Key On-Going Projects (References)
EPC Of Obiafu/Obrikom to Oben (OB3) Gas Transmission Pipeline System LOT B - 67 km X 48-inch
This starts from the Intermediate Pigging station at Umukwata (around KP 63.45) in Delta State and
terminates at Oben Node in Edo State. The project also include: Engineering Design of the entire
Gas transmission pipeline system, LOT A and LOT B (130 km x 48-inch), Construction of the Gas
treatment Plant, Launcher and Receiver Stations, Installation of the Line Break Valves, Cathodic
protection system, Major and Minor River crossings, Major and Minor Road crossings, Railway
crossing, associated Earth and Civil works, Electrical/Instrumentation and Telecommunication
works, Testing and commissioning. The project belongs to the Nigerian National Petroleum
Corporation (NNPC).
It is worthy to note that currently this is the largest Gas transmission pipeline system to be built in
Nigeria.
ON-GOING
EPC of National Integrated Power Project (NIPP) Lot 1 Gas transmission Pipeline System covering 16-inch and 18-inch Gas Pipelines
EPC of National Integrated Power Project (NIPP) Lot 1 Gas transmission Pipeline System covering
16-inch and 18-inch Gas Pipelines This includes construction of Gas metering station, Yard
Fabrication, Construction and Installation of Cathodic protection systems, Road Crossings, Hook up
and Tie-in works, Hot Tap works, Electrical/Instrumentation and Telecommunication works, Earth
and associated Civil works, Testing and Commissioning works. The Project belongs to the Niger
Delta Power Holding Company Limited and when completed shall supply Gas to Gas Turbine power
Plant at Ihobvor, in Edo State of Nigeria.
ON-GOING
EPC of National Integrated Power Project (NIPP) Lot 2 Gas transmission Pipeline System
EPC of National Integrated Power Project (NIPP) Lot 2 Gas transmission Pipeline System
SYSTEMS This covers 18-inch Gas Pipelines, including construction of Gas metering stations, Yard
Fabrication, Construction and Installation of Cathodic protection systems, River and Road
Crossings, Hook up and Tie-in works, Hot Tap works, Electrical/Instrumentation and
Telecommunication works, Earth and associated Civil works, Testing and Commissioning works.
The Project belongs to the Niger Delta Power Holding Company Limited and when completed shall
supply Gas to Gas Turbine power Plant at Egbema in Imo State and Gbaran - Ubie in Bayelsa State
of Nigeria.
ON-GOING
Construction, Testing and Commissioning Of 37.8 km X 24-inch Oron Gas Pipeline System
This includes Construction and Installation of the flow line systems, Road Crossings, Hook up and
Tie-in works. Testing and Commissioning works. Laying/welding of pipeline, NDT of welded joints,
field joints coating, flush/hydrotest
ON-OING
Engineering, Procurement and Construction for 102.8 km x 12-inch Crude Oil Pipeline System from Umusadege to Eriemu for Umugini Asset Company Limited (UACL)
Scope of work:
1. 1. Construction of 102.8 km x 12-inch Crude Oil Pipeline from Umusadege to Eriemu , both in
Delta State of Nigeria.
2. 2. Construction, Installation and Piping of the Valve Pit inclusive of barred tee at Ogini
3. 3. Associated Earth and Civil works including perimeter fencing at Ogini
4. 4. Provision of portable Water, Valves, Pressure Gauges, pumps, Retaining Tanks etc. as
required for successful Hydro testing.
5. 5. Fabrication and Installation of Pipe supports and shoes at the pig trap locations.
6. 6. Electrical and Instrumentation works.
7. 7. Major and Minor Road crossings.
8. 8. Testing and Commissioning works.
9. 9. Provision of “As built” documentation.
The Project belongs to Umugini Asset company Limited (UACL)
COMPLETED
Upgrade of Ikeja/NGC City Gate For OANDO Gas and Power (Gaslink Nigeria Limited)
The scope consists of the following Phases, namely;
Phase 1: Commissioning of Installed Scrubber/Meters (STREAM 1)
1. 1. Tightening of installed facilities and piping works.
2. 2. Leak test and Nitrogen purging of the installed facilities.
3. 3. Electrical and instrumentation works.
4. 4. Wire brushing and Anti- corrosion works.
5. 5. Commissioning of the scrubber/meter and purging of the facility with Nitrogen prior to
introduction of Gas through the inlet valve.
6. 6. Reinstatement and cleaning of the site.
Phase 2: Installation and commissioning of Scrubber/Meter (STREAM 2)
1. 1. Decommissioning and removal of the existing scrubber.
