p3o® workbook€¦ · a decision‐enabling and support business model for all business change...

103
The Knowledge Academy P3O® WORKBOOK

Upload: others

Post on 30-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

  The Knowledge Academy 

P3O® WORKBOOK

Page 2: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

Instructions to Follow 

Please follow the below Instructions before reading this workbook: 

1. Open workbook in Adobe Reader or any other pdf reader

2. Write your answer and Save the pdf by pressing Ctrl+S

3. Upload this workgroup at the time you request for the exam

Page 3: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

Contents 

Overview .................................................................................. 3 

Why Have a P3O®? ................................................................. 10 

Case Study: P3O® Pilot ........................................................... 19 

Designing a P3O® Model ........................................................ 20 

Implement and Re‐energise................................................... 44 

Case Study: No Skeletons in the Cupboard at BT Design ...... 59 

How to Operate a P3O® ......................................................... 60 

Roles ....................................................................................... 72 

Case Study: Skipton Building Society ..................................... 89 

Glossary of Terms and Definitions ......................................... 96 

Page 4: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

3  

Overview Definitions 

PPM Portfolio, Programme, and Project Management (also including value and risk 

management). 

Portfolio The totality of an organisation’s investment (or segment thereof) in the changes required to 

achieve its strategic objectives. 

Programme A temporary, flexible organisation structure created to coordinate, direct, and oversee the 

implementation of a set of related projects and activities in order to deliver outcomes and 

benefits related to the organisation’s strategic objectives. 

Project A temporary organisation that is created for the purpose of delivering one or more business 

products to an agreed business case. 

Portfolio Management A coordinated collection of strategic processes and decisions that, together, enable the 

most effective balance of organisational change and business as usual. 

Project Management The planning, delegating, monitoring, and control of all aspects of the project, and the 

motivation of those involved, to achieve the project objectives within the expected 

performance targets for time, cost, quality, scope, benefits, and risk. 

 

What is a P3O®? 

A decision‐enabling and support business model for all business change within an 

organisation.  

This includes single or virtual structures, i.e. offices (permanent and/or temporary), 

providing a mix of central and localised functions and services, and integration with 

governance arrangement and the wider business such as other corporate support functions. 

The elements that make up P3O®: 

Organisation Portfolio Office 

Hub Portfolio Office 

Programme Office 

Project Office 

Centre of Excellence 

Page 5: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

4  

 

 

 

 

 

 

 

          

An example of a P3O® Model Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Key Functional Areas of P3O® 

The three main functional areas of P3O® require different competencies, skills, and 

experience: 

 

1. Strategic planning or portfolio support – focusing on supporting senior management 

decision‐making. This includes the continuous portfolio definition practices of 

understand, categorise, prioritise, balance and plan, management dashboards, and 

most importantly the provision of challenge, scrutiny, and oversight. 

 

2. Tactical or delivery support – focusing on hands‐on support to the successful delivery 

of change, sometimes through a flexible pool of delivery programme and project 

resources to enable fast mobilisation. 

 

3. Centre of excellence or capability support – focusing on the development of 

standard processes, promoting consistent portfolio, programme, and project 

working practices. This ensures that their adoption of the programme and project’s 

environment, size, complexity, importance, capability, and risk.  

Page 6: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

Exercise

In the pyramid illustrated below, assign where portfolios, programmes, and projects sit in 

relation to one‐another. 

Fill in the blanks regarding the differences between portfolio, programme, 

and project management (answers on next page) 

1. ________ management is just the management of an individual, standalone project

2. A project is usually part of a ___________, but a ___________ cannot be part of a

project

3. Programme management is the management of several ________, directly

addressing how they are managed themselves

4. __________ deliver strategies, whereas projects will be strategy‐driven

5. _________ are made up of programmes

6. Portfolio management determines the priorities of the ___________

Page 7: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

6  

Project management is just the management of an individual, standalone project 

A project is usually part of a programme, but a programme cannot be part of a 

project 

Programme management is the management of several projects, directly addressing 

how they are managed themselves 

Programmes deliver strategies, whereas projects will be strategy‐driven 

Portfolios are made up of programmes 

Portfolio management determines the priorities of the programmes 

 

Business as Usual The way a business normally achieves its objectives. 

 

‘Run the business, Change the business’ Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

 

 

 

 

 

 

Organisational Context 

An effective P3O® can increase an organisation’s chance of successfully delivering on its 

strategic objectives by maximising benefits realised from its continued investment in 

business change programmes and projects. 

It maintains a ‘big picture’ understanding of the business change portfolio 

Provides decision support to ensure the right programmes and projects are launched 

Provides standards and processes to ensure a consistent delivery 

Delivers an independent oversight, scrutiny, and challenge, to ensure things are 

done correctly 

Assistance in the building of a competent workforce capable of first‐class 

programme and project delivery 

Page 8: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

7  

Improving upon organisational accountability, decision‐making, transparency, and 

visibility 

Protecting revenue and spend 

Executing change more effectively and efficiently to improve programme and project 

delivery 

Defending reputation and stakeholder confidence 

Without the involvement of an effective P3O® model, organisational strategic objectives 

may still be reached, but potentially in a fragmented or unstructured way.  

This, therefore, could have an adverse effect on expected outcomes and generate a 

significant threat to any already scarce resources. 

 

P3O® Model elements aligned with portfolio, programme, and project lifecycles 

Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Page 9: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

8  

Structures of Portfolio 

There are five types of ‘model’ in P3O® that describe the way, in both structure and nature, 

how offices and their functions can be organised. 

1. Organisation Portfolio Office Model – A single, permanent organisation level 

portfolio office, focused on strategic portfolio support, planning, delivery support, 

and COE functions, with temporary programme and project offices set up to support 

new initiatives as they are launched. 

 

2. Hub and Spoke Model – Large organisation model with multiple de‐centralised 

permanent portfolio offices designed to serve specific divisions, geographical 

regions, business units, departments, or functions. 

 

3. Temporary Office Model – No permanent office exists, temporary programme and 

project offices (or individuals with support skills) are set up as new initiatives are 

launched. 

 

4. Virtual Office Model – No physical central office. Business or functional units carry 

out P3O® functions across the organisation. 

 

5. Small Organisation Model – Very small office, or a single individual. Usually focused 

on consistency of methods/training etc. 

 

Quiz 

 

1. There are five key functional areas of P3O®.  

A. True B. False 

 

2. What is a portfolio? 

 

A. A decision‐enabling and support business model for all business 

change within an organisation 

B. A temporary organisation that is created for the purpose of delivering 

one or more business products to an agreed business case 

C. The totality of an organisation’s investment (or segment thereof) in 

the changes required to achieve its strategic objectives 

Page 10: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

9  

D. A coordinated collection of strategic processes and decisions that, together, enable the most effective balance of organisational change 

and business as usual 

 

3. The Organisation Portfolio Office Model is… 

 

A. A very small office, or a single individual 

B. A single, permanent organisation 

C. A large organisation D. None of the above 

 

4. A programme’s lifecycle is comprised of… 

 

A. Identify, Define, Deliver Capability/Realise Benefits, Close B. Define, Deliver Capability, Identify, Realise Benefits C. Define, Realise Benefits/Deliver Capability, Initiation, Close D. Start‐up, Identify, Initiation, Realise Benefits 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

B, C, B, A 

Page 11: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

10  

Why Have a P3O®? Any policies and performance requirements of an organisation are typically realised via 

portfolios, programmes, projects, and operational business units. 

An integrated set of outcomes and benefits are measured, managed, monitored, and 

refined to ensure that optimal investment and strategic goals are achieved. 

 

Benefits of a P3O® 

A strong visibility of progress 

 

Predictability of delivery 

 

‘Big picture’ view 

 

A consistency to approach and delivery 

 

Decision‐making transparency 

 

How Do P3O®s Add Value? 

By adding an appropriate P3O® model in an organisation, it will optimise and improve the 

delivery and implementation of business change. 

An ideal P3O® will be able to operate and deliver the right services within an organisation’s 

matrix structure. This will ensure that programmes and projects can coexist with existing 

permanent functions. 

A compelling business case must be presented to senior managers and other senior‐level 

support in order to approve the venture.  

Any potentially realised benefits will need to be fully understood as well as an estimation of 

costs. 

Any P3O® model worth its weight should be able to answer the questions ‘What value will it 

add to the organisation?’ and ‘How will it work?’ with special consideration to 

organisational and business divisional boundaries. 

The agreement of the P3O®’s vision, operating model, and transition plan is integral to any 

sort of sustained success it will yield.  

Careful management is necessary in order for the P3O® to deliver value after it has been 

implemented and established. 

Change management is a vital part of a successful implementation. This change will be 

widespread, though, and will affect multiple stakeholder groups. 

Page 12: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

11  

It is recommended that the implementation is run as a programme, with the appropriate 

best‐practice management and governance in place.  

However, some organisations may have to limit the change to a small, single office. In which 

case, the P3O® design and implementation phases will be managed as a project. 

It is important to effectively engage with stakeholders, communicate well, and keep an eye 

on benefits.  

A decent understanding of any problems that may arise, and opportunities intended to 

realise, would also be advantageous. 

 

Governance Focus 

Business Change Strategy 

Business Change Design 

Business Change Delivery 

Business Change Value 

 

Governance requirements, and the way in which the governance is supported and enabled, 

will fluctuate depending on the organisation. An ideal P3O® will fulfil all of these 

requirements. 

Page 13: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

12  

Business change governance support and enablement Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

The P3O® can add real value to any senior management decision‐making and governance 

capability if it: 

Is an appropriate model for the organisation 

 

Is adequately resourced 

 

Interfaces with decision‐making bodies 

 

Has services aligned with other service providers within the organisation, such as 

finance, procurement, or audit 

 

 

 

Page 14: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

13 

Best Management Principles for extracting value from programme 

and project investment: 

Govern effectively – How P3O®s can help 

Providing support to Senior Responsible Owner and senior management

Ensuring risks, issues, and changes are escalated to the right decision‐making

authority

Making sure complete, timely, and accurate data is collected at source so that

analysis and amalgamation enables quality decision‐making

Hold people to account – How P3O®s can help 

Providing the Senior Responsible Owner and senior managers with decision‐making

support

Ensuring that the right decisions are escalated to the right people, with relevant

information to support the decision‐making process

Providing standard role descriptions and terms of reference for the boards

Providing support, coaching, and training for all roles available

Prioritise investment, align and adjust to business strategy – How P3O®s can 

help 

Maintaining a register of all programmes and projects within the portfolio, including

any ideas in the pipeline

Facilitate and support pre‐programme and project scoping workshops

Support risk identification workshops

Providing a fast‐track mobilisation service to programmes and projects

Supporting feedback from programmes and projects to strategy

Safeguard value – How P3O®s can help 

Supporting the business‐case process

Providing a benefits tracking service to business owners

Page 15: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

14  

Ensuring benefits are not double‐counted and that the measurement process is 

robust and usable 

 

Helping to get more value via benefits from investment across programmes and 

projects 

Invest in people and process – How P3O®s can help 

Developing tailored approaches based on Best Management Practice approaches 

and ensuring that they are easily accessible to everybody in the PPM community 

 

Developing training, coaching, and mentoring approaches for all roles within the 

PPM environment 

 

Advising on skills and capability assessments 

Track progress through highlight and exception‐based reporting – How P3O®s 

can help 

Providing timely reporting and exception management service from project to 

portfolio level 

 

Developing management dashboards that engage and focus senior management on 

the key risks and matters that affect the delivery of the portfolio 

 

Making sure that the data collection process operates proficiently and effectively 

 

 

 

 

 

 

 

 

 

 

Page 16: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

15  

Exercise 

List as many benefits for a P3O® as you can. 

Investment for the P3O® 

 

Identifying the Stakeholders 

It is essential to identify and engage with your stakeholders, especially in regards to a 

programme that could affect many of them. 

Senior managers who will benefit from the change should be identified and engaged 

immediately.  

They will need to buy into the benefits that they will receive and use their influence to drive 

the change forward. 

Another critical success factor is the nomination of a P3O® sponsor, making sure they are a 

senior manager with authority, influence, and charisma.  

This person must embody the P3O® vision and ensure organisational commitment at all 

levels. 

 

Identifying the Problem 

The success of a change programme hinges on the understanding of problems that need to 

be solved, and realising what opportunities need to be maximised. 

 

Page 17: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

16  

Consensus between the board on the serious issues and problems is essential, too.  

This assures that the P3O® sponsor fully understands what success looks like across the 

organisation at all levels.  

Gathering these views and gaining a consensus on the right issues could take the form of 

interviews, workshops, or surveys.  

By debating any problems in open sessions, the root cause of these problems, and their 

solutions, will be recognised and defined. 

 

Overcoming Common Barriers 

Lack of Focus 

There can be a reluctance from senior managers to consider the full requirements of a P3O® 

model, instead focusing on a single component (training, PPM, framework development 

etc.) 

This can only partially deliver the P3O® functionality, which will then lead to restrictions on 

the value of the P3O®, and a failure of realised benefits. 

 

In many organisations, two problems inhibit gaining the consensus of senior executives: 

Many executives do not understand how change management should work, with no 

differentiation to other forms of management 

 

Executives who do have some understanding, though, do not understand what is in 

it for them 

 

Funding the P3O® Model 

Another barrier when building a consensus is the perception of the overhead associated 

with P3O® operations. Some stakeholders will be reluctant to fund the overhead to 

structure a P3O® model. 

Once the P3O® is operational, an effective way to maintain focus on the value of P3O® is to 

report on achievements towards the success measures against the cost of the P3O® 

business units. 

Some organisations might not see the value in providing support to programmes and 

projects, so a project manager might take cost‐cutting measures so that tasks can be 

completed within budget.  

This can lead to a staggered, slower‐pace of change throughout the organisation, as well as 

potentially delay benefits. 

Page 18: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

17  

Challenging the Current Culture 

A proposed P3O® model might challenge the current culture in an organisation, which can 

threaten the ability of the P3O® to realise any forecasted benefits. 

If the embedded culture is at senior level, it can be especially difficult to impose a new 

model, with the potential for failure considerably higher. 

Effective stakeholder analysis and a strong communications plan will assist in breaking down 

these barriers. 

Bureaucracy of the P3O® Processes and Standards 

A common barrier to building a consensus among senior management is the perceived 

bureaucracy associated with compliance with repeatable processes and governance 

arrangements for the delivery of business change. 

Processes should be kept as simple as possible, and new processes should align with existing 

procedures that are already seen to add value. 

It would be beneficial to introduce, or strengthen, formal sign‐offs for business cases and 

implement a gated sign‐off approach to stop rogue projects at its inception. 

In order for projects and programmes to be deemed a success, most of the services that are 

described in the P3O® model must be carried out. 

Other Barriers 

Some other common barriers include: 

 

A lack of authority for the P3O® to provide the governance and control 

arrangements 

 

Inadequate use of the individual P3O® offices, or lack of integration with other 

functions, within the wider organisation 

 

A lack of clarity in the roles, responsibilities, and accountabilities of the P3O® staff 

 

No clarity in the scope of individual P3O® offices 

 

Absence of commitment from senior management to the P3O® concept 

 

Timescales 

The projected timescales for a programme to be established and implemented can differ 

depending on the level of value to be achieved, and/or the level of activity to be 

undertaken. 

Page 19: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

18  

A typical change programme to move an organisation from Level 1 P3M3® maturity, to Level 

3 P3M3® maturity could take between 18 months and two years. 

This timeframe can be varied due to the level of investment to shorten it, or a lack of 

investment, which will slow it down. 

A stepped approach to change is the ideal way of implementation, allowing capabilities to 

be introduced and fully embedded.  

Timescales are ultimately driven by the ability of senior management and their appetite for 

making decisions on the way forward. 

