pacs iqr estec 13 january 2005 mech qual status 1 pacs iqr mechanical qualification status and plans...
TRANSCRIPT
Mech Qual Status 1
PACS IQR ESTEC 13 January 2005
PACS IQR
Mechanical Qualification Status and Plans for PFM
Reinhard KatterloherR. Graue, D. Kampf, R. Hofferbert, M.
v.Berg
Mech Qual Status 2
PACS IQR ESTEC 13 January 2005
Overview Mechanical Qualification Status and Plans for PFM
• FPU structure - mirrors - baffles - black paint - impact of additional heaters and flashers
• Filter wheels• Calibration sources• Grating assembly• Chopper• WE units• Delta Cryovibration Qualification Matrix• (PhFPU presented by LR)• (Ge:Ga arrays presented by JS)
Mech Qual Status 3
PACS IQR ESTEC 13 January 2005
FPU structure, mirrors, baffles: main data
• Total mass allocation in IID-A for PACS is 140 kg,mass requirement is met (margin 13.2 kg), FPU CQM has 74.1 kg
• Eigenmodes of complete FPU above 100 Hz,requirement is met for all axes (x,y,z = 188,122,104 Hz)verified by cryogenic vibration of FPU STM
• Mirror environmental tests OK, Au coating no concern (initial NCR closed), optical alignment check/stability on FPU CQM not done,after FPU STM cryo-vibration dummies mechanically checked
• Baffles structural OK
• Upgrades for PFM: none, except- additional baffles required to reduce stray light inside the FPU spectrometer section (see presentation by AP),- modification of detector baffles to carry flashers for curing
Mech Qual Status 4
PACS IQR ESTEC 13 January 2005
PACS FPU Architecture – 6 Stand Alone Modular Substructures
Top Optics with Chopper (C.Z.) and 2 Calibration Sources
Image Slicer
Bolometer Optics with Filter Wheel
PhFPU with 0.3 K Cryo-Cooler (CEA)
Collimator with Grating Assembly (CSL)
Spectrometer with Ge:Ga – Photoconductor Arrays (MPE), Filter Wheels, Distribution Boards (Cold Electronics)
Level 0 Thermal Links -
Thermal Feed Throughs (1.7 K)
Mech Qual Status 5
PACS IQR ESTEC 13 January 2005
FPU Analyses
Physical Analyses Optical Analyses Thermal
Analyses Mechanisms
Analyses Structural Analyses
Tolerancing Analyses/ Budgets
Straylight Analysis
Strength Analysis
Deformation/ Distortion Analysis
Load Analysis
Ray Tracing ,
Spot Diagram Quasi Static
Analysis Functional Analysis
Natural Modes Analysis
Mass Properties Analysis
All FPU Analyses Performed
Mech Qual Status 6
PACS IQR ESTEC 13 January 2005
PACS FPU Structural Verification
Reduced Functional Test
Functional Test(LHe)
Vibration Test - tbc(LHe)
Ambient VibrationTest (Qualification )
Physical Measurement
Functional Tests
Prel. OpticalPerformance Tests *
CQM
Vibration Test(LHe - tbc)
Vibration Test(ambient)
Physical Measurement
Mass / StructuralDummy
Reduced Functional Test
Functional Test(LHe)
Cold Vibration Test
Ambient VibrationTest (Acceptance)
Physical Measurement
Functional Tests
Prel. OpticalPerformance Tests *
PFM
Reduced Functional Test
Functional Tests(LHe)
Ambient VibrationTest (Acceptance)
Physical Measurement
Functional Tests
Prel. OpticalPerformance Tests *
FS
F PF PU Test Pro g ra m
Tests completed
Similarity• CQM and STM were
manufactured parallel with the same drawingsout of the same lot
Qualification Tests• STM vibration tests
Conclusion: FPFPU Housing is structurally qualified
Tests completed
LHe-VibrationVibration res.src.