2. 2. Associated civil works to allow the installation of the new scrubber.
3. 3. Installation of the new scrubber/flow meter and piping works.
4. 4. Fabrication of piping spools for the installation of Automatic drain and vent.
5. 5. Installation of Gantry.
6. 6. Leak test and nitrogen purging of the installed scrubber.
7. 7. Electrical and Instrumentation works.
8. 8. Wire brushing and Anti-corrosion works.
9. 9. Commissioning of the scrubber/meter and purging of the facility with Nitrogen prior to
introduction of Gas through the inlet valve.
10. 10. Reinstatement and cleaning of the site.
The Project belongs to OANDO Gas and Power (Gaslink Nigeria Limited)
ON-GOING
EPC for the Construction of Greater Lagos Phase IV Gas Distribution Network System
EPC for the Construction of Greater Lagos Phase IV Gas Distribution Network System covering a
total of 8.2 km x 12-inch Gas transmission pipeline with the Design capacity of 45mmscfd and an
operating capacity of 30mmscfd to cover IJORA to BONNY CAMP Axis. The project belongs to
Gaslink Nigeria Limited, subsidiary of OANDO Gas and Power. The project is to be carried-out in
three different segments, namely; SEGMENT 1:[ From IJORA 7UP to FIRST POWER BY IJORA
OLOPA], SEGMENT 2: [From IJORA FISH MARKET to NEGRIS IPP (MARINE POWER)],
SEGMENT 3: [ From NEGRIS IPP to BONNY CAMP UNDER-BRIDGE].
ON-GOING
EPC Of Pressure Reduction Metering System (PRMS)
EPC of Pressure Reduction Metering System (PRMS) for the Gas Supply to the Niger Delta Power
Holding Company Limited (NDPHC) Turbine Power Plant at Alaoji. The project belongs to the
Nigerian Gas Company Limited (NGC), subsidiary of the Nigerian National Petroleum Corporation
(NNPC). The project is to be carried-out in two segments, namely; SEGMENT 1 : (Execution of
outstanding Engineering design), SEGMENT 2:(Suppy and Delivery of Equipment and materials
including Cost Insurance and Freight (CIF) to Onne port and delivery to Alaoji Site).
ON-GOING
Summary of Recent Work Experience (On-Going/Completed)
S/
N
NAME OF
PROJECT
BRIEF DESCRIPTION OF
PROJECT SCOPE
CLIENT &
LOCATION
PROJECT
STATUS
1 EPC of
OBIAFU/OBRIKO
M to OBEN (OB3)
Gas transmission
Pipeline system
LOT B (67 km x
48-inch)
• Construction, installation
and commissioning of
OBIAFU/OBRIKOM to OBEN
(OB3) Gas transmission
Pipeline system LOT B (67km
x 48-inch) from the
Intermediate Pigging station
at Umukwata (around KP
63.45) in Delta State and
terminates at Oben Node in
Edo State.
• Complete Engineering
Design of the entire Gas
transmission pipeline system
LOT A & LOT B (130km x 48-
inch)
• Design and Construction of
the Gas treatment Plant,
Launcher and Receiver
Stations
• Installation of the Line Break
Valves
• Cathodic protection system
• Major and Minor River
crossings
• Major and Minor Road
crossings
• Railway crossing
• Associated Earth and Civil
works
• Electrical/Instrumentation
works
Nigerian National
Petroleum
Corporation
(NNPC), Delta
State and Edo
State both in
Nigeria
ON GOING
• Telecommunication works
• Testing and commissioning
2
EPC of 24 km x
24-inch Gas
transmission
Pipeline system
from Owaza to
NDPHC Power
Plant at Alaoji
• Construction, installation
and commissioning of 24km x
24-inch Gas transmission
Pipeline system from Owaza
to NDPHC Power Plant at
Alaoji, including, Four (4)
major road crossings, Third
party facilities crossings, 28-
inch x 24-inch pig traps
• Intermediate Pigging
Stations (IPS)
• Installation of 24-inch Ball
Valve for future connection
• Associated Earth and Civil
works
• Cathodic Protection system
• Electrical/Instrumentation
works
• Testing and commissioning
Nigerian Gas
Company Limited
(NGC). Abia State
of NigeriaCOMPLETE
D
3EPRS of a Gas
Pipeline.