 

Quiz 

 

1. A ‘big picture’ view is NOT a benefit of a P3O® model. 

 

A. True B. False 

 

 

2. Which of the following is NOT an aspect of governance focus? 

 

A. Business Change Strategy B. Business Change Value C. Business Change Design D. Business Change Process 

 

3. Any P3O® model worth its weight should be able to answer the question: 

 

A. ‘What value will it add to the organisation?’ 

B. ‘Are our benefits double‐counted?’ C. ‘How many months will it take to implement this change?’ 

D. ‘How many workshops will we need to hold?’ 

 

 

Page 20: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

19  

4. How long could it take for an organisation to move from a Level 1 to a 

Level 3 P3M3® maturity? 

 

A. Between 12 months and 2 years 

B. Between 18 months and 2 years 

C. Between 6 months and a year 

D. Between 2 years and 3 years 

 

 

 

Case Study: P3O® Pilot Based at Tameside Council in Ashton‐Under‐Lyne, Greater Manchester, Martin McCann has 

spent the last few years developing and implementing their tailored Project Management 

Approach. As part of the Transformation Team, his main role is to encourage, support the 

adoption and application of best practice project and programme management within the 

organisation.  

‘The implementation of the Project Management Approach underpins the Council’s 

Transformation Programme, which has a large number of new and existing projects within 

its remit. We’re facing changes which are both exciting and challenging,’ Martin says.  

He was keen for Tameside to be among the first organisations to pilot the new P3O® 

guidance from OGC. P3O® brings together a set of principles, processes, and techniques to 

facilitate effective portfolio, programme, and project management through enablement, 

challenge, and support structures. These structures also bridge the gap between the 

strategy and policy makers and the Council’s service delivery teams.  

‘I met Anne Marie Byrne, the P3O® project manager, at a conference, and from what she 

said about P3O® I knew that it would be both relevant and timely for my organisation to 

take part,’ Martin said.  

Martin and his colleagues have been tasked with setting up a Programme Office to provide 

monitoring, reporting, and control information on the Transformation work programme. 

‘The P3O® guidance is a comprehensive, practical resource that pulls together threads from 

all the OGC best practice methods. The guidance provides both interesting and useful 

information and it came at the perfect time for me to start applying it. It has helped solidify 

and structure many of my plans and ideas for setting up our own PSO. It has also provided 

me with good ideas on how to sell it to the right people within the organisation,’ he says.  

Martin also plans to use the P3O® guidance to incorporate relevant generic and functional 

roles and responsibilities into the job descriptions of any new programme office staff. ‘I 

have tried to link the P3O® roles and responsibilities to the functions and services the 

B, D, A, B 

Page 21: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

20  

programme office intends to provide over the next few years, illustrating the levels of 

resource we’ll need if we want to run an effective programme office that continues to meet 

our needs as the Council’s PPM capabilities increase. Given that it can take a few years to 

start reaping the benefits of more effective programme management, I want to plant the 

seeds and start the process as early as possible, whilst managing expectations properly on 

the way!’  

‘The manual will be a real boon to anyone starting out on setting up a P3O®. It does a good 

job of tying P3M3®, PRINCE2®, and MSP® together in a comprehensive fashion, which is 

exactly what a good P3O® should be able to do. I also found that reading the P3O® guidance 

has helped clarify my understanding of how to apply MSP® in general,’ he says. 

 

 

Designing a P3O® Model The design of a P3O® model should address: 

 

The P3O® model itself and how it will be deployed 

How many separate offices there should be 

The functions and services they offer 

Where component offices are physically located 

 

Organisational factors that can cause variations on the models: 

Economic sector (public, private, voluntary) 

Size of the organisation 

Approach to organisational governance arrangements 

Number, size, complexity, and duration of projects 

Organisational portfolio, programme, and project management maturity 

Centralisation vs decentralisation of core services 

If the business is driven by local or central investment decisions 

Any opportunities provided by the organisation for growth of staff 

If there is a mind‐set of continual improvement in the organisation 

Whether programmes and projects are carried out as internally focused initiatives, 

or if they are delivering to a client base 

Any geographical divisions of the organisation 

 

Another dimension that drives the P3O® model is the business goals of the organisation, 

which could include the following: 

Improving the quality/quantity of the service 

Page 22: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

21  

Reducing time to market 

Increasing revenues 

Reducing costs 

Improving the quality of a product 

 

As outlined in the first module of the workbook, a P3O® provides a decision‐

enabling/delivery support structure for change within an organisation.  

The three functional areas in which the P3O® can provide this service: 

Strategic planning/portfolio support functions 

 

Delivery support functions 

 

Centre of excellence functions or services 

These functional areas require different skills, competencies, and experience. Often, offices 

are set up to focus on one of these areas, or rather a large office split up into teams. 

It is essential for the head of the P3O® to develop the services in line with business 

requirements and continually demonstrate the value of these services provided. 

Design Considerations for a P3O® Model 

Reporting Lines 

 

‘Where should a P3O® sit within the organisation?’ 

 

‘Where should its component offices report in terms of line management?’ 

 

There is no simple or single answer to these questions, because a P3O® model is usually 

made up of different components and offices that serve a business need. 

For a P3O® to maximise its value to an organisation, though, it will need to report to a main 

board director (strategy or business change). 

Where an organisation portfolio office exists, it should report to a main board director, the 

CEO, COO, CFO, or CIO.  

However, if the portfolio office is a hub in a decentralised model, aligned with a particular 

division or department, then report to the divisional director. 

Reporting lines should also be reflected in programmes and projects.  

Page 23: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

22  

Consider whether there will be direct reporting lines to the programme or project manager, 

and also if the programme office/hub portfolio office reports to the programme or project 

directors. 

Centralised vs Decentralised Offices 

In many organisations, a single P3O® office will sit in a central corporate function or 

department.  

This office performs one, or all, of the portfolio support, delivery, or COE functions. Some 

organisations will set up an office for each of these.  

In other organisations, specifically large or functionality‐focused ones, with decentralised 

decision‐making and a strategy of deploying local resources closest to business delivery, 

there may be a small central office with portfolio support and COE functions working out of 

hub offices. 

Decentralised models tend to focus their support on local need, but care must be taken to 

ensure that a consistent organisation‐wide set of standards are enforced. 

 

P3O® Model with an Organisation Portfolio Office 

In this model, there is one permanent P3O® office, which may be called the organisation 

portfolio office. This office carries out the following activities: 

 

Strategic planning/portfolio support – Enabling strategies, prioritisation, senior 

management decision support 

Delivery support – Flexible resource pool of delivery support staff (specialists, 

coordinators, support officers etc.) 

Centre of excellence – Standards, assurance, competencies, and training 

Depending on the maturity of the organisation, and where the office reports within the 

organisational structure, the office’s services may be limited. It may also have to work with 

other organisational departments to deliver all requirements. 

If a programme or project creates a temporary office, the support staff will need to be 

trained appropriately and they may be line‐managed through the organisation portfolio 

office or the business units themselves. 

However, in some organisations, strategic planning support functions may have evolved into 

a separate office under a strategy director. An example of this is displayed below: 

Page 24: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

23  

An example of a P3O® model separate strategic portfolio office Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

Where this occurs, the ideal scenario would be a merging of the two offices under a single 

director. If this is not a viable option, though, then the two offices should work closely with 

each other. 

Underlying Success Factors for Models with an Organisation Portfolio Office, Advantages 

and Consequences 

A P3O® champion representing senior management continuity of support 

Allows for decision‐making at senior levels and drives action through other 

management teams 

 

However, the P3O® is not recognised, processes are not used, and processes are not 

embedded in the culture and the initial rollout effort is wasted 

 

Clarity of strategy and direction for management of change 

Gives direction for prioritisation and capacity planning 

 

Page 25: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

24  

However, the organisation does not have a portfolio of programmes and projects 

aligned to the organisation’s goals, and too many programmes or projects are 

started that do not add real value to the organisation 

 

A highly respected, charismatic, and comfortable head of P3O® 

Gives the P3O® units gravitas across the organisation, and the head of P3O® is 

invited to senior planning meetings so they can influence decisions 

 

However, P3O® requirements are not considered when key restructuring decisions 

are made, and rolling out standards and methods across an organisation is difficult 

 

A portfolio office that is staffed with highly competent senior staff 

The ability to empathise with delivery programmes and projects, knowledge of what 

works and what does not, and getting the respect of others is easy 

 

However, P3O® can be seen as just an admin office, or a ‘post box’ 

 

An established programme/project management forum/community of practice (COP) 

Lessons are shared ‘in context’ – of how enterprise standards translate into reality, 

the organisation portfolio office can learn directly from programme and project 

managers, and any changes in industry practices can be communicated easily to the 

full PPM community 

 

However, there is a potential for local programme offices to form cliques, with no 

sense of corporate identity, and there is no face‐to‐face forum to discuss and debate 

issues and updates to organisational best practice 

A blueprint for the P3O® that is regularly reviewed and updated in line with 

improvements 

Allows for a structure and focus for P3O® development and delivery, and utilised to 

focus senior management’s attention on the added value of the P3O® and challenge 

attempts at cost‐cutting 

 

However, the purpose and services of the P3O® model are vulnerable to constant 

change as senior managers champion changes over time, and personal visions 

intervene 

 

An intranet or collaboration zone where all PPM staff can access best practice and 

standards 

Page 26: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

25  

A single source of access for standards that are periodically updated, and 

lessons/emerging industry good practice can be centrally applied and easily accessed 

by all 

 

However, local standards evolve and develop constantly, and individuals will save 

templates on local drives and do not keep up with 

changing best practice 

 A P3O® champion representing senior management continuity of support     Clarity of strategy and direction for management of change     A highly respected, charismatic, and comfortable head of P3O®     A portfolio office that is staffed with highly competent senior staff     An established programme/project management forum/community of practice (COP)     A blueprint for the P3O® that is regularly reviewed and updated in line with improvements   

Gives the P3O® units gravitas across the organisation, and the head of P3O® is invited to senior planning meetings so they can influence decisions   Allows for a structure and focus for P3O® development and delivery, and utilised to focus senior management’s attention on the added value of the P3O® and challenge attempts at cost‐cutting   Allows for decision‐making at senior levels and drives action through other management teams   Lessons are shared ‘in context’ – of how enterprise standards translate into reality, the organisation portfolio office can learn directly from programme and project managers, and any changes in industry practices can be communicated easily to the full PPM community   The ability to empathise with delivery programmes and projects, knowledge of what works and what 

Page 27: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

26  

Exercise Match‐up the relevant advantages with each 

underlying success factor. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

does not, and getting the respect of others is easy   Gives direction for prioritisation and capacity planning  

Page 28: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

27  

P3O® model with hub portfolio offices connected by spokes 

A P3O® model with hub portfolio offices will have a permanent central organisation 

portfolio office that is connected to a number of permanent decentralised offices. These 

offices then act as hub portfolio offices to the temporary programmes and projects that 

they service.  

This model is often referred to as a hub‐and‐spoke model, providing the benefit of 

scalability for large organisations and supports business ownership by maintaining a level of 

decentralisation. 

All information flows, and processes arranged, so that they move along spokes to the 

organisation‐level office at the centre. 

The figure illustrated below depicts a permanent central organisation portfolio office with 

hub portfolio offices. 

 

An example of a P3O® model hub portfolio offices temporary programme Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

Page 29: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

28  

This model is often the choice for large, more complex organisations, possibly with a multi‐

national reach. A geographical spread of sites may necessitate the setting up of separate 

portfolio offices. 

Programmes and projects will use the standards and assurances from the corporate COE or 

the local hub portfolio office, depending on the size and maturity of the organisation. 

 

Underlying success factors for hub portfolio offices 

An effective capacity planning and flexible resourcing model 

Allows for the geographic clustering of resources, and resources will be familiar with 

the local business model and working practices 

However, resources continue to be bought in, or asked to travel over a large 

geographical area 

Availability of good heads of portfolio offices using core standards and methods 

Provides a flow‐down of good practice and standards with localised tailoring and 

application 

However, the local hub portfolio offices develop their own standards and do not 

share best practice, and the transfer of staff across portfolio offices requires 

constant training 

An established heads of portfolio/programme offices forum 

Consistency of application of enterprise or corporate best practice, and learning 

from each other how best to apply enterprise or corporate standards 

However, the local hub portfolio offices develop their own standards and do not 

share best practice, and the transfer of staff across portfolio offices requires 

constant training 

Virtual P3O® Model 

The ultimate decentralised model is the virtual P3O® model, where there is no permanent 

office. 

Any functions and services are embedded in the organisation’s business delivery units, with 

activities undertaken by a central strategy or business‐planning office or the finance 

department. 

This model typically exists in organisations with a high‐level of PPM maturity, where 

consistent standards are embedded, the PPM resources are highly competent, and P3O® 

functions and services can be provided across the organisation without the need for a 

physical structure. 

A significant aspect of this model is the programme, risk, and project management 

forums/communities of practice.  

Page 30: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

29  

All PPM professionals come together at regular events to share best practice and learn 

about any new methods of working. 

It is commonplace for a virtual P3O® to be developed using external resources and internal 

collaboration tools. 

This allows a more community‐based connection, with a similar core team. In terms of cost‐

reduction, this could be valuable for an organisation to explore further as its PPM maturity 

rises. 

Underlying success factors in the virtual office model 

The organisation has a P3M3 maturity level of three or above 

Allows for consistent, reliable working practices, as well as a culture of review and 

continual improvement 

However, there is no consistent way of working and there is the potential that 

multiple methods will progress across the organisation 

Established programme/project management forums 

The sharing of best practice and a collaborative approach to the updating and 

embedding of these practices 

However, the base standards and practices can stagnate, and any updates without 

consultation are seen as an imposition and consistency of approach disappears over 

time 

A single point of ownership by a senior PPM professional for portfolio, programme, and 

project standards 

The senior professional is outward‐facing to look for and contemplate advances in 

best practice 

However, local variations sneak in and the earlier work is undone 

Standards are continually developed and embedded through reference to external best 

practice 

Provides a single point of reference for virtual teams to access, which is updated 

regularly 

However, local variations sneak in and the earlier work is undone 

A strong, underlying PPM culture 

Those involved in delivering change (mainly the senior board members) understand 

their roles and the benefits of a consistent approach 

However, programmes and projects act individually and do not deliver consistent 

working practices, and the training overhead for programme and project managers 

to bring boards and business resources up to date is excessive 

 

Page 31: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

30  

Exercise Match‐up the relevant advantages with each underlying success factor. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 The senior professional is outward‐facing to look for and contemplate advances in best practice  

   Those involved in delivering change (mainly the senior board members) understand their roles and the benefits of a consistent approach     Allows for consistent, reliable working practices, as well as a culture of review and continual improvement  

   The sharing of best practice and a collaborative approach to the updating and embedding of these practices     Provides a single point of reference for virtual teams to access, which is updated regularly   

  The organisation has a P3M3 maturity level of three or above     Established programme/project management forums     A single point of ownership by a senior PPM professional for portfolio, programme, and project standards     Standards are continually developed and embedded through reference to external best practice     A strong, underlying PPM culture   

Page 32: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

31  

Permanent vs Temporary Offices 

In a P3O®, it is usually recommended that permanent offices be established in order to 

provide functions and services that support ongoing portfolios, senior management 

decision‐making, and the setting of generic standards for all change initiatives. 

These permanent offices are likely to be organisation portfolio offices, local hub portfolio 

offices, and COEs, resourced by permanent staff that are trained to perform specific 

functions. 

When a new programme or project is launched, it may require its own temporary 

programme or project office.  

If there is a permanent office with a central flexible delivery team, then these resources may 

be requested from there. 

This ensures that the start‐up process is fast‐tracked and costs are kept to a minimum due 

to already trained staff.  

However, in some organisations the central pool either may not exist or will not be big 

enough to cope with the demand, in which case staff will be seconded to project roles. 

Some organisations might develop a framework agreement with a partner organisation to 

provide all programme and project staff (managers and support). 

Whenever contract or framework staff are used, though, they should be inducted into the 

organisation’s standards and ways of working. 

