Obsolescence Management in Long Term Projects
OMAINTEC 2016
Stuart Kelly
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Management | Integrated Logistic Support | Training
Introductions
Stuart Kelly
– Ex Head of Obsolescence Management Policy, UK MOD • Ensuring proactive OM implemented as part of the Defence acquisition
process • Advice & Guidance to >200 projects
– Currently Managing Director of Through Life Support Limited
• Providing Advice & Guidance, Tools and Training to Improve OM Capability
– President International Institute of Obsolescence Management
– Committee member looking after IEC62402:20007
– Visiting Fellow at Cranfield university
Obsolescence Management | Integrated Logistic Support | Training
Through Life Support Ltd.
• We provide all the support required to set up, deliver and implement a proactive Obsolescence Management framework comprising of:
– Policy
– Plans
– Processes
– Tools
– Contractual guidance
– Comprehensive training programs.
Obsolescence Management | Integrated Logistic Support | Training
Through Life Support Ltd
Sectors
• Defence
• Oil and Gas
• Nuclear
• Rail
• Financial
• Marine Engineering
• Telecommunications
Obsolescence Management | Integrated Logistic Support | Training
Stuart Kelly
President International Institute of Obsolescence Management
– For professionals worldwide who are dedicated to furthering their knowledge and understanding of the Obsolescence Management discipline and who wish to network with a wide group of companies from a global membership.
IIOM
Obsolescence Management | Integrated Logistic Support | Training
What is Obsolescence?
Obsolescence Management | Integrated Logistic Support | Training
What is Obsolescence?
“The transition from availability from the
original manufacturer to unavailability”
IEC 62402:2007
Obsolete –
“no longer in production by the original manufacturer to the original specification”
New Version IEC 62402
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Risk
0 5 10 15 20 25 30
Supply of Part
User Requirement
0 5 10 15 20 25 30
Supply of Part
User Requirement
In an ideal world…
Reality…
Years
Years
OBSOLESCENCE RISK
Obsolescence Management | Integrated Logistic Support | Training
Time
Avai
labi
lity
Development & Initial
Production
Period of steady
availability
Item is Obsolescent
Period of Obsolescence
Manufacturer announces
future end of production
date
End of production
Item is Obsolete
Product Life Cycle
Obsolescent
Obsolete
EOL
Obsolescence Management | Integrated Logistic Support | Training
Life from to
•• Average lifecycles: electronic componentsAverage lifecycles: electronic components– Linear/interfaces 8 years
– Logic families 6 years
– Displays 3 years
– Gate arrays 2 years
– Microprocessors 2 years
– Programmable logic devices 1 year
– Memory families 9 months
–– Overall averageOverall average 3.25 years3.25 years
A B
Obsolescence Management | Integrated Logistic Support | Training
Source – IHS iSupply (COG Conference)
Obsolescence will not go away…..
2000
2500
3000
3500
4000
4500
5000
5500
6000
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
END OF LIFE NOTICES
Obsolescence Management | Integrated Logistic Support | Training
DATA PROCESSING 33.3%
WIRED COMMUNICATIONS 6.4%
WIRELESS COMMUNICATIONS
23.5%
CONSUMER ELECTRONICS 18.0%
AUTOMOTIVE ELECTRONICS 7.9%
INDUSTRIAL ELECTRONICS 9.9% MILITARY / AEROSPACE
1.0%
Semiconductor revenues by end market
Source – Application Market Forecast Tool (AMFT)
Obsolescence Management | Integrated Logistic Support | Training
Legislation causes obsolescence
RoHS
Restriction of the Use of Certain Hazardous Substances in
Electrical and Electronic Equipment Directive
e.g. Lead, which is used in soldering on the vast majority of
electronic circuit boards.
REACH
Registration, Evaluation, Authorisation and Restriction of Chemical
Substances.
Restricts the use of substances that are used in parts.