Mech Qual Status 7
PACS IQR ESTEC 13 January 2005
FPU Cryovibration Qualification Breakdown
FPFPU QualifikationKT Units
Filter Wheels(Bolometer andSpectrometer #)
DistributionBoards (Blue and Red)
2K Therm Strap #FPFPU
SuspensionFPFPU
HousingDet Suspension #
Similar to CQM
Qualification TestsComplete
Housing Qualified
Similar to CQM
Qualification TestsComplete
Suspension Qualified
Similar to CQM
Qualification TestsComplete
Filter WheelsQualified #
Similar to CQM
Qualification TestsComplete
Distribution BoardsQualified
CQM
Qualification TestsComplete
CQM
Detector Suspension Qualfiied #
CalibrationSource
Similar to CQM
Qualification TestsComplete
Calibration SourceQualified
2K StrapsQualified #
All Items Qualified# means remaining problems to be solved resp. delta-vibration to be
done
Mech Qual Status 8
PACS IQR ESTEC 13 January 2005
Structural Analyses - Status
Evaluation of ambient (STM) and cold vibration tests (Cryo STM) FEM calibration Load analyses with calibrated model (cryo-vibration test) Strength analyses for FPU metallic and CFRP components Cryogenic material properties analyses CoG, MoI analyses Displacement, distortion, deformation analyses
All Documentation released
Mech Qual Status 9
PACS IQR ESTEC 13 January 2005
Approach to FPU PFM Cryovibration
• Protection of sensitive subsystems during acceptance vibration,random loads not to exceed 10 g rms
• Dynamic analysis of PACS on CSL shaker performed by ESA- response of red and blue bolometer FPA and their relation with a point on the outside of PhFPU housing determined- mounting of a triplet-accelerometer foreseen
• Frequencies and Q-values are to be checked during warm FPU-STM vibration at MPE
• Notching at the PACS feet during PFM cryovibration at CSL
Mech Qual Status 10
PACS IQR ESTEC 13 January 2005
FPU PFM Test Plan and PFM MAIV Status• Subsystem level (FW, CS, DBs, Substructures)
– Mechanical and Thermal Test program as given in Test Plan (similar to CQM)
– Outbaking at 80 °C (minimum)
– Functional test program as given in test plan (similar to CQM)
– Substructures alignment verification -Cryogenic stability tests (tbc)• System level (FPU)
– Cryovibration test (KT support at CSL)
– Functional test (KT support at MPE)
MAIV Status Metallic items manufactured CFRP items manufactured and static load tested Calibration Sources manufactured and partly assembled FW assemblies manufactured, pre-tested on motor drive level, partly
assembled Pre-assembly (fit check in progress)
Mech Qual Status 11
PACS IQR ESTEC 13 January 2005
FPU Black Paint: main data of KT72
• PACS-RFW-0003 agreed: out-gassing requirements met• Optical performance: satisfying• Adhesion on Al surfaces: satisfying• Particle release below 100ppm, improvement advised:
impact of pre-vibration under investigation, additional cryogenic vibration planned in February 2005,CEA: concerned about particle fall-out onto bolometer FPAs,MPE: protection of grating/FW bearings might be advisable
• Upgrade for PFM: very likely none
Mech Qual Status 12
PACS IQR ESTEC 13 January 2005
Impact of additional Heaters and Flashers
• 2 heater resistors on the red detector array: mass increase 0.2% > no impact on mechanical behaviour
• 2 flashers mounted at the end of each detector array baffle:mass increase few % > no impact on mechanical behaviour
• Additional wiring inside the FPU required (mass negligible)• Re-routing on both distribution boards required (redesign)
mass increase on one board due to a new connector> no impact on structural properties expected
For detector curing PACS needs to implement additional heaters and flashers in the FPU. The impact on the mechanical properties of both detector arrays (Upgrade for PFM) is estimated as follows (detailed design in progress):
Mech Qual Status 13
PACS IQR ESTEC 13 January 2005
FPU Filter Wheels
• Photometer FW : OK (initial blocking by a screw resolved)• Spectrometer FW problematic:
- during CQM ILT blocked at 4K - during warm-up partial movement at 90K
• Currently investigations on CQM wheel at KT in progress:- at 77K higher friction observed- ball bearing sensitive to abrasion during warm vibration?- baffle removed for better inspection of drive - blocking of rotor on one Hall sensor found- new cryogenic verification test planned
• Upgrade for PFM: revised tolerance of bearing support
Mech Qual Status 14
PACS IQR ESTEC 13 January 2005
Filter Wheel Assembly
Required Torque to Leave the Filter Position : 0.5 Ncm
Maximum Motor Torque Performance : 4.2 Ncm.