With an organisation that has a low PPM maturity level, each new programme or project is 

usually staffed with local business people, sometimes supplemented with contract staff to 

bring in any additional expertise. 

Although there is no organisation portfolio office, there may be an underlying project 

method, which is defined on the company intranet or already established in the company’s 

culture.  

This model suffers from inconsistency of approach on programmes and projects, with 

extreme variations in terms of delivery success, dependent on local business managers’ 

competence. 

Underlying success factors for temporary offices 

Centrally documented programme or project standards and templates 

All programme and project managers will have a central point to refer to for 

standards and templates, and there will be a consistency of approach and 

terminology across the organisation 

However, all programme and project managers act individually and use their own 

templates, and where there is a large contract PPM pool, external staff bring their 

own familiar standards and ignore any internal enterprise or corporate ways of 

working 

Page 33: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

32  

A consistent approach to programme and project management training through the 

procurement of an approved set of courses and training providers 

All staff are advised to go on similar courses through a standard set of providers, and 

this training will be upheld by consistent messages and language 

However, staff select which courses they wish to attend, meaning there are 

inconsistencies in the language and messages. Additionally, training providers are 

not able to tailor courses specifically to a local company’s culture 

An established heads of programme/project offices forum, including key staff from 

portfolio offices 

Allows for the consistency of application of enterprise or corporate best practice, as 

well as the learning from one another about how best to apply these standards 

However, local offices develop their own standards and do not share best practice, 

and the transfer of staff across programme and project offices requires constant re‐

training 

 

Co‐located vs Distributed Models 

The ideal scenario is to have a permanent organisation office with staff physically co‐

located, ensuring team cohesion and consistency of approach. 

However, in some organisations, because of a lack of physical office space, or an adherence 

to work/life‐balance policies allowing individuals to work from home, the team will work in 

a distributed model. 

Where a distributed office or team exists, it is important that there is a recognised single set 

of standards, albeit with separate owners for components of the standards. 

It is crucial that the distributed team communicates frequently, with meetings, central 

information portals, and collaborative working practices. 

 

What Functions and Services Should the P3O® Offer? 

High‐level Functions and Services 

The many functions and services that the P3O® provides should be able to contribute 

directly to the outcomes required by the organisation, whilst being based on the business 

drivers, levels of governance, and customer demands. 

Although every office may deliver all of their functions and services, they may also have a 

different functional emphasis: planning, delivery, or COE.  

Page 34: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

33  

Organisation portfolio offices typically focuses on delivery support services, but temporary 

programme and project offices will focus on delivery support services. 

High‐level functions and services of a P3O® model Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Integration with the Wider Organisation 

The P3O® will not exist in a vacuum. It is vital to understand how the functions and services 

provided will integrate into the wider organisation. 

Page 35: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

34  

A common failure of permanent P3O®s is a lack of integration of the model within the wider 

organisation model.  

It is the job of the head of the P3O® to understand who is responsible for what various tasks 

and functions, as well as how the model, and the various offices within it, will interact with 

them. 

 

Other functions include: 

 

Strategy development and management, including business planning 

 

IT service management (release, change, and configuration) 

 

Human resources 

 

Marketing/public relations 

 

Procurement/purchasing/commercial, including bid management 

 

Finance 

 

Corporate risk management 

 

Corporate information assurance 

 

Audit 

 

Quality 

 

Business operation 

 

Other professional resources will exist in a matrix management environment with local 

business lines management, but a professional link to an organisation portfolio office or 

COE, just as P3O® resources do. 

Clarity is needed in terms of roles and responsibilities for delivering functions and services 

across business areas. 

Embedded resources may be assigned to another programme or project temporarily, but 

their original department will ultimately still control them and the processes that they 

follow. 

Page 36: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

35  

The figure illustrated below is an example of the embedding of resources from an 

organisation portfolio office, COE, and business functions into a temporary programme 

office. 

An example of the embedding of resources from an organisation portfolio office Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

The P3O® model provides the governance backbone for all change within an organisation, 

certifying that all decisions are made at the appropriate level and in a timely manner. 

Effective collaboration with all bodies across the organisation is necessary due to the 

influence on decision‐making.  

This relationship needs to be clearly defined and rules of engagement recognised as well. 

Governance must be agreed and defined in terms of: 

 

Who makes the decision and when 

 

What delegated limits of authority are in place 

 

The rules and routes for escalation and cascading of information, risks, issues, and 

changes 

 

This agreement should reflect the governance and information required to meet the needs 

of all stakeholders. 

Page 37: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

36  

Independence of P3O® Assurance Services 

Independent assurance services are often included within a P3O® service offering. These 

may take many forms, such as coordinating or facilitating gated reviews, regular health 

checks, internal or independent audits, and lesson reviews. 

Assurance teams can also provide quality assurance to programmes and projects by 

providing an assurance resource (full or part‐time) or independent guidance on the tailoring 

of processes in the start‐up stage. 

It is essential that the assurance service is independent of the programme or project 

delivery, and there are no conflicts of interest. 

The P3O® itself should be subject to independent assurance and external audit itself, paying 

particular attention to the external review of COE functions and services, to ensuring that 

good practice is being kept up‐to‐date with changing industry standards and trends. 

Within a multi‐programme/project environment, staff across the P3O® may carry out 

assurance at appropriate checkpoints and at gated reviews.  

Independent assurance external to the delegated assurance from the programme or project 

board may be requested by senior management, and may be focused on fulfilment of 

strategy, impact on business operations, management of dependencies, or other areas of 

concern. 

 

Information Assurance 

The value of information assurance varies from organisation to organisation. Banking 

organisations and others with sensitive information will understand that it is vital to their 

business, and that they will need to invest both a lot of time and money into maintaining 

their robust systems, processes, and procedures. 

The Data Protection Act and the Freedom of Information legislation defines the minimum 

statutory guidelines for all organisations – with implications for all portfolios, programmes, 

and projects. 

Information assurance is based on three concepts: 

Confidentiality 

Integrity 

Availability 

These mean that information is only available to those who have a need and the authority 

to see it, only those with the correct authority can change information, and that the 

information is available whenever and wherever the business necessitates it to be. 

Careful consideration of the information assurance requirements for projects and its 

outputs is imperative at the beginning of the process. 

Page 38: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

37 

In cases where the information assurance function or department is separate within an 

organisation, the P3O® should engage appropriately with the experts within it and follow 

the process of embedding information assurance resources into portfolio, programme, and 

project offices. 

Non‐PPM Functions and Services 

Sometimes, it may be necessary for the P3O® to undertake its functions and services outside 

of the PPM area of operations. 

This could involve: 

Providing a secretariat service to management boards

Looking after travel and accommodation

Liaising with procurement regarding the acquisition of equipment of resources

Exercise 

In the alignment of governance services provided by the P3O®, governance must be agreed 

and defined in terms of: 

_____ makes the _________ and when

What delegated limits of ________ are in place

The ______ and routes for escalation and ___________ of information, risks, issues,

and ________

Fill in the blanks. 

Authority, Rules, Changes, Who, Cascading, Decision 

Answer is on the next page. 

Page 39: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

38  

Answer: 

Governance must be agreed and defined in terms of: 

 

Who makes the decision and when 

 

What delegated limits of authority are in place 

 

The rules and routes for escalation and cascading of information, risks, issues, and 

changes 

 

Sizing and Tailoring of the P3O® Model 

Questions to be asked when designing a P3O® model: 

 

‘How many people will the P3O® need?’ 

 

‘What level should they be at?’ 

 

The key drivers for the size of a P3O®: 

 

The number and size of the programmes and projects to be serviced by the P3O® 

 

The number of functions and services to be provided by the P3O® 

 

The size of the organisation 

 

There are, however, many more factors to be considered. 

A P3O® may service a single programme, a number of programmes, or the organisation’s full 

portfolio of change. 

The PPM maturity of the organisation needs to be taken into account by the P3O® model, in 

order to determine the detailed size and design of the individual offices within the 

organisation. 

The size and design also depends on the P3O® vision and the business drivers that it is set 

up to assist. 

The number of staff within a P3O® inside of an organisation can vary between one person to 

over one‐hundred. On average, though, the figure is between five and ten people, especially 

when individuals are undertaking a generic role. 

Page 40: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

39  

Sizing a permanent organisation portfolio office or a hub portfolio office will differ from 

sizing a temporary programme or project office. 

For temporary offices, resources may be: 

 

Taken from a flexible resource pool within a hub portfolio office 

 

Engaged on a temporary basis from the contract market 

 

Engaged as a work package through a framework agreement with a management or 

PPM consultancy company 

 

The structure of the P3O® model has an impact on the number of required resources. 

It could be a more cost‐effective solution to upgrade an existing programme office to a hub 

portfolio office to provide services to programmes and projects, rather than establishing a 

dedicated programme or project office. 

A mature organisation portfolio office, or an organisation with flexible resource pools, will 

most likely have reduced staffing costs. 

The design and shape of a P3O® model should not be carried out just by formula, as no 

formula can fully take into account every small aspect of any organisation or programme. 

 

Sizing Option One – By Budget 

This is based on the size and financial investment in the portfolio or programme. Usually, 

the overall cost of the P3O® will range between 3% and 5% of the total financial investment. 

The level of P3O® provision will vary as the portfolio changes or the programme progresses. 

 

Sizing Option Two – By Size 

This second model calculates the size of a temporary programme office, and bases these 

calculations on the headcount of the programme. 

The table on the next page illustrates how the overall headcount of a programme office is 

taken as a percentage of the programme headcount. 

It assumes the programme office: 

 

Produces some management reporting 

 

Uses basic IT tools 

 

Works within an environment where the P3M3 maturity level is between 2 and 3 

Page 41: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

40  

 

 

An adjustment to these numbers will be required for these situations: 

 

A higher or lower level of P3M3 maturity 

 

Additional services provided 

 

Programmes spread over multiple locations 

 

Complex or novel programmes 

 

Programmes with a large number of third parties 

 

Programmes with intricate finances and/or benefit management plans 

 

Programmes with a large number of projects 

 

The need for short‐term resources required for peak loading 

 

Programmes with a complex stakeholder communication plan 

 

Sizing Option 3 – By Function 

In this model, an estimate is made of the number of hours or days required per month for 

each service the P3O® plans to deliver. 

This is then converted into the number of full‐time equivalent employees required for each 

service, which then gives an estimate of the number of resources needed for the P3O®. 

The size of an office, and the activities that it carries out, will vary throughout the project or 

programme lifecycle. 

This exercise should be carried out at least twice: once in the definition stage, and another 

at the start of implementation. 

Unit  Headcount 

Programme  30  60  120  200  300  500  1000 

Programme office  3  4  7  9  12  17  25 

% programme office staff  

10  7  6  5  4  3  3 

Page 42: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

41  

The number of programmes or projects within the portfolio may drive sizing for some 

functions at any time, whereas other functions could be driven by the governance structure 

and required input. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 FTEs per functional area for a P3O® sizing model Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Additional Considerations for a Temporary Programme or Project Office 

Temporary programmes and projects will notice a variance in their sizes throughout the 

lifecycles too. 

This is where the use of flexible resource pools through hub portfolio offices can become of 

value. 

In the definition stage of a programme or project, internal consultancy is required for 

establishing and tailoring standard processes, initiating the reporting cycle, developing 

plans, and fast‐tracking the team. 

Through the implementation and delivery phases, the need for constant planning support 

reduces because the programme/project manager will take responsibility for the updating 

of the plan. 

Page 43: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

42  

The assurance role should continue in order to provide continuity, support through lesson 

sharing, ongoing health checks, gated reviews, and advice. 

Generic support from specialist may also be required during the delivery stage, dependent 

on the size and complexity of the programme or project. 

The closedown and post‐implementation review section of a programme or project will no 

longer require delivery resources.  

However, internal consultancy could assist in the independent lesson reviews and 

evaluations. 

A commonly found problem when reviewing temporary programme offices is that their 

programme support staff is too large. 

Often, this is because the number of staff is established during the definition phase and 

then the staff is kept on to assist the project manager with their job. 

Solutions to this problem include: 

 

Setting up hub portfolio offices with flexible resource pools, therefore utilising the 

available support to provide delivery throughout the lifecycle 

 

Engaging consultancy support in the definition stage of a programme or project, 

usually from a COE, external organisations, or PPM consultancy companies 

 

Engaging contract staff to assist in the definition phase. A problem with this, 

however, is that the staff will not be trained in local standards and will often bring 

their own processes on board 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 44: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

43  

Quiz 

 

1. For temporary offices, resources may be… 

 

A. Fully engaged in order to meet expectations 

B. Integrated into the wider organisation C. Carrying out information assurance tasks 

D. Taken from a flexible resource pool within a hub portfolio office 

 

2. Information assurance is based on three concepts: 

 

A. Integrity, Definition, Availability B. Confidentiality, Integrity, Availability C. Availability, Integration, Definition D. Confidentiality, Definition, Availability 

 

3. ‘Reducing time to market’ is a business goal of an organisation that 

drives the P3O® model. 

 

A. True B. False 

 

4. The ultimate decentralised model is the ________________, where 

there is no permanent office. 

 

A. Organisation Portfolio Office Model 

B. Virtual P3O® Model 

C. Hub Portfolio Offices Model 

D. Procurement Standards Model 

 

 

 

  D, B, A, B 

Page 45: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

44  

Implement and Re‐energise Introduction to the Implementation Lifecycle 

The P3O® implementation lifecycle has four major steps, which are supported by MSP® 

Principles: 

Identify 

Define 

Deliver 

Close 

 

Implementation Lifecycle for a permanent P3O® Model Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.   

Identify 

This process assesses the current state of P3O® provision and identifies the key 

stakeholders. Outline documentation for the P3O® model is created at this point, including a 

summary document called a Brief, which require validation by management. 

Activities also include: 

Agreeing the P3O® Vision 

Demonstrating the Value 

Agreeing the appropriate cost model 

 

Identifying stakeholders 

The portfolio, programmes, and projects cannot be considered successful without the 

stakeholders being satisfied. One can recognise the stakeholders from the information 

about the budget, project sponsor, objects, schedule, assumptions and constraints, and Top 

Management. One can get a large amount of information about the stakeholders by 

Page 46: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

45  

interviewing the experts, or through a brainstorming session. Good questions to consider 

are: 

Who has direct involvement in the projects and/or programmes? 

Who has indirect involvement?   

Who are the suppliers ? 

Who are the competitors? 

Who can make your portfolio/programme/projects fail? 

Who may be affected by the outcomes? 

 

Assessing the current state  

The main purpose here is to drive the right information from your analysis and assessment. 

Impartial honesty is the best policy at this stage. You will need to gather opinions from 

various stakeholders and pull together as much factual information about the current 

portfolio, programmes, and projects you can find. 

There are several forms of assessment, including: 

P3M3 Maturity Assessment 

PPM Maturity Model 

Value Matrix 

 

P3M3® Maturity Assessments 

 

P3M3 Structure Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

Page 47: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

46  

The level of organisational maturity in portfolio delivery demonstrates how well the organisation can support its programmes and projects. The P3M3® Maturity Model is a specific management maturity model to assess organisational effectiveness. There are seven perspectives taken into consideration: 

Management Control 

Benefits Management 

Financial Management 

Stakeholder Management 

Risk Management 

Organisational Governance 

Resource Management  There are five levels of maturity: 

0. Awareness 1. Repeatable 2. Defined 3. Managed 4. Optimised 

 A programme uses a P3M3® Model to: 

Improve performance 

Assess maturity of projects 

Measure itself against one or more perspectives 

Ensure it is working consistently across all projects                    Overview of P3M3 Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Page 48: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

47  

Value Matrix 

The P3O® Value Matrix is a simple tool to assist senior managers in determining their core problems and assessing the scope of the P3O® model. In order to create a vision of what the P3O® model should provide, we need to understand what is offered now and how effective it is. Typical questions to ask during the data gathering are: 

Are the existing P3O®s doing the right thing? 

