. Member secretary suggested that OPGW installation may be taken up in Punjab at the earliest and should be completed before onset of paddy season i.e May,17 to avoid shutdown during this period . POWERGRID agreed for the same and informed that by Sept’ 2017 works for all the states would be completed.

POWERGRID may update present status.

2.1.3 Status of OPGW connection at NHPC Power Stations ( Agenda by NHPC)

2.1.3.1 At Dhauliganga Power Station :There are two links (OPGW and PLCC) for data telemetry at Dhauliganga Power Station. OPGW link of Dhauliganga Power Station is down since 05.04.17 and data is being telemetered through PLCC which is intermittent in nature. The matter has been brought to the notice of NRLDC/POWERGRID.

POWERGRID may update the status.

Page 4 of 21

2.1.3.2 At other NHPC Power Stations: As per minutes of 10th

POWERGRID may update the status of Dulhasti, Bairasiul, Sewa-II and Parbati-III powers stations.

TeST sub- committee meeting (Point No. 2.1.1, A) POWERGRID informed that OPGW laying for Dulhasti would be completed by May,2017. It was further informed that OPGW connectivity for Bairasiul and Sewa-II station has been completed and after terminal equipment supply, link would be commissioned by July, 2017.

2.1.4 OPGW connectivity to NR generating stations ( Agenda by NRLDC):

2.1.4.1 It is understood that approval of OPGW connectivity to following generating

stations was approved in NRPC.

i. Karcham HEP ii. Jhajjhar TPS iii. Sorang HEP iv. Parbati-III HEP

These stations are yet to be connected on wideband. The plan for implementation may be discussed and finalised.

2.1.4.2 OPGW connectivity of Nathpa Jhakri was discussed in detail during the 10th

TeST Sub-Committee meeting and it was decided that SJVL will revert in this regard to NRPC. No information till date has been received in this regard.

Present status may be discussed and decided.

2.1.5 Optical fibre connectivity from SLDC Dehradun to Rishikesh: (Agenda by POWERGRID and NRLDC)

In 10th

TeST meeting issue of Optical fibre connectivity from SLDC Dehradun to Rishikesh was discussed. Under ULDC scheme, communication equipment and EPABX at Dehradun SLDC is supplied and installed, however these equipment could not be commissioned due to non-availability of communication link. ICCP link from Dehradun to Roorkee has been running on BSNL lease line and from Roorkee POWERTEL have provided channel from Roorkee to NRLDC on lease, initially this link was taken from POWERTEL for two months. However as of now, it is working since more than one and half year. PTCUL was requested to provide Six (06) fibers on their link from Dehradun to Rishikesh, so that it can be connected to ULDC network at Rishikesh and SDH supplied by Tejas and EPABX can be commissioned. A letter dated 13.04.2017 was issued to PTCUL by NRPC in this regard. Subsequently, the matter was also discussed with SE,SLDC, PTCUL, who had agreed to share the communication link.

PTCUL may update the status.

Page 5 of 21

2.6 Implementation of OPGW under Package-I (a) (Agenda by HPSEB):

2.1.6.1 HPSEB informed that Under package-I (a), OPGW of about 545.335 Km is to be laid on HPSEBL transmission network and as per LoA work was to be completed by 31.03.2017, however, during 10th

TeST, it was agreed by POWERGRID that by September, 2017 works for all the states would be completed.

2.1.6.2 Under said Package OPGW laying work on HPSEBL transmission network was started w.e.f. 09.02.2017 by M/s Ten Dot Net cable Pvt. Ltd., and as on date 22.06.2017, only 66 km. of OPGW against 545.335 Km. has been laid on HPSEBL transmission network. It is pertinent to mention here that prevailing pace of OPGW laying work by the firm is very slow and with such pace work would not be finished by the firm as agreed during 10th

TeST meeting i.e. by September, 2017. Further, NR-II, PGCIL, Jammu has been requested through various correspondence and e-mail to deploy more teams for expedite of OPGW stringing work. In response, NR-II vide e-mail dated 15.05.2017 has circulated the MoM held between PGCIL & M/s Ten Dot Net cable Pvt. Ltd., according to which:

i. M/s Ten Dot assured that 01 gang will reach at site by 12.05.2017 for 132 kV Jutogh-Maliana line and will be completed in the month of May, 2017.

ii. M/s Ten Dot assured to deploy 02 nos. more erection gangs for

HPSEBL links by end of May, 2017.

2.1.6.3 Neither OPGW stringing work on 132 kV Jutogh-Maliana line has been started by the firm nor 02 nos. more erection gangs for HPSEBL links has been deployed by the firm. Firm may be directed to deploy more teams so that stringing of OPGW could be finished by targeted schedule i.e. September, 2017. POWERGRID may update the status.

