Oklahoma Capitol Restoration Project
2300 N Lincoln Blvd. Oklahoma City, OK 73105
April 2016 – Monthly Progress Report
MONTHLY OVERVIEW
� House 109 Demolition
Begins
� House 109 Abatement
Begins
� Master Planning Work
Sessions Continue
� Existing Conditions
Investigations Continue
REPORT CONTENTS
Cover Letter
Executive Summary
Preconstruction Status
Construction Schedule
Request for Information
Submittal Log
Construction Photos
2601 NW Expressway, Suite 501W 73107 | t 405.254.1050 f 405.254.1055 | www.manhattanconstruction.com
Manhattan Job #
3707
Design/Builder:
Project Owner:
Oklahoma Capitol Restoration
2300 N Lincoln Blvd. Oklahoma City, OK 73105
April 2016 � Monthly
Progress Report
Cover Letter
Tab 1 Executive Summary
Tab 2 Preconstruction Status
• Document deliverable status
Tab 3 Construction Schedule
• Schedule narrative
• Critical Items
• Schedule Update
Tab 4 Requests for Information (RFIs)
• RFI Summary Log
Tab 5 Submittal Log
• Submittal Package Summary Log
Tab 6 Construction Photos
• Detailed progress photos – current month
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
April 2016
1�1
Monthly Progress Report
For
Oklahoma Capitol Restoration
April 2016 In April, construction kicked off with make safe activities and full demolition of the existing House 109 space. In addition to the House 109 construction activities, Priority 1 space planning and design development continues. Below is a recap of the major construction & design milestones that are upcoming and their completion status:
1. Senate 309 & House 112 Final Completion Pending AR#01
2. House 109 Building Permit Approved Achieved March 7, 2016
3. House 109 Start of Construction Achieved, April 18, 2016
4. House 109 Permanent Power Projected July 29, 2016
5. House 109 Conditioned Air Projected August 10, 2016
6. House 109 Final Fire Marshal Inspection Projected August 31, 2016
7. House 109 Substantial Completion Projected September 13, 2016
8. Priority 1 50% Design Development Review Projected June 15, 2016
9. Priority 1 65% Design Development Submission Projected August 3, 2016
Prime Contract Status The prime contract has been updated with Contract Amendment #2 to include funding for the entirety of the Priority 1 scope. The Amendment was executed on May 2, 2016. Design Status The 100% Construction Documents for the House 109 space have been submitted and reviewed by the AE1/OMES team. Planning & development of the full interior restoration project is ongoing. The Design Build team, OMES and AE1 are very near completion of the Priority 1 space allocation plans in conjunction with the House & Senate. The Design Build team spent much of the month of April coordinating with the numerous agencies affiliated with the Capitol Restoration including the State Historic Society, Arts Council, Department of Public Safety, Department of Tourism, Oklahoma Highway Patrol, State Forestry & Agricultural Department, and the OMES Facilities Management team.
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
April 2016
1�2
Schedule Status The construction progress for House 109 work remains on schedule through the completion of demolition and the start of abatement. Abatement work is expected to be complete the first week of May and will be followed by the Post�Demolition conference on May 5th. Design Development also continues on schedule. The Design Build team will host a design update work session for the OMES/AE1 team in June 2016 and will follow later in the summer with a formal design submission at the 65% Design Development milestone. Several major construction activities will commence after the 65% Design Development review. These activities include: procurement of long lead electrical gear, generator, and elevator components; structural procurement to infill the existing light well shafts adjacent to the restrooms; and temporary construction work in the basement in preparation for the beginning of Priority 1 construction. Request for Information (RFI’s) Current RFI Summary Log attached in Tab 4. Submittals Current Submittal Log attached in Tab 5. Cost Events & Authorization Requests There are currently two submitted proposals for Phase I.
� Authorization Request #01 – Punchlist Proposal Items � Authorization Request #02 – Marble Floor Evaluation & Proposal – Pending Priority 2 funding.
Construction Progress
House of Representatives 6 109 Early work has progressed smoothly in the House 109 renovation. With only minor abatement work required in the removal of the existing floor mastic, the majority of the demolition phase will be complete in less than 3 weeks total duration. Upon completion of the demolition & abatement phase, the framing and rough�in activities will commence. These activities will take the project well into the summer with finish out beginning in August.
Prepared by: Andrea Gossard, Project Manager
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration
April 2016
2�1
Document Deliverables:
• 100% Construction Documents were submitted for House of Representatives 109 on April 14, 2016. These documents have been reviewed by the OMES/AE1 team.
• 50% Design Development Documents for Priority 1 scope will be reviewed with the OMES/AE1 team on June 15, 2016.
• 65% Design Development Deliverable for Priority 1 scope is expected to be submitted on August 3, 2016.
Design Status Report:
Frankfurt Short Bruza Architects Engineers Planners
Monthly Project Status Report
Date: April 29, 2016 Project: 15151DB – Capitol Interior Restoration
To:
Name Company/Position Phone Email
Kyle Nelson Manhattan Construction Co. 405.254.1050 [email protected]
From: Roger Klein
Project Manager Re: Monthly Project Status Report – April 2016
This project status report is being provided to you to in order to document our status on the
current Capitol Restoration Project, as required by OMES.
PREREQUISITE PHASE 1 PROGRESS
The construction for Phase 1 - House of Representatives 112 and the Senate 309 tenant
improvement project is complete with the exception of a few outstanding punch-list change
requests under review by the owner.
