of an evaluation of performance measures for prefabricated submerged concrete breakwaters: section...
TRANSCRIPT
An Evaluation ofof Performance Measures for Prefabricated Submerged
Concrete Breakwaters: Section 227
Cape May Point, New Jersey
Demonstration Project
Donald K Stauble - Engineer Research & Development Center,Donald K Stauble - Engineer Research & Development Center, Coastal and Hydraulics LaboratoryCoastal and Hydraulics LaboratoryJ.B. Smith - Philadelphia DistrictJ.B. Smith - Philadelphia DistrictRandall A. Wise - Philadelphia DistrictRandall A. Wise - Philadelphia District
Beachsaver Reef
Double-T SillDouble-T Sill 2.5 Year Results2.5 Year Results
National Shoreline Erosion Control Development & Demonstration Program
Innovative Shoreline ProtectionUS Army Corpsof Engineers
DEMONSTRATION SITESDEMONSTRATION SITES
Cape May Point, NJCape May Point, NJ
National Shoreline Erosion Control Demonstration and Development Program
US Army Corpsof Engineers8
.… demonstrating innovative coastal shoreline protectionmethods with an emphasis on evaluation of nontraditionalapproaches to prevent coastal erosion and improve shorelinesediment retention.
OBJECTIVES OBJECTIVES
1)1) To evaluate the effectiveness of the two To evaluate the effectiveness of the two submerged structuressubmerged structures in retaining sand on the beach in retaining sand on the beach as compared with as compared with unprotectedunprotected groin compartments groin compartments
2)2) Compare the effectiveness of the more costly Compare the effectiveness of the more costly Beachsaver ReefBeachsaver Reef with the less costly with the less costly
Double-T SillDouble-T Sill in retaining sand in retaining sand in groin compartmentsin groin compartments
3)3) Evaluate ability of bothEvaluate ability of both structures to retainstructures to retain Beach Fill material Beach Fill material after placementafter placement
SITE LOCATIONSITE LOCATION
CAPECAPEMAYMAYPOINTPOINT CAPE MAYCAPE MAY
MEDOWSMEDOWSCAPECAPEMAYMAYCITYCITY
CAPE MAY POINTCAPE MAY POINT issouthern most beach in New Jersey atentrance to Delaware Bay
N
HISTORICAL SHORELINE CHANGEHISTORICAL SHORELINE CHANGE
Problem:Problem:Beach erosion Beach erosion due to wavesdue to wavesand tidal currentsand tidal currents
Atlantic Ocean
Del
awar
e B
ay
N
Tidal Currents
Tidal Currents
WavesWaves
18791899
1936
1943
19711977
1986
Photo 2003
BEACHSAVER REEFBEACHSAVER REEF
Interlocking line
Placed in ~ -9 ft NAVD of water ~ -2.7 m NAVDTop of reef just below water line at Low water
(1.5 ft)
(15.5 ft)(10 ft)
(6 ft)
Three reef units placed over each filter fabric scour prevention layer
Landward sideLandward side
Sand excavation Sand excavation Required under Required under some units, fill some units, fill under othersunder others
Filter Fabric Filter Fabric Layer PlacementLayer Placement
Beachsaver unitsBeachsaver units
PrefabricatedPrefabricatedConcreteConcreteBreakwaterBreakwater
waves
Landward sideLandward side
DOUBLE – T SILLDOUBLE – T SILL Units placed on sand (no filter cloth)At ~ -9 ft NAVD w/ crest at –6 ft at low waterAt ~ -2.7 m NAVD w/crest at –1.8 m at low water
30’–0” Long
9.14 m
3.66 m
3’-0” 6’-0”
12’-0”
4”
2’-10”
7 ¾”
length = 30’-0”
4 ¾” MARINE GRADE CONCRETE w/ REBAR
0.96 m
Alignment - PlanAlignment - Plan ViewView
Interlocking EndInterlocking End
Sill ConceptSill Concept
PrefabricatedPrefabricatedConcrete SillConcrete Sill
0.12 m
Cell 1Cell 1Rock Rock SeawallSeawall
Cell 2Cell 2
94 Beachsaver Reef
94 Beachsaver Reef
Cell 3Cell 3
