AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS – Photo Report
• Key Plan showing the Camera positions , Click on the Icon to review respective status:
12
3
4
5
6
7
8
9
10 1112 13 14
15
1617
18
19
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 01
• Package I – Filling work in progress.
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 02
• Package I – Filling work in progress.
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 03
• Package I – Filling work in progress.
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 04
• Package I – Filling work in progress.
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 05
• Package I – Filling & Piling work in progress.
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 06
• LEFT – Package II terrace slab & block work activities going on
• RIGHT – Package I first floor column & slab activities going on
Key Plan
12
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 07
• Package II – terrace slab, headroom and block work activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 08
• Package I – Block work, First floor column and Terrace slab activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 09
• LEFT – Package I Block work and Terrace slab activities going on
• RIGHT – Package II Block work and OHT activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 10
• Package II – Pile cap, plinth beam, Ground and first floor roof slab activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 11
• Package II – Pile cap, plinth beam, Ground and first floor roof slab activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 12
• Package II –Ground and first floor roof slab activities going on
Key Plan
7
8
9
10 1112
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 13
• Package II – Pile cap, plinth beam, Ground and first floor roof slab activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 14
• Package II – Piling activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 15
• Package II – Piling activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 16
• Package II – Piling activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 17
• Package II – Piling & pile cap activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 18
• Package II – Piling activities going on
Key Plan
13 1415
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS More Views
• .
VIEW FROM PACKAGE_01 FILLING AREA EAST SIDE VIEW
SOUTH-EAST SIDE VIEW WEST SIDE VIEW
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS More Views
• .
GROUND ROOF & 1ST FLOOR COLUMN IN PACKAGE 01 PLINTH BEAM & GROUNDFLOOR COLUMN IN PACKAGE 01
PLINTH BEAM & GROUNDFLOOR COLUMN IN PACKAGE 02 ROOF SLAB CONCRETING IN PACKAGE 02
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS More Views
• A1 West Villa #203 (Inside View)
FRONT ELEVATION ENTRANCE FOYER
LIVING AREA KITCHEN, DINING & UTILITY
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS More Views
• A1 West Villa #203 (Inside View)
GROUND FLOOR BEDROOM ACCESS TO FIRST FLOOR
FIRST FLOOR BEDROOM FIRST FLOOR TOILET
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS More Views
• A1 West Villa #203 (Inside View)
PRIVATE TERRACE FIRST FLOOR BEDROOM
ACCESS TO TERRACE OPEN TERRACE