FSB has been working with the staff of the House or Representatives, the Senate, and
OMES/AE1 on the signage package to be incorporated into the Phase 1 Pre-requisite projects.
Final signage in these locations is pending fabrication and installation.
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
2�2
HOUSE OF REPRESENTATIVES 109 PROGRESS
FSB has developed 100% construction documents for the House of Representatives 109 tenant
improvement project. FSB submitted 100% CD’s to MCC on April 15th, for bidding.
A post demolition conference is scheduled for May 5th, for the House of Representatives 109
renovation area to document any building fabric of historical significance. This meeting will be
attended by FSB Historic Preservation Consultant Stephen Kelly, FSB, Manhattan Construction,
AE1/Mass Architects, and OMES.
Additional construction documents were issued by FSB under the heading of “Architects
Supplemental Information”. ASI 001 was issued on 4/13/16 to address the owner requested
change to include the toilet accessories in the construction documents, and to be supplied and
installed by the contractor. ASI 002 was issued on 4/27/16 to address owner requested floor
plan changes to relocate the Breakroom and add a File Room.
DESIGN STANDARDS
FSB published and issued the Draft of Design Standards for review by AE1/OMES on 2/5/2016.
The Design Standards are in review and will be modified as required in subsequent design
phases.
The Design/Build Team will be researching historical reference material for building materials,
colors, and finishes that have been lost during earlier renovations. Also, the team will be
searching for new historically compatible materials and finishes to be submitted for review and
addition to the Design Standards for incorporation into the Capitol Restoration.
PRIORITY 1 DESIGN PROGRESS
April has been a very eventful and productive month as a team of design consultants have
visited the Capitol to study and propose design options for the Priority 1 design of the
Basement, or proposed New Ground Floor, New Visitor Entry, and Rotunda. The Design/Build
team is scheduled to provide Design Development Documents on August 1, 2016.
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
2�3
Security Work Session #1 was held April 6th with the Sextant Security Group’s Paul Dooley
and Terry Robinette, Capital Security/OHP Officers, Michael McClelland and John Paul, along
with members of the Design Build Team, OMES, and AE1 Mass Architects. Topics of discussion
were the new security screening station in the new Visitor’s Entry, surveillance camera
locations, the future control room, and other security spaces.
The Art Conservation meetings on April 8th and April 9th were attended by WWCCA Art
conservator Carmen Bria and members of the Oklahoma Arts Council, Amber Sharpels, Alan
Atkinson, Alyson Atchison, and the Design/Build team. The main concern discussed was the
protection and storage of the fixed and movable artwork collections in the Capitol building.
Proposed solutions acceptable to the meeting participants was to store the movable artwork
offsite, and cover the large fixed art with framed boxes. Also discussed was the UV protection
of the art from artificial and natural light.
A Capitol Materials Management meeting was held on April 14th with OMES Facilities
Management, Doug Kellogg, FSB, and Manhattan, to discuss the management of supplies,
waste, maintenance, housekeeping, storage, etc., in the Capitol. Several user agencies were
invited to identify the types of materials managed in the Capitol. Other topics of discussion
were, OMES Storage, access to the OMES office area, access to the loading dock, loading dock
screening, deliveries, and housekeeping facilities.
OMES Capitol Project Manager Trait Thompson arranged a meeting on April19th, with the two
Design/Build Teams (Interior and Exterior) and the Office of Disability Concerns to discuss
ongoing accessibility issues in and on the grounds of the Capitol Building. In the meeting Doug
Macmillan (ODC) indicated that some physically challenged visitors are unable to participate in
the Capitol visitor experience due to the restrictive access of the 100 year old building. The
Design/Build team emphasized that all areas scheduled for renovation and all new construction
under Priority 1 would address all aspects of accessibility per ADAG 2010. The Design Build
team further explained that the proposed and funded Priority 1Visitor Entry would provide a
significant increase in accessible and barrier free design in the Capitol.
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
2�4
The Historic Preservation Consultant, Stephen Kelley returned to the Capitol on April 20th to
meet and discuss the Priority 1 Scope and the Preservation effort in the basement and rotunda.
He also provided a preservation salvage list for the Basement and inspected the cracking of the
plaster walls in the Rotunda. An out-briefing meeting was held with SK, Manhattan, and FSB on
April 22nd, to discuss the plaster assessment and possible repair recommendations.
The Hesman Group, Foodservice Facility Designers, Randy Norman and Scott Heskett met with
the Design Build team on April 20th to propose possible design solutions for enhanced Food
Service, snack bar, vending, and seating. The Hesman group will develop preliminary schematic
design of possible kitchen equipment and the locations of the necessary plumbing, power, and
food service infrastructure.
On Thursday April 21th, FSB Architects hosted a five hour Capitol Restoration Design Workshop
to develop ideas and possible solutions to enhance the “Visitor Experience” at the Oklahoma
State Capitol. Members of the Design/Build team were joined by OMES, AE1 -Mass Architects, as well as user agencies including The Oklahoma Arts Council, The Oklahoma Department of
Tourism, and The Oklahoma Historical Society. Workshop participants provided background
information, described their current roles at the Capitol, and discussed future needs and “Big
Ideas” for the Capitol Restoration. Other design concepts discussed were “Engaging the
Public”, “Symbolism at the Capitol”, and “Telling the Story of the Capitol”. FSB Architects
Fred Schmidt and David Ketch gave a presentation of the most recent design drawings
including plans and interior renderings.