• Mobilizing of resources
• Carrying out construction
and hooking up (sectional
replacement) of 24-inch x
250m Manifold by-pass line
Shell Petroleum
Development
Company Limited
(Bomu), Rivers
State of Nigeria
COMPLETE
D
4 EPC of Oando
128km x 18-inch
• Construction, Installation
and Commissioning of 128km
OANDO Gas and
Power (East
COMPLETE
D
South-South gas
transmission
pipeline system
from Ukanafun in
Akwa Ibom State
to Unicem Plant at
Calabar, Cross
River State
x 18-inch Gas lines
• Scope include R.O.W.
survey, ditching ,
welding/laying of pipeline,
NDT of welded joints, field
joints coating,
flush/hydrotest/drying/Nitroge
n purging of the Gas pipeline
• Associated Earth and civil
works
• Major and minor river
crossing (width ranging from
1.3km to 800m
• Major and Minor road
crossings
• Creek crossings
• Construction of complete
City Gate facilities,
• Construction and Installation
of: PRMS, LBV’S, IPS
• Electrical, Instrumentation
works and
Telecommunication works
• Testing and commissioning.
• The Gas pipeline
transverses across the
following terrains: Land,
swamp, creeks, rocky terrain,
thick forest and Hilly areas.
Horizon Gas
Company Limited)
Akwa Ibom and
Cross River States
of Nigeria
5 EPC for NIPP LOT
1 gas transmission
pipeline system
covering 18-inch
and 16-inch gas
pipelines, including
gas metering
station facilities
• Engineering design, FEED,
Procurement, Construction
and Commissioning of the
following gas pipelines;
• 1.5km x 18-inch from
Escravos to Lagos Pipeline
(ELP) kp 87.928 to Ihobvor
gas metering station
• 1km x 18-inch from Pan
Ocean Oil Company (POOC)
Niger Delta Power
Holding Company
Limited, Ihobvor at
Benin, Edo State
of Nigeria
ON GOING
to ELP
• 14km x 16-inch from NPDC
Oredo flowstation to ELP kp
51.3
• Construction and installation
of gas metering station
facilities
• Construction of asphalted
access road
• Associated Earth and civil
works
• Hot Tap works
• Cathodic protection works,
• Road crossing
• Electrical, Instrumentation
and Telecommunication
works
• Testing and commissioning
6 EPC for NIPP LOT
2 (Egbema and
Gbarain-Ube) gas
transmission
pipeline systems
covering 18-inch
pipeline, including
gas metering
station facilities
A. NIPP EGBEMA LOT 2
• Engineering design, FEED,
Procurement, Construction,
Commissioning of the
following gas pipelines
• 4km x 18-inch from SPDC
East (Egbema main) to
Egbema Power Plant
• 8km x 18-inch from Egbema
West flow station to Egbema
Power plant
• 12km x 18-inch from Addax-
Izombe flow station to
Egbema Power Plant
• Construction and installation
of Gas metering facilities,
• Associated Earth and Civil
works
• Cathodic protection works
• Hot Tap works
• Road crossing
• Electrical , Instrumentation
Niger Delta Power
Holding Company
Limited,
Egbema in Imo
State and Gbarain
- Ube in Bayelsa
State of Nigeria
ON GOING
and Telecommunication
works
• Testing and commissioning
B. NIPP GBARAIN - UBIE
LOT 2
• Engineering design, FEED,
Procurement, Construction,
Commissioning of the gas
pipeline
• 1.5km x 18-inch from SPDC
gas plant to Gbarain gas
metering station
• Construction and installation
of gas metering facility
• Associated Earth and Civil
works
• Cathodic protection works
• Hot Tap works
• Road crossing
• Electrical , Instrumentation
and Telecommunication
works
• Testing and commissioning
7 EPC of 27km x 12-
inch gas
transmission
pipeline system,
including gas
metering station
and pigging station
facilities
• Engineering Design, FEED,
Procurement, Installation and
Commissioning of 27km x 12-
inch Gas Pipeline system.
• Scope include R.O.W.
survey, ditching,
welding/laying of pipeline,
NDT of welded joints, field
joints coating,
flush/hydrotest/drying/Nitroge
n purging of the Gas Pipeline
• Associated earth and civil
works
• Electrical, instrumentation
and cathodic protection works
Geometric Power
Aba Limited
(GPAL) Osisioma
in Aba, Abia State
of Nigeria
COMPLETE
D
• Hot Tap works
• Testing and commissioning.