2.1.7 Installation of OLTE under Package - V & Package IV (a). (Agenda by

HPSEB)

2.1.7.2 Under package-V, Terminal equipment (SDH & PDH) is to be installed on 14 Nos. HPSEBL locations and DCPS & battery are to be installed on 08 nos. locations, however, as per LoA work was to be completed by 31.03.2017. NR-II, PGCIL through e-mail dated 26.12.2016 had intimated tentative schedule for completion of installation of OLTE & DCPS as under:

Page 6 of 21

i) SDH& PDH: FAT from 15.01.2017 to 19.01.2017. Material expected to reach site by 15.02.2017. Commissioning & SAT by 27.03.2017.

ii) DCPS & Battery: FAT from 20.02.2017 to 01.03.2017. Material

expected to reach site by 12.03.2017. Commissioning & SAT by 31.03.2017

2.1.7.3 As on date i.e. 22.06.2017, no material has been received by HPSEBL and

NR-II. POWERGRID,NR-II may intimate the latest status.

2.1.7.4 Under Package IV (a), terminal equipment is to be installed on 24 Nos.

HPSEBL locations and DCPS & battery are to be installed on 18 Nos. HPSEBL locations. POWERGRID,NR-II, may intimate latest status.

2.1.8 OPGW Requirement for UP ( Agenda by UPPTCL)

2.1.8.2 OPGW for Additional requirement for CS & SS Package-III (a) awarded to

M/s Prem Tower: Status regarding following Ckts. may be updated:

i) AGRA-1------- AGRA_PG ii) GRK-1------- GRK_PG iii) AZAM-1------GRK

2.1.8.3 OPGW for State sector, additional requirement (Package-1 a) awarded to

M/s SDGI- offshore contact: In last TeST Sub-committee meeting, it was informed by POWERGRID that balance supply (1972 kms) would be done in April’17 and equipments installation would be completed by Sep’17. Latest status may be given by POWERGRID.

2.1.8.4 OPGW for State Sector (Package-V) awarded to M/s ZTT/ECI/Steel Product: During 10th

2.1.8.5 POWERGRID may update latest status and also provide schedule for installation & commissioning of Terminal equipments as per following priority and also provide details regarding completion of works for each circuit.

TeST sub-committee meeting it was informed by POWERGRID that out of total 1664 kms, installation has been completed for 1560 kms and balance OPGW work would be completed shortly.

i) Agra – Hathras –Harduaganj ii) Muradnagar- Sahibabad- Noida Sector.62- Noida Sector 20

Page 7 of 21

2.1.9 Training program for STU personnel on OPGW related aspects:

2.1.9.2 In 8th TeST meeting POWERGRID agreed to arrange a training program for STU

personnel on OPGW related aspects so that they become familiar with O&M activities of OPGW. It was also agreed that each STU would nominate 3 to 4 Engineers for the training. The issue was further discussed in 35th TCC and 39th NRPC meeting held on 1st and 2nd

May 2017,wherein, POWERGRID had agreed to organise the training on its own expenditure.

POWERGRID may give latest status. 2.2 Communication issues

2.2.1 Communication plan for channel redundancy and to back-up NRLDC

(Agenda by NRLDC) The provision of redundant communication was discussed in 8th and 10th TeST held on 26th July 2016, and 22nd March, 2017, respectively. However, redundant data communication at NRLDC is yet to be completed. After testing, as on 31st

2.2.2 Earthing issue at 220 kV Moga station (Agenda by POWERGRID)

May 2017, only 58 out of 116 NR stations were found with data redundancy POWERGRID may inform the action plan and target to complete above task.

POWERGRID informed that Cards of Communication equipment got faulty/burnt at 220kV Moga station of PSTCL due to earthing issue in s/s. Cards have been burnt at least six (06) times in last one and half year, however no action has been taken up by PSTCL to replace or separate earthing for communication equipment, even after repeated reminders to higher officials of PSTCL. Testing of earthing may be done through third party (SAMEER - Govt. of India). POWERGRID will not deploy any vendor to this sub-station for rectify /replacement of the cards without testing and installation of new earthing, as 5-6 cards had already been replaced which have financial implication. PSTCL may give action plan to resolve earthing issues.

2.2.3 Implementation of Regulation on Communication ( Agenda by NRLDC) 2.2.3.1 Formation of guideline for calculation of “Availability of Communication

System”

The regulation on communication has been issued on 15th May, 2017 with an effective date of 1st

July,2017. As per the regulation 7.3 (ii) “The RPC Secretariat shall certify the availability of communication equipment for CTU, ISGS, RLDCs, NLDC, SLDCs based on the data furnished by RLDC”

Page 8 of 21

Further, as per regulation 7.3 .(i) “(i) NPC shall be responsible for issuance of the guidelines with the approval of the Commission on “Availability of Communication System” in consultation with RPCs, RLDCs, CTU, CEA and other stakeholders within a period of two months from the date of notification of these regulations.”