What is the current perception from stakeholders ‐ is it favourable and why? 

Are they doing what they do well? Do we have the right people and skills with correct level of seniority and authority to get things done? 

What should a P3O® stop doing? 

What should a P3O® start doing? 

By debating these issues in an open session, core problems can be identified, defined, and the P3O® model design to resolve or limit them through the services provided. The Value Matrix is intended to generate discussion and should be considered as part of a well‐planned and facilitated workshop or interview. 

P3O® also suggests using a Value Matrix to determine the scope of the support and assurance services to which the organisation has access. The matrix considers three levels of change management that an organisation may experience in handling portfolio, programme, and project management. 

P3O® Value Matrix Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

 

Page 49: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

48  

Agreeing the Vision 

The Vision Statement describes what the P3O® is and what it intends to do, describing a 

compelling future state in a way that  a variety of stakeholders can understand it, in order to 

be convinced to support and invest in the P3O®. It uses the current reality as part of its 

justification, using the current state assessments and business case, and provides sufficient 

context and direction to enable the blueprint development. 

Demonstrating the Value 

The Business Case provides the justification for the proposed investment and should be 

reviewed throughout the introduction of P3O®. Content and structure will vary between 

P3O®s, because there is no ‘one size fits all’ solution. Outputs can be summarised as a list of 

desired outcomes. It should be aimed at senior management. In constructing the business 

case and gaining commitment from senior managers, it is important to understand which 

benefits are achievable and what elements of P3O® capability will need to be in place to 

realise those benefits.  

The Business Case will include: 

Aims 

Background/Reasons 

Objectives for Portfolio, Programmes, and Projects 

Cost Benefit Analysis 

Possible risks 

Exercise 

In the box explain the impact of the results of the P3M3 maturity assessment on the design, planning and delivery of the P3O® Model and the P3O® Blueprint  

 

Page 50: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

49  

Define 

This process establishes the team, refines the Vision Statement and the Blueprint. It works 

on Stakeholder Engagement and delivers an implementation plan. This is all summarised in 

a Programme Definition Document, which should be validated by management. It also 

includes developing, modelling, and validating the benefits. 

 

Refining the Vision Statement 

The outlined vision statement needs to be developed and refined to include a high‐level 

view of outcomes that will be achieved across process, organisational, technology, and 

information areas once the P3O® implementation is completed. Its main purpose is to 

market the goals of the programme across with wider organisation. 

 

The Blueprint  

Blueprints often use the POTI Model to define the scope of all changes taking place as a result of the projects. POTI stands for Processes, Organisation, Technology, and Information; the four areas that outline all elements compiling the P3O® scope.   Processes Projects adapt current processes and implement new ones. Any operational business models that will undergo change due to the projects in the programme and portfolio come under this area. For example: 

Performance Levels 

Functions and Services 

Use of pictures, process models, or swimlanes   

Organisation All personnel and HR organisation information, including any changes made, requirements for the business, and organisational culture. For example: 

Re‐arrangement of staff 

Training requirements 

Roles and Responsibilities 

Governance   Technology All P3O® technology requirements are included in this section, including equipment, tools, systems, and resources. For example: 

Equipment needs 

New networks or systems   

Page 51: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

50  

Information This area consists of mostly intangible data, such as new information requirements for stakeholders. This may not be available early on in the blueprint development. For example:  

Changes to reporting systems and requirements 

Project/Programme specific data outcomes  

Information Assurance  

An important factor to consider when developing the blueprint is the type of P3O® culture 

the organisation hopes to create. A culture is a pattern of responses discovered, developed, 

or invented during a group’s history of handling problems that arise. Culture determines 

what sort of actions and behaviour is acceptable, relevant, workable, or implausible. Below 

are characteristics of a beneficial P3O® model: 

 

Information Sharing: Describes the exchange of programme and project data to 

report information, knowledge, and wisdom between roles, technologies, and the 

broader organisation. 

 

Focus on learning: P3O®s provide services to enable improvement, so rather than 

track data looking for failure, they review and challenge documentation early on in 

the process, in hope of increasing portfolio, programme, and project maturity.  

 

Value focus to all activities: The aim here is to improve decision making and focus 

on finding more attractive options rather than opting for any alternative. There is a 

P3O® need for greater depth, a clear governance structure, and a sound conceptual 

basis for relating strategic objectives to each investment. 

 

Innovative: For P3O®s, innovation looks to implement new ideas, create dynamic 

products, and improve services. The successful delivery of projects and programmes 

is the measuring tool for innovation. 

 

Service focussed: P3O®s place significant impact on customer service as a 

cornerstone to realising financial and quantifiable benefits. As programmes rely 

more on consultancy services, it is vital that P3O®s look to continually improve the 

services they offer. 

 

Proactive analysis: Instead of reacting to a situation post‐occurrence, P3O®s support 

seeing potential problems before they occur through proactive analysis. Taking 

action towards a risk as it happens, rather than after, leads to a reduced impact and 

cost 

 

 

Page 52: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

51  

Threats to achieving the Blueprint 

Lack of continued senior management commitment 

 

Resistance to change 

 

Overly focussed on toolsets, processes, and templates 

 

Managing the implementation of P3O® as a project 

 

Initial lack of quality of portfolio or programme information 

 

The P3O® becomes the de‐facto of business change 

 

Insufficient support to utilise or recruit required skills 

 

Plan stages or tranches 

Many P3O®s are closed down within a five‐year period, so it is important to clarify early 

benefits to stakeholders for their investment. These can then be used to fund later tranches, 

so that if the P3O® does last, it will finance itself.  

 

The first tranche of delivery should contain early benefits that achieve demonstrable 

improvements and easily implemented deliverables. A portfolio register is useful at 

this stage, so stakeholders and management can see all the strategies, benefits, and 

impacts of programmes and projects on the organisation as a whole. This should 

include a defined investment budget and balanced set of resources. 

 

Aligning the development of P3O® capability with the normal organisation business‐

planning cycle is also a good idea as it allows for integration of the P3O® model and 

its benefits into the business budget lifecycle.  

 

A projects dossier aims to improve PPM maturity within the organisation and the 

figure below shows an outline plan based on the dossier.  

When developing a projects dossier, it is important to consider: 

Existing PPM maturity and targets 

Priorities for capability development 

Ability to embed change 

Functions and services as a results of P3O® added value 

Pace of change requirements 

Resource capacity 

Scale of portfolio 

Risks to delivery and planned benefits 

 

Page 53: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

52  

 

Outline plan for a P3O® establishment and PPM maturity development programme Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Develop, Model, and Validate the Benefits 

Develop a benefits management strategy, benefits map, benefit profiles, and a benefits realisation plan as defined in MSP®. 

Some of the benefit drivers a P3O® can provide are: 

Increased cost savings 

Increased cost avoidance 

Increased strategic alignment 

Increased programme and project throughout 

Optimisation of benefits 

Increased level of portfolio management maturity 

Reduction in threats 

Maximisation of opportunities 

More effective use of resources 

A benefits map will illustrate the relationship between outputs, capabilities, outcomes, benefits, and objectives. This is crucial to learn about the cause and effect relationship between the elements in a programme. The benefits map contributes heavily to the benefits realisation plan, outlining the realisation sequence through a chain of benefits. Timescales can also be developed from the map, informing the creation of schedules within the realisation plan.  

 

Page 54: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

53 

Deliver 

The P3O® guidance strongly recommends and incremental approach to implementation (in 

tranches) with a focus on the realisation of benefits in each increment. 

Deliver new capability, and transition and stabilise operations 

Successful delivery of project outputs that enable benefits within time, cost, and quality 

restraints is a key aim of implementing P3O®. However, it is vital to ensure the rate of 

change is bearable by the organisation and ongoing support throughout integration is 

maintained. 

Realising the Benefits 

Benefits realisation has three stages: 

Pre‐transition

Transition

Post‐transition

There can be a tendency to be over‐optimistic with expectations when defining and setting targets of benefits. This can produce commitments from key stakeholders early on, which is incredibly beneficial to the programme’s early stages. However, when the benefits are reviewed, the support gained at the start could easily falter due to failed promises.  

Choosing suitable KPIs (Key Performance Indicators) is crucial in benefits management. Current KPIs must be supplemented by other measures to assess the benefits realised by the programme. Some of these measures may fluctuate due to process variations or seasonal trends, so it is important to understand and reflect this in the relevant plans. 

Benefit Reviews 

Benefits reviews can be time‐driven or event‐driven, taking place, at a minimum, at the end of each tranche to ensure that benefits realisation is still on track. 

The objectives of a benefits review is to: 

Assess and update each individual benefits profile and benefits realisation plan

Check that all benefits are aligned to the programme’s objectives

Inform stakeholders and senior management of the progress in benefits realisation

Assess the level of benefits achieved against the benefits realisation plan

Page 55: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

54  

Assess the performance of the changed business operations against their original performance levels 

Review the effectiveness of how benefits management has been handled, sharing any learned lessons 

Reviews will require the benefits realisation plan itself, as well as its benefits map and any relevant individual benefit profiles. If any concerns arise, then the benefits management strategy should be revisited. 

Close 

When a specific programme has been developed to set up a new P3O® capability, formal 

closure and post‐implementation and benefit reviews are essential. This enables making the 

P3O® capability part of ‘business‐as‐usual’ and allows time to reflect.  

Exercise: Give some examples of the steps you would take in the Buyitall scenario that 

would incorporate these characteristics within its P3O® model 

Information Sharing   

Focus on learning   

Value focus to all activities   

Innovative   

Service focussed   

Proactive analysis   

Page 56: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

55  

Temporary Programme or Project Office 

The temporary programme or project office is designed specifically for a finite lifecycle. This 

means there are different requirements on size, scale, and complexity. There are key 

success factors involved in the setting up of a temporary office: 

 

Organisational Context 

When there is an organisation portfolio office or hub portfolio office in place, the temporary 

programme/project office may be resourced with standards and templates provided by the 

Centre of Excellence. The processes of the temporary office will be a standard function 

provided by the organisational portfolio office: 

 

An example of a P3O® model temporary programme and project offices Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Page 57: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

56  

In organisations without an Organisation Portfolio Office or Centre of Excellence, the set‐up 

of the temporary programme/project office will rely on the local business team responsible 

for the relevant programme or project and the maturity of their approach to PPM and its 

processes. A physical programme or project environment is also required, perhaps using 

existing business facilities to provide workspace, equipment, and software etc. Some 

organisation have equipped office areas with team‐working tools specifically for short‐term 

use.  

 

Definition and Implementation 

It is suggested that 10% of the programme/project timescale be spent on establishing the 

temporary office, alongside other start‐up activities at the beginning of the 

project/programme. The structure and functions of the temporary programme or project 

office are determined in the initiation documentation and these requirements will drive the 

office model and its processes. 

Some key requirements are:  

A configuration library 

Guidelines for storage and security of documents 

Tools, including drawing and collaboration tools 

The temporary programme or project office may be run by one person, or a team of generic 

or function‐based roles. Deciding what skills are required takes into account the 

stakeholders, the business environment, the scope, and the timescales. For example, a 

project with multiple stakeholders with complex requirements might need a specialist 

stakeholder and communications role.  The members of the office may be permanent staff 

taken from the Organisation Portfolio Office or other areas of the business. They could also 

be temporary or contract resources, brought in specifically.  

Wherever the resources are drawn from, induction and team building would be beneficial. If 

a COE exists, it can provide an introduction into the organisation standards, or a manager 

can give a project or programme briefing. 

 

Running a temporary office through to delivery 

The temporary office should constantly evaluate its processes to ensure they are the best 

approaches, as well as its resources to check they are still providing value. It is 

recommended that these reviews take place at the end of each tranche between the 

programme manager and the office.  

 

 

 

Page 58: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

57  

Key areas to focus on: 

 

Key areas of focus for a temporary programme or project office  Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Closing and Recycling the temporary office 

Due to its finite lifecycle, the temporary office must ensure its documentation, benefits, 

contracts, and resources can be correctly transferred to operational areas.  

If an organisation has tools, methods, and skills from a previous programme or project, it 

can be left as part of a temporary office. It is common to mistakenly reinvent these 

elements, when they are actually buried in documentation. Reusable elements include 

processes, templates, tools, or best practices approaches, which should be fed back into the 

COE to ensure a learning organisation.  

 

 

 

 

 

 

 

 

Page 59: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

58  

Quiz 

 

1. What does the P in POTI Model stand for? 

A. Performance 

B. Processes 

C. Project 

D. Portfolio 

 

 

2. Which stage of the implementation cycle is the business case most 

relevant? 

A. Identify 

B. Define 

C. Deliver 

D. Close 

 

3. How might your strategy change, knowing that some P3O®s only last 

about five years? 

A. Adjust the blueprint 

B. Reduce timescales 

C. Emphasise early benefits 

D. Increase costs at early stages 

 

4. Which document outlines the details of all programmes/projects 

A. Blueprint 

B. Projects Dossier 

C. Business Case 

D. Portfolio Register 

  

 

 

 

 

1B, 2A, 3C, 4D 

Page 60: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

59  

Case Study: No Skeletons in the Cupboard at BT Design This case study describes how P3O® helped the senior management at BT Design make 

business‐critical decisions.  

Designed to enable decision‐making and support organisations going through large‐scale 

change, Portfolio, Programme, and Project Offices (P3O®) is the latest best practice 

guidance from OGC. Programme Manager Chris Barnes discusses how BT Design used P3O® 

to create a Centre of Excellence. Utilising a highly professional group of evangelists for P3O® 

to maximum effect, BT Design established a portfolio management approach which showed 

senior management how the business was functioning.  

In 2008, BT Design (the design and implementation arm of BT) was partway through a 

significant transformation: the rapid expansion into new markets and geographies meant 

we had to rationalise many disparate operational systems and legacy platforms in order to 

realise significant potential benefits. We initiated Milestone – a programme aimed at 

coordinating delivery of these rationalisation efforts, and paving the way for new ‘twenty‐

first century’ platforms and technologies that would enhance our customers’ experience.  

Milestone’s first objective was to understand the nature of the activity already underway. 

Milestone brought together existing programmes focused on network rationalisation, where 

there was a large element of interdependency. It was clear that these programmes were 

being delivered in different ways and were at different stages in their lifecycles.  

We needed to set out consistent approaches to deliver the programmes and follow best 

practice. We felt that P3O® would give us consistency, delivery support and the ability to 

develop our capability. A programme management approach, which underpinned our 

activities with a proven set of tools, was very appealing.  

We charted the lifecycle of programme and project management capabilities to underpin 

how much flexibility we had, so we could assess which programmes were a priority and 

which were not.  

We adopted a portfolio management approach for strategic planning, looking at 

programmes together and analysing how well board‐level decisions were made. Some 

programmes were very large but we wanted to know what their business case was, what 

their benefits were and what management information could support their structure. We 

wanted to be able to provide information that would help senior management make 

informed decisions. We also looked at best practice and the use of MSP® and PRINCE2®, as 

well as BT’s own expertise. We wanted to deliver a tailored approach to programmes and 

grow capability. We decided to implement P3O® from the top down and to set 

requirements that way. We showed the senior management team improved ways to report 

on costs and on what benefits their programmes brought the organisation. We 

demonstrated how important that kind of information is and how it filters down into 

projects. Because we wanted to maximise resources, we had to make some tough, high‐

level decisions. Having the correct information and being able to plan strategically was key. 

The reporting structure of P3O® allowed the flow of information to be traced back to its 

source. 

Page 61: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

60  

How to Operate a P3O® Overview of Tools and Techniques 

 

Tool 

A data manipulation system that informs and improves decision‐making through presenting 

programme and project information and data.  

Tools may be used in the following ways: 

Individual 

Collaborative 

Integrated 

 

Technique 

A procedure to accomplish a certain activity or task. Techniques use tools to collect, 

manipulate, and present the inputs and outputs. 

