oliver grievson - wwem - experiences of a mcerts remedial works programme
TRANSCRIPT
What am I going to say
MCERTS Self Monitoring of Flow – A brief summary
A history in terms of Anglian Water
The remedial works programme
Case Study 1 – A major problem converted to a minor one
Case Study 2 – How do you know its working?
Case Study 3 – When all else fails – A large installation and its consequences
Key Learning points – What to do and what not to do
The future innovation
MCERTS – A little bit of Background
MCERTS Self Monitoring of Effluent Flow
Environment Agency run scheme managed by SIRA certification
Requirement for all wastewater and industrial sites over 50m3/day to monitor the total daily volume to the water environment
All meters that are used under the scheme have to have gone through product certification
Approximately 3,500 to 4,000 sites in England & Wales
WASCs account for approximately 90% of the sites
All sites have to be inspected every 5 years by a certified MCERTS Inspector according to a MCERTS guidelines
MCERTS – Anglian Water’s context
Anglian Water is the largest of all of the WASCs in terms of MCERTS Monitoring of flow with 693 sites qualifying works
This equates to over 750 flow meter installations spread over a geographic area from Canvey Island to Grimsby
This splits into
240 sites with Electromagnetic flow meters
430 sites with Ultrasonic flow meters
22 using other flow measurement technologies
A number of these sites are low flows which are difficult to measure
MCERTS – Anglian Water’s history
Anglian Water put a large number of flow meter installations in before the MCERTS regulations were fully formed and followed best practise at the time including burying flow meters
The MCERTS regulations changed and this included the verification of flows every 5 years
When sites came up for recertification those sites failed the MCERTS inspection as the flows couldn’t be manually verified
This left a legacy issue for Anglian Water to resolve
As of the start of 2012 Anglian Water had 174 of 693 sites with a flow meter that had an expired certificate because of a failed inspection or a site that had never been inspected.
This was the worst performance of all of the Water & Sewerage Companies
The remedial works programme
To turn the Anglian Water performance around a remedial works programme was put in place
A business case for £1.28 million was put together covering all 174 sites.
The scope of the programme had to be reactionary as not all of the sites had been scoped. The eventual number of sites remediated was 80 although all 174 sites had to be investigated
By the time the business case was confirmed and the project went into delivery there was a total of 8 months to deliver all 80 sites to meet the deadline of the end of the calendar year when the EA assessed compliance
4 Categories
Simple Certifications
Minor Works
Verification Works
Major Works
Minor Works
Minor Works fell into a number of different categories
1. Where the original installation was not of a sufficient standard
2. Where the asset had reached the end of its asset life
3. Where maintenance had fallen short and damage had been caused to flow meter installations
4. Sites where the current installation couldn’t necessarily be certified
5. Some element of the flow was not counted and needed to be for MCERTS standards
Case Study 1 - Minor Works
The site in Case Study 1 was a site that the current layout of the treatment works prevented it from being certified.
There was no practical way in which the site could pass an MCERTS Inspection as it was too dangerous
There were 3 options
1. Replace the inlet flume
2. Install a partial flow electro-magnetic flow meter at the final effluent of the treatment works upstream of the storm return
3. Install a partial flow electro-magnetic flow meter on the overflow from the storm tanks during bathing water season.
All 3 options were going to cost over £50k and take
approximately 3 weeks to complete
Case Study 1 - Minor Works
The solution was to hot tap the pipe that was on the surface and thus needed no excavation and install an insertion flow meter on a permanent basis
Technology that had recently receive product certification
Total cost of £8k and gave Anglian Water a capital saving of over £45k over the next cheapest option
Case Study II - Verification of Flow Meters
Wasn’t originally part of the MCERTS standards but rightly was included.
Requires an independent flow meter check of each and every installation
PROBLEM
Flow meters were installed without taking this into account
SOLUTION
Hot tap pipe and using the insertion technique as a temporary verification point
1 site saving of £58k total programme saving of £90k
Major Works
As part of the programme there were occasions that there no other choice but to instigate a major works to install a flow meter installation
All over £50k
Was relevant to approximately 5 sites.
One case it the major works started as minor works and turned into very large job
Main cause were where flow meters had been buried or a previous installation had been done badly with MCERTS not taken into account
Case Study III - Major Works
Two choices for a certified flow meter installation
Option 1 - Replace the inlet flume at a cost of approximately £45k
or
Option 2 - Replace the broken & buried flow meter at the final effluent to the works and put a chamber around it at a cost of about £20k
The sensible solution seemed to be Option 2
Sensible isn’t always right
Once excavated there was no flow meter
There was an asbestos outfall pipe
And a very large hole in the ground
The solution
Remove the asbestos pipe
Replace the outfall pipe
Put a new flow meter in pipe full conditions
All in 24 hours as the site would need to be overpumped
22 hours later and £100k later
Sensible isn’t always right
Once excavated there was no flow meter
There was an asbestos outfall pipe
And a very large hole in the ground
The solution
Remove the asbestos pipe
Replace the outfall pipe
Put a new flow meter in pipe full conditions
All in 24 hours as the site would need to be overpumped
22 hours later and £100k later
Key learning points from the Remedial works programme
There are some key learning points from this remedial works programme and from the operation of MCERTS Flow Meters in general. These are
1. Asset Capture
2. Burying of electro-magnetic flow meters
3. Maintenance
4. Asset Standards
5. Product Certified Flow Meters
6. Installation of the right product in the right place in the right way
7. Training
What’s happened since ………Flow Innovation
Despite their being good technologies on the market Anglian Water will work with flow meter manufacturers to develop technologies.
This allows development of technologies to get the right meter for the right application.
Three trials have been conducted in the last 18 months, with one more to come and a fifth in talks at the moment.
Looking forward to AMP 6The need for investment & reliability
The reason why:
Challenging Installations still to come
Ageing assets
And a large base maintenance programme
120 EM-meter cleans