8
EPC for Akute
Independent
Power Project,
including
construction of
13km x 8-inch
HDPE Gas
transmission
pipeline system
and pressure
reduction metering
system (PRMS)
• Engineering, Procurement,
Construction, Installation, &
Commissioning of 13km x 18-
inch High Density
Polyethylene (HDPE) Gas
transmission pipeline system
• Including the Engineering,
Procurement, Construction,
Installation, and
Commissioning of 12 MW
Gas turbine power plant
• Major and minor river
crossings
• Major and minor road
crossings
• Associated Earth & Civil
works
• Construction and Installation
of PRMS
• Cathodic protection works
• Hot Tap works
• Electrical and
Instrumentation works
• Testing and commissioning
OANDO GAS AND
POWER (Akute
Power Limited)
Akute, Lagos State
of NigeriaCOMPLETE
D
9
Emergency
pipeline repairs
(EPRS) by
sectional
replacements and
clamping on
delivery lines
• Pipelines and facilities leak
repairs by clamping,
reinforcements and sectional
replacement.
• Manifold facilities
maintenance by corrosion
protection, repairs/servicing,
upgrade and replacements,
• Testing and commissioning
TOTAL E&P NIG.
Limited Rumuekpe
Rivers State of
NigeriaCOMPLETE
D
10 Relocation of
600m x 14-inch
gas pipeline
system
• Detail Engineering Design,
Procurement and
Construction of 14-inch x
600m Gas Pipeline across a
river.
Notore Chemical
Industries. Onne,
Rivers State of
Nigeria
Engineering,
Procurement
and weight
coating are
completed.
• Scope also include; ROW
Survey, Dredging, Pipeline,
Ditching, Weld & Lay, NDT,
Field Joint Coating, CP,
Hydro Testing, (cleaning,
Flushing, Pigging, Drying
• Nitrogen Purging of the Line
and Commissioning
Construction
work-scope,
is on-hold.
11
GTS pipeline
emergency
response and
maintenance
contract for NLNG
LTD
• Emergency Land and
Swamp pipelines and
facilities leak repairs by
clamping, composite
materials, sectional
replacement, etc.
• Facilities maintenance by
corrosion protection,
repairs/servicing, upgrade
and replacements.
NLNG (land and
Swamp) On-GOING
(CALL-OUT
CONTRACT)
12
Engineering,
Procurement and
Construction of
Greater Lagos
Phase III Gas
Distribution
Network Systems
for Gaslink Nigeria
Limited
• Construction, Installation
and Commissioning of: 22km
x 18-inch Gas Pipeline, 38km
x 14-inch Gas Pipeline and
45km x 12-inch Gas Pipeline.
• Scope include R.O.W.
survey, pipeline ditch
excavation, welding/laying of
pipeline, NDT of welded
joints, field joints coating,
flush/hydrotest/drying of Gas
pipe lines
• Installation of four (4)
Pressure Reduction and
Metering Stations (PRMS)
• Execution of associated civil
works
• Maintenance of the gas
facility for two (2) years.
OANDO GAS AND
POWER (Gaslink
Nigeria Limited)
Lagos State,
NigeriaCOMPLETE
D
13 Major emergency
pipeline repairs
and manifold
• Installation and
Commissioning of dia. 8-inch
x 5km gas line.
Shell Petroleum
Development
Company Limited
COMPLETE
D
rehabilitation for
swamp areas
• Scope include R.O.W.
survey, pipeline ditch
excavation, welding/laying of
pipeline, NDT of welded
joints, field joints coating, and
flush/hydrotest/drying of Gas
pipeline
• Associated civil works.
Eastern Swamp
Rivers/Bayelsa
States of Nigeria
14
Engineering,
Procurement and
Construction of
Gas Distribution
Network Systems
Phases 1 & 2 for
Gaslink Nigeria
•Construction, Installation and
Commissioning of: 30km x 6-
inch Gas pipeline, 48km x 8-
inch Gas pipeline and 23km x
12-inch Gas pipeline • Right
Of Way ( R.O.W) survey,
pipeline ditch excavation,
welding/laying of gas
pipeline, NDT of welded
joints, field joints coating
• Flush/hydrotest/drying of
gas pipeline
• Installation of CP system
• Associated Earth and Civil
works.
OANDO GAS AND
POWER (Gaslink
Nigeria Limited),
Ikeja Lagos State
of NigeriaCOMPLETE
D
15 23km x 6-inch
Cawthorne
Channel Cryogenic
NGL product
pipeline
• The project was on the
Construction and
Commissioning (in a swamp
terrain) of 23km x 6-inch
Natural Gas Liquid product
pipeline, from Cawthorne
Channel to Bonny .