Motor & Position Indicator are in Powerless Dormitory Mode between Operations
Position Locking Principle: Contact-less Magnetic System
No Launch Lock Mechanism Required
Mech Qual Status 15
PACS IQR ESTEC 13 January 2005
FPU Calibration Sources
• Cryogenic qualification on EM during FPU STM vibration
• Upgrade for PFM: None
Mech Qual Status 16
PACS IQR ESTEC 13 January 2005
Calibration Source Lay-out
Wavelength/scattering optimised surfaces
• 2 identical Calibration Sources mounted in FPU
• Operation at 4 K, Emitter temperature 50 - 100 K
Sphere (inner diameter 51 mm) Redundant Combined Sensor and Emitter (PT 500) Circular aperture (diameter 12 mm) with Si lens put in front of aperture Surface with Lambertian stray light behaviour and high reflectivity (> 0.992) Emitter suspension:
4 filigree GFRP struts with 24 x 0.25 x 0.25 mm³ Titanium coated for 4 wire connection to the source
Mech Qual Status 17
PACS IQR ESTEC 13 January 2005
FPU Grating Assembly
• Cryogenic vibration qualification on EM plus additional qualification (vibration, cryo-cycling) on CQM incl. launch lock mechanism at subsystem level: OK
• Movement quality of grating CQM: OK• Functionality of launch lock mechanism of CQM: OK
• Upgrades for PFM:- modified routing of internal harness needed- Inductosyn transformer needs to be mounted inside the grating assembly (for CQM currently on FPU outside)- Fixation of grating plate on axis has to be improved- cleanliness before delivery for integration with FPU to be improved and protection cover advised
Mech Qual Status 18
PACS IQR ESTEC 13 January 2005
FPU Chopper
• Development performed as specified in IHDR presentation(environmental tests, lifetime test …)
• Minor deviations for CQM:- envelope violation of cable housing (solved)- cryovibration done on subunit level at 77K only (agreed) (no LHe vibration with CQM performed)
• Upgrades for PFM:- no deviation from MPIA/ZEISS development plan foreseen- Au coating of mirror very likely to be changed (thickness and coating process to be improved)
Mech Qual Status 19
PACS IQR ESTEC 13 January 2005
WE Units• AVM / STM WE Unit testing
- No structural tests required in general- STM BOLC: Vibration tests done : validation of design > Problem with displacement of boards- STM BOLC PSU sub-unit vibrational tested : OK
• CQM / AVM ILT- No structural test on WE Units foreseen
• PFM (QM) WE Units- Full environ. test program agreed before FM delivery to MPE- First structural results for QM SPU available (> some NCRs)- New mechanical design for DPU CFM / PFM, will be fully tested
• Mass margin for PACS is 13.2 kg in total (DECMEC mass uncertainty not critical in this respect)
Mech Qual Status 20
PACS IQR ESTEC 13 January 2005
Delta Cryo-vibration Qualification Matrix of FPU Subunits
ILT phase
AVM CQM PFM FS
FPU STM CQM PFM CQM refurb.
DPU AVM AVM PFM QM
SPU AVM AVM PFM EM
DECMEC AVM EM PFM QM+
BOLC BOLCSIM QM1 (QM2) PFM
QM2
WIH AVM AVM PFM QM
EGSE ILT ILT ILT ILT
FPU Subunit Delta cryo- vibration
qualification
Scheduled
PhFPU(bolom.+cooler)
Done(upgraded STM)
October 04
Ge:Ga-array internal cooling link with I/Fs
Open(STM housing + FM components)
March 05
Ge:Ga-array suspension strut electr. insulation
Open(STM housing + FM components)
March 05
Grating assembly CQM incl. L Lock
Done(CQM)
February 04
Unchanged Development Concept & Model Philosophy since IHDRApproval of PACS-RFW-0007 expected !