RLDC needs to keep records of the communication outage based on requirements of the guidelines to be decided by NPC and approved by Commission since 1st

July, 2017.

Member may discuss.

2.2.3.2 Issuance of Technical Standards for the communication system

As per regulation 7.1 (ii) “CEA shall formulate and notify technical standards, cyber security requirements in accordance with the Cyber security Policy of the Govt of India from time to time, protocol for the communication system for Power Sector within the country including the grid integration with the grid of the neighboring countries.” Further, guideline for interfacing requirements needs to be formulated within 60 days from the issuance of the technical standards to be issued by CEA. Member may discuss.

2.2.3.3 Formulation of planning criteria for the communication system

As per regulation 7.1 (i) “CEA shall formulate communication planning criterion and guidelines for development of reliable communication system for power system of India duly considering requisite route redundancy ,capacity, as well as requirements of smart grid and cyber security.” Member may discuss.

2.2.4 UPPTCL Communication issues : (Agenda by UPPTCL)

2.2.4.1 Delay in Supply & Installation of FOTE Equipments: In 10th

2.2.4.2 Channel Routing Plan: It was requested earlier also that channel Routing Plan as per currently implemented scheme is required for analyzing cause of non-reporting stations and channel redundancy planning is urgently required for smooth data reporting at the earliest.

TeST Sub-committee meeting, POWERGRID representative informed that supply & installation of FOTE equipment would be done in April’17 and commissioning would be done by June’2017 for all UPPTCL links. But till date even supply of FOTE equipments is not completed. Due to this lot of problems are faced in real time data availability of data from Agra 765 kV, Agra 400 kV, Agra 220 kV, Greater Noida, Hathras Shamsabad etc. .This is causing problem in real time calculation of correct drawl from central sector resulting in financial loss on account of UI charge.

Page 9 of 21

2.2.4.3 Sharing of weekly Availability Report of Important Links on Tejas/Fibre Home Network: As per MOM of 10th

2.2.4.4 Share folder links between main NRLDC to Backup SLDC is still not working.

TeST sub-committee, POWERGRID & NRLDC are to share weekly availability report generated through NMS for various links provided on Tejas/ Fibre home networks but till date this has not been started.

2.2.5 RVPNL communication issues ( Agenda by RVPNL)

RVPNL informed following issues for necessary action by POWERGRID:

a) Configuration of additional VF channels (approx 100 nos.) at various MUX locations of Rajasthan for up-coming RTUs.

b) Rectification of faults & repairing of faulty modules of 48 V HBL make DCPS installed at SLDC, Heerapura.

2.3 RTU issues

2.3.1 Replacement of old S900 RTUs:

2.3.1.1 The issue regarding replacement of existing S 900 RTUs installed under ULDC Phase – I was discussed in the 8th , 9th(special) &10th

2.3.1.2 The issue was further discussed in 35

Meetings of TeST Sub-Committee. Accordingly a group was constituted for finalising RTU specifications and short listing of RTU models. RTU specification was finalized by the group after incorporating comments and the same is available on NRPC website.

th TCC and 39th NRPC meeting held on 1st and 2nd

Members may update the status .

May 2017, wherein it was decided that the group would not shortlist the models, instead it would only prepare specifications keeping in view compatibility requirement of RTUs with SCADA. It was also decided that necessary action may be taken by all the concerned utilities on their own without delay to replace the S900 RTUs as per their technical specification and requirement by ensuring compatibility of the new RTUs with SIEMENS SCADA system. The technical specifications of the RTU, finalised by the group, may be used as reference. Same was conveyed by NRPC secretariat to all constituents, vide letter dated 26.05.2017.

2.3.2 GPRS connectivity for RTU installed under J&K PDD (Agenda by POWERGRID);

Page 10 of 21

2.3.2.1 On request of J&K PDD, POWERGRID have placed an order for GPRS based system for 20 nos. of RTUs at Jammu SLDC in May, 2015. However, broadband connection with static IP at SLDC, Jammu and 20 nos. of data enabled SIM cards for RTU sites was to be arranged by J&K PDD to enable data reporting of these RTUs at Gladani SLDC as a standby channel. This work is still pending since more than 2 years. In view of non-availability of SIM cards and Static IP, the system could not be commissioned. POWERGRID is going to short close the contract. PDD, J&K may give action plan for arrangement of static IP and SIM Cards.

2.3.3 RTU & AMC related issues (Agenda by HPSEB):

2.3.3.1 If any additional bays are to be interfaced with the SIEMENS RTU and are

not included in the BOQ, the modalities may be finalized. M/S PGCIL informed that rate contract for interfacing additional bays shall be finalized by them in due course of time but the same is still awaited.

