Noveco ePM new functionality in Release 3.0 support pack 01

Upload: others

Post on 06-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Noveco  ePM    new  functionality  in    Release  3.0  support  pack  01  

Page 2: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning Managing Cost Accruals

Cross Project budget Adjustments (variations)

New Project tree

Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 3: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning in the Workbench

Project with Revenue plan from Sales Order (with billing plan)

Page 4: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Plan By Period: Plan Revenue

Choose ‘PLAN REVENUE” and distribute Plan Revenue by period

Page 5: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Drill Down to Sales Order from the WB From the Workbench you can go to Sales Order overview

Double click to drill down into sales order details

Page 6: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Sales Order billing plan

The Billing Plan was updated automatically from the Workbench

Page 7: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Configuration

The only required configuration in Noveco is to maintain version 0 in Plan Revenue SAP standard Sales Order billing plan configuration must be completed

Page 8: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning

Managing Cost Accruals Cross Project budget Adjustments (variations)

New Project tree

Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 9: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

Steps performed at that point: - planned MATERIALS on WBS for 470,000 USD - raised PO for the total amount of 300,000 USD - Posted GR/IR for the amount of 30,000 USD At this point we know that additional services were provided (or materials were delivered) for the amount of 15,000 USD, but our Supplier has not sent us the latest invoice.

Page 10: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

Select Costing line with MATERIALs, switch to change mode and click on Detailed Forecasting

Page 11: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

In detailed view we can see that we have ordered “Structural Steel” Based on the currently processed invoices, our PO is 10% complete

We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, you will drill down into PO item view from that screen

Page 12: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

You can enter amount (yet to be invoiced) into the “PO Accrued O/Cur” (object currency) Or you can enter “Value of Work Done” as a percentage, system will automatically calculate “PO Accrued O/Cur” value

Page 13: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

When finished click “Confirm”

Page 14: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

The Accrued Cost amount is copied into the aggregated view from Detailed Forecasting This Value will be saved in PS Info System Note. You don’t have to use “Detailed Forecasting”. You can enter value of accrued costs in “Forecast” tab

Page 15: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

From the Workbench you can go to PS Hierarchy reports

Page 16: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

This hierarchy report is delivered with Noveco ePM package

Page 17: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

Cost Accruals appear in PS report

Now you can report on total value of Accrued Costs for all your projects for a specific Period (in our case it was June 2015) !!! IDEA: If your Finance Dept. needs to see this amount in P&L report for the reported month you can make a journal posting to a special GL account crediting a special “Accrual” Internal Order. This way you leave project costs out of accrual postings and reversals cycle made by the finance.

Page 18: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

Accrual Costs will be automatically reduced next time the Invoice for our Purchase Order is posted

Page 19: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

We post GR and IR for the amount of 15,000 USD for our PO

Page 20: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Managing Cost Accruals

When Project forecasts are recalculated (click “Refresh”) the Accrued Cost is reduced automatically In our example they are wiped out to zero by actual costs

Page 21: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning

Managing Cost Accruals

Cross Project budget Adjustments (variations)

New Project tree

Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 22: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Cross Project Adjustments

You can now create cross project Adjustment Variations. The system issues a warning message when WBS elements (or Network activities) belong to different projects

Page 23: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning

Managing Cost Accruals

Cross Project budget Adjustments (variations)

New Project tree Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 24: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

New Project Tree

The new ALV Tree is set for the Workbench with configurable Layouts

Page 25: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

New Project Tree

… and there are more fields to choose from

Page 26: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning

Managing Cost Accruals

Cross Project budget Adjustments (variations)

New Project tree

Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 27: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Plan By Period enhancements

Two splitters are now in place to manually modify sizes of the sub-screens by dragging them.

Page 28: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Plan By Period enhancements

To Copy Distribution pattern from Budget to Cost To Complete, you now must select a year (does not matter if you select line with ‘%’ or ‘$’) To copy all years, select all lines

Page 29: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Revenue Planning

Managing Cost Accruals

Cross Project budget Adjustments (variations)

New Project tree

Enhancements to Plan by Period

Enhancements to Detailed Forecasting

New  Functionality  in  Release  3.0  support  pack  01:  

Page 30: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting

To Perform Detail Forecasting in the WB you must activate it in the Noveco Configuration for your project Planning Profile As default, this indicator is not selected

Page 31: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting enhancements

Two splitters are now in place to manually modify sizes of the sub-screens by dragging them.

Page 32: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting enhancements

Now you can plan detailed forecast from different Project WBS or NWA, different cost elements etc. You can now navigate the tree and the Detailed Forecasting tab is updated as you navigate

Page 33: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting enhancements

Dynamic filters are now available to filter out only those line items that you want to work with. For Example, if you want to work with Purchase Orders Only, click “Filter = PO” button

Page 34: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting enhancements

Example, Filter “Filter = PO” is applied

Page 35: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

Detailed Forecasting enhancements

If you want to work with Detailed Forecasting and don’t need Detail Distribution screen click on “Expand Screen” button

Page 36: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

The Detailed Forecasting Screen is expanded. Note that splitters are still available, they were set to the bottom of the screen. You can still drag them up. If you want to restore screen to its default structure, click “Restore Screen”

Page 37: NovecoePM&& new&functionality&in ... - SAP Project Systems€¦ · We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, ... This

For more information visit Noveco Systems on www.novecosystems.com