Security Work Session # 2 was held on April 27th, and was attended by The Sextant Security
Group, OHP Security, OMES, AE1, Manhattan, and FSB. The follow up meeting was required to
review the surveillance camera requirements, location, equipment and extent of coverage. Also
discussed was enhanced security and visitor screening.
An Elevator coordination meeting on April 29th was attended by members of the MCC/FSB
Design/Build team to discuss options for the new passenger and service elevators scheduled
for installation in the Priority 1 design. A representative from the American Elevator Co. also
attended to assist the team with car sizes and equipment options. Topics of discussion were
standard and custom platform sizes available for the existing hoist ways, required overhead
and pit depth, enclosed machine room requirements, and coordination with the state elevator
inspector. The design team also discussed interior finishes, 2 speed doors with the original
period design decorative finishes, lighting and floor indicator lights.
Page 4 of 4
CONSTRUCTION SCHEDULE
SECTION 3
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
3�1
House of Representatives 109
Schedule Status: Upon completion of the 100% Construction Documents and approval to proceed, demolition work on House 109 began in the 3rd week of April. As demolition progressed, the Design Build team reviewed the existing structural conditions around the existing elevator shaft. With the existing conditions varying slightly from the planned structural infill, the Manhattan field staff and structural engineer coordinated on the revised structural layout. This structural infill is scheduled to begin immediately following the abatement work because this floor space will house the new House 109 electrical room, making both of these activities critical path to completion of the project. By the end of April, the revised structural detail is complete and procurement of the materials can commence. Critical Schedule Events: Nearly all critical schedule events correlate with material procurement items. Below is a tracking log of all major material delivery items currently on the schedule:
Item Description Estimated
Installation Date Estimated
Delivery Date Actual Delivery
Date
Heat Pumps 06/17/16
Light Fixtures – Can Lights 06/16/16
Electrical Panels 06/16/16
Light Fixtures – 2’x4’ Fixtures 07/28/16
Millwork 08/02/16
Flooring 08/17/16
Doors & Hardware 08/22/16
Signage 09/06/16
Milestone Description Baseline Schedule
Last Month’s Update
Current Month Update
Gain or Loss this Month
Building Permit 03/07/16 3/7/16 3/7/16 Receive 100% CD's 03/21/16 4/4/16 4/7/16 +3 50% Fire Marshal Inspection 06/01/16 6/27/16 6/23/16 �4
Permanent Power 07/11/16 7/29/16 7/29/16 0
Conditioned Air for Climatization 07/25/16 8/10/16 8/10/16 0
Interim Substantial Completion 08/19/16 9/13/16 9/16/16 +3
Tenant Move7In 08/22/16 9/16/16 9/19/16 +3
Activity ID Calendar Activity Name Orig Dur
Rem Dur
Start Finish
Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109Prerequisite Phase 2 - L1 House 109
PermitsPermitsPermitsPermitsPermitsPermitsPermits
PH2-FM15 3707-5 Day w/Hol FM Review / Approve Building Permit 15 0 22-Feb-16 A 07-Mar-16 A
PH2-FM20 3707-5 Day w/Hol Release FA / FS Design Drawings 7 0 09-Mar-16 A 08-Apr-16 A
PH2-FM30 3707-5 Day w/Hol FM Review / Approve FS 15 4 11-Apr-16 A 29-Apr-16
PH2-FM25 3707-5 Day w/Hol FM Review / Approve FA 10 4 18-Apr-16 A 29-Apr-16
Material ProcurementMaterial ProcurementMaterial ProcurementMaterial ProcurementMaterial ProcurementMaterial ProcurementMaterial Procurement
Procurement Phase SummariesProcurement Phase SummariesProcurement Phase SummariesProcurement Phase SummariesProcurement Phase SummariesProcurement Phase SummariesProcurement Phase SummariesPROC2-LEAD 3707-7 Day w/o Long Lead Items - Phase 2 Level 1 House 109 - HAMMOCK 1 94 18-Apr-16 A 28-Jul-16
OAU & Heat PumpsOAU & Heat PumpsOAU & Heat PumpsOAU & Heat PumpsOAU & Heat PumpsOAU & Heat PumpsOAU & Heat PumpsPROC2-1000 3707-5 Day w/Hol MCC Receive / Review Submittal 1 0 18-Apr-16 A 18-Apr-16 A
PROC2-1110 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-Apr-16 A 02-May-16
PROC2-1210 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 03-May-16 23-May-16
PROC2-1310 3707-5 Day w/Hol Fab & Deliver Heat Pumps 10 10 24-May-16 07-Jun-16
Electrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsElectrical Panel Boards @ Electrical RoomsPROC2-1010 3707-5 Day w/Hol MCC Receive / Review Submittal 1 0 18-Apr-16 A 18-Apr-16 A
PROC2-1120 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-Apr-16 A 02-May-16
PROC2-1220 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 03-May-16 23-May-16
PROC2-1410 3707-5 Day w/Hol Fab & Deliver Panels 25 25 24-May-16 28-Jun-16
PROC2-1360 3707-5 Day w/Hol Fab & Deliver Cans 30 30 24-May-16 06-Jul-16
Light FixturesLight FixturesLight FixturesLight FixturesLight FixturesLight FixturesLight FixturesPROC2-1020 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 04-May-16* 04-May-16
PROC2-1190 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 05-May-16 25-May-16
PROC2-1290 3707-5 Day w/Hol Fab & Deliver Light Fixtures 35 35 26-May-16 15-Jul-16
Casework & Wood TrimCasework & Wood TrimCasework & Wood TrimCasework & Wood TrimCasework & Wood TrimCasework & Wood TrimCasework & Wood TrimPROC2-1430 3707-7 Day w/o Advertise Bid Package - Casework & Trim 21 21 26-Apr-16 16-May-16
PROC2-1030 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 17-May-16 17-May-16
PROC2-1130 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-May-16 24-May-16
PROC2-1230 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 25-May-16 15-Jun-16