2.3.3.2 As per the Article 5 1.2 (iii) ( c) of Maintenance Contract, integration of new equipment (RTU, Workstations, Printers, Switch, Router, ICCP connection etc.) with Main and Backup Control Centre System is included in the maintenance contract whereas same has been shown excluded in the AMC Contract. The relevant extract is reproduced as under:

Article 5 1.2 (iii) ( c) of Maintenance Contract: “Integration of new equipment (RTU, Workstations, Printers, Switch, Router, ICCP connection etc.) with Main and Backup Control Centre System” is included in the maintenance contract

2.3.3.3 Whereas exclusions of Scope of AMC includes RTU Integration. Members may discuss.

2.3.4 Signing of side letter to MoU for AMC: (Agenda by POWERGRID)

Side letter for MoU for AMC contract (RTU maintenance, etc) has been send to Constituents as per discussion in last meeting. However, MoU yet to sign by most of the constituents. Members may discuss.

2.4 AMC Issues of SIEMENS RTUs installed under ULDC- 2 (Agenda by DTL):

2.4.1 Additional bays are required to be integrated in the RTUs of M/s Siemens at Mehrauli, Patparganj and Wazirabad Substations ( installed under ULDC#2), however no rates are available in the existing contracts.

2.4.2 No rates available in the existing Contracts for procurement of RTU database software for the Siemens make RTUs installed at Mehrauli, Patparganj and Wazirabad Substations ( installed under ULDC 2).

Page 11 of 21

2.5 Role of POWERGRID in Resolution of Contractual issues with M/s Siemens: 2.5.1 The responsibility for implementation of ULDC#2 project in all SLDC’s lies with

POWERGRID, in which various Contracts were signed between M/s SIEMENS and PGCIL/POSOCO/SLDC’s. However all the contracts are interlinked, such that breach of any contract makes the Contractor liable for damages under other Contracts also. Recently, while calculating the percentage availability of system for making payment to Siemens, difference in the understanding of method of calculations ( as detailed out in Volume II , Technical Specifications) emerged between Siemens and DTL, for which POWERGRID’s representative was asked to attend a meeting along with Siemens. POWERGRID vide their mail as brought out below, have not agreed to be part of this meeting.

“As such POWERGRID have no specific role in AMC contract which is signed between M/s Siemens and Constituents and due to other preplanned works on same day, we are not able to attend the said meeting.”

2.5.2 On the contrary, POWERGRID have themselves issued a letter to Siemens on 09.05.17 stating that the Defect liability period has been completed on 31.03.17 and AMC for all SLDC’s system started from 01.04.17.

2.5.3 All the Specifications/ T&C’s have been made by POWERGRID as such, it shall not be possible to enforce the T&C of Maintenance Contract (Third Contract) without the involvement of POWERGRID. Members may discuss.

2.6 Disposal of old and obsolete SCADA equipment of ULDC Phase - I. (Agenda by BBMB) BBMB informed that ,the issue regarding disposal of old/obsolete equipment dismantled after commissioning of ULDC Phase – 2 as well as the methodology for its cost adjustment is under regular discussion since first meetings of TeST sub-committee, In the 10th

POWERGRID may update the status.

Meeting of TeST, it was informed by POWERGRID that the recovery of charges against the ULDC-I package was expected to be completed by July,17, after which constituents can dispose the equipment. It was agreed that POWERGRID would issue letters to constituents indicating the exact date after which the disposal action could be initiated by the Constituents.

3.5 Operational issues in EMS / SCADA system

3.1.1 Calculation of actual drawal in SCADA ( Agenda by NRLDC)

3.0 Issues in Unified Load Dispatch & Communication scheme of NR (Phase-II):

Page 12 of 21

The error checking for the tie lines were also discussed during the last meetings. It was decided to compare the SEM and SCADA data for each points and points for which % age errors are more than 3% will be reported for correction. It is observed that except UP & HVPNL, no report was available for discrepancy and hence it is presumed that there was no error found at least in the tie lines on which drawal calculations are being done. Members may confirm.

3.1.2 Manual replacement of calcheck data at SLDC end (Agenda by UPPTCL)

3.1.2.1 It was agreed earlier that in case of failure of RTU/SAS/Communication system of central sector entities manual replacement of data in SCADA will be done by NRLDC but the same is not being ensured properly.

3.1.2.2 Manual replacement of calcheck data at SLDC end is also a challenge as many of the POWERGRID stations are unmanned and therefore obtaining adequate value for replacement is arduous & time consuming. To overcome such recurrent problems a mechanism needs to be developed for timely acknowledgment, quick response & speedy resolution to these issues.

Members may discuss.