Standard techniques can be found: 

Within corporate or P3O® standards and policies  

In knowledge repositories 

With programme or project resources through skills transfer or coaching  

Within P3O® templates and deliverables guides 

Through the communication of approaches 

 

 

Benefits of Tools and Techniques 

 Automation of Business Procedures 

  Reduced staff requirements  Reduced overhead on project delivery teams  Reduced need for manual processes e.g. data collection, printing, and distribution 

 

Improved Compliance with Business Procedures 

  Due to automation of workflows, approvals, and governance mechanisms  Integration of business processes with organisation components 

 

 

Page 62: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

61  

Improved Timelines of Decision‐Support Information 

Allowing automatic validation of information against standards  Providing audited business rules around the information  Enabling reallocation of manual processing time to improving information quality  Providing structure to decision‐support information processes  Introducing automated ways of assessing decision‐support information 

 

Improved Decision Making 

Integration of data into repositories provides improved visibility and analysis of 

cross‐programme information  Due to ability to automate view and structure of information  Improved capability to perform what if and scenario analysis  

 

Improved Management 

Connectivity allows for improvements to collaboration between programme/project 

team members 

 

Improved Staff Competence  

Skills transfer  

Reduced reliance on conventional wisdom, and a transfer of knowledge to known 

facts based on historical information 

 

Rationalisation of legacy systems 

Tools for the P3O® that are of an integrated nature may be able to rationalise a 

number of disparate systems 

 

Critical Success Factors 

Focus on adding value to the organisation rather than the features of the tool 

Marketing often focusses on the tool’s features and sophistication rather than their 

use to the organisation  Research services that compare tools also focus on the functions of the tool, when 

they should look at ease of implementation and the quality and credibility of the 

organisation behind the tool  The Blueprint needs to consider any use and benefits of tools that will support the 

P3O® and match the correct tool to the right requirement 

Page 63: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

62  

Match the sophistication of the tools and techniques to the PPM Maturity of 

the organisation 

The standard of the tools and techniques needs to align with the organisational 

maturity because they need to integrate with the business processes, information 

flows, and the competencies of the resources using them 

 

There is a need for programme and project standardisation and data quality 

Advanced tools that can prioritise projects based on data received on costs, benefits, 

etc., cannot work if the data quality is too low, as a result of a lack of project lifecycle 

Ensure the governance for programme and project delivery is in place to enable 

decision making , and align the software with this decision making structure 

 

Understand the intent of the tool or technique 

Some tools will be developed for specific purposes, or aligned with standards of a 

specific industry to better suit their needs. This means that if offered to the wider 

market, it might not be easily adapted to a new environment  Understand the management methods from which the tool/technique was derived 

 

Implement tools as part of an organisational change effort 

Tool suppliers often want a quick implementation, so will sometimes provide 

standard project frameworks or transition plans for implementing tools  It is critical to consider and plan the enabling projects and subsequent projects 

around the tool implementation project.   Manage the tool implementation as a business change project and not as a 

technology implementation  Clear guidance and training should be developed and delivered as part of the 

implementation activities  Tools should be assessed for the time and effort they will require in case new skills 

within the P3O® are required, or if the PPM community will need more time 

 

Maximise successful programme and project delivery through incremental 

implementation 

Consider how implementation may be adopted incrementally to concentrate the 

efforts of the delivery team 

Use pilot and early adopters and ensure all plans and successes are communicated 

effectively to the PPM community 

Page 64: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

63  

The disadvantages/problems of ‘big bang’ project implementation equally apply to 

tool implementation 

 

Agree tool ownership within the organisation 

For integrated tools across the hub portfolio offices, it is important that ownership 

and accountability for tool operations are clearly outlined and enables users to 

provide feedback and enhancements 

 

Exercise 

Explain how organisational maturity impacts on successful tool 

implementation in relation to the CSFs outlined above: 

 

 

Page 65: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

64  

P3O® Tools 

Examples of Tools 

Strategic Mapping Software  EPM Solutions  Enterprise Architecture Systems  Knowledge Management Systems  Performance Management Systems  Risk Management Systems  Requirements Management Systems 

 

Enterprise PPM (EPM) Solutions 

These are the most common integrated tools used in the P3O® that aid in data collection, 

maintenance, and reporting all in one solution. This enables a roll‐up of information from 

one data source to all project/programme levels; they can produce integrated reports for 

multiple audiences from a single set of data. A wide range of EPM solutions are available but 

organisations have difficulty utilising them due to low PPM maturity – this emphasises how 

PPM maturity is a vital consideration in tool selection. 

 

Selecting and Implementing an EPM Solution 

 

Key questions to consider when developing a requirements document for the selection and 

implementation of enterprise PPM solutions 

 

Strategic 

How will the PPM tools support the proposed P3O® Model? 

What is the key objective of the PPM tools?  

Do the features match the organisation’s requirements? 

Is the organisation planning to use the PPM solution to support strategic or business 

planning cycles? 

What features will be required now, and as the maturity of the organisation increases? 

Is the current PPM maturity appropriate for a move from individual tools to 

collaborative tools? 

What is the track record of PPM tools within the organisation? 

Does the organisation need to purchase and implement the PPM tools as part of a 

permanent P3O® model, or use an outsourced solution as part of a temporary P3O® 

model? 

How will senior management respond to new ways of working as a result of PPM 

solutions? 

What are the organisational change management implications of moving to a PPM 

solution? 

Page 66: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

65  

Is the organisation’s investment in multiple individual tools/software less efficient or 

effective than implementing an enterprise PPM solution? 

What are the risks associated with the implementation of the PPM solution and how will 

they be managed 

Process 

What processes will the PPM solution be aligned with? Can it support the current 

processes and evolve to accept the new processes? 

What processes can be done more efficiently using the PPM solution than by the 

manual one? 

What benefits can be realised by implementing more features? 

Which processes are the highest priority to implement to realise early benefits? 

How will the PPM solution integrate with the wider organisation? 

Organisation 

What roles and responsibilities will the PPM solution require? 

What skills/competencies are required to implement, maintain, and improve the 

PPM solution? 

Will the PPM maturity of the organisation impact positively or negatively the PPM 

solution, and the realisation of its benefits? 

Are suitably skilled resources available to operate the PPM solution in production? 

Tools and Technologies 

Will the architecture support project delivery? 

What licence requirements best suit the organisation’s approach? 

Should the tools be purchased outright, outsourced, or used via a host solution? 

Are the PPM tools easily configurable? 

What costs are associated with the customisation of the tool? 

What integration requirements will there be to legacy or line‐of‐business systems? 

What are the minimum data requirements? How much effort is needed to ensure all 

aspects of information assurance? 

Information Flows 

What key questions are being asked by senior management about the portfolio? 

What information is needed from project/programmes to achieve this? 

What information does the organisation need to monitor to achieve better 

outcomes? 

Will the information be automatically rolled‐up, or will multiple systems be needed? 

Can data be easily migrated from current approaches into the PPM solution? 

Can data be easily validated after migration to maintain data quality? 

What capability is there to provide metrics on the health of the information within 

the EPM solution? 

Page 67: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

66  

P3O® Techniques 

Examples of Techniques 

Portfolio Prioritisation and Optimisation  Complexity Modelling  Management Dashboards  Knowledge Management  Business Process Swimlanes  Capacity Planning  Assurance, Gated reviews, and Health Checks 

 

Prioritisation and Optimisation 

Objective: To categorise the programmes and projects within a portfolio, based on agreed 

measures that are commonly financial or use a multi‐criteria analysis, such as risk.  

 

 

Benefits: Aids in determining where investment should be directed, rather than all projects 

going full‐throttle, using the same resources and being cost inefficient. It supports senior 

management in decision–making, evaluating how programmes/projects are aligned with 

strategic objectives. 

 

 

 

 

 

 

 

 

 

An example of strategic alignment and risk level diagram Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

 

Page 68: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

67  

Complexity Modelling 

Objective: To determine the appropriate lifecycle and governance for the programme/ 

project based on its complexity. 

Benefits: Provides a structured approach to the tailoring of the standard lifecycle and 

governance, thus providing both flexibility and standardisation of portfolio management 

requirements. 

Activities involved: The organisation must determine the criteria for the complexity of 

projects and programmes. Analysis is performed to discover the drivers and their 

parameters for the aforementioned criteria. Weightings are applied to create an algorithm 

that results in an overall complexity score. The complexity score is used to determine the 

recommended governance structures and tailored lifecycle for the project. 

It is important to know that this technique will require refinement and ongoing review to 

ensure that the weightings are appropriate to the governance applied. 

 

Capacity Planning for Resource Management 

Objective: To understand the resource capacity and competency supply‐and‐demand‐ levels, 

as well as take action to match these appropriately to delivery requirements. 

Benefits: Reduces any obstacles in relation to capacity or competency that may impede 

project/programme delivery 

Sometimes, capacity planning is just an annual baseline for the planned porfolio that 

informs project portfolio phasing to reduce gaps between resource supply and demand for 

the year. It may also only address the capacity of key known resources points of failure, or it 

may include competencies as well. As P3O® capacity increases, capacity planning may 

involve frequent assessments based on resource experience.  

 

Knowledge Management 

Objective: To create an environment, including providing tools and processes, to support the 

creation and sharing of knowledge. 

 

Often confused with information management, knowledge management differs in that it 

includes ideas, insights, experience. Due the difficulty of documenting that data, knowledge 

management focuses on connection people.  

The P3O®’s management of knowledge should be sensitive to the organisation’s view of 

knowledge, but the P3O® can also change the opinion of the organisation by introducing 

new knowledge management principles that tap into previously undervalued knowledge. 

 

Page 69: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

68  

Management Dashboards  

Objective: To provide decision‐support information across the portfolio using highlight and 

exception‐based reporting, therefore giving a rolled‐up view of more detailed information.  

 

Benefits: Supplements larger volumes of detailed reporting, allowing the decision‐makers to 

better determine progress and understand where intervention may be required.  

 

Activities Involved: When the programme or project sends in a status report, the dashboard 

rearranges the data across different metrics. This allows the project board to quickly see key 

information and evaluate where requires attention. The management board is updated 

periodically and provided to the relevant governance group. The design and content of the 

board must be fit for purpose for the relevant decision‐making bodies. Fitness for purposeis 

confirmed by each of them, to ensure all requirements are satisfied. 

It is important to note that this technique requires trustworthy and reliable information as 

its main input. Information Assurance shoould be applied to all data to ensure is trusted to 

be the one version of the truth. If traffic lights are used, there must be consistent, agreed 

use of red, amber, and green to ensure objective reporting.  

 

An example of a portfolio management dashboard Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

Page 70: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

69  

Assurance, Gated Reviews, and Health Checks 

Objective: To provide an individual assessment of the performance of the portfolio, 

programme, or project against its objectives and the standards. 

Benefit: Provides objective assurance of the decision‐support information inputted into the 

P3O® and the reactive ability to get the programme or project back on track 

 

Business Process Swimlanes 

Objective: To document standard and repeatable business processes with appropriate 

linkages and agreed accountabilities. 

Benefits: Documents, baselines, and continually updates repeatable processes as progress 

evolves in response to lesson sharing and increased PPM maturity. 

 

 

An example of a swimlane for schedule management Based on AXELOS P3O® material. Reproduced under licence from AXELOS Limited. All rights reserved.  

 

Page 71: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

70  

Exercise: Match up the techniques and their objectives 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

To determine the appropriate lifecycle and governance for the programme/project based on its complexity.  To provide an individual assessment of the performance of the portfolio, programme, or project against its objectives and the standards.  To create an environment, including providing tools and processes, to support the creation and sharing of knowledge.  To understand the resource capacity and competency supply‐and‐demand‐ levels, as well as take action to match these appropriately to delivery requirements.  To document standard and repeatable business processes with appropriate linkages and agreed accountabilities.  To provide decision‐support information across the portfolio using highlight and exception‐based reporting, therefore giving a rolled‐up view of more detailed information.  To categorise the programmes and projects within a portfolio, based on agreed measures that are commonly financial or use a multi‐criteria analysis, such as risk. 

  Prioritisation     Complexity Modelling     Management Dashboard     Knowledge Management     Business Process Swimlanes     Capacity Planning     Assurance, Gated reviews, Health checks  

Page 72: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

71  

Quiz 

 

1. Which statement regarding Assurance functions and services is FALSE?  

A. Takes various forms including regular health checks B. Carries out audits of the programme performance C. Provides guidance on the decision support information D. Provides independent assurance in addition to that provided 

by a Programme Board 

 2. What tool links information in a hierarchical manner for multiple 

business change initiatives?  

A. Individual B. Collaborative C. Integrated D. Assurance 

  

3. Which of these is NOT a benefit of tools and techniques?  

A. Improved compliance with business procedures 

B. Reduced staff requirements 

C. Provides structure to decision‐support information 

D. Rationalisation of legal systems 

 

4. Where are standard techniques typically documented?  

A. Within knowledge repositories  B. Within the Portfolio Office Business Case C. Within P3O® templates and deliverables guides 

D. Within a number of places  

 

 

  C, C, D, D 

Page 73: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

72  

Roles P3O®s categorise roles into three sections: Management, Generic, or Functional. If the office 

is large and/or permanent, the functional roles will often be assigned to one or more 

people, whereas if it is small or temporary, the roles are often amalgamated under one job 

desciption. 

 

Management Roles 

 

All management roles require: 

Strong leadership and management skills, coupled with strong PPM skills 

The ability to make and maintain relationships with all parts of the business, to 

ensure all initiatives meet the requirements of the portfolio board 

An understanding of the bigger picture and the objectives of the portfolio in regards 

to the wider environment and how to ensure alignment with wider policy and 

strategic initiatives 

Established relationships across the business and portfolio, including senior 

managers, programme and project teams, and third‐party service providers 

 

P3O® Sponsor 

Purpose: 

To support and guide the implementation and continuing lifecycle processes of the 

P3O® 

Use strong leadership, management, and authority to establish and continually 

improve the P3O® 

 

Responsibilities: 

Develop and maintain business case, to secure the investment to re‐energise the 

P3O® 

Ensure business needs and issues are addressed properly 

Review whether projects and programmes are aligning with wider policies 

Identify how P3O® can assist in the change portfolio of other business areas 

Risk Management 

 

 

Head of P3O® (Permanent Office) 

Page 74: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

73  

Purpose:  

To set‐up and run the permanent office, perhaps taking over the role of portfolio 

manager as well 

To ensure the integrity of the portfolio and its contents 

Identify any gaps in iniatives to clarify which activities will fill them 

 

Responsibilities: 

Work with senior management to define and implement the portfolio framework 

Create strategies for the planning, monitoring, and delivery of the portfolio 

Support the portfolio director in agreeing projects to include in the portfolio 

Maintain relationships with other business initiatives to prevent responsibility 

overlap 

Design management dashboards 

Allow programmes and projects access to strategic information 

Establish framework agreements for the purchase, roll‐out, and maintenance of PPM 

tools, training, and consulting 

 

 Head of Temporary Programme or Project Office 

Purpose: 

To set‐up and run the temporary office  

Identify any gaps in iniatives to clarify which activities will fill them 

Have the ability to deputise for the programme manager 

 

Responsibilities: 

Support overall integrity and coherence of programme or project 

Support the programme manager in agreeing projects to include in the programme 

Ensure exisiting initiatives and projects are adopted into the programme 

Agree project closure with programme/project manager 

Maintain relationships with other programmes to prevent responsibility overlap 

Identify dependencies among the programme, its projects, and other initiatives 

Report progress via management dashboards 

Run end‐of‐tranche reviews and benefits reviews 

Discover the reasons why strategic initiatives are underperforming  

Inform project or programme of any changes 

Be responsible for team objectives and continual improvement of P3O® service 

Workload management and prioritisation between ad hoc requests and deliverables 

 

Page 75: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

74  

Generic Roles 

Portfolio Analyst 

Purpose: 

To facilitate development and management of an optimised portfolio 

Ensure senior management decisions lead to fulfillment of strategic objectives 

Responsibilities 

Provide strategic overview of all portfolio contents, reporting anomalies 

Evaluate process for possible improvements to aid project workflow and delivery 

Manage prioritisation model 

Initiate reviews of post‐programme/project evaluation reports and benefits to 

ensure all goals are met 

Design portfolio delivery plan, resource schedule, risk register, KPIs, and portoflio 

dependencies register 

Assess benefits management across programmes to identify gaps and overlaps and 

eliminate double counting   

Scan for impending strategy or policy changes 

Provide aggregrated analysis to the strategy board 

Develop portfolio stakeholder strategy and ensure effective communication 

Programme or Project Specialist  

Purpose: 

To provide specialist hands on support for programme and project managers 

Promote PPM management methods and standards to implement best practice 

Provide a consultancy service to boards (could be advice centre or have a specific 

purpose like workshops) 

Work with programme manager and business managers to define governance levels 

and decide on level of support 

Responsibilities  

Coordinate information about the running, progress, and problems of 

programmes/projects 

Provide briefings on their roles and responsibilities to the board and assurance staff 

Review completed programmes/projects to gather preventative information on 

problems and/or good practice 

Design and support governance and reporting 

Build register of approved training courses and PPM events, detailing content, level, 

and dates  

Maintain a repository of good programme/project documentation and a library of 

other useful resources, such as training aids or reference materials 

Page 76: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

75  

Programme/Project Officer 

Purpose: 

To improve the planning and delivery process, by collecting and maintaining data in 

consistent form 

Responsibilities: 

Establish guidelines, procedures, and templates to collect and maintain consistent 

data 

Implement information management system, and manage all configuration libraries 

Provide basic training in configuration management techniques 

Establish risk, issue, and change control processes and templates and assist in their 

delivery  

Provide a coordination/administration service to a programme or project 

Exercise: Your organisation does not have enough funds to fill all these roles. Evaluate their use, by 

filling out the table below with a summary of the main consequences to the P3O® if 

they’re lost. 