PROC2-1300 3707-5 Day w/Hol Fab & Deliver Trim 5 5 16-Jun-16 22-Jun-16
PROC2-1380 3707-5 Day w/Hol Deliver & Paint Trim (Shop) 15 15 23-Jun-16 14-Jul-16
PROC2-1400 3707-5 Day w/Hol Fab & Deliver Casework 10 10 15-Jul-16 28-Jul-16
Floor CoveringFloor CoveringFloor CoveringFloor CoveringFloor CoveringFloor CoveringFloor CoveringPROC2-1440 3707-7 Day w/o Advertise Bid Package - Floor Covering 21 21 26-Apr-16 16-May-16
PROC2-1040 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 17-May-16 17-May-16
PROC2-1140 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-May-16 24-May-16
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2016 2017
FM Review / Approve Building Permit
Release FA / FS Design Drawings
FM Review / Approve FS
FM Review / Approve FA
Long Lead Items - Phase 2 Level 1 House 109 - HAMMOCK
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Heat Pumps
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Panels
Fab & Deliver Cans
MCC Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Light Fixtures
Advertise Bid Package - Casework & Trim
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Trim
Deliver & Paint Trim (Shop)
Fab & Deliver Casework
Advertise Bid Package - Floor Covering
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
Start Date 23-Feb-15
Finish Date 18-Nov-20
Data Date 26-Apr-16
Run Date 02-May-16
Page 1 of 4
3707-CR13
TASK filters: 2 Month Back + All
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707TASK filters: 2 Month Back + All Remaining, Activity Code.
Activity ID Calendar Activity Name Orig Dur
Rem Dur
Start Finish
PROC2-1240 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 25-May-16 15-Jun-16
PROC2-1330 3707-5 Day w/Hol Fab & Deliver Tile 18 18 16-Jun-16 12-Jul-16
PROC2-1390 3707-5 Day w/Hol Fab & Deliver Carpet 18 18 13-Jul-16 05-Aug-16
Doors / HardwareDoors / HardwareDoors / HardwareDoors / HardwareDoors / HardwareDoors / HardwareDoors / HardwarePROC2-1450 3707-7 Day w/o Advertise Bid Package - Doors / Hardware 21 21 26-Apr-16 16-May-16
PROC2-1050 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 17-May-16 17-May-16
PROC2-1150 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-May-16 24-May-16
PROC2-1250 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 25-May-16 15-Jun-16
PROC2-1370 3707-5 Day w/Hol Fab and Deliver Door Frames 30 30 16-Jun-16 28-Jul-16
PROC2-1420 3707-5 Day w/Hol Fab and Deliver Doors / Hardware 30 30 16-Jun-16 28-Jul-16
SignageSignageSignageSignageSignageSignageSignagePROC2-1080 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 01-Jun-16* 01-Jun-16
PROC2-1170 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 02-Jun-16 08-Jun-16
PROC2-1270 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 09-Jun-16 29-Jun-16
PROC2-1340 3707-5 Day w/Hol Fab & Deliver Signage 20 20 30-Jun-16 28-Jul-16
SecuritySecuritySecuritySecuritySecuritySecuritySecurityPROC2-1090 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 01-Jun-16* 01-Jun-16
PROC2-1180 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 02-Jun-16 08-Jun-16
PROC2-1280 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 09-Jun-16 29-Jun-16
PROC2-1350 3707-5 Day w/Hol Fab & Deliver Security 20 20 30-Jun-16 28-Jul-16
GlazingGlazingGlazingGlazingGlazingGlazingGlazingPROC2-1460 3707-7 Day w/o Advertise Bid Package - Glazing 21 21 26-Apr-16 16-May-16
PROC2-1060 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 17-May-16 17-May-16
PROC2-1160 3707-5 Day w/Hol AE2 (FSB) Receive / Review Submittal 5 5 18-May-16 24-May-16
PROC2-1260 3707-5 Day w/Hol AE1 (Mass) Receive / Review Submittal 15 15 25-May-16 15-Jun-16
PROC2-1320 3707-5 Day w/Hol Fab & Deliver Glazing 10 10 16-Jun-16 29-Jun-16
Granite TopsGranite TopsGranite TopsGranite TopsGranite TopsGranite TopsGranite TopsPROC2-1470 3707-7 Day w/o Advertise Bid Package - Granite Tops 21 21 26-Apr-16 16-May-16
PROC2-1070 3707-5 Day w/Hol MCC Receive / Review Submittal 1 1 17-May-16 17-May-16
PROC2-1200 3707-5 Day w/Hol Fab & Deliver Granite 25 25 18-May-16 22-Jun-16
Toilet Partitions & AccessoriesToilet Partitions & AccessoriesToilet Partitions & AccessoriesToilet Partitions & AccessoriesToilet Partitions & AccessoriesToilet Partitions & AccessoriesToilet Partitions & AccessoriesPROC2-1100 3707-5 Day w/Hol Fab & Deliver Toilet Partitions & Acc. 25 25 27-Jun-16* 01-Aug-16
ConstructionConstructionConstructionConstructionConstructionConstructionConstruction
Interim MilestonesInterim MilestonesInterim MilestonesInterim MilestonesInterim MilestonesInterim MilestonesInterim MilestonesM-PH2-CSC 3707-5 Day w/Hol Interim Substantial Completion - Phase 2 0 0 16-Sep-16*
Schedule Driven MilestonesSchedule Driven MilestonesSchedule Driven MilestonesSchedule Driven MilestonesSchedule Driven MilestonesSchedule Driven MilestonesSchedule Driven MilestonesM-PH2-NTP 3707-5 Day w/Hol NTP 0 0 18-Apr-16 A
M-PH2-FM50 3707-5 Day w/Hol 50% Fire Marshall Inspection Complete Level 1 0 0 23-Jun-16
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2016 2017
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Tile
Fab & Deliver Carpet
Advertise Bid Package - Doors / Hardware
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab and Deliver Door Frames
Fab and Deliver Doors / Hardware
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Signage
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Security
Advertise Bid Package - Glazing
MCC Receive / Review Submittal
AE2 (FSB) Receive / Review Submittal
AE1 (Mass) Receive / Review Submittal
Fab & Deliver Glazing
Advertise Bid Package - Granite Tops
MCC Receive / Review Submittal
Fab & Deliver Granite
Fab & Deliver Toilet Partitions & Acc.
