oral presentation i-75 from north of sr 80 to south of sr 78 contract: 12165 fmn: 413066 1 62 01...

50
Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Upload: basil-jordan

Post on 25-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Oral PresentationI-75 from North of SR 80

to South of SR 78Contract: 12165 FMN: 413066 1 62 01

April 11, 2012

Page 2: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Agenda

• Awareness/approach to project‒ Understanding of scope‒ Unique issues ‒ Best of value added

• Proposed staffing‒ Quantity‒ Availability‒ Qualifications/certifications‒ Quality/experience on other projects‒ Team’s past performance on similar projects

• Other considerations‒ Communications‒ Commitment

Page 3: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Volkert Team Experience

Page 4: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Understanding of Scope

• D/B/F $80M lump sum 21st Century Vision project to widen 1.6 miles of I-75 to eight lanes

• Two step D/B procurement process‒ CEI support for 140 days

• Full FHWA oversight• Widening of four pairs of bridges

‒ Caloosahatchee River (steel main span) ‒ Tidal Creek ‒ Tidal Marsh ‒ Popash Creek

Page 5: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Understanding of Scope

• CEI duration 1,220 days• Construction duration 1,050 days• New noise barrier walls at I-75/SR 80

Interchange • Stormwater management facilities • Drainage improvements to SR 78 • Milling and resurfacing of I-75, ramps, median

crossover• Structural ITS accommodations• Median barrier system • Utility coordination/relocation

Page 6: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Understanding of Scope

CEI role• Assistance during procurement phase

‒ Assist with review of ATCs‒ Book of promises

• Manage D/B design and permitting‒ Review and acceptance of CPM and schedule of values‒ ERC and submittal tracking‒ Review comment clarity

• CEI services during construction‒ Construct the project in accordance with all contract

documents and approved permits‒ Utilize CPPR as needed

• Communication‒ Partnering

Page 7: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Procurement overview• Bridge inspection

report recommendations

• Designing for vessel collision

• Field attachments welding

• Lateral bracing• Cross frame

connection plates • Bridge drainage

Page 8: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Inspection report items – verify in RFP Paint entire steel

span Replace fender

system• Replace all deck

expansion joints• Repair footing

delaminations• Replace access

ladders/platform

Page 9: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Designing for vessel collision• Barge traffic has

decreased• New/larger

foundations and piers to distribute vessel impact loads

• Increased construction costs

Suggest – review with SDO

Page 10: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Field attachments/welding• RFP prohibits field

attachments and welding to bridge girders web/flanges

• Eliminates use of cross bracing for loads

• Drilling of bolt holes allowed by SDG

Suggest – clarify RFP language

Page 11: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Lateral bracing• RFP directs removal of

the lateral bracing and connection plates

• Current design practice considers bracing unnecessary

• Removal may not add value

Suggest – revisit RFP with SDO

Page 12: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Cross frame connection plates • Plates are welded to girder web and

compression flange• Results in fatigue prone connection where

girder flange is in tension • RFP requires new detail to correct Solution – standard detail

Page 13: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Bridge drainage • RFP states, “bridge

drainage shall not discharge directly into the Caloosahatchee River”

• RFP Q&A, “portion of the bridge can continue to discharge into…”

• Widening of SB bridge to high side of superelevated curve

Suggest - clarifying RFP intent

Page 14: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Design Development overview• Managing D/B/F

payments• Prioritizing and

tracking submittals • Review comments

for clarity and conformance with contract

Page 15: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Managing D/B/F payments • First availability payment is August 2013• Payments governed by D/B/F contract

terms• Future payments after CEI contract term Solution - we will manage this effectively

Cash Availability Schedule

Page 16: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Prioritizing submittals • D/B/F team design schedule is critical • Significant volume of design documentation/plans• Submittals must be prioritized for efficient reviews Review comment clarity • Comments must be focused on compliance with

‒ RFP requirements ‒ Department criteria

Solutions - we will lead the design partnering effort with D/B/F team EORs and District 1; we will review every comment

Page 17: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Construction overview• Environmental impacts

‒ Smalltooth sawfish, manatee‒ Outstanding Florida Waters

• Caloosahatchee National Wildlife Refuge‒ Public recreation area access‒ Great Calusa Blueway Paddling Trail

• Morse Shores and Dos Rios noise barrier walls• Maintenance of traffic

‒ Marine and vehicular• Bridge construction methods • Pile driving• Coordination with adjacent projects• Blue logo signs relocation

Page 18: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Noise barrier walls

Page 19: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Impacts to wetlands, wetlands species, and essential fish habitat • Construction conditions commitments to NMFS