3.1.3 Monitoring of UFR, DF/DT and SPS feeder in SCADA( Agenda by NRLDC):

3.1.3.1 In the 10th

TeST meeting, the issue of mapping UFR, df/dt and SPS was discussed. Hon’ble Central Electricity Regulatory Commission (CERC), order dated 23rd December 2013 in petition no 221/MP/2012 has ordered as follows:

“(c) UFRs and df/dt relays also be mapped on the SCADA system of each state so that they can be monitored from SLDC/NRLDC. (d) All STUs and SLDCs to map/network the UFR and df/dt on their SCADA system.”

3.1.3.2 It is observed that the telemetry values are mostly not available in HVPNL and

DTL whereas , Uttarakhand, is yet to send the displays. Members may furnish the details regarding availability of telemetry of all the feeders on which the UFR and DF/DT relay have been provided, if not, the schedule for implementation of telemetry for the same. The schedule for availability of displays for Uttarakhand may be submitted.

3.2 Networking issues of SCADA in UP : (Agenda by UPPTCL) 3.2.1 UPPTCL informed that the issue of Sub- LDCs (Panki, Moradabad, Modipuram)

to SLDC Lko. was discussed in 10th Test Sub committee meeting . In 83rd MRM it was informed by POWERGRID that new Tejas equipments had been installed

Page 13 of 21

at all SubLDCs except Sultanpur & Varanasi. All sub- LDCs to SLDC/Backup SLDC, Connectivity of Remote Consoles & Terminal Servers may be shifted to Tejas. As per POWERGRID suggestion shifting of Sub-LDC Panki, Moradabad, Modipuram & SLDC Lucknow data on Tejas was tried by team of, Siemens, Tejas & UPPTCL Engineer between 29-05-2017 to 01-06-2017.But performance of SCADA system on Tejas was worse than through Fibre home/MRO Tech. Networking issues of SCADA during simultaneous reporting of RTUs to Main & Backup SLDC is still unresolved. This has also been raised by UPPTCL with POWERGRID vide letter no. 184/Scada & IT/SLDC dated 05/06/2017. Members may discuss.

3.3 Availability of data regarding new element Charging : System for dissemination of information regarding commissioning details of charging of new element, above 132 KV, on real time basis, to all STUs/SLDCs/RLDCs through SCADA system needs to be established. Members may discuss.

3.4 SCADA Issues raised by State SLDCs

3.4.1 Pending SCADA Issues ( Agenda by BBMB):

Following issues in respect of SCADA/EMS System installed at BBMB SLDC under ULDC Phase – II are still pending:

3.4.1.1 Implementation of Multisite Configuration:

The implementation of Multisite Configuration between BBMB SLDC and PSTCL SLDC is still pending due to non-availability of communication links. In the 10th

Members may discuss.

TeST meeting , it was intimated that a group was constituted by NRPC vide letter No. NRPC/OPR/108/04/2016/5328-40 dated 10.06.2016 and the report of the group was awaited. It was also deliberated that due to transfer of some of the members of the group, the proceedings of the group was affected.SE, NRPC requested all the concerned utilities to send nomination of an alternate member in the group, latest by 31.03.2017, so that the group may be reconstituted and the task is completed. POWERGRID representative informed that communication would be provided as per recommendation of the group after submission of the report.

3.4.1.2 Database Synchronisation:

A document containing database synchronization procedure was forwarded by POWERGRID vide their e-mail dated 02.06.2016. The document was perused and it was found that the procedure did not provide methodology for synchronization of TNA, IFS and ICCP databases. In this regard, the clarification

Page 14 of 21

was sought from SIEMENS/POWERGRID vide email dated 05.06.2016. However, M/s SIEMENS had neither provided clarifications nor incorporated necessary modifications in the document. In 8th

Members may discuss.

Test meeting, the difficulties being faced during database modification and synchronization process was deliberated and to overcome these problems some proposals were suggested, but none of them have been implemented so far. Lot of problems are being faced in maintaining the availability of real time data at BBMB SLDC in the absence of proper database synchronization procedure. The issue was discussed in detail in the 10th meeting of TeST and after detailed deliberations it emerged that there were several similar issue, which needs proper coordination with concerned vendors. It was decided that a meeting would be arranged at NRPC, New Delhi with all the concerned vendors of ULDC scheme and the concerned State utilities to discuss and resolve the issues.