Interim Substantial Completion - Phase 2
NTP
50% Fire Marshall Inspection Complete Level 1
Start Date 23-Feb-15
Finish Date 18-Nov-20
Data Date 26-Apr-16
Run Date 02-May-16
Page 2 of 4
3707-CR13
TASK filters: 2 Month Back + All
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707TASK filters: 2 Month Back + All Remaining, Activity Code.
Activity ID Calendar Activity Name Orig Dur
Rem Dur
Start Finish
M-PH2-IT 3707-5 Day w/Hol LV/FA/IT Complete 0 0 10-Aug-16
M-PH2-FM80 3707-5 Day w/Hol 80% Fire Marshall Inspection Complete Level 1 0 0 10-Aug-16
M-PH2-FM100 3707-5 Day w/Hol Final Fire Marshall Inspection Complete Level 1 0 0 29-Aug-16
M-PH2-SUBST 3707-5 Day w/Hol Substantial 0 0 16-Sep-16
M-PH2-FINAL 3707-5 Day w/Hol Prerequisite Phase 2 Punch List 0 0 22-Sep-16
Construction Phase SummariesConstruction Phase SummariesConstruction Phase SummariesConstruction Phase SummariesConstruction Phase SummariesConstruction Phase SummariesConstruction Phase SummariesC-PH2L1-HS 3707-7 Day w/o Construction - Phase 2 Level 1 House 109 - HAMMOCK 125 144 18-Apr-16 A 16-Sep-16
Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109Prerequisite Phase 2 - Level 1 House 109C-PH2-1030 3707-5 Day w/Hol Pre Demo Mtg w/ Owner 1 0 09-Mar-16 A 09-Mar-16 A
C-PH2-1040 3707-5 Day w/Hol Temp Walls Bsmt 2 0 12-Mar-16 A 13-Mar-16 A
C-PH2-1050 3707-5 Day w/Hol Demo Bsmt 2 0 12-Mar-16 A 13-Mar-16 A
C-PH2-1010 3707-5 Day w/Hol Temp Power / Lighting 5 0 18-Apr-16 A 19-Apr-16 A
C-PH2-1020 3707-5 Day w/Hol Make Safe 5 0 18-Apr-16 A 21-Apr-16 A
C-PH2-1060 3707-5 Day w/Hol Demo 1st Floor 5 0 18-Apr-16 A 22-Apr-16 A
C-PH2-1110 3707-5 Day w/Hol MEP Demo 7 1 18-Apr-16 A 26-Apr-16
C-PH2-1070 3707-5 Day w/Hol DOL Inpection (Fr iable Matl) Not Req (As Of) 1 0 22-Apr-16 A 22-Apr-16 A
C-PH2-1000 3707-5 Day w/Hol DOL Inspec tion 1 1 26-Apr-16 26-Apr-16
C-PH2-1080 3707-5 Day w/Hol Demo Dog House Power 10 10 26-Apr-16 09-May-16
C-PH2-1090 3707-5 Day w/Hol Asbestos Abatement 5 5 27-Apr-16 03-May-16
C-PH2-1150 3707-5 Day w/Hol Elev Demo (above 1st Deck) 5 5 27-Apr-16 03-May-16
C-PH2-1130 3707-5 Day w/Hol Post Demo Mtg w/ Owner 0 0 03-May-16
C-PH2-1140 3707-5 Day w/Hol Subcontractor OH Corrdination Mtg 1 1 04-May-16 04-May-16
C-PH2-1100 3707-5 Day w/Hol FRP Stair Infill 3 3 04-May-16 06-May-16
C-PH2-1190 3707-5 Day w/Hol FRP Elev Shaft 3 3 04-May-16 06-May-16
C-PH2-1160 3707-5 Day w/Hol OH Elec RI 15 15 05-May-16 25-May-16
C-PH2-1220 3707-5 Day w/Hol Basement Elevator Demolition 5 5 09-May-16 13-May-16
C-PH2-1120 3707-5 Day w/Hol Frame Walls 7 7 09-May-16 17-May-16
C-PH2-1210 3707-5 Day w/Hol OH Sprinkler RI 15 15 12-May-16 02-Jun-16
C-PH2-1180 3707-5 Day w/Hol Bsmt Plumb Rough In 3 3 18-May-16 20-May-16
C-PH2-1170 3707-5 Day w/Hol OH Mech RI (w/ Heatpumps) 20 20 19-May-16 16-Jun-16
C-PH2-1200 3707-5 Day w/Hol Mech Piping RI 7 7 23-May-16 01-Jun-16
C-PH2-1230 3707-5 Day w/Hol Dog House Buildout 30 30 03-Jun-16 15-Jul-16
C-PH2-1240 3707-5 Day w/Hol Frame Hard Lids 5 5 17-Jun-16 23-Jun-16
C-PH2-1310 3707-5 Day w/Hol Sheetrock 5 10 24-Jun-16 08-Jul-16
C-PH2-1260 3707-5 Day w/Hol MEP In-Wall 8 8 29-Jun-16 11-Jul-16
C-PH2-1280 3707-5 Day w/Hol Tape/Bed/Paint 10 10 07-Jul-16 20-Jul-16
C-PH2-1570 3707-5 Day w/Hol Overhead Low Voltage IT (By Owner) 5 5 12-Jul-16 18-Jul-16
C-PH2-1330 3707-5 Day w/Hol Tile RR / Break 5 5 21-Jul-16 27-Jul-16
C-PH2-1250 3707-5 Day w/Hol Ceiling Grid w/ Borders 5 5 21-Jul-16 27-Jul-16
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2016 2017
