Gulf Cooperation Council Interconnection Authority GCCIA TRANSMISSION & DISTRIBUTION Engineer GCC Interconnection Project - Phase I P122 Site Acceptance Test Report MiCOM P122 87B1-B Bay Ref: Substation: SUMMARY REVISION PAGES 0 1 1 PURPOSE OF TESTS 2 X 2 REFERENCE DOCUMENT 2 X 3 SCOPE 2 X 4 RELAY TERMINLOGY 3 X 5 TEST EQUIPMENT 3 X 6 PRE-REQUISTES 3 X 7 PROCEDURES 4 X 8 RECORD TEST SHEET 5 X 8.1 RELAY INFORMATION 8.2 CT DATA: 8.3 PRODUCT CHECKS 8.4 MEASURMENT VALUE TEST: 8.5 87B HIGH IMPEDANCE DIFFERENTIAL PROTECTION 8.6 EXTERNAL STABILIZING RESITANCE MEASURMENT 8.7 EXTERNAL NON LINEAR RESITANCE MEASURMENT 8.8 CT SECONDARY RESISTANCE MEASURMENT : 8.9 BINARY INPUT TEST : 8.10 BINARY OUTPUT TEST: 8.11 FIXED LED INDICATIONS TEST: AREVA T&D GCCIA / SNCL Signature Signature Name Name Date Date Doc. No. REV- 1 Page 1 of 15

Upload: samiahmedmansour

Post on 20-Nov-2015

16 views

Category:

Documents


4 download

DESCRIPTION

AREVA

TRANSCRIPT

1

Gulf Cooperation Council

Interconnection Authority

GCCIATRANSMISSION & DISTRIBUTION

Engineer

GCC Interconnection Project - Phase I

P122Site Acceptance Test Report

MiCOM P122

87B1-BBay Ref:Substation:

SUMMARYREVISION

PAGES01

1PURPOSE OF TESTS2X

2REFERENCE DOCUMENT2X

3SCOPE2X

4RELAY TERMINLOGY 3X

5TEST EQUIPMENT3X

6PRE-REQUISTES3X

7PROCEDURES4X

8RECORD TEST SHEET5X

8.1 RELAY INFORMATION

8.2 CT DATA:

8.3 PRODUCT CHECKS

8.4 MEASURMENT VALUE TEST:

8.5 87B HIGH IMPEDANCE DIFFERENTIAL PROTECTION

8.6 EXTERNAL STABILIZING RESITANCE MEASURMENT

8.7 EXTERNAL NON LINEAR RESITANCE MEASURMENT

8.8 CT SECONDARY RESISTANCE MEASURMENT :

8.9 BINARY INPUT TEST :

8.10 BINARY OUTPUT TEST:

8.11 FIXED LED INDICATIONS TEST:

8.12 LED INDICATIONS TEST:

8.13 FINAL CHECK

1 PURPOSE OF TESTSThe purpose of the tests is to check the full functionality of the protection relay.This procedure does not intend to check that all alarms and trips are correctly sent to the DCS or SCADA level. This part is already developed into dedicated DCS or SCADA Commissioning procedures.2 REFERENCE DOCUMENTSDOCUMENTDOCUMENT REFERENCEVERSION/ DATEREMARKS

Protection Line Diagram

Schematic Drawing

Service Manual

Operation Manual

Protection Relay Coordination Principles

Relay setting Calculation

LED Display Configuration

3 SCOPE

Substation Name :-

Diameter:

Bay :

Panel Number :

Relay Denomination in Scheme

Scheme to be Checked Relay Functionality Test.

4 TERMINOLOGYCode ( ANSI) Terminology

87BBusbar High Impedance Differential Protection

5 TEST EQUIPMENT USED

Sl NoDescriptionMakeEquipment

Sl No.Calibration dateCalibration due date

1.Secondary Injection Kit

2.Multimeter

3.LaptopNA

Setting software

Type : MICOM S1 Studio

Version : 2.14

6 PRE - REQUISITES

PRE-REQUISITESREMARKS

All Safety Condition Are Ok

All Competent Personnel Available For The Test

Ac & Dc Supply Availability And Security

PPE Safety Available.

All Other Relevant Safety Instructions Been Followed

Coordination With Other Parties ( GIS, Transformer, Etc..)

7 TEST PROCEDURESThe following procedures are written for demonstrating the main protection functions of the P821 relay using an Omicron test set or similar. The tests do not test the boundaries of all available function characteristics. They do test that the function is operating at a point on one chosen characteristic. This document is to be referred to when performing commissioning tests in association with the commissioning section of the service manual.

NOTE :

All the Test are performed in the Test Switch.

Omicron CMC156 Test Equipment or Any Equivalent To Be Used7.1 87RB High Impedance Differential Relay (87 Protection)- Inject Secondary Voltage across the metrosell (Phase R), and increase voltage until the relay operates.