3.4.1.3 Running of State Estimator:

BBMB is facing problems in keeping the State Estimator running due to Database Synchronization issues. It may be pertinent to mention here that BBMB has 100% telemetry of all its stations and all the circuit breakers and isolators are wired and reporting. However, on account of power system changes in other constituents, the TNA model is updated by respective constituent in their own database but the same is not propagated to other constituents. The matter was discussed in the 8th Meeting of TeST and it was decided that NRLDC would share its TNA model on monthly basis with all constituents during database synchronization process so that the changes made by all constituents in TNA are updated at all SLDCs. In the 10th

Meeting of TeST, BBMB expressed concern that unless a proper procedure is put in place for periodic synchronization of common TNA model and ICCP database, it would not be possible to run the State Estimator successfully. However, the proposal of BBMB was not accepted by NRLDC. After detailed deliberations, it was decided that training of one week duration would be arranged at each Constituent location. It was also decided that all the Constituents would nominate the officers who are responsible for running State Estimator, so that hands on training could be imparted to them directly on their system. It is requested that the training on TNA applications may be arranged at the earliest.

It is further requested that the underlying problems relating to database updation and maintenance of TNA Model may also be resolved in consultation with M/s SIEMENS during training so that the State Estimator can function smoothly.

3.4.1.4 Adoption of IPv6 on SCADA IT Network:

Page 15 of 21

In the 36th USMG Meeting held on 18.02.2014, it was brought out by BBMB that the ministry of Communication & Information Technology, Government of India has circulated the IPv6 Deployment Roadmap to all the Central Government Ministry/Department/State/UTs to facilitate them in the task. A copy of the roadmap is available on internet at http://www.dot.gov.in/sites/default/files/Roadmap%20Version-II%20English%20_1.pdf . All the Government Organizations were advised to follow a phased transition approach depending on the complexity and the IPv6 readiness of their current networks and systems. Accordingly, it was suggested that the SCADA/EMS System, which was under procurement at that time, may be got configured on IPv6. It was however intimated by POWERGRID that the installation & commissioning of SCADA/EMS System under ULDC Phase – 2 is at an advance stage. The system platform being procured is IPv6 ready but at present is being commissioned with IPv4 keeping in view the integration requirements with existing system. After commissioning of new system, the security audit of the system shall be got conducted and the recommendations of IPv6 Deployment Roadmap shall be progressively finalised and implemented within deadline set by ministry i.e, Dec., 2017. Since the commissioning of new SCADA/EMS System has been completed, POWERGRID may implement the roadmap for transition of SCADA/EMS IT System from IPv4 to IPv6, which is to be completed by Dec., 2017.

3.4.1.5 Preparation of Cyber Security Policy and Cyber Crisis Management Plan for

SCADA/EMS System

Various references are being received from CEA and NHPC (Nodal agency appointed by Ministry of Power for ensuring compliance related to Cyber Security in Power Sector) to prepare the Cyber Security Policy at the earliest. It is also pertinent to mention that Power & Energy Sector has been identified as Critical sector by Govt. of India, which needs to be protected from potential Cyber threats.

Cyber Security Policy and Cyber Crisis Management Plan in respect of the SCADA/EMS System installed under ULDC Phase – 2 needs to be prepared and got implemented at the earliest.

Members may discuss and decide further course of action on the matter.

3.4.2 SCADA Issues of H.P. (Agenda by HPSEB)

3.4.2.1 HPSEB informed that SOE’s of the following Sub-Stations are not being generated in the SCADA:

i) 220kv Sub-station Jeori

Page 16 of 21

ii) 132kv Sub-station Darlaghat iii) Malana HEP iv) 132kv Sub-station Palampur v) Phozal HEP

3.4.3 Issues of PSTCL(Agenda by PSTCL)

3.4.3.1 Multisite link issue: Due to non functioning of multisite functionality, data is being transferred through ICCP. PGCIL may take up the matter with M/s Siemens Ltd. for its early solution.

3.4.3.2 Third party Security audit of SCADA/EMS:

Third Party Security audit of SCADA/EMS planned for the month of May 2017 is still pending. PGCIL is may take up the matter with M/s Siemens for conducting the same.

3.4.3.3 EMS training schedule: Latest schedule for EMS training at SLDC Patiala is

still awaited. PGCIL may arrange the training at earliest.

3.4.4 Pending SCADA issues of UPPTCL( Agenda by UPPTCL)

3.4.4.1 UPPTCL informed the following major problems to be resolved by M/s Siemens persist since long:

i. Testing of Multisite functionalities including complete switchover of Main&

Backup SLDC. ii. Switchover to NMS 2 is not taking place since shifting of Main SLDC from

Shakti Bhawan to New SLDC building at Gomti nagar. iii. Commissioning of PDS is due. iv. Functioning of EMS is pending in OTS & its consoles. v. Non-submission of analysis reports of various incidents. vi. Frequent Core Dump on various servers at main & backup SLDCs. vii. Action on various problems written in defect register from Nov’16 to April’ 17

are still pending. Even timely acknowledgement of problems written in defect register is not done by Siemens site engineers.