LV/FA/IT Complete
80% Fire Marshall Inspection Complete Level 1
Final Fire Marshall Inspection Complete Level 1
Substantial
Prerequisite Phase 2 Punch List
Construction - Phase 2 Level 1 House 109 - HAMMOCK
Pre Demo Mtg w/ Owner
Temp Walls Bsmt
Demo Bsmt
Temp Power / Lighting
Make Safe
Demo 1st Floor
MEP Demo
DOL Inpection (Fr iable Matl) Not Req (As Of)
DOL Inspec tion
Demo Dog House Power
Asbestos Abatement
Elev Demo (above 1st Deck)
Post Demo Mtg w/ Owner
Subcontractor OH Corrdination Mtg
FRP Stair Infill
FRP Elev Shaft
OH Elec RI
Basement Elevator Demolition
Frame Walls
OH Sprinkler RI
Bsmt Plumb Rough In
OH Mech RI (w/ Heatpumps)
Mech Piping RI
Dog House Buildout
Frame Hard Lids
Sheetrock
MEP In-Wall
Tape/Bed/Paint
Overhead Low Voltage IT (By Owner)
Tile RR / Break
Ceiling Grid w/ Borders
Start Date 23-Feb-15
Finish Date 18-Nov-20
Data Date 26-Apr-16
Run Date 02-May-16
Page 3 of 4
3707-CR13
TASK filters: 2 Month Back + All
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707TASK filters: 2 Month Back + All Remaining, Activity Code.
Activity ID Calendar Activity Name Orig Dur
Rem Dur
Start Finish
C-PH2-1350 3707-5 Day w/Hol Lighting 10 10 26-Jul-16 08-Aug-16
C-PH2-1340 3707-5 Day w/Hol Device Walls 5 5 29-Jul-16 04-Aug-16
C-PH2-1550 3707-5 Day w/Hol IT Trim Out (By Owner) 5 5 29-Jul-16 04-Aug-16
C-PH2-1320 3707-5 Day w/Hol Door Frames 7 7 29-Jul-16 08-Aug-16
C-PH2-1270 3707-5 Day w/Hol Grills / Diff 5 5 02-Aug-16 08-Aug-16
C-PH2-1290 3707-5 Day w/Hol Speakers (By Owner) 5 5 04-Aug-16 10-Aug-16
C-PH2-1300 3707-5 Day w/Hol FA Device Out 5 5 04-Aug-16 10-Aug-16
C-PH2-1360 3707-5 Day w/Hol Paint Door Frames 5 5 09-Aug-16 15-Aug-16
C-PH2-1380 3707-5 Day w/Hol Drop Tile 2 2 11-Aug-16 12-Aug-16
C-PH2-1370 3707-5 Day w/Hol Wood Trim 10 10 11-Aug-16 24-Aug-16
C-PH2-1390 3707-5 Day w/Hol Carpet 5 5 15-Aug-16 19-Aug-16
C-PH2-1410 3707-5 Day w/Hol Doors / Hardware 5 5 18-Aug-16 24-Aug-16
C-PH2-1400 3707-5 Day w/Hol Casework (Less Doors/Drawers) 10 10 18-Aug-16 31-Aug-16
C-PH2-1530 3707-5 Day w/Hol MCC Pre-Punch 5 10 18-Aug-16 31-Aug-16
C-PH2-1450 3707-5 Day w/Hol T&B 7 7 24-Aug-16 01-Sep-16
C-PH2-1430 3707-5 Day w/Hol TP / Accessories 3 3 25-Aug-16 29-Aug-16
C-PH2-1470 3707-5 Day w/Hol Final Paint 5 5 25-Aug-16 31-Aug-16
C-PH2-1420 3707-5 Day w/Hol Plumb Fixtures 2 2 26-Aug-16 29-Aug-16
C-PH2-1460 3707-5 Day w/Hol Glazing / Stops 2 2 26-Aug-16 29-Aug-16
C-PH2-1440 3707-5 Day w/Hol Granite / Cab Doors/Drawers 5 5 30-Aug-16 06-Sep-16
C-PH2-1480 3707-5 Day w/Hol AE1/Owner Punch List 10 15 01-Sep-16 22-Sep-16
C-PH2-1500 3707-5 Day w/Hol Touch Up Paint 2 2 09-Sep-16 12-Sep-16
C-PH2-1490 3707-5 Day w/Hol Final Clean 2 2 15-Sep-16 16-Sep-16
C-PH2-1510 3707-5 Day w/Hol Owner Move In 4 4 19-Sep-16 22-Sep-16
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
2016 2017
Lighting
Device Walls
IT Trim Out (By Owner)
Door Frames
Grills / Diff
Speakers (By Owner)
FA Device Out
Paint Door Frames
Drop Tile
Wood Trim
Carpet
Doors / Hardware
Casework (Less Doors/Drawers)
MCC Pre-Punch
T&B
TP / Accessories
Final Paint
Plumb Fixtures
Glazing / Stops
Granite / Cab Doors/Drawers
AE1/Owner Punch List
Touch Up Paint
Final Clean
Owner Move In
Start Date 23-Feb-15
Finish Date 18-Nov-20
Data Date 26-Apr-16
Run Date 02-May-16
Page 4 of 4
3707-CR13
TASK filters: 2 Month Back + All
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707TASK filters: 2 Month Back + All Remaining, Activity Code.