 

P3O® Sponser     

Head of P3O®     

Head of Temporary Office     

Portfolio Analyst     

Programme Specialist     

Programme Officer     

Page 77: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

76  

Functional Roles 

Benefits and Value 

Purpose 

The purpose of the benefits and value role is that a reliable ‘fit for purpose’ approach to 

benefits and value management is implemented and applied through the portfolio or 

programme, and that benefits realisation is enhanced from the organisation’s investment in 

change. 

This role is typically undertaken by the portfolio benefits manager, or by someone that 

reports to the portfolio benefits manager. 

The finance department also plays a vital role in shaping the approach, methods, and 

standards to be implemented. 

Responsibilities 

Developing and sustaining the P3O®’s benefits management framework 

Forming the infrastructure essential in the implementation of the benefits 

management framework 

Providing training and awareness‐building meetings on the application of the 

benefits management framework 

Contributing in the investment appraisals, making sure that business‐case benefits 

forecasts are dependable, and that they meet the organisation’s benefits eligibility 

rules 

Working with the business change managers and their teams to encourage more 

effective benefits management practices 

Providing guidance and support to the PPM and business‐as‐usual colleagues on the 

expansion of initiative‐level benefits forecasts and benefits management policies 

Providing assurance on the effectiveness of benefits management 

On behalf of portfolio or programme management: 

o Assisting the agreement of the benefits management strategy 

o Leading benefits and dis‐benefits identification activities 

o Leading and facilitating MoV studies 

o Holding benefits‐mapping workshops, as well as evolving and maintaining a 

benefits map 

o Facilitating agreement on the benefits realisation plan 

o Upholding the benefits forecast 

o Evaluating the impact of change requests for their possible effect on benefits 

realisation 

o Tracking and reporting benefits realisation development for the dashboard 

o Escalating issues with benefits realisation, as appropriate 

Setting the standards for, and observing, post‐implementation reviews to compare 

benefits realised with the benefits forecast 

Page 78: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

77  

Working with the business managers or business change mangers to recognise 

further opportunities for benefits management 

Frequently revising and improving the effectiveness of benefits management 

arrangements 

Assessing benefits management across a number of programmes or projects to 

detect gaps, overlaps and conflicts, and eliminating double‐counting in the benefits 

plans of individual programmes and projects 

 

Commercial 

Purpose 

The purpose of the commercial role is to ensure that the organisation carries out the role of 

‘informed customer’, and that all commercial/procurement practices and decisions meet 

the designated standards and offer the organisation value for its money. 

It can also take on the role of supplier relationship manager, developing efficient and 

effective relationships with suppliers, outsourcers, and partners. 

This role may be a P3O® role, but is more likely to be embedded in the P3O®, with formal 

line management from the commercial, procurement, or purchasing function. 

Responsibilities 

Early engagement with commercial, procurement, or purchasing teams to scope the 

commercial element of the portfolio, programme, or project 

Providing ongoing liaison with commercial, procurement, or purchasing teams 

Providing liaison with the relevant statutory procurement functions 

Developing and executing the portfolio, programme, or project procurement 

strategy 

Undertaking contracts management, including tracking deliverables against existing 

contracts and managing any third‐party or sub‐contractor contracts 

Ensuring that all contracts remain up‐to‐date and exit strategies are in place 

Providing analysis of any requests for change that may have a contractual impact 

Coordinate purchase order activities 

Ensuring compliance with any applicable organisational, national, and international 

standards and legislation 

Providing commercial expertise/advice to the portfolio and programme teams, and 

constituent projects 

Facilitating relationships between the organisation’s senior management 

community, SROs, and senior managers within the supplier community 

Taking on supplier relationship manager responsibilities, which may include: 

o Aiding the management of supplier and contractual risk, gauging all aspects 

of supplier performance, and initiating remedial actions whenever and 

wherever required 

Page 79: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

78  

o Conducting contractual reviews with all major suppliers to the programme or 

project on a regular basis 

o Handling all aspects and stages of the contract lifecycle on behalf of the 

programme or project manager 

o Sustaining a catalogue of suppliers, services, products, and contracts within 

the programme or project 

o Providing a single liaison and contact point for all supplier and contractual 

issues 

o Developing a full understanding of supplier strategies, plans, business needs, 

and objectives 

o Ensuring that the programme or project is working in partnership with 

suppliers, building on long‐term relationships 

o Enabling the development and negotiation of appropriate, achievable, and 

viable contracts and contractual goals with suppliers 

o Facilitating the negotiation of ‘value‐for‐money’ services and products with 

all suppliers 

 

Communications and Stakeholder Engagement 

Purpose 

The purpose of this role is to make sure that the management of the portfolio, programme, 

or project’s stakeholders is effective. 

Responsibilities 

Sustaining the list of stakeholders and their interests 

Leading the work to detect and document the programme stakeholders, their 

interests, and their possible influence on the programme 

Aiding the formulation of a stakeholder engagement strategy and the related 

portfolio, programme, or project communications plan to ensure: 

o An awareness amongst all stakeholders of the benefits and influences of the 

portfolio or programme 

o That expectations do not drift out of line with the planned delivery 

o Commitment from stakeholders to the changes being presented, confirming 

the long‐term success of the portfolio, programme, or project 

o That all stakeholders are educated on the progress before, during, and after 

the implementation or delivery of the project outputs and programme 

outcomes 

o The promotion of key messages from the portfolio, programme, or project 

o A demonstration of the commitment to meeting the requirements of the 

portfolio, programme, or project sponsors 

o True two‐way communication with stakeholders due to encouragement in 

providing feedback 

Page 80: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

79  

Endorse opportunities to maximise the benefits acquired from the portfolio or 

programme 

Organise stakeholder engagement and communication, ensuring effective timing 

and interdependency management of communications 

Coordinate internal portfolio and programme communications 

Monitor the effectiveness of communications 

Handle press enquiries 

Establishing and sustaining any portfolio, programme, or project intranet site or 

information portal 

 

Information Management 

Purpose 

The purpose of this role is to act as the custodian and guardian of all master copies of the 

portfolio, programme, or project’s information. 

This role should ideally work closely with the security function or department in an 

organisation in order to confirm that full information and physical security is considered 

within a portfolio, programme, or project. 

Responsibilities 

Making sure that significant information assets are under configuration management 

and change control, sharing information within the project, programme, or portfolio 

Producing and operating libraries or other storage areas to store products and keep 

reference materials up‐to‐date 

Developing and handling document control procedures to cover baseline 

management, controlled issue of master documents, version control, document 

history, and distribution lists 

Creating an identification scheme for all products, and assisting in the identification 

of products 

Establishing and administering baselines 

Controlling the receipt, storage, and issue of all portfolio, programme, or project 

products 

Keeping a record of all issued copies of products and informing holders of any 

alterations to their copies 

Undertaking configuration audits and maintaining status information on all products 

Guaranteeing that supplier configuration items are under control by providing a 

single point of entry entering, and exiting, the programme for such items 

Seeking out knowledge about how to access relevant information outside of the 

programme office, other systems in the organisation, and internet resources 

Ensuring that procedures are put into place to handle the security and secrecy of 

programme/project documentation or other assets 

Page 81: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

80  

Consultancy and Performance Management 

Purpose 

The purpose of this role is to offer internal consultancy and expertise in PPM and 

organisation processes, as well as the monitoring of certain programmes and projects.  

The services provided are focused on sustaining a minimum set of standards and achieving 

the target performance. 

Post holders should seek to continually improve the performance of the portfolio, 

programme, and projects within an organisation. 

Responsibilities 

Making sure that their own procedures and templates are maintained in line with 

industry best practice 

Setting up and maintaining a performance improvement plan 

Setting up and tracking portfolio, programme, or project metrics to monitor and 

control performance 

Sharing lessons and formulating action plans 

Providing professional high‐level planning skills for programmes and projects 

Providing project assurance service to project and programme boards, either directly 

or through the engagement of third‐parties 

Running facilitated workshops 

Undertaking mentoring or coaching of portfolio, programme, or project staff, 

including programme and project sponsors/SROs 

Undertaking portfolio, programme, or project induction 

Creating case‐study material and feeding back to the COE 

Performing programme and project fast‐track, start‐up, and closure assistance 

Assisting in programme and project ‘rescues’ through hands‐on development and 

the delivery of action plans 

Acting as a trainer in PPM for internal courses/workshops 

Acting as method specialist/experts in PPM 

Providing technical leadership, coaching, and mentoring in all PPM tool utilisation 

Providing consultancy‐style services to programme and project delivery teams at the 

definition stage, as well as throughout the lifecycle 

Carrying out health checks on programmes and projects at any time during the 

lifecycle 

Providing business performance monitoring and reporting 

Keeping abreast of, and evaluating the effectiveness of, new programme and project 

management tools and techniques 

Providing performance deviation escalation management 

 

 

Page 82: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

81  

Finance 

Purpose 

The purpose of the finance role is to create a professional finance function within the 

portfolio, programme, or project to ensure the timely provision of funding and effective 

financial control. 

This may be a P3O® role, but is more likely to be embedded in the P3O® with formal line 

management from the finance function. 

Responsibilities 

Working with the chief finance function to assist the availability of suitably profiled 

funding across financial periods 

Controlling budget allocations and estimates of future spending 

Evolving and sustaining the portfolio, programme, or project financial controls 

Revising and tracking portfolio, programme, or project costs and revenues 

Evaluating and collecting portfolio, programme, and project financial information 

Assisting in benefits profiling 

Handling invoicing and collection activities 

Arranging monthly financial reports for the portfolio, programme, or project 

manager 

Producing and maintaining financial models for the depreciation and amortisation of 

programme and project costs 

Providing programme accountancy aid with: 

o Development and refinement of programme and project business cases 

o Creating and distributing financial reports 

o Development and maintenance of the resource management plan 

o Advice on cost control and opportunities for savings 

o Adherence to accounting procedures 

o Capitalisation of capital assets 

 

Issue 

Purpose 

The purpose of this role is to take the lead in ensuring that the portfolio, programme, or 

project has operative processes in place to recognise, monitor, and solve any issues. 

Responsibilities 

Developing and executing the issue management strategy, making sure that the 

commercial function leads on contractual issues 

Communicating the issues management strategy, and the benefits of following it, to 

all personnel 

Forming and sustaining the portfolio, programme, or project issues register 

Page 83: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

82  

Registering issues for ensuing investigation and resolution, monitoring items 

identified as requiring action, prompting timely actions, and reporting on whether 

required actions have been carried out 

Making sure that all issues have a nominated owner 

Ensuring that the agreed responses to issues are planned, resourced, and applied 

Communicating with stakeholders, particularly those who are directly affected either 

by the issue itself or by the response to the issue 

Assessing how effective any issue response has been 

Aiding in the regular monitoring and review of all issues 

Examining issue registers across the portfolio, programmes, and projects, regarding 

issues and their handling 

Enabling cross‐programme/cross‐project impact analysis 

Escalating issues to a higher authority 

Liaising with the information role on configuration management 

 

Change Control 

Purpose 

The purpose of this role is to take the lead in ensuring that the portfolio, programme, or 

project has effective processes in place to identify, monitor, and resolve changes. 

Responsibilities 

Developing and applying the change control process, making sure that the 

commercial functions lead on contractual changes 

Clearly communicating the change control process and the benefits of following it, to 

all personnel involved with the portfolio, programme, or project 

Creating and sustaining the portfolio, programme, or project change register 

Registering changes for subsequent investigation and resolution 

Making sure that all changes have a nominated owner 

Ensuring that all changes have appropriate impact analysis and are planned, 

resourced, and implemented through formal configuration management 

Communicating with stakeholders, particularly those who are directly affected either 

by the change itself or by the response to change 

Assisting in the regular monitoring and review of all changes 

Examining change registers across the portfolio or programme to look for common 

themes and establishing consistent resolution procedures 

Forming and maintaining an efficient two‐way flow of information between the 

portfolio, programmes, and their projects 

Escalating changes to a higher authority 

Liaising with the information role on configuration management 

 

Page 84: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

83  

Planning and Estimating 

Purpose 

The purpose of the planning and estimating role is to take charge in facilitating the 

development and maintenance of the portfolio, programme, or project plan and 

dependency logs. 

Responsibilities 

Outlining planning standards for portfolio, programmes, or projects to enable ease 

of roll‐up of milestone data and dependencies 

Facilitating the design, development, and ownership of the portfolio, programme, or 

project plan 

Sustaining and updating the plans, advising on missed forecasted milestones, missed 

dependencies, and impact assessment  

Maintaining and updating resource plans, advising on resource clashes and 

shortcomings 

Making sure all product‐based plans include activities, time, and resource estimates 

for risk mitigation 

Ensuring quality review activities and associated time have been allocated accurately 

Investigating interfaces and dependencies between projects, recommending 

appropriate actions where anomalies exist or in any areas of concern 

Undertaking the tracking and maintenance of dependencies 

Creating and operating mechanisms to track portfolio, programme, or project 

delivery against the plan 

Recognising and reporting deviations and trigger reports where appropriate 

Reviewing plans against the business‐as‐usual plans to ensure change can be 

adopted effectively 

Providing estimating support to the portfolio, programmes, or projects 

Defining and managing time‐recording processes 

Making sure that impending policies or strategy changes are evaluated for their 

influence on the portfolio, programme, or project plans or dependencies 

 

Planning and Estimating 

Purpose 

The purpose of this role is to take responsibility for facilitating the development and 

maintenance of the portfolio, programme, or project plan and dependency logs. 