- Record the operating Voltage and current at both the relay terminal and metrosell.-Repeat same procedure above for phase Y and B.7.2 Testing of Binary Inputs :

This test checks that all the opto-isolated inputs on the relay are functioning correctly. (3 opto-isolated inputs for the P122).

The opto-isolated inputs should be energized one at a time. Ensuring correct polarity, connect the auxiliary voltage to the appropriate terminals for the input being tested.

The line "INPUTS" in the "OP. PARAMETERS" menu gives the state of each input, a '1' indicating an energized input and a '0' indicating a de-energized input. When each input is energized one of the digits on the bottom line of the display will change to indicate the new state of the inputs.

7.3 Testing of Binary Outputs :

This test checks that all the output relays are functioning correctly. (6 output relays for the P122).The output relays should be energised one at a time. Connect a continuity tester across the terminals corresponding to output relay 1 .

In the following window in the "Relay Satus" sub-menu of the "OP PARAMETERS" menu:

Relay 8 7 6 5 4 3 2 1

Status 0 0 0 0 0 0 0 1

Repeat the test for each relay.Operation will be confirmed by the continuity tester operating for a normally open contact and ceasing to operate for a normally closed contact.

NOTE: It should be ensured that thermal ratings of anything connected to the output relays during the test procedure is not exceeded by the associated output relay being operated for too long. It is therefore advised that the time between application and removal of relay testing kept to the minimum.If the Outputs are assigned for function this will be tested along with Functional test of relays.

8 RECORD TEST SHEET8.1 RELAY INFORMATION

Type No.:P122Designation :

Model No :Nominal Current :

Serial Number Nominal Voltage` :

Firmware Version :Aux. Volts :

8.2 CT DATA:

CT rated primary current set as

CT rated secondary current set as

Ignd-CT rated primary current set as

Ignd-CT rated secondary current set as

8.3 PRODUCT CHECKS Relay damaged?

Rating information correct for installation?

Case earth installed?

External wiring checked against diagram?

Test block connections checked?

Measured auxiliary supplyV dc

LCD front panel display

Clock set to local time?

Time maintained when aux. supply removed?

8.4 MEASURMENT VALUE TEST:

Current Measurement

Phase injectedCurrent injected (Amps)Current read on relay display (A)

PH-NIRIYIBIN

L1-E1.000

L2-E1.000

L3-E1.000

L1-L2-L31.00

8.5 HIGH IMPEDANCE DIFF CURRENT 87B: PhaseMeasured Operating Voltage Measured Current at MetrosellMeasured Current at RelayCurrent Setting of RelayTime settingOperating Time at 2* Oper.V

R

Y

B

8.6 EXTERNAL STABILIZING RESITANCE MEASURMENT : PhaseDesignation In DrawingTheoretical ValueMeasured Value

RR111

YR121

BR131

8.7 EXTERNAL NON LINEAR (MERTCIL) RESITANCE MEASURMENT : PhaseDesignation In DrawingTheoretical ValueMeasured Value

RR1

YR2

BR3

8.8 CT SECONDARY RESISTANCE MEASURMENT : PhaseTheoretical ValueMeasured Value

R

Y

B

8.9 BINARY INPUT TEST :

Input No.Terminal No.ActiveFunction AssignedsheetResult

122-24HighNOT USED**

226-28HighNOT USED**

317-19HighNOT USED**

* SPARE: wired up to terminal blocks.

** NOT USED: Not wired.

8.10 BINARY OUTPUT TEST:

Output No.Terminal No.TypeFunction Assigned

(Aux relay operated)sheetResult

12-6NONOT USED**

2-4NC

28-12NONOT USED**

8-10NC

314-16NOTO BUS 1A GROUP-B262

418-20NONOT USED**

51-3NOSPARE*264

65-7NOSPARE*264

* SPARE: wired up to terminal blocks.

** NOT USED: Not wired.

8.11 FIXED LED INDICATIONS TEST:

LED No.LED LabelColorResult

1TripRed

2AlarmYellow

3WarningYellow

4healthyGreen

8.12 LED INDICATIONS TEST: ( LEFT SIDE LED)

LED No.LED LabelColorResult

1

2

3

4

8.13 FINAL CHECKSItem

Description Result

1All test equipment, leads, shorts and test block removed safely?

2Disturbed customer wiring re-checked?

3All commissioning tests disabled?

4Circuit breaker operations counter reset?

5Current counters reset?

6Event records reset?

7Fault records reset?

8Disturbance records reset?

9Alarms reset?

10LEDs reset?

11Secondary front cover replaced? (If applicable)

REMARKS

END OF REPORT

AREVA T&DGCCIA / SNCL

SignatureSignature

NameName

DateDate

Doc. No.REV- 1Page 4 of 9