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
41
RFI’s
Capitol Interior Restoration Project # 37072300 N Lincoln Blvd. Oklahoma City, OK 73105 Tel: 405-521-2147 Fax:
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp
001 Existing Wall Condition 8/4/2015 8/14/20158/11/2015Manhattan Construction Company
Frankfurt Short Bruza
002 Demo Existing 6" Concrete Wall 8/13/2015 8/14/20158/20/2015Manhattan Construction Company
Frankfurt Short Bruza
003 Slab Infills details 8/25/2015 8/28/20159/1/2015Manhattan Construction Company
Frankfurt Short Bruza
004 MC Feeder Cables 8/27/2015 9/8/20159/3/2015Manhattan Construction Company
Frankfurt Short Bruza
005 New Door Lay Out Senate 3rd Floor 8/28/2015 8/28/20159/4/2015Manhattan Construction Company
Frankfurt Short Bruza
006 Bid Questions 9/1/2015 9/2/20159/8/2015Manhattan Construction Company
Frankfurt Short Bruza
007 Tie in of Existing Plumbing 3rd Floor 9/3/2015 9/10/20159/10/2015Manhattan Construction Company
Frankfurt Short Bruza
008 House UPS 9/9/2015 9/18/20159/15/2015Manhattan Construction Company
Frankfurt Short Bruza
009 Door Hardware Specs vs Plans 9/14/2015 9/22/20159/18/2015Manhattan Construction Company
Frankfurt Short Bruza
010 Lead Paint Abatement 9/25/2015 10/12/20159/29/2015Manhattan Construction Company
Mass Architects, Inc.
011 Building Envelope 9/25/2015 10/12/20159/29/2015Manhattan Construction Company
Mass Architects, Inc.
012 Voltage for H1, H1E, H2, H2E 9/30/2015 10/1/201510/2/2015Manhattan Construction Company
Frankfurt Short Bruza
013 New Paint Schedule 10/22/2015 10/29/201510/29/2015Manhattan Construction Company
Frankfurt Short Bruza
014 Keying 11/3/2015 1/4/201611/18/2015Manhattan Construction Company
Mass Architects, Inc.
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
42
RFI’s
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp
015 Exterior Windows 11/3/2015 1/4/201611/18/2015Manhattan Construction Company
Mass Architects, Inc.
016 Color Selection Fabric Wrapped Panels 11/12/2015 11/17/201511/17/2015Manhattan Construction Company
Frankfurt Short Bruza
017 Security 11/12/2015 11/24/201511/27/2015Manhattan Construction Company
Mass Architects, Inc.
018 Capitol Maintenance 11/17/2015 3/25/201611/23/2015Manhattan Construction Company
Mass Architects, Inc.
018-R001
Capitol Maintenance - Water Infiltration 4/27/2016 5/17/2016Manhattan Construction Company
Mass Architects, Inc.
019 Structual Load 12/16/2015 12/22/201512/23/2015Manhattan Construction Company
Frankfurt Short Bruza
020 H 109 Dog House Electrical Panel 4/25/2016 5/2/2016Manhattan Construction Company
Frankfurt Short Bruza
21Total Number of RFIs for this project: 2
Total Created Total Outstanding
OUTSTANDING SUBMITTAL LOG
SECTION 5
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
5�1
Submittals
Capitol Interior Restoration Project # 37072300 N Lincoln Blvd. Oklahoma City, OK 73105 Tel: 405-521-2147 Fax:
Number-Rev From Company Description To Company Sent Due Rec'd ActionDays +/-
Frankfurt Short Bruza
00001-26 0533-0 Manhattan Construction Company H 109 Raceway and Boxes for Electrical Systems - Product Data
Frankfurt Short Bruza 4/20/2016 5/4/2016 Action Pending
10002-26 2200-0 Manhattan Construction Company Low-Voltage Transformers - Product DataFrankfurt Short Bruza 4/28/2016 5/3/2016 Action Pending
-80001-26 5200-0 Manhattan Construction Company Emergency Lighting - Product Data Frankfurt Short Bruza 4/28/2016 5/12/2016 Action Pending
-50001-26 2726-0 Manhattan Construction Company Wiring Devices - Product Data Frankfurt Short Bruza 4/25/2016 5/9/2016 Action Pending
10001-26 5119-0 Manhattan Construction Company LED Interior Lighting - Product Data & Shop Drawings
Frankfurt Short Bruza 4/28/2016 5/3/2016 Action Pending
-80001-26 0519-0 Manhattan Construction Company Low-Voltage Electrical Power Conductors and Cables - Product Data
Frankfurt Short Bruza 4/28/2016 5/12/2016 Action Pending
-80001-26 0526-0 Manhattan Construction Company Grounding and Bonding for Electrical Systems - Product Data
Frankfurt Short Bruza 4/28/2016 5/12/2016 Action Pending
-120003-23 3113-1 Manhattan Construction Company H-109 Metal Ducts - Grilles, Registers and Diffusers
Frankfurt Short Bruza 5/2/2016 5/16/2016 Action Pending
-70004-23 8146-2 Manhattan Construction Company H 109 Water To Air Heat Pumps -Climatemaster
Frankfurt Short Bruza 5/4/2016 5/11/2016 Action Pending
Mass Architects, Inc.