94 Beachsaver Reef
94 Beachsaver Reef
01 Fill01 Fill
Cell 4Cell 4
Control w/Control w/
01, 04 Fills01, 04 Fills
Cell 5Cell 502 Beachsaver Reef02 Beachsaver Reef01 Rock & Gabion wall01 Rock & Gabion wall
Cell 6Cell 602 Double-T Sill02 Double-T Sill
Cell 7Cell 7ControlControl
Cell 8Cell 8ControlControl
CAPE MAY POINT SITE LAYOUTCAPE MAY POINT SITE LAYOUT
Recent Shore Protection History:Recent Shore Protection History:1950’s 9 Groins constructed1950’s 9 Groins constructed6/94 Cell 2,3 - 6/94 Cell 2,3 - Beachsaver ReefBeachsaver Reef 1/01 Cell 3,4 - 1/01 Cell 3,4 - Beach fillBeach fill2001 Cell 5 - 2001 Cell 5 - Rock & Gabion wallRock & Gabion wall9/029/02 Cell 5 Cell 5 - - Beachsaver Reef Beachsaver Reef
w/ filterw/ filter 10/0210/02 Cell 6Cell 6 - - Double-T SillDouble-T Sill3/043/04 Cell 4Cell 4 -- Beach FillBeach Fill12/04 Cell 1-6 - 12/04 Cell 1-6 - Eco Sys ResEco Sys Res Bch FillBch Fill
SECTION 227 PROJECTSECTION 227 PROJECTCell 5Cell 5 – Beachsaver Reef– Beachsaver ReefCell 6 – Double-T SillCell 6 – Double-T Sill
Cape MayCape May LighthouseLighthouse
#
#
#
#
#
#
#
#
##
#
##
#
#
$T
$T
$T
$T
$T
$T$T
$T
$T
SITE BATHYMETRYSITE BATHYMETRYElevation Range (ft)
-60 - -55
-55 - -50
-50 - -45
-45 - -40
-40 - -35
-35 - -30
-30 - -25
-25 - -20
-20 - -15
-15 - -10
-10 - -5
-5 - 0
0 - 5
5 - 10
10 - 15
15 – 20
25 - 30
10/28/03
Marginal Flood
Channel
She
lf29 Profile Lines
ScourHole
Cel
l 1 -
Co
ntr
ol
Cel
l 2 –
94
Bea
chsa
ver
Shoal
Cel
l 3 –
94
Bea
chsa
ver
Cel
l4 –
Con
trol
/Fill
Cell 5
– B
each
save
r Ree
f
Cell 6 – D
ouble-T
Cell 7 - Control
Cell 8 - Control
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP45 200007 CMP45 200101 CMP45 200203 CMP45 200304CMP45 200307 CMP45 200310 merged CMP45 200402 CMP45 200404CMP45 200407 CMP45 200410 CMP45 200501 CMP45 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP41 200007 CMP41 200101 CMP41 200203 CMP41 200304CMP41 200307 fix CMP41 200310 merged CMP41 200402 CMP41 200404CMP41 200407 CMP41 200410 CMP41 200501 CMP41 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP37 200007 CMP37 200101 CMP37 200203 CMP37 200304CMP37 200307fixsmo CMP37 200310 merged CMP37 200402 CMP37 200404CMP37 200407 CMP37 200410 CMP37 200501 CMP37 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP29 200007 CMP29 200101 CMP29 200203 CMP29 200304CMP29 200307 CMP29 200310 merged CMP29 200402 CMP29 200404CMP29 200407 CMP29 200410 CMP29 200501 CMP29 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP26 200007 CMP26 200101 CMP26 200203 CMP26 200304CMP26 200307 fix CMP26 200310 merged CMP26 200402fix CMP26 200404fixCMP26 200407 CMP26 200410 CMP26 200501 CMP26 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP23 200007 CMP23 200101 CMP23 200203 CMP23 200304CMP23 200307 CMP23 200310 merged CMP23 200402 CMP23 200404fixCMP23 200407 CMP23 200410 CMP23 200501 CMP23 200504
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP20 200007 CMP20 200101 CMP20 200203 CMP20 200304CMP20 200307 CMP20 200310 merged CMP20 200402fix CMP20 200404CMP20 200407 CMP20 200410 CMP20 200501 CMP20 200504
Cell 1Cell 1ControlControl
Cell 2Cell 219941994BeachsaverBeachsaver
Cell 3Cell 319941994BeachsaverBeachsaver
Cell 4Cell 4ControlControl
-60
-50
-40
-30
-20
-10
0
10
20
30
0 1000 2000 3000 4000 5000 6000 7000
Ele
vatio
n (
ft)
Distance Offshore (ft)
Cape May Point
CMP33 200007 CMP33 200101 CMP33 200203 CMP33 200304CMP33 200307 all CMP33 200310 merged CMP33 200402fix CMP33 200404fixCMP33 200407 CMP33 200410 CMP33 200501 CMP33 200504
Cell 5Cell 5227 227 BeachsaverBeachsaver