• This involved R.O.W survey,
and clearing pipeline ditch
excavation/backfilling,
welding/laying, NDT of
welded joints, field joint
coating/holiday detection
• River crossings construction
• Piling and installation of
block valve stations
• Yard fabrication
• Cathodic protection works
Global Gas and
Refining Company
Ltd. Eastern
Swamp Rivers
State of Nigeria
COMPLETE
D
• Hydrotest and drying of the
gas pipeline. As-built
documentation
16
Emergency
pipeline repair
services , land and
swamp
• Emergency Land
flow/pipelines and facilities
leak repairs by clamping and
sectional replacement
• Facilities maintenance by
corrosion protection,
repairs/servicing, upgrade
and replacements.
Nigeria. Agip Oil
Company. Eastern
Land
Rivers/Bayelsa
States of Nigeria
COMPLETE
D
17
Cathodic
protection
grounded
replacement at
Rumukroshe &
Apara sites
• Mobilising resources and
carrying out Sinking of deep
well GROUNDBED
• Installation of the ground
bed facilities
• Electrical and solar
panel/systems
installation/hook-up
Shell Petroleum.
Development.
Company. Limited,
Port Harcourt Land
Rivers State of
Nigeria
COMPLETE
D
18 Engineering,
Procurement and
Construction for
102.8km x 12-inch
Crude Oil Pipeline
System from
Umusadege to
Eriemu for Umugini
Asset Company
Limited (UACL)
• Construction, Installation
and commissioning of
102.8km x 12-inch Crude Oil
Pipeline from Umusadege to
Eriemu
• Construction, Installation of
the Valve Pit and barred Tee
at Ogini
• Associated Earth and Civil
works including perimeter
fencing at Ogini
• Provision of portable water,
valves, pressure gauges,
pumps, retaining tanks etc.
as required for successful
hydrotesting
• Fabrication and Installation
of pipe supports and shoes at
the pig trap location
• Electrical and
Instrumentation works
Umugini Asset
Company Limited
(UACL)
Umusadege/Eriem
u in Delta State of
Nigeria
COMPLETE
D
• Major and minor road
crossings
• Testing and Commissioning
works
• Provision of “As built”
documentation
19
Rehabilitation of
Product Tanks in
Bonny terminal
(Zakhem-Oilserv
limited)
• Total rehabilitation of 21
nos. crude oil storage tanks
• Including surface piping
• Maintenance, repairs and
replacement works
Shell Petroleum
Development
Company. Limited
Eastern Land and
Swamp Bonny,
Rivers State of
Nigeria
COMPLETE
D
20
36-inch Trans
Niger pipeline
manifold
construction
• Mobilizing resources and
carrying out fabrication,
installation
• Hooking up of piping works
via normal process and hot
taps
• Corrosion protection via
painting
• Cathodic protection systems
• Civil works.
Shell Petroleum
Development
Company Limited
Port Harcourt Land
Ogoni area -
Rivers State of
Nigeria
COMPLETE
D
21 Construction &
commissioning of
15km x 12-inch
and 15 km x 4-inch
Elelenwo west to
Agbada 1 bulk and
test pipelines
respectively..
• Design, Procurement,
Installation and
Commissioning of 15km x 12-
inch and 15km x 4-inch oil
pipelines.
• Scope include R.O.W.
survey, pipeline ditch
excavation, creek and
seasonal swamp crossing,
welding/laying of pipeline,
NDT of welded joints, field
joints coating
• Flush/hydrotest/dewatering
of oil lines
• Fabrication
Shell Petroleum
Development
Company Limited
Port Harcourt
Land, Rivers State
of Nigeria
COMPLETE
D
• Installation of two (2)
scraper traps
• Associated facilities design
construction
• Installation of deep well
ground bed (Cathodic
Protection).
22
Laying and
flushing of
pipelines/
abandonment of
delivery lines
• Mobilisation of resources
• Laying of 4-inch water
supply pipeline
• Pigging of pipeline (22km x
20-inch) using foam and gel
pigs train, and inhibited
water.
• Dewatering and mothballing
of pipeline.
Shell Pet. Dev. Co.
Ltd Port Harcourt
land Rivers State
of Nigeria COMPLETE
D
23 Riser replacement
• Riser upgrade works; riser
burial and removing of
substandard risers and
replacing with new ones.
Shell Petroleum
Development.
Company Limited,
Eastern land and
Swamp (Rivers
State)
COMPLETE
D
24
Pipeline repairs,
manifold upgrade
& rehabilitation
(land and swamp)
• Pipelines and facilities leak
repairs by clamping,
reinforcements and sectional
replacement
• Manifold facilities
maintenance by corrosion
protection
• Repairs/servicing, upgrade
and replacements.
