Page 1: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 01

• A Block – Seventeenth Floor Pour 1 reinforcement & Pour 2 shuttering in progress.5th Floor Block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 2: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 02

• A Block – Seventeenth Floor Pour 1 reinforcement & Pour 2 shuttering in progress.5th Floor Block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 3: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 03

• A Block – Seventeenth Floor Pour 1 reinforcement & Pour 2 shuttering in progress.5th Floor Block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 4: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 04

• B Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 5: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 05

• B Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 6: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 06

• B Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 7: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 07

• B Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 8: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 08

• C Block – Thirteenth Floor Pour 3 checking, Fourteenth floor pour 1 shuttering in progress.5th floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 9: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 09

• C Block – Thirteenth Floor Pour 3 checking, Fourteenth floor pour 1 shuttering in progress.5th floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 10: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 10

• C Block – Thirteenth Floor Pour 3 checking, Fourteenth floor pour 1 shuttering in progress.5th floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 11: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 11

• C Block – Thirteenth Floor Pour 3 checking, Fourteenth floor pour 1 shuttering in progress.5th floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 12: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 12

• D Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 13: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 13

• D Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 14: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Position - 14

• D Block – Terrace floor pour 1 reinforcement & Pour 2 shuttering in progress. 5th Floor block work in progress.

Key Plan

11

233

55

6666

77

8

101010

9911

13

12

1414

444

Page 15: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 16: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 17: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 18: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 19: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 20: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 21: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 22: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• External Block work in progress.

Page 23: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• Internal Door frame fixing & Conduiting in progress.

Page 24: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• Internal Duct Block Work in Progress.

Page 25: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• Internal Door frame fixing in progress.

Page 26: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• Internal lobby Block work in progress.

Page 27: Pacifica aurum    Phase I Construction Photo

AURUM_Photo Report - Phase 01

Comments :

Phase 01 – Monthly Photo report Block Work

• Internal Toilet Block work in progress.