‒ Sea turtle, smalltooth sawfish, manatee

Smalltooth sawfish habitat and education • Nursery habitat includes Charlotte Harbor Estuary • Will restrict contractor marine operations• Education program commitment Solutions - extensive review and analysis of construction plan and prepare/deliver the education program

Page 20: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Caloosahatchee National Wildlife Refuge • Established in 1920, 40 acres, three islands • “Preserve and breeding ground for natural birds”• Construction operations must be minimized Public recreation access • Great Calusa Blueway Paddling Trail – closure

necessary• Orange Harbor RV Park • Local fishermen Solutions - extensive planning, public information and continuous monitoring of contractor’s operations

Page 21: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Outstanding Florida Waters • Impacts typical construction operations • “Zero” NTU increase above background• Major concern of Department, SFWMD, Lee

County and City of Fort MyersSolution - continuous emphasis and vigilance

Blue logo signs • Coordinating temporary removal Solution - Florida logos coordination

Page 22: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Maintenance of traffic• Marine

– USCG notice to mariners

• Vehicular– Coordination with

SWIFT Center

Page 23: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Bridge construction methods • Commitment to top down

or work trestle bridges• Barges restricted to

adequate depth • Straddle cranes produce

unequal load distribution

Solution - we will be engaged continuously with the contractor to minimize environmental risks and impacts

Page 24: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Pile driving• 44 test piles on

conceptual plans• 24” pile, length from

60’ to 140’• Test pile program is

developed and managed by D/B/F team

Solution – experienced staff

Page 25: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Unique Project Issues

Coordination with adjacent projects • I-75 Widening from Luckett Road to

SR 80 ‒ Estimated completion is May/June 2013

• I-75 Widening south of SR 78 ‒ Letting in May 2012‒ Construction start in September 2012

Solutions - seamless integration with SR 80; we will attend SR 78 progress meetings

Page 26: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Approach – Procurement

Objective • Same project

understanding– Crystal Gorman and

Nikesh Patel– DDE Bernie Masing

and his staff– Design Project

Manager Ray Porter– Structures Design

Office– D/B/F EORs

Page 27: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Approach – Procurement

Execution • Jim Lynch, PE,

available • Scott Collister, PE,

CPCM, available • Can attend all ATCs

and meetings • No limits on support

Unmatched FDOT procurement and CC2 Bridge CEI expertise

Page 28: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Approach – Design Development

Objectives • Final plans and specifications

‒ Comply with RFP and Department criteria

‒ “Released for Construction” on schedule

Execution • Design Partnering “Kick-Off”• Maximize ERC efficiency • In-depth review of D/B/F Quality

Management Plan• QA Audit during first 120 days

Every comment reviewed by Jim Lynch, PE

Page 29: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Best of Value Added

CEI QA/QC program• Provide QA Plan within 30 days of CEI

contract award• Executed semi-annually• Comprehensive - covers all phases• Includes interviews with Department,

contractor and project staff• World class written report

Page 30: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Best of Value Added

• Florida Bridge Professionals‒ Scott Collister, PE, CPCM‒ John Horn, PE‒ Tom White, PE‒ Paul Looney, CEP, CSE, PWS

• Office at no cost to Department‒ Same as adjacent project‒ Coordination with adjacent I-75 projects

• James “J” White has dual roles as CSS/Assistant PA• PA, CSS and all Senior Inspectors have CTQP

Concrete Level 2• Secure FTP site and GoToMeeting

Page 31: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Best of Value Added

Florida Bridge Professionals • John Horn, PE

‒ Project CEI Services QA/QC Manager‒ 23 years of bridge/Volkert experience‒ Steel and concrete structure design

experience‒ CC2 bridge portfolio

I-10/I-110 Interchange I-10 Escambia Bay Emergency Repairs I-10 Twin Spans, Lake Pontchartrain

Page 32: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Best of Value Added

Florida Bridge Professionals • Tom White, PE

‒ Tampa bridge design department leader ‒ 35+ years of bridge design experience‒ Steel and concrete structure design experience‒ Bridge portfolio

D/B Selmon Expressway Widening, Hillsborough County

I-75 Bridge Widening, Lee County SR 80/US 27 Interchange, Hendry County SR 25/US 27 bridges over CSX RR, Polk County

Page 33: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Awareness/Approach to Project

Best of Value Added

Florida Bridge Professionals • Paul Looney, CEP, CSE, PWS

‒Project environmental specialist ‒20+ years of ecology/wetlands

experience‒Permit and construction monitoring

expertise Wetlands Threatened/endangered species

Page 34: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Overview

Team selection • Subconsultants we have worked with • Most highly qualified CEI

professionals• CC2 bridge over water experience • Focused on delivering the project

safely• Committed to delivering project

quality

Page 35: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Project Staffing Chart