Shell Petroleum
Development
Company Limited
Eastern land and
Swamp Rivers and
Bayelsa States of
Nigeria
COMPLETE
D
25 Pipeline clamping
(swamp & land)
• Pipelines leak repairs by
clamping and reinforcements
(using normal methods,
shoring and cofferdam)
Shell Petroleum
Development
Company Limited,
Eastern land and
Swamp Rivers and
COMPLETE
D
Bayelsa States of
Nigeria
26
Replacement of
Aba Gas
Distribution
Network System
• Procurement, Installation
and Commissioning of 6-inch
and 4.3km x 4-inch Gas
pipelines.
• Scope include R.O.W.
survey, pipeline ditch
excavation, welding/laying of
pipeline, NDT of welded
joints, field joints coating
• Road crossings by method
of thrust boring
• Flush/hydrotest/drying of
gas lines, and modification of
gas manifolds
• Associated civil works.
Shell Petroleum
Development
Company Limited,
Eastern Land –
Aba, Abia State of
Nigeria
COMPLETE
D
27
Supply and
installation of
generator set &
overhead tank at
Kalaibiama health
centre
• Supply and installation
works on generator and
overhead tank (civil, electrical
and mechanical works
inclusive)
Shell Petroleum
Development
Company Limited,
Eastern land and
Swamp Rivers
State of Nigeria
COMPLETE
D
28 EPC for the
construction of
greater Lagos
phase iv gas
distribution
network system
covering a total of
8.2 km x 12-inch
gas transmission
pipeline with the
design capacity of
45mmscfd and an
SEGMENT 1: FROM IJORA
7UP TO FIRST POWER BY
IJORA OLOPA
• 1no. Tie-in point at Ijora
using Hot Tapping
mechanism
• 4nos. Road crossing using
Thrust Boring mechanism
• Construction of 3nos
Concrete Valve Pits with
Man-Hole for Sectionalizing
Gaslink Nigeria
Limited, subsidiary
of OANDO Gas
and Power (Lagos
State)
ON GOING
operating capacity
of 30mmscfd to
cover Ijora to
bonny camp axis.
The project will be
carried-out in three
(3) segments.
Valves and Valve Tees
• 1no River crossing at Ijora
Causeway, width 260m using
Horizontal Directional Drilling
(HDD) Technology
• Design, Procurement and
Installation of Fiber Optic
Cable
• Construction of 1.8km x 12-
inch Gas pipeline including
Stringing, Ditching, Weld &
Lay, NDT, Backfilling and
etc…
• Design, Procurement and
Construction of Cathodic
protection system
• Construction and
Connection of 150m x 8-inch
Gas spur pipeline
• Testing, Pre-Commissioning
and Commissioning of the
main Gas pipeline and the
Gas Spurline
SEGMENT 2: FROM IJORA
FISH MARKET TO NEGRIS
IPP (MARINE POWER)
• 1no River crossing at Eko
Bridge, width 986m using
Horizontal Directional Drilling
(HDD) Technology
• 7nos. Road crossing using
Thrust Boring mechanism
and 7nos by open cut method
• Construction of 3nos
Concrete Valve Pits with
Man-Hole for Sectionalizing
Valves and Valve Tees
• Construction of 1.8km x 12-
inch Gas pipeline including
Stringing, Ditching, Weld &
Lay, NDT, Backfilling and
etc…
• Design, Procurement and
Construction of Cathodic
protection system
• Design, Procurement and
Installation of Fiber Optic
Cable
• Construction and
Connection of 150m x 8-inch
Gas Spur pipeline
• Testing, Pre-Commissioning
and Commissioning of the
main Gas pipeline and the
Gas Spur line
SEGMENT 3: FROM
NEGRIS IPP TO BONNY
CAMP UNDER-BRIDGE
• 1no River crossing, width
954m using Horizontal
Directional Drilling (HDD)
Technology
• 3nos. Road crossing using
Thrust Boring mechanism
and 3nos by open cut method
• Construction of 0.6km x 12-
inch Gas pipeline including
Stringing, Ditching, Weld &
Lay, NDT, Backfilling and
etc…
• Construction of 1nos
Concrete Valve Pit with Man-
Hole for Sectionalizing Valves
and Valve Tees
• Design, Procurement and
Construction of Cathodic
protection system
• Design, Procurement and
Installation of Fiber Optic
Cable
• Testing, Pre-Commissioning
and Commissioning of the