-130005-23 8146-0 Frankfurt Short Bruza H 109 Water To Air Heat Pump - Desert Aire
Mass Architects, Inc. 5/3/2016 5/17/2016 Action Pending
-120001-26 28 16-0 Frankfurt Short Bruza H-109 Enclosed Switches and Circuit Breakers
Mass Architects, Inc. 5/2/2016 5/16/2016 Action Pending
-130001-26 0553-0 Frankfurt Short Bruza H-109 Identification for Electrical Systems
Mass Architects, Inc. 5/3/2016 5/17/2016 Action Pending
-120001-26 0544-0 Frankfurt Short Bruza H-109 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
Mass Architects, Inc. 5/2/2016 5/16/2016 Action Pending
-130001-26 0529-0 Frankfurt Short Bruza H-109 Hangers and Supports for Electrical Systems
Mass Architects, Inc. 5/3/2016 5/17/2016 Action Pending
-120002-26 0943-0 Frankfurt Short Bruza H-109 - Network Lighting Controls Mass Architects, Inc. 5/2/2016 5/16/2016 Action Pending
OUTSTANDING SUBMITTAL LOG
SECTION 5
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
5�2
Number-Rev From Company Description To Company Sent Due Rec'd ActionDays +/-
00002-22 4213-0 Manhattan Construction Company Commercial Water Closets - Product Data
Mass Architects, Inc. 4/20/2016 5/4/2016 Action Pending
00002-22 4213.16-0
Manhattan Construction Company Commercial Urinals - Product Data Mass Architects, Inc. 4/20/2016 5/4/2016 Action Pending
00002-22 4216-0 Manhattan Construction Company Commercial Lavatories and Sinks - Product Data
Mass Architects, Inc. 4/20/2016 5/4/2016 Action Pending
750003-00 4253-0 Manhattan Construction Company Draft- Design Standards Mass Architects, Inc. 2/5/2016 2/19/2016 Action Pending
-80002-26 2416-0 Manhattan Construction Company H 109 Panelboards Mass Architects, Inc. 4/28/2016 5/12/2016 Action Pending
-80004-23 3113-0 Manhattan Construction Company Metal Ducts - Louver - Product Data Mass Architects, Inc. 4/28/2016 5/12/2016 Action Pending
360001-23 3300-0 Manhattan Construction Company Mock-up Slot diffuser Mass Architects, Inc. 3/15/2016 3/29/2016 Action Pending
-80002-23 3423-0 Manhattan Construction Company HVAC Power Ventilators - Product Data Mass Architects, Inc. 4/28/2016 5/12/2016 Action Pending
00002-22 1119-0 Manhattan Construction Company Domestic Water Piping Specialties - Product Data
Mass Architects, Inc. 4/20/2016 5/4/2016 Action Pending
24Number of Submittal Packages in this Project:
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration
April 2016
6�1
Left: PreDemolition photo of the House 109 main corridor. Below: PostDemolition photo of the House 109 space, approximately same location as above.
House 109 – Demolition Begins
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
6�2
House 109 as demolition progresses.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
6�3
Above: A jobsite wide safety meeting is held each week with all workers on site to review relevant safety topics to the work taking place. Chris Thurman, Manhattan Assistant Superintendent, leads this week’s meeting. Right: Existing floor finishes are scraped from the concrete structure. The black adhesive below the existing tile must go through the abatement process.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
6�4
Left: The Arts Council invited the DesignBuild team to tour the Oklahoma City National Memorial & Museum as an example in storytelling from a museum perspective. In the coming months, the Arts Council will be working with the DesignBuild team to program and select potential artwork for installation after the renovation is complete. Left: The Lutron Quantum Lighting Control System was fully programmed and made functional for the House 112 & Senate 309 spaces in April. The OMES Facilities Management team received training on the new light management system and its operation.
Left: The DesignBuild team, security consultants from the Sextant Group, OMES/AE1 and Oklahoma Highway Patrol reviewing and discussing the design plans for the new security system.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration April 2016
6�5
Left: The FrankfurtShortBruza team led a Visitor Experience Visioning session for the Art’s Council, Historical Society, Department of Tourism and the OMES/AE1 team. Pictured here is a photo of Dr. Blackburn with the Historical Society giving a brief history of the Capitol building through the years.
Right: Manhattan Construction employees volunteered at a couple community events throughout April. The first event (top) was the Oklahoma Heart Association 2016 Central Oklahoma Heart Walk. The second was Rebuilding Together OKC’s Annual Work Day. (Below) Rebuilding Together OKC is an organization that rebuilds lives and neighborhoods by making homes safe, warm and dry for lowincome senior citizens in the Oklahoma City metropolitan area.