Responsibilities 

Describing planning standards for portfolio, programmes, or projects to enable ease 

of roll‐up of milestone data and dependencies 

Page 85: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

84  

Assisting in the design, development, and ownership of the portfolio, programme, or 

project plan, making sure that all milestones and internal and external dependencies 

are recognised, recorded, and observed 

Sustaining and updating plans, advising on missed forecasted milestones, and impact 

assessment 

Maintaining and updating resource plans, and advising on resource clashes and 

shortcomings 

Ensuring all product‐based plans include activities, time, and resource estimates for 

risk mitigation 

Making sure quality review activities and associated time have been allocated 

accurately 

Evaluating interfaces and dependencies between projects, and recommending 

appropriate actions where anomalies exist, or where there are areas of concern 

Undertaking the tracking and maintenance of dependencies 

Establishing and operating mechanisms to compare the portfolio, programme, or 

project delivery against the plan 

Detecting and reporting deviations and trigger exception reports when appropriate 

Revising plans against business‐as‐usual plans to ensure change can be adopted 

effectively 

Providing estimating support to the portfolio, programmes, or projects 

Defining and managing time‐recording processes 

Ensuring impending policy of strategy changes are assessed for their impact on the 

portfolio, programme, or project plans 

 

Quality Assurance 

Purpose 

The purpose of the quality assurance role is to lead the work to ensure that any new 

products or services delivered by the portfolio, programme, or project are fit for purpose 

and capable of delivering the benefits required by the organisation board. 

Responsibilities 

Ensuring compliance with any applicable organisational, national, and international 

standards and legislation 

Bringing together portfolio, programme, or project staff of different disciplines and 

drive the group to plan, formulate, and agree a comprehensive quality management 

strategy and quality management plan 

Creating consistent quality practices and standards 

Making sure tests and procedures are properly understood, carried out and 

assessed, and product modifications are investigated if necessary 

Working with the finance manager/analyst to ensure the portfolio, programme, or 

project complies with audit requirements 

Page 86: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

85  

Developing bespoke processes, and standards and templates for quality 

management 

Coordinating quality reviews of portfolio, programme, or project documents and 

deliverables 

Providing health checks 

Providing direction on quality criteria, reviewers, and sign‐off authority to ensure 

cross‐portfolio or cross‐programme reliability 

Working with commercial/purchasing staff to ensure an effective interface with 

suppliers’ quality systems and oversee the quality review process for contractual 

supplier deliverables 

Liaising with COE or other bodies to arrange stage‐gated reviews 

Coordinating gated reviews and stage reviews, and ensuring all information is 

available in a timely manner and a quality format 

 

Resource Management 

Purpose 

The purpose of the resource management role is to ensure that current and future 

programmes and projects are equipped with enough human resources of the right skills, at 

the right time they are needed. 

Responsibilities 

Providing a capacity planning and resource tracking service across a portfolio or 

programmes 

Capturing the resource requirements of the portfolio, programme, or project and the 

P3O® itself 

Forecasting future resource needs, based on portfolio/programme/project plans, 

close liaison with the relevant managers, and wider business plans  

Providing a view of commitments on other programmes/projects and/or on 

business‐as‐usual activities that will influence the ability of a portfolio, programme, 

or project to deliver 

Deciding on the best source for the required resources, depending on the long‐term 

requirements of a particular skill and its likely availability 

Planning and initiating the acquisition of the essential staff, in terms of both skill 

content and quantity, ensuring they are in place at the time needed 

Observing the deployment of staff, arranging new postings in advance of 

assignments ending, to meet staff development needs, and to maintain a good 

match of skill to role 

Working with human resources and line management to facilitate succession 

planning, including knowledge management and leavers’ process as required 

Sustaining a database of resources, for people and their skills/attributes, location, 

availability, contact details, and lead responsibility for the resource 

Page 87: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

86  

Taking an active role in the training and development of portfolio, programme, or 

project staff to increase the available skills capability and capacity within the 

business 

Revising the provision of skills audits to regulate whether the proposed 

programme/project staff have the required skills to deliver their role on the 

programme or project 

Establishing formal mentoring and coaching guidelines and mechanisms 

Providing ‘help squads’ – supplementary skills to fill shortfalls within the portfolio, 

programme, or project 

Handling consultants’ and interims’ contractual status, closely monitoring use of 

externals to ensure ongoing value for money 

Managing resource planning, data collection, and PPM skills development 

 

Risk 

Purpose 

The purpose of this role is to take the lead in making sure that the portfolio, programme, or 

project has effective processes in place to identify and monitor risks, has access to reliable 

and up‐to‐date information about risks, and uses the appropriate controls and actions to 

deal with risks. 

Responsibilities 

Creating a risk management strategy for the P3O® in accordance with the corporate 

risk management policy 

Forming and maintaining the portfolio, programme, or project risk register 

Supporting the identification and ongoing management of risks by running risk 

workshops and risk‐review workshops 

Making sure that all risks have a nominated owner 

Ensuring all project risks that have wider programme implications are escalated and 

dealt with at programme level 

Providing cost estimates for all outstanding risks and making sure that risk mitigation 

costs do not exceed risk occurrence costs 

Communicating with stakeholders, particularly those who are directly affected either 

by the risk itself or by the risk responses 

Evaluating how effective any response actions have been and whether the risks 

identified have actually materialised, including the realisation of opportunities 

Reviewing all risks on a constructive, ‘no blame’ basis 

Establishing and sustaining an efficient two‐way flow of information between the 

portfolio, programmes, and their projects regarding risk handling 

Examining risk registers across the portfolio or programme  

Establishing consistent mitigation and contingency plans for risks that should be 

tackled across the portfolio or programme 

Page 88: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

87  

Supporting the sharing of risk registers with the supplier community 

Assessing and monitoring the effectiveness of risk processes and refining it as 

necessary 

 

Reporting 

Purpose 

The purpose of the reporting role is to provide a reporting service to the portfolio, 

programme, or project. 

Responsibilities 

Providing consistent reports to boards, including a commentary on performance, 

coordinating upward aggregation of data/information, and reports 

Making sure the reports are reliable through consistent traffic lights 

Recognising and reporting abnormalities and trigger exception reports when 

appropriate 

Developing procedures to fulfil the internal reporting needs of the programme, 

including the development and production of any contractual reports 

Making sure that reporting deadlines are achieved 

Ensuring that the reporting process is robust, exception‐based, and flexible enough 

to meet the changing needs of the programme or project 

Creating a weekly/monthly reporting calendar with reminders to information 

contributors 

Implementing and managing the weekly and monthly reporting cycle, chasing 

information as required and challenging the quality of the component data 

Building and sustaining an information base of trend data for the programme or 

project reporting 

 

Secretariat/Administrator 

Purpose 

The purpose of this role is to provide portfolio, programme, or project administrative 

support and a secretariat function for the relevant boards. 

Responsibilities 

Sustaining knowledge/reference libraries/repositories in relation to governance 

boards 

Supporting facilities requirements as far as possible, matching supply to demand 

Assisting the resource management role with the acquisition of resources by 

maintaining relationships with external organisations that can supply them 

Page 89: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

88  

Supporting the quality assurance role by liaising with the COE or other bodies to 

assemble health checks, audits, third‐party reviews and stage‐gated reviews 

Forming a help desk for enquiries/issues/problems 

Assisting in administrative support to the P3O®, including workshop/meeting 

administration and the establishment and maintenance of the filing system 

Providing logistical support for training courses 

Providing administrative support for other non‐PPM activities 

 

Tools Expert 

Purpose 

The purpose of the tools expert role is to provide expertise in the software tools to support 

the change environment. 

This provides support to the PPM community to configure software, or to provide training 

and coaching in its use. 

Responsibilities 

Inspecting the market to source tools 

Liaising with tools vendors regarding requirements specifications 

Liaising with tools vendors regarding implementation plans and training 

Carrying out internal mentoring/coaching in tools 

Advising new programmes and projects on the appropriate use of tools 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 90: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

89  

Case Study: Skipton Building Society  

Summary 

Skipton Building Society is the fourth largest building society in the UK, with assets of about 

£14.6 billion, 840,000 members, and 1,200 employees. At the beginning of 2010, after 

incurring losses in the core business following the market crash in 2008, it faced a 

substantial challenge in returning the business to profitability while meeting the 

expectations of its board and the Financial Services Authority (FSA).  

A review in March 2010 highlighted the need to consider some 80 plus ‘necessary’ projects, 

yet the organisation did not have the processes and capability in place to prioritise 

resources, or deliver them.  

Between April and September 2010, a portfolio and project investment governance 

framework and portfolio office were implemented to enable Skipton Building Society to 

validate, prioritise, and deliver the necessary business changes with the resources available, 

at an acceptable risk. This work used various aspects of the Portfolio, Programme, and 

Project Offices (P3O®) guidance, which is part of the Best Management Practice portfolio, 

adapted to Skipton Building Society’s needs.  

Defining the governance framework first, followed by setting up the portfolio office while 

engaging the senior executive team in a top‐down approach worked well. Establishing the 

transformation (portfolio) board early created a demand for set up and operation of the 

portfolio office services. Nine months after set up, the portfolio office and transformation 

board were both working well. However, some challenges remained, notably resource 

management, integrating the IT shared services organisation into the process and 

integration with the corporate planning process. 

 

Background 

The company was created on 1 May 1853 as the Skipton and District Permanent 

Benefit Building Society 

Today, Skipton Building Society is the fourth largest building society in the UK, with 

assets of about £14.6 billion, 840,000 members, and 1,200 employees. The building 

society has a group structure comprising the core business and a number of 

subsidiaries that are run independently; notable among these are Homeloan 

Management Ltd (HML) and Connells  

As a building society, several factors make the organisation different from a bank: 

o The management must do what is best for its members (customers), who are in 

effect the shareholders 

o It must lend for mortgages and be largely funded through retail deposits 

Following the market crash in 2008, the core business suffered losses in 2009, only 

making a profit because of the contribution from its subsidiaries 

Page 91: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

90  

In February 2010, Skipton Building Society had to lay off staff for the first time to 

reduce costs and faced significant challenges in restoring the profitability of the core 

business, while meeting greater demands for reporting, controls and performance 

from FSA 

Before 2008 – Project management resources and capability were based within the 

IT organisation 

2008 – The business projects team was set up, which includes project managers, 

business analysts, and project support functions 

2009 – IT‐based project managers were transferred to the business projects team. 

The team expands to five project managers, two project support staff, and five 

business analysts 

2009 – Project methodology based on PRINCE2® defined and signed‐off: 

o Scarborough Building Society merger project completed  

o Chesham Building Society merger project completed 

February 2010 – Reorganisation leads to disbanding of project office functions within 

business projects team 

 

The Challenge 

In March 2010, senior management recognised that there were significant challenges 

ahead, which would require a transformational change within Skipton Building Society, 

alongside the delivery of a significant number of projects to meet the expectations of the 

board and external regulators (FSA). A review of the project landscape undertaken by 

internal staff and external consultants identified the following issues: 

Eighty‐plus possible ‘necessary’ projects outlined by management, including a critical 

‘profit improvement plan’ 

Planning processes were not sufficient to enable comprehensive prioritisation, 

approval, on‐going control of the portfolio, nor delivery of the benefits for each 

programme/project. Projects were initiated by individual managers, with 

prioritisation based on ‘who shouts loudest’ 

Programmes/projects were not being tracked for costs or realisation of benefits 

Project sponsors ‘sponsored’, but project managers ‘owned’, projects 

No accountability for outcomes or benefits  

‘Business projects’ were viewed as ‘IT based’, and hence often the ‘responsibility’ of 

IT to deliver 

Delivering change was viewed as ‘project delivery’; that is, delivery of an IT system or 

other output 

The challenge was then to enable the organisation to validate, prioritise, and deliver the 

necessary business changes with the resources available, at an acceptable risk. Key to 

meeting this challenge was establishing a governance framework for the business change 

portfolio and a portfolio office to support it. 

Page 92: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

91  

Governance Framework 

Working with the senior management team, we agreed the need to drive change from the 

top of the organisation and to incorporate governance of business change within the overall 

corporate governance framework. In this respect, the P3O® ‘run the business, change the 

business’ concept was helpful in understanding the need. 

It was agreed at the outset in April 2010 that the scope of any governance framework would 

exclude subsidiaries as these operate independently (except where they require core 

Skipton Building Society or group resources). 

Thus, the transformation board was established to be ‘accountable for the selection, 

prioritisation, and authorisation of all Project Investments within the Skipton Building 

Society’. The transformation board reports into the senior management committee, which 

comprises the senior executive management team chaired by the chief executive. The 

transformation board sits alongside the management boards responsible for operational 

management of the business. The portfolio office reports to the chair of the transformation 

board, who is the transformation director.  

Alongside the transformation director, the membership of the transformation board 

consists of the group finance director (an executive director) with the company secretary as 

second representative for the central functions; the head of the retail board with the head 

of mortgage operations as a second representative for the retail board; and the chief 

information officer to represent IT. 

Terms of reference for the transformation board were defined, agreed by the 

transformation board, and then approved by the chief executive. These were published 

alongside other corporate governance information under the auspices of the company 

secretary.  

In addition, we defined a five‐gate investment management process, whereby the 

transformation board at each gate, with resources (people and funding), would authorise 

project investments allocated to the next gate. The details of this process are a tailored 

version of PRINCE2. The transformation board has the ability to reassess and authorise the 

continuation of, or stop, a project at each gate. Submissions to the transformation board at 

each gate are appropriate evolutions of an investment case, increasing in detail to gate C 

and then focusing on outcomes and benefits at gates D and E.  

Within this process, the transformation board is the escalation point for any issues that 

cannot be resolved by individual business owners and project boards, and the 

transformation board, in turn, escalates issues to the senior management committee.  

The portfolio office supports and facilitates this governance framework, with the head of 

the portfolio office filling the role of secretary to the transformation board. 

 

 

Page 93: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

92  

Portfolio Office 

Building on the existing business projects team, the portfolio office was established to 

explicitly support the governance framework. Therefore, its functions follow directly from 

those required by the governance framework. 

In P3O® terms, we followed the ‘organisation portfolio office’ model with additional 

elements. As per the governance framework, the portfolio office does not directly cover 

subsidiary companies, which are run as independent businesses, but do sometimes use 

Skipton Building Society resources.  

Due to the size of the organisation (circa 1000 staff within the main office), and the 

relatively low level of maturity with respect to programme and project management, we 

incorporated project delivery resources (project managers and business analysts) within the 

structure.  

In addition, as Skipton Building Society had a particular issue with large volumes of small‐

scale changes to core operational systems, a specific change request management function 

was incorporated into the structure. Effectively, this provides a permanent project 

management/support capability for dealing with on‐going change requests within the single 

portfolio office structure.  

Project support and resourcing were essentially existing functions within the previous 

business projects team. Investment management, performance management, and portfolio 

reporting functions had to be built from scratch, along with the change request 

management capability.  

The implementation of the portfolio office was carried out in a series of tranches, or stages 

in line with P3O® guidance. However, it is based on a mix of priorities for the portfolio office 

and the ability to recruit and develop the staff. The initial focus was on getting control of in‐

flight projects and enabling the transformation board to start assessing the most urgent 

new projects.  

One of the key issues in setting up a portfolio office is the resourcing of the portfolio office 

itself and assessing the necessary mix of roles, capabilities, and capacity. Our approach was 

based on assessing the functions, the volume of work, and capabilities available, in line with 

the approach outlined in the P3O® guidance. 

Of these, the head of the portfolio office and investment manager roles were the most 

significant. The scope of the head of portfolio office role dictated the use of external 

consulting and interim staff to drive forward, although the support and engagement of the 

incumbent head of business projects was critical in the transition. For the investment 

manager role, we were able to recruit internally for a finance manager who already had 

experience of building business cases for corporate acquisitions and disposals. This internal 

recruit was then provided with some coaching support from an external consultant on the 

full scope of the role. 

Page 94: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

93  

In addition, the performance management and portfolio reporting roles were initially led by 

external consultants, transitioning to internal staff and new recruits through coaching and 

mentoring over a three to six month period.  

 

Comments on P3O® 

The P3O® guidance says ‘P3O® provides a decision‐enabling/delivery‐support model for all 

business change within an organisation’. As such, it provides a wealth of detail on the 

possible benefits of setting up a P3O®, including organisational models, steps to carry out, 

and things to do to set up and establish the necessary infrastructure. Making the most of all 

this guidance, however, does require you to have a clear idea of what you are trying to 

achieve.  