viii. Non-attending of various issues reported since November’16 to February’17. ix. Automatic transfer of historical data from Main to Backup SLDC & vice versa

is not taking place after restoration of Multisite even if the failure is for short duration. Process of manual transfer given by M/s Siemens is also not useful for transfer of large data.

x. Proper procedure has not been developed by M/s Siemens for registering / lodging complaints. During meeting with Siemens on 23-05-2017, it was

Page 17 of 21

informed that it is in implementation stage at NRLDC and will be ready for other constituents within 15-20 days but it is still pending.

xi. Site engineers of Siemens often do not get ample & timely support form Back office team. Moreover, there are not sufficient manpower at back office to give timely support to site engineers due to which problems remain pending for long time.

xii. Events/messages recorded at Main & Backup SLDC are not matching even when multisite communication link is available.

xiii. SOE of same day taken on different dates shows number of discrepancies. SOE of Main SLDC for 30-04-2017 taken on 1st, 2nd and 3rd

xiv. Archive message of same day taken on different dates are also different. This issue has also been raised during 83

May’17 has been emailed to Siemens on 03-05-2017 but response/action from Siemens is still pending.

rd

xv. When suspected data is replaced in SCADA, the status of same shows O.k in eDNA report instead of replaced status. This issue was raised in 10

MRM but Siemens response is still awaited.

th TeST meeting as well as in 83rd

xvi. Historical Data (Values as well as message) for data before 20-04-2017 is unavailable at backup SLDC Modipuram.

MRM but problem is still unresolved.

xvii. Transfer of Historical data on Tape and its replay at Main/Backup SLDC is still pending/not demonstrated by Siemens.

xviii. Following problems of backup SLDC reported to Siemens several times are still unattended.

xix. Non Working of DG set in Auto Mode xx. Non Working of Insight Power Management software on UPS console. xxi. Replacement of damaged doors of server racks and E-shape table. xxii. Maintenance of defective Router at Sub-LDC Panki, Terminal Server at Lko. xxiii. Following EMS Application are not running since beginning and no support

has been provided by Siemens in running these applications.

a) Security Analysis b) Security Dispatch c) Transmission Corridor Monitoring d) Load Foreasting

3.4.5 Delay in Database Synchronization between Constituents: (Agenda by

UPPTCL)

a) Problems in Synchronization of Network map have been observed every time and Network map display is still not in synchronism with NRLDC.

b) Synchronization with NRLDC/Constituents is yet to be done regularly on monthly basis.

Page 18 of 21

3.4.6 Time mismatch observed in SOE ( Agenda by RVPNL):

RVPNL informed about time mismatch, observed in SOE generated in the SCADA system for incidence of complete outage of Kawai-Kalisindh-Chhabra complex in Rajasthan on dated 20th May-2017 (20.06 Hrs.) for 765 KV GSS Phagi and 765 KV GSS Anta.

Members may deliberate technical reasons for this incident.

4.1 Present Status of Telemetry (Agenda by NRLDC):

4.1.1 Non-Availability / Reliability of Telemetry

The new stations at 400 kV are being integrated in the system. Though the telemetry integration is ensured before charging the new element, the reliability of telemetry is not at all ensured. The reliability of telemetry of the following stations are very poor :

400 kV Hapur 400 kV Chitorgarh 400 kV Chabra 400 kV Banauli

400 kV Muradnagar(N) 400 kV Talwandi Saboo

400 kV Bawana CCGT 400 kV Srinagar

400 kV Nathore 400 kV Muktshar 400 kV Kashipur 400 kV Uri

400 kV Mathura 400 kV Nakodar 400 kV Rishikesh 400 kV Fatehabad

400 kV Karcham Wangto 400 kV Parvati – II 400 kV Parvati - III

Reliability of telemetry for some of the stations are poor since its integration. Member may discuss the issues and action plan for restoration of reliability.

4.1.2 The problem in the RTU / SAS gateway (Agenda by NRLDC):

It has been observed that though the communication has been provided, redundant ports are not available in the following stations leading to non-availability of real time data in case of one channel failure:

Station Status Kanpur 765 Port faulty Bhiwadi(PG) Port faulty Saharanpur Port faulty

Manasar Port faulty Koldam Port not available Rampur Port not available

4. Telemetry Related Issues

Page 19 of 21

RAPP-A Port not available

Kurushetra Automatic failover not Available

RAPP-C Port not available

Concerned Utilities may give action plan for restoration / provision of the port for reliable communication.

4.1.3 Telemetry of digital status (Agenda by NRLDC):

The importance of correct Digital telemetry was discussed in all the TeST sub-committee meeting and it is observed that there is no improvement in this regard. It is was decided in 10th

TeST Sub-committee meeting that the constituent will furnish the availability status of 220 kV and above stations and improvement there of.

Members may furnish the status of digital data telemetry of the stations for and the same may be discussed for further improvement.