Cell 6Cell 6227 227 Double-TDouble-T
Cell 8Cell 8ControlControl
Cell 7Cell 7ControlControl
Scour Hole/Flood Channel
FloodChannel
FloodChannel
FloodChannel
Shoal
Shoal
Shoal
Shoal
Shoal
Shoal
Shelf
Shelf Shelf
Shelf
Shelf
Shelf
Shoal
Shoal
• Functional PerformanceFunctional Performance
SandSand Retention -Retention - Volume ChangeVolume ChangeChange in MHW Shoreline PositionChange in MHW Shoreline Position
• Economic PerformanceEconomic PerformanceReduction in Renourishment Quantities -Reduction in Renourishment Quantities -& Lengthening Fill Cycle & Lengthening Fill Cycle
• Structural PerformanceStructural PerformanceStructural Stability -Structural Stability - Change in Structure Crest ElevationChange in Structure Crest Elevation
Alongshore IntegrityAlongshore IntegrityDepth of ScourDepth of Scour
MONITORING PROJECT PERFORMANCEMONITORING PROJECT PERFORMANCE
Improve ProtectionImprove ProtectionReduce UncertaintyReduce UncertaintyReduce CostsReduce Costs
FUNCTIONAL PERFORMANCEFUNCTIONAL PERFORMANCE
Cell 4 Control
Cell 5 Beachsaver Reef
Pre -Fill
Post -Fill
4 Months
Volume Change
%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U
%U%U%U%U%U%U%U%U%U%U%U%U%U%U%U
##########################################################################
Pre fill - October 2004 Post-Fill – Jan/Feb 2005 4 Months – April 2005(Photo October 2003)
FUNCTIONAL PERFORMANCEFUNCTIONAL PERFORMANCEMHW Shoreline ChangeMHW Shoreline Change
Cell 4 - Control
Cell 5 - Beachsaver
Cell 6 - Double-T
Cell 3 - 94 Beachsaver
Cell 2 - 94 Beachsaver Cell 1 - Control
ECONOMIC PERFORMANCEECONOMIC PERFORMANCE – Construction CostsConstruction Costs
5 weeks @cost of $1,440/lf5 weeks @cost of $1,440/lf
72 10-ft-long units covering 720 ft72 10-ft-long units covering 720 ft• Filter cloth installationFilter cloth installation• Excavation and fill requiredExcavation and fill required• Placement of units w/ diverPlacement of units w/ diver
Beachsaver ReefBeachsaver Reef – – 16 Aug to 25 Sep 0216 Aug to 25 Sep 02
4 days @ cost of $345/lf4 days @ cost of $345/lf
22 30-ft-long units covering 660 ft22 30-ft-long units covering 660 ft• NO Filter cloth installationNO Filter cloth installation• Excavation and fill NOT required Excavation and fill NOT required • Placement of units w/ diverPlacement of units w/ diver
(Cost of rock used in both cells to tie into groin tips not included in linear foot cost)
Double-T SillDouble-T Sill – 26 Sep to 2 Oct 02 – 26 Sep to 2 Oct 02
ECONOMIC PERFORMANCE -ECONOMIC PERFORMANCE -
Reduction in Renourishment Quantities & Lengthening Fill Cycle Reduction in Renourishment Quantities & Lengthening Fill Cycle (Economic Performance/Life Cycle Cost Analysis)(Economic Performance/Life Cycle Cost Analysis)
Structures designed to act as a sill to retain sand within the groin compartmentStructures designed to act as a sill to retain sand within the groin compartment
Lower Cape May Meadows/Cape May Point Eco System Restoration ProjectLower Cape May Meadows/Cape May Point Eco System Restoration Projectconstructed December 2004 will document fill retention and extension ofconstructed December 2004 will document fill retention and extension ofrenourishment cycle time in cells with and without structuresrenourishment cycle time in cells with and without structures
Based on present monitoring Based on present monitoring Anticipated savings in:Anticipated savings in:• Initial fill retentionInitial fill retention• Longer renourishment intervalsLonger renourishment intervals in cells with Beachsaver Reefsin cells with Beachsaver Reefs