In our case, the driver was straightforward: in order to make the governance framework 

function, and for senior management to be able to make the required decisions with regard 

to the business change portfolio, a portfolio office was a necessity. The consequences of not 

having one were obvious from the review in March 2010.  

While there was discussion about ‘building the business case for P3O®’, it is not clear 

whether one can do this if building the P3O® is itself providing the tools to build business 

cases. Whenever we considered this question, it seemed like we would simply end up going 

in circles in a chicken and egg situation.  

P3O® defines a number of roles around analysis, benefits, commercial, and financial aspects. 

We combined these within the investment manager role. We created a link to the finance 

function by transferring someone from finance into the role, but their direct reporting line is 

to the head of the portfolio office and hence the transformation board.  

We fully defined the governance structure, processes, and templates (for example, 

investment case, risk tracking, etc.) before investing in any integrated tools. Once these had 

been defined, implementing a tool accelerated the acceptance and engagement of staff in 

the process. Indeed, being able to produce up‐to‐minute reports accelerated the pull for 

data from the transformation board. 

Two other aspects that are not mentioned, particularly in the guidance, but were relevant 

was risk management, and assurance. With reference to risk management, we worked with 

the operational risk function within Skipton Building Society to integrate 

portfolio/programme/project risk management with their processes and tools. With regard 

to portfolio/programme/project assurance, we engaged with the internal audit function in a 

similar way to operational risk. 

 

Other Best Management Practice Guidance 

This case study focuses on the set up of the Skipton Building Society business change 

governance framework and portfolio office, and hence P3O®. However, P3O® was not used 

Page 95: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

94  

in isolation. The full set of activities undertaken at Skipton Building Society to address the 

project‐related issues faced in March 2010 covered all aspects of project governance and 

delivery, so PRINCE2, Managing Successful Programmes (MSP®), and the newly released 

Management of Portfolios (MoP®) guidance were all relevant. 

 

What Worked Well 

Starting with an assessment of the project investment, the landscape within Skipton 

Building Society enabled the identification of gaps and weaknesses, which were 

addressed as part of the design and implementation 

The top‐down approach: previous efforts to set up P3O® structures had been driven 

by bottom‐up and did not succeed, whereas working with the senior executive team 

in terms of their requirements helped set up success 

Defining the governance framework first drove the requirements for the portfolio 

office and eased the definition and implementation of services, roles, processes, and 

tools required 

Setting up the transformation (portfolio) board early on and driving decisions 

created a pull on portfolio office services 

Having the project delivery resources within the portfolio office eased the transition 

to new methods of working 

Defining governance processes and templates (Word/Excel/PowerPoint) for key 

documents eased the selection and implementation of an integrated tool to support 

governance 

In turn, implementing a tool that directly supported the governance process eased 

acceptance and transition to the new processes and ensured a single source of 

project investment data. With further work, this tool now incorporates all project 

costs, resources and project information required to represent the portfolio 

Recruiting the investment manager from within finance helped with building links 

between the portfolio office and finance 

Supplementing internal resources with experienced external consultant/interim 

resources to provide coaching and support accelerated implementation 

 

Challenges 

Resource management and tracking. Across the organisation, there was a mix of no 

tracking, with spreadsheets or systems being used to track time for different 

purposes. A common spreadsheet was developed to capture project effort but this 

was not successful and different approaches are being used for different resource 

groups 

A lack of previous exposure to structured approaches concerning business change 

required more effort and attention throughout the organisation to embed the 

changes. While project managers, or others with at least a working familiarity of 

Page 96: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

95  

PRINCE2®/MSP® and related standards, easily adapted to the governance process 

requirements, those without such exposure found it harder to adapt 

Senior managers and executives required more support in understanding and 

exercising their roles on project boards or as business owners (senior responsible 

owners) than expected. Coaching helped but more formal workshops/training would 

have been better 

Lack of a process and structure around strategic planning and the development of 

articulated strategic objectives hampered portfolio governance. In retrospect, this 

should have been addressed in parallel with the governance framework 

Multiple sponsors at executive level. While the engagement of senior executives was 

very positive, having two formal sponsors with different expectations created 

challenges in agreeing particular issues 

 

Remaining Challenges/Questions 

How to best integrate the IT shared services organisation that supports multiple 

subsidiaries? At the moment, they have to work with each subsidiary’s portfolio 

process 

How to handle resource management going forward? The initial approach involves 

multiple tools (i.e. a single process/tool has not been mandated) 

How to best integrate the portfolio office with the corporate planning process? 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 97: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

96  

Glossary of Terms and Definitions  

Aggregated risk  

The overall level of risk to the programme when all the risks are viewed as a totality rather 

than individually. This could include the outputs of particular scenarios or risk combinations.  

Assurance  

All the systematic actions necessary to provide confidence that the target (system, process, 

organisation, programme, project, outcome, benefit, capability, product output, deliverable) 

is appropriate. Appropriateness might be defined subjectively or objectively in different 

circumstances. The implication is that assurance will have a level of independence from that 

which is being assured.  

Benefit  

The measurable improvement resulting from an outcome perceived as an advantage by one 

or more stakeholders.  

Centre of Excellence (COE)  

A coordinating function for all or part of P3RM ensuring change is delivered consistently and 

well, through standard processes and competent staff. It may provide standards, 

consistency of methods and processes, knowledge management, assurance, and training. It 

may also provide strategic oversight, scrutiny, and challenge across an organisation’s 

portfolio of programmes and projects. It may be a function within a wider scope of P3O® or 

may be the only function of a P3O®. This function provides a focal point for driving the 

implementation of improvements to increase the organisation’s capability and capacity in 

programme and project delivery.  

Chief Executive Officer (CEO)  

Describes the role in a commercial organisation with the highest level of authority for the 

total management of the business.  

Chief Financial Officer (CFO)  

Describes the role in a commercial organisation with the highest level of authority for the 

management of the financial risks, planning, and reporting for a business. This role will 

generally report to the CEO. 

Chief Information Officer (CIO)  

Describes the role in a commercial organisation with the highest level of authority for the 

management of Information Technology for the business. This role will generally report to 

the CEO but may also report to the CFO in smaller organisations.  

 

Page 98: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

97  

Chief Operating Officer (COO)  

Describes the role in a commercial organisation with the highest level of authority for the 

development, design, management, and improvement of the open systems that create and 

deliver the organisation’s products and/or services. This role will generally report to the 

CEO.  

Cost centre  

An accounting term used to describe a division, business unit or part of an organisation that 

does not directly contribute to achieving profit for a company. It indirectly contributes to 

the organisation by providing a service or support function to profit‐making parts of the 

organisation.  

Design Authority  

A role or function (permanent, temporary, or virtual) that provides expert specialist advice 

or owns some corporate function, service, standard, or strategy that will be affected, or a 

major programme outcome or change that needs to be controlled. This could be an IT or 

property infrastructure design, or a major service contract; it could also be a business 

process model or the programme or corporate Blueprint. The Design Authority provides 

expertise and guidance on a specific area to ensure there is appropriate alignment and 

control when changes are being planned and implemented. At a programme level, this role 

may advise or own the Business Blueprint management on behalf of the programme 

manager. At the enterprise level, this role may manage the Enterprise Architecture of the 

organisation.  

Dis‐benefit  

An outcome perceived as negative by one or more stakeholders. Dis‐benefits are actual 

consequences of an activity, whereas a risk has some uncertainty about whether it will 

materialise 

End Project Report  

A report given by the project manager to the Project Board that confirms the handover of all 

products and provides an updated Business Case and an assessment of how well the project 

has done against its Project Initiation Document.  

Enterprise Project (or P3RM) Management (EPM)  

A term usually referred to by software vendors in relation to software (i.e. EPM tools) that 

assists an organisation manage across multiple projects and programme delivery using a 

common resource pool through to strategic analysis of investment through portfolio 

management. This term does not reflect the actual offerings of the tools in that they 

generally can support at portfolio, programme, and project (P3RM) level.   

 

Page 99: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

98  

Expert Reference Group  

A team of subject matter experts that can be used in a P3RM organisation to provide input, 

advice, and challenge to the role accountable for an output or outcome to ensure that it 

reflects the wider experience rather than an individual’s perspective only. It is important to 

note that the role accountable for the output or outcome maintains the final decision and 

should not treat an Expert Reference Group as a committee. An Expert Reference Group 

may be drawn together at points in time or may be fully allocated to a project or 

programme.  

Full‐time equivalent (FTE)  

A technique used to measure human resource involvement in a project, programme, or 

operational activities. It is generally required where human resources are allocated across 

multiple roles (e.g. 70% allocated to a project and 30% allocated to business operations). An 

FTE of 1 means that a person or the sum of all people’s effort is 100% allocated to an 

activity, based on the number of working hours available, treatment of overtime, and other 

parameters. 

Gated Review  

Structured reviews of a project, programme, or portfolio as part of formal governance 

arrangements that are carried out at key decision points in the lifecycle to ensure that the 

decision to invest as per agreed Business Cases and plans remains valid.   

Governance (business change)  

Encompasses the structures, accountabilities and policies, standards, and process for 

decision‐making within an organisation for business change to answer the key strategic 

questions of ‘Are we doing the right things?’, ‘Are we doing them the right way?’, ‘Are we 

getting them done well?’ and ‘Are we getting the benefits?’  

Health check  

A health check is a quality tool that provides a snapshot of the status of a project, 

programme, or the portfolio. The purpose of a health check is to gain an objective 

assessment of how well the project, programme, or portfolio is performing relative to its 

objectives and any relevant processes or standards. A health check differs from a Gated 

Review in that it is a tool used for assurance purposes by the P3O® to inform specific actions 

or capability maturity development plans, whereas a Gated Review is part of formal 

governance arrangements.  

 

Hub and Spoke  

A term to describe a system of organisational design for P3O® where there is a centralised 

office (the hub) connected to a number of smaller decentralised offices (the spokes) each 

with a sub‐set of the centralised office’s business objectives, functions and services. All 

Page 100: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

99  

information and processes (connections) are arranged so that they move along spokes to 

the hub at the centre. A Hub and Spoke model provides the benefit of scalability for large 

organisations and supports business ownership by maintaining a level of decentralisation.  

Information Hub  

The centralised element of the Hub and Spoke model for P3O® in terms of information flows 

(see Hub and Spoke definition). It supports highlight and exception‐based reporting for 

projects, programmes and/or portfolios by amalgamating information with the process and 

information owned by the central office as the Information Hub. 

Information Technology Infrastructure Library (ITIL)  

A set of guides on the management and provision of operational IT services.  

Informed customer  

An individual, team, or group with functional responsibility within an organisation for 

ensuring that spend on IS/IT or other procurement is directed to best effect, i.e. that the 

business is receiving value for money and continues to achieve the most beneficial outcome. 

The term is often used in relation to the outsourcing of IT/IS. Sometimes also called 

‘Intelligent customer’.  

Key Performance Indicator (KPI)  

Metric (either financial or non‐financial) that is used to set and measure progress towards 

strategic objectives for an organisation.  

Management Board  

Generic term used to describe either project Management Boards, programme 

Management Boards or Portfolio management boards, or any combination based on the 

P3O® context.  

Management Dashboard  

A technique to represent vast amounts of decision‐support information at an amalgamated 

level using tabular and graphic representation such as graphs and traffic lights.  

Managing Successful Programmes (MSP)  

An OGC publication/method representing proven programme management good practice in 

successfully delivering transformational change, drawn from the experiences of both public 

and private sector organisations.   

Mandate  

Information created externally to a project or programme that forms the terms of reference 

and is used to start up a PRINCE2® project or identify an MSP® programme. A Mandate may 

be initiated through an unstructured approach, or it may be derived from strategic planning, 

business planning or portfolio management processes.  

Page 101: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

100  

Matrix management  

A type of organisational management in which human resources with similar skills are 

pooled together for the assignment of work to other parts of an organisation. In this 

approach, there is a separation between line management and line of authority in that a 

person may report to several project, programme, or business managers to undertake 

multiple work assignments at different times but have a line of authority to a different 

manager altogether.  

Organisation Portfolio Office  

A type of P3O® model that is designed to centrally manage the investment process, strategic 

alignment, prioritisation and selection, progress tracking and monitoring, optimisation, and 

benefits achieved by an organisation’s projects and programmes on behalf of its senior 

management.  

P3M3  

OGC’s Portfolio, Programme, and Project Management Maturity Model.  

P3O® Sponsor  

A senior manager with appropriate authority who champions the establishment and 

evolving operation of the P3O®. They will ideally be a member of the main board.  

P3RM  

An acronym to describe portfolio, programme, project, and risk management together.  

Peer review  

Specific review of a project or any of its products where personnel from within the 

organisation and/or from other organisations carry out an independent assessment of the 

project. Peer reviews can be done at any point within a project but are often used at stage‐

end points.  

PESTLE  

Acronym for ‘Political, Economic, Social, Technological, Legal, and Environment’ and is a 

technique used generally in organisational change management to undertake an 

environmental scan at a strategic level.  

Pet project  

A project that is championed by an executive in an organisation that may be aligned to an 

individual goal or goal for a specific part of the business, but not aligned to the strategic 

imperatives of the organisation as a whole.   

 

 

Page 102: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

101  

Portfolio, Programme, and Project Offices (P3O®)  

The decision enabling and support business model for all business change within an 

organisation. This will include single or multiple physical or virtual structures, i.e. offices 

(permanent and/or temporary), providing a mix of central and localised functions and 

services, integration with governance arrangements and the wider business, such as other 

corporate support functions.  

PRINCE2®  

A method that supports some selected aspects of project management. The acronym stands 

for PRojects IN Controlled Environments.  

Programme Brief  

A statement that describes the specific objectives, required benefits, potential risks, outline 

costs, timescales, and potentially options for delivery for a programme.  

Project Brief  

A statement that describes the purpose, cost, time and performance 

requirements/constraints for a project.  

Project Executive  

The individual who is ultimately responsible for a project. Their role is to ensure that the 

project is focused throughout its lifecycle on achieving its objectives and delivering a 

product that will achieve the forecast benefits.  

Project Initiation Document (PID)  

A logical document that brings together the key information needed to start a project on a 

sound basis and to convey that information to all concerned with the project.  

Resource  

An organisation’s physical or virtual entities (human or other) that are of limited availability 

and can be used to undertake operations or business change.   

Risk potential assessment (RPA)  

A standard set of high‐level criteria against which the intrinsic characteristics and degree of 

difficulty of a proposed project are assessed. Used in the UK public sector to assess the 

criticality of projects and so determine the level of OGC Gateway Review required.  

Scale of risk  

A standard technique for estimating the probability and impact of a risk across an 

organisation, portfolio, programme, or project. This may be provided as part of a risk 

management standard (external) or a Risk Management Strategy or Policy.  

Page 103: P3O® WORKBOOK€¦ · A decision‐enabling and support business model for all business change within an organisation. This includes single or virtual structures, i.e. offices (permanent

102  

Senior Responsible Owner (SRO)  

The single individual with overall responsibility for ensuring that a project or programme 

meets its objectives and delivers the projected benefits.  

Swimlane  

A method for documenting business process flows that separates each process step into a 

row (or lane) of accountability for individual roles or groups.   

SWOT  

Acronym for ‘Strengths, Weaknesses, Opportunities, and Threats’. An analysis technique to 

determine favourable and unfavourable factors in relation to business change or current 

state.  

Taxonomy  

A classification of things, or the principles underlying such a classification. The term may be 

applied to relationship schemes such as parent–child hierarchies and network structures. A 

taxonomy might also be a simple organisation of kinds of things into groups, or even an 

alphabetical list. 

Zero‐based Cost Centre  

Similar to a cost centre, except that the division, business unit or part of the organisation 

cross‐charges other parts of the organisation for some or all of its services or activities to 

achieve a spend of zero when its costs and income from cross charging are added up.