4.1.4 ICCP communication between PTCUL and NRLDC(Agenda by NRLDC): ICCP communication link between PTCUL and NRLDC is highly non-reliable and there is outage of days together. Till time Fibre optic connectivity is established alternate channel may be arranged at the earliest.

4.2 Telemetry issues (Agenda by UPPTCL): 4.2.1 It has been noticed over the time that there have been co-ordination issues with

POWERGRID in reference to calcheck data accessed from POWERGRID substations. The errors/inaccuracies observed in telemetry data obtained from substations of POWERGRID persist for long although regular requests are made to address the same.

4.2.2 The inaccuracy/ mismatch (in SCADA Vs SEM) for the following calcheck points of UP State was reported in past months but problems at POWERGRID ends are yet to be resolved.

i) 400 /220 kv Allahabad PG ICT -III ii) 400 /220 kv Bhagpath PG ICT –I iii) 400 kv Mainpuri PG Parichha iv) 400 kv Kanpur PG Orai

A nodal officer from POWERGRID may be nominated for better co-ordination. 4.2.3 Non-availability/inaccuracy in real time SCADA data with SEM at 400 KV

Madhura s/s .NRLDC is requested to resolve the problem of SCADA data mismatch with SEM and restore accuracy of telemetry data.

Page 20 of 21

5.1 URTDSM Project Status (Agenda by POWERGRID)

Materials has been dispatched for 5 control centres under URTDSM Project and for balance control centres it will be dispatched by June month end. All the Constituents should ensure space for installation of Servers in SLDC control rooms and availability of manpower to implement the Project before target date, Dec, 2017.

5.2 Constraints for URTDSM project (Agenda by POWERGRID): 5.2.1 Shutdown required for CT/PT termination at various station under URTDSM

Project

POWERGRID is installing PMUs at various sub-stations of central and state sector. For commissioning of PMUs at site, CT/PT and DI termination is required for existing CR panels. CT/PT termination for most of the stations has been done in live line condition. However some of the stations specially generating units of NTPC and UPRVUNL are insisting for shutdown for CT/PT termination.

After discussion with NRLDC for shutdown, vendor has been deployed 4 times at Obra-BTPS and 3 times at Singrauli station, however at last moment shutdown could not be allowed citing grid related issues. Now vendor is very reluctant to visit again at site citing shutdown issues and commissioning also hampered due to this. In each sub-station 30-30 min. shutdown is needed for each of the feeder for CT/PT connections.

Members may discuss.

5.2.2 Space for installation of PDC under URTDSM Project at PTCUL(Agenda by

POWERGRID):

PTCUL is yet to provide space for installation of PDS / PDC at SLDC Dehradun. PDS Materials were dispatched to Dehradun in Feb’16, However, PTCUL officials did not take delivery of PDS materials even the matter was discussed during 7th

PTCUL may ensure space for PDC at site.

TeST meeting, now PDS is temporarily stored at Dehradun sub-station of POWERGRID and FAT for PDC is going on and PDC will be dispatched in July’ 2017.

5.3 Latest update on URTDSM: (Agenda by PSTCL)

As per original schedule conveyed by POWERGRID, URTDSM project for supply/installation/commissioning of 3 no. PMU’s was scheduled to be completed by Mar/April 2017, and accordingly the same was conveyed to Punjab State Electricity Regulatory Commission (PSERC), but, works are still pending for completion at SLDC control centre, Ablowal. As per latest updates received from

5. Unified Real Time Dynamic State Measurement (URTDSM) Scheme.

Page 21 of 21

POWERGRID, FAT for PDC was scheduled on 10.04.2017 but, as mentioned above, control centre activities are still pending. POWERGRID may provide latest status of this project, so that PSERC may be intimated about the same.

5.4 URTDSM Communication issues: (Agenda by UPPTCL)

PMUs at some location in UP have been installed and requested POWERGRID to provide details of communication routes & availability status and connectivity to servers at SLDC Lko., so that monitoring of communication routes may be done and bottleneck, if any, may be removed before commissioning of URTDSM project. POWERGRID may update.

5.5 BBMB URTDSM ISSUES ( Agenda by BBMB):

In the 10th

POWERGRID may give a firm schedule for supply and commissioning of UPS at BBMB SLDC.

meeting of TeST, POWERGRID representative informed that FAT of PDC is scheduled in April, 17 and the delivery is expected to be done in May, 2017. However, no equipment has been received at BBMB SLDC so far. It is also brought out that the URTDSM equipment cannot be installed at BBMB SLDC, until the commissioning of new UPS to be supplied at BBMB SLDC is completed.

POWERGRID may also provide activity wise PERT chart of all the activities to be carried out at BBMB SLDC under URTDSM Project so that the activities can be planned properly.