Page 36: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Staff Quantity

• Start dates CEI 5.2.12 D/B/F Contract 9.15.12

• Total time 1,220 days• Total effort 400 staff months

Page 37: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

Scott Collister, PE, CPCM • Principal-In-Charge• 25+ years of infrastructure experience• Former Director of Transportation

Development, District 7 • Bridge portfolio• D/B Ringling Bridge Replacement• D/B US 19 Barge Canal Bridge Replacement • I-4/Selmon Connector • First FDOT “Build/Finance” Project

Page 38: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

Jim Lynch, PE, Senior Project Engineer • 25+ years of experience delivering projects• FDOT Resident Engineer experience

‒ Marrel Barber Bridge ‒ Roosevelt Bridge ‒ Evans Crary ‒ Big John Monahan

• CEI for 160 road and interstate projects‒ I-75 in Lee County‒ I-95 D/B Rest Area in Martin County

• Delivering Luckett Road/SR 80 I-75 Widening Project• Fort Myers resident • 50% available April 24, 2012

Page 39: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

Anthony Fresolone, Project Administrator • 18+ years of CEI experience• Six years CC2 experience• Seven over water bridge projects• CTQP Concrete Level 2• Bridge CEI experience

‒ I-10 Twin Spans Bridge Replacement ‒ I-10 Escambia Bay Emergency Repairs ‒ I-10/I-110 Interchange ‒ I-110 Fairfield to Airport Boulevard‒ SR 173 Blue Angel Parkway ‒ Perdido Pass Bay Bridge Painting

• QA/QC for Luckett Road/SR 80 I-75 Widening• Certified Steel Coatings Inspector (SSPC) • 100% available April 24, 2012

Page 40: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

James “J” White, Jr., CSS/Assistant PA• 28+ years of CEI experience • CTQP Concrete Level 2• Bridge CEI experience

‒ I-75 Caloosahatchee Asbestos Removal ‒ Mariana Avenue Bridge Widening ‒ I-75 Deck Replacement/Widening, Charlotte County‒ I-75 over Kings Highway Bridge Deck Replacement‒ I-75 over SR 80 Bridge Deck Replacement‒ I-75 Caloosahatchee Bridge Repairs

• PA for Charlotte County ITS D/B Project• Certified Final Estimates Level 2 instructor• 100% available April 24, 2012

Page 41: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

Norman Brownlie, Senior Bridge Inspector • 15+ years of experience • CTQP Concrete Level 2• Bridge experience

– Sanibel Causeway Bridge Replacement

– Florida’s Turnpike Widening over Canal 38

– SR 80 over Okaloacoochee River

– Matanzas Pass Bridge Painting

Mike Edge, Senior Bridge Inspector • 16+ years of experience • CTQP Concrete Level 2• Bridge experience

– Toledo Blade Bridges – Sanibel Causeway

Bridge Replacement

Page 42: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Availability/Qualifications

Steve Wall, Senior Bridge Inspector • 27+ years of experience • CTQP Concrete Level 2• Bridge experience

– Vanderbilt Road – Estero Parkway Flyover– Clearwater Pass Bridge– Sanibel Causeway

Bridge Replacement

Robert McCrumb, Senior Roadway Inspector • 20+ years of experience • CTQP Concrete Level 2• QC Manager for iROX

D/B • Senior Inspector for I-

75 Luckett Road/SR 80, Vanderbilt Beach Road, Bee Ridge Road, SR 64, SR 70, SR 80

• Bridge experience– Myakka River Bridge

Page 43: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Qualifications/Experience Matrix

Page 44: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Experience on Similar Projects

Page 45: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Proposed Staffing

Experience on Similar Projects

Page 46: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Other Considerations

Communication

Objectives • Effective communications• Efficient communications Execution• Choose best method, email, teleconference,

meeting• GoToMeeting• Volkert secure FTP site• Open lines of communication – internal and

external • Public involvement support

Page 47: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Other Considerations

Commitment

Page 48: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Other Considerations

Commitment

I-75 Luckett to SR 80• Personnel changes• Jim Lynch moved to Fort Myers• Tom White involved in review of

CSIs and other structural issues• Bridge inspection staff provided

guidance on HMLP issues35% DBE commitment

Page 49: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

The Volkert Team is Prepared andCommitted to Deliver this Project!

Page 50: Oral Presentation I-75 from North of SR 80 to South of SR 78 Contract: 12165 FMN: 413066 1 62 01 April 11, 2012

Questions and AnswersThank You!