main Gas pipeline
29 EPC of the
Pressure
Reduction
Metering System
(PRMS) for the gas
supply to the Niger
Delta Power
Holding Company
Limited (NDPHC)
Turbine Power
Plant at Alaoji. The
scope of work is in
two (2) segments
FIRST SEGMENT:
EXECUTION OF
OUTSTANDING
ENGINEERING DESIGN ON
THE FOLLOWING:
• Cold vent system
comprising of Low and High
pressure blow down facilities
(Valves, Actuated Valves, all
piping, etc. and controlled by
the Programmable Logic
Controller “PLC”
• Fuel/Instrument Gas system
skid including associated
upstream and downstream
piping and electric heating
facilities
• The 6-inch interconnecting
piping between the boiler
package and the heat
exchangers
• Metering station PLC
system for monitoring and
control of the field equipment,
volumetric flow of each meter
run and the totalized
volumetric flow
• Isometric drawings of all
equipment and associated
piping for the plants
• Volumetric control syste
B). SECOND SEGMENT:
Nigerian Gas
Company Limited
(NGC), subsidiary
of NNPC Alaoji,
Abia State of
Nigeria
ON GOING
SUPPLY AND DELIVERY OF
THE FOLLOWING
EQUIPMENT AND
MATERIALS INCLUDING
COST INSURANCE AND
FREIGHT (CIF) TO ONNE
PORT AND DELIVERY TO
ALAOJI SITE:
• 1 no. Inlet Emergency Shut
Down Valve (ESD)
• 2 nos. Stream of heat
exchangers
• 1 no. Instrument and Fuel
Gas systems
• 3 nos. Stream of regulators-
skid packages
• 3 nos. Stream of orifice
metering and 1 no. Turbine
metering-skid packages,
complete with all the
necessary Valves
• Volumetric control system -
1no. Cold vent system
• Dual flow computer
panel/PLC, Remote Terminal
Unit (RTU) panel with hot
standby and interface
protocol for Supervisory
Control Data Acquisition
(SCADA) connection
• 1 no. Gas Chromatograph
(GC) - 1 no. 125 KVA Gas
driven Generator - 1 no. 10
KVA Uninterrupted Power
Supply (UPS) system with
battery bank
• Associated Instrumentation
for the filter separators
including level control Valves
- Installation of the
equipment/materials and
provision of Vendor’s
representatives for the testing
and commissioning of the
completed metring station
• Commissioning and supply
of 2 years operational spare
parts
• Training of NGC operations
and maintenance personnel
• Testing and commissioning
of the PRMS and its
associated facilities including
the Gas Chromatograph
• Provision of “As-Built”
drawings/documentations, all
project data books as well as
the operating and
maintenance manuals
• Submission of the project
Close-Out report to NNPC at
the completion of the contract
SUMMARY OF SHELL PETROLEUM DEVELOPMENT CORPORATION OF NIGERIA LIMITED PROJECTS
S/
NoDESCRIPTION OF PROJECT
COMPLETION
DATE
SPDC PROJECTS
124-inch Gas Flare line by clamping at cawthorn channel (2) Gas
Plant09/2010
224-inch NCTL Post defect repair using Cofferdam at Fusokiri
completion09/2010
324-inch Leak repair using Diamond Wrap at Sanbarth (1)
completion09/2010
418-inch Bunkering points L/R delivery line by clamping at Soku-
Anguliama competition07/2010
5 24-inch Trunk Line by clamping at Bodowest completion 07/2010
6 24-inch Trunk Line by clamping at Kalibiama completion 06/2010
7 20-inch Riser at Buguma Completion 05/2010
8 16-inch Pig retrieval at Nun-River completion 05/2010
9 24-inch Manifold By-Pass Sectional Replacement at Bomu (3) 04/2010
10 16-inch Pig retrieval at Nun-River 03/2010
11 10-inch DL Disused line Salvaging at Nun-River 02/2010
12 24-inch NCTL Leak Repair Using Cofferdam at Opobo Channel 01/2010
13 24-inch NCTL Leak Repair Using Cofferdam at Opobo Channel (3) 01/2010
14 10-inch & 18-inch Bunkering Points at Soku (7) 11/2009
15 Sign Post Installation at SPDC Locations 11/2009
16 28-inchNCTL Leak repair using Cofferdam at Cawthrorne Channel 11/2009
17 10-inch & 18-inch Delivery Line Leak repair at Soku (6) 11/2009
