Citrus & Banana Packhouse Projects 2014-2016
by SP de Beer
African Realty Trust Pty Ltd
Pack House Equipment 2014Before
Pack House Equipment 2014After
Additional Class 2 Line 2014
Chem-free
Packhouse Building• Before • After
Carton Store• Before • After
Electricity• Before • After
Fruit trailers 2014• Before • After
Pre-grade 2016• Before • After
Palletising
Banana Packhouse 2014• Before • After
Banana Packhouse 2014• Before • After
Water Purification 2014Before After
Coffee break
Accomplishments with completed projects
• Cost savings on wax and chemicals• Wax & Chemicals: 10.8% due to better grading before
the chemical bath and wax• 0n 30 trailers p/h we are running the packhouse 40%
slower than the previous season which means more time for better grading
• New Palletising:• Eliminates all bottle-necks – directly from line to
dispatch• No more traffic of forklifts between palletising stations,
pack line and workers• Created more space for folded cartons