Affects both parts and processes
Obsolescence Management | Integrated Logistic Support | Training
Electronic
Components Mechanical
Parts Software
Skills
Tools
Test
Equipment
Materials
Processes
What Goes Obsolete?
Obsolescence Management | Integrated Logistic Support | Training
What is the Impact of Obsolescence?
Obsolescence Management | Integrated Logistic Support | Training
Impact of Obsolescence
Some examples
• A [nuclear] plant lost 8 days of production due to failure of an obsolete voltage isolation card in the rod control system.
• 22.2% of nuclear plants are experiencing or risking plant outages as a result of equipment obsolescence problems.
• KC-10 programme spent $264,000 to resolve the issue of one obsolete part.
• Merlin Mk1 helicopter: £1.15 billion upgrade primarily to resolve electronics obsolescence issues
• Test Equipment – Redesign costs of £114K to resolve an obsolete Waveform Analyser (cost £3K)
Source: Plant Support Engineering: Obsolescence Management - Nov 2008
Obsolescence Management | Integrated Logistic Support | Training
The Bottom Line ………..
Obsolescence in long life projects is inevitable.
It is now impacting on equipment even before entering
service
It can happen quickly, could cost lots of unplanned money
to sort and directly affect equipment availability
The only way to mitigate the risk is by managing
obsolescence
Obsolescence Management | Integrated Logistic Support | Training
What is Obsolescence Management?
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Management
• Understand the parts in your project.
• Understand the current, and future obsolescence risk.
• Put steps in place to mitigate known risk.
• Reduce the impact of obsolescence on your:
a) Capability
b) Cost
Obsolescence Management | Integrated Logistic Support | Training
Resolution Costs
£
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Status vs
Obsolescence Risk
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Status
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Status
• First step in Obsolescence Management is to understand the current obsolescence status of a part: – Is it currently procurable from the original
manufacturer?
• How to achieve Obsolescence Status of a Bill of Material (BOM) – Component Monitoring Tool
– Manual Monitoring
Obsolescence Management | Integrated Logistic Support | Training
Component Monitoring Tool
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Monitoring Tool
Obsolescence Management | Integrated Logistic Support | Training
Through Life Support Ltd
Obsolescence STATUS Reports
Obsolescence Management | Integrated Logistic Support | Training
A part is obsolete – so what?
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Risk
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Risk
Obsolescence Management | Integrated Logistic Support | Training
Through Life Support Ltd.
• Obsolescence Risk Analysis.
Obsolescence Risk Analysis – PROJECT A
High Risk
Medium Risk
Low Risk
Obsolescence Management | Integrated Logistic Support | Training
High Level Risk Assessment Process
Obsolescence Management | Integrated Logistic Support | Training
Looking Forward
• Obsolescence Prediction -
Obsolescence Management | Integrated Logistic Support | Training
Risk Assessment
• A good risk assessment is at the heart of a good Obsolescence Management Plan
• Obsolescence Risk Register is at the heart of a good risk assessment – all decisions must be recorded.
• Decisions must be regularly reviewed.
Obsolescence Management | Integrated Logistic Support | Training
Obsolescence Management Plan
(OMP)
“description of the strategies for the
identification and mitigation of the effects
of obsolescence through all stages of
the life of a product”
IEC 62402:2007
Obsolescence Management | Integrated Logistic Support | Training
Other Points to Consider
• When should Obsolescence Management begin?
– At the beginning
• Contracting for Obsolescence Management
– Needs to be robust
– Who Pays?
• Measure OM Performance
– "If you can't measure it, you can't improve it.“ Peter Drucker
– Cost Avoidance
– Return on Investment
• Predict the Cost of Obsolescence
Obsolescence Management | Integrated Logistic Support | Training
Summary
• Obsolescence Risk is inevitable in Long Life Systems
• Implement proactive Obsolescence Management processes to analysis, understand and mitigate obsolescence risk.
– Extend operational life
– Reduce through life costs
• Measure performance
• Predict Obsolescence Costs