Purpose:Purpose: Relate engineering Relate engineering performance to economic costsperformance to economic costsGoal:Goal: Evaluate improved Evaluate improved performance (benefits) performance (benefits) in relation to investment (costs)in relation to investment (costs)
BEACH FILL Performance –BEACH FILL Performance –
Placed Cell 1-6 - December 2004To Protect Coastal Wetland
4 months later4 months later
Post-fill: +7 ft to –42 ft shoreline gain/retreat 100% to 79% volume remaining
Cell 4Cell 4 Cell 5Cell 5
1 Source:• Nearshore
Placed 326,917 cu yd
Cape May Point toCape May MeadowsEco-System RestorationProject
Cape May Point 227 Beachsaver Reef
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
0
050100150200250300350400450500550600650700750
Distance NW from Groin 5 (ft)
Ele
va
tio
n b
elo
w N
AV
D8
8 (
ft)
Construction 8/16-9/25/02 As-built 10/07/02 4/14/2003 7/11/2003
10/24/2003 02/20/2004 5/5/2004 7/19/04
10/11/04 2/7/2005 4/21/2005
off line
CMP 34 CMP 33 CMP 32CMP 35
BEACHSAVER REEF - SETTLEMENTBEACHSAVER REEF - SETTLEMENT
A’
A
A’ A
CELL 5
Cell 5-Beachsaver
Area of most SettlementArea of most Settlementup to 4 ft (1.2 m) within 6 monthsup to 4 ft (1.2 m) within 6 months
10/2002 to 4/2005
SeawardBeach
Area of cutArea of fill
-3 ft
-9 ft
Design Depth
CPM33
CPM34
CMP33CMP34
STRUCTURAL PERFORMANCESTRUCTURAL PERFORMANCE – – Structural StabilityStructural Stability
Cape May Point 227 Double-T
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
0
050100150200250300350400450500550600650700
Distance NW from Groin 6 (ft)
Ele
va
tio
n b
elo
w N
AV
D8
8 (
ft)
as-built 10/07/02 4/14/2003 7/25/2003 11/04/2003 02/20/2004
05/05/2004 07/19/2004 11/08/2004 02/07/2005 4/21/2005
sand covered between arrows
since 7/25/03
onlyexposedDouble-T's
onlyexposedDouble-T's
Post-Fill
CMP36CMP37CMP38CMP39
DOUBLE T SILL - SETTLEMENTDOUBLE T SILL - SETTLEMENT
B’
B’
B
B
Cell 6-Double-T
CELL 6
2 to 3 ft (0.5 to 1 m) Settlement & 2 to 3 ft (0.5 to 1 m) Settlement & Complete Burial under 1 to 2 ft (0.3 to 0.6 m)Complete Burial under 1 to 2 ft (0.3 to 0.6 m)
of sand within 6 monthsof sand within 6 months
10/2002 to 4/2005
-6 ft
Design Depth
-9 ft
CPM37
CMP37
STRUCTURAL PERFORMANCE -STRUCTURAL PERFORMANCE -
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
400 500 600 700 800
Ele
vatio
n, ft
(N
AV
D)
Distance from Baseline, ft
Cape May Point
CMP37 200203 CMP37 200304 CMP37 200307fixsmo
Pre-installation
6-month post
9-month post Double-T Sill Location
Installation Depth
Approximate Settlement
Line CMP33 6-month postLine CMP33 9-month post
Beachsaver Reef
Line CMP34 9-month postLine CMP34 6-month post
Beachsaver ReefBeachsaver Reef
Double-T SillDouble-T Sill
CHANGE IN STRUCTURECHANGE IN STRUCTURECrest Elevation,Crest Elevation,Alongshore Integrity Alongshore Integrity &&Depth of ScourDepth of Scour
ScourTrough
SUMMARYSUMMARY
227227 Project constructed August - October 2002Project constructed August - October 20022.5 Year Quarterly Monitoring Results Reported Here 2.5 Year Quarterly Monitoring Results Reported Here Eco System Restoration Project const. - December 2004Eco System Restoration Project const. - December 2004
Preliminary Findings:Preliminary Findings:
• Retention of sand greatest in groin compartments w/ Beachsaver Reefs even w/ settlement
• Double-T Sill vs. Beachsaver Reef could not be evaluated due to settlement of Double-T Sill
• Anticipated savings in retention of beach fill w/ Beachsaver Reefs
Cape May Point, NJ Demonstration Site