18 10-inch & 18-inch Bunkering Points repair at Soku (5) 10/2009
1928-inch and 24-inch Leak repair by Clamping using Cofferdam at
Boro/Sanbarth10/2009
20 10-inch & 18-inch Bunkering Points Repair at Kpokpokiri 08/2009
21 16-inch TL Defect Point ID & Repair at Kolo-Creek 08/2009
22 28-inch NCTL Leak repair by Clamping at Ogboro 07/2009
2324-inch Riser Leak repair by Sectional Replacement using
Cofferdam at Adamakiri07/2009
24 10-inch DL Leak Repairs @ Oporoma 07/2009
25 28-inch NCTL by clamping at Krakrama (2) 06/2009
26 10-inch DL Bunkering Points Repair at Nun river 06/2009
27 10-inch DL 3 points leak repair at Onyoma 05/2009
28 24-inch Leak Repair NCTL Clamping at Opobo Channel (1) 10/2009
29 30-inch Flange Installation at Bomu (2) 05/2009
3010-inch & 18-inch Bunkering Points Repair by Clamping at Soku
(3)04/2009
3110-inch & 18-inch Bunkering Points Repair by Clamping at Soku
(2)03/2009
32 24-inch LR NCTL Clamping at Bomu (1) 02/2009
33 24-inch LR Gas plant Soku (1) 02/2009
SUMMARY OF NLNG PROJECTS
S/
NoDESCRIPTION OF PROJECT
COMPLETION
DATE
NLNG PROJECTS
1 IP Verification Dig on Soku-Rumuji 28" pipeline 14/2/2014
2 Elok Gas Pipeline Leap Repair 14/2/2014
3 GTS Pipeline Emergency Response and Maintenance. Otari FTO 18/02/2014
4 GTS Pipeline Emergency Response and Maintenance 19/08/2013
5Carry out GTS Proximity Survey on the Rumuji Bonny ROW: Mapping
of GPS Coordinates along the ROW13/07/2012
6
GTS Proximity Survey on the Obiafu-Ubeta: Carry out GTS Proximity
Survey on Ubeta-Obiafu Pipeline to ascertain that the provisions of the
Oil Pipeline Act WRT encroachment and Population Density are met
13/07/2012
7 Field Assessment of the GTS and Gathering Geographic information 04/03/2012
8Direct Current voltage Gradient Survey (DCVG) on Rumuji- Bonny
(KP 32.8-51.51) pipeline in Obite-Ubeta21/03/2012
9Carry out Direct Current Voltage Survey (DCVG) on the Obite-Ubeta
pipeline21/03/2012
10 Carry out Direct Current Voltage Survey (DCVG) on the Soku-Rumuji 21/03/2012
pipeline
11Dig-up Verification of IP Metal Loss Feature at KP 7021 on Ubeta-
Rumuji (T1) Section of GTS 1 in Kreigani13/03/2012
12GTS1 Inspection of Repair Patched Plates on Leak Points - S2
KP13.9 Kreigani Leak site03/01/2012
13 Side Sonar Scan of GTS Pipeline Crossing at Agba Ndele 11/10/2011
14 CP Trouble Shooting of Trains 1, 2 and 3 at NLNG Bonny Plant 09/12/2011
15Backfilling and remediation of exposed T2 pipeline and ROW neat
Gbukuma community22/08/2011
16 Provision of GTS emergency response and maintenance service 08/08/2011
17 GTS-1 CP Remedial works for Obite-Ubeta pipeline section 08/01/2011
18 GTS-1 CP Remedial works for Obite-Rumuji pipeline section 08/01/2011
19 GTS-1 CP Remedial works for Obiafu-Ubeta pipeline section 08/01/2011
20 GTS-1 CP Remedial works for Rumuji-Bonny pipeline section 08/01/2011
21Mechanical backfilling of the Gas transmission Pipeline section
(100m) along the NLNG GTS ROW at GBUKUMA in Rivers State08/2011
22 Sandbagging of new Calabar River Crossing (KP34+612) 19/05/2011
23GTS Pipeline Emergency Response & Maintenance (T2 KP 53.5 Leak
repair)17/9/2010
24Sandbagging of the Sambreiro River Crossing at Odiadje on NLNG's
GTS ROW16/7/2010
25Leak Repair by Screw Plugging & Sleeving on 28-inch Gasline at
Soku Completion06/2010
26 36-inch Gasline Screw Plugging & Sleeving at Okrika 06/2010
27 36-inch GAS LR by screw plugging using Cofferdam at Soku using 01/2010
Houseboat
28 KP 60 Adamakiri Re-Entry 01/2009
SUMMARY OF TOTAL E&P NIGERIA LIMITED
S/
NoDESCRIPTION OF PROJECT
COMPLETION
DATE
TOTAL E&P LIMITED PROJECTS
112-inch Obagi Leak Repair of Explosive Damaged at Rumuekpe
Pipeline (2)10/2009
2 Repair of Explosive Damaged 12-inch at Obagi Pipeline 08/2009