Noveco ePM new functionality in Release 3.0 support pack 01
Revenue Planning Managing Cost Accruals
Cross Project budget Adjustments (variations)
New Project tree
Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
Revenue Planning in the Workbench
Project with Revenue plan from Sales Order (with billing plan)
Plan By Period: Plan Revenue
Choose ‘PLAN REVENUE” and distribute Plan Revenue by period
Drill Down to Sales Order from the WB From the Workbench you can go to Sales Order overview
Double click to drill down into sales order details
Sales Order billing plan
The Billing Plan was updated automatically from the Workbench
Configuration
The only required configuration in Noveco is to maintain version 0 in Plan Revenue SAP standard Sales Order billing plan configuration must be completed
Revenue Planning
Managing Cost Accruals Cross Project budget Adjustments (variations)
New Project tree
Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
Managing Cost Accruals
Steps performed at that point: - planned MATERIALS on WBS for 470,000 USD - raised PO for the total amount of 300,000 USD - Posted GR/IR for the amount of 30,000 USD At this point we know that additional services were provided (or materials were delivered) for the amount of 15,000 USD, but our Supplier has not sent us the latest invoice.
Managing Cost Accruals
Select Costing line with MATERIALs, switch to change mode and click on Detailed Forecasting
Managing Cost Accruals
In detailed view we can see that we have ordered “Structural Steel” Based on the currently processed invoices, our PO is 10% complete
We can see Actual costs by PO and its remaining (to be invoiced) value If you double click on PO number, you will drill down into PO item view from that screen
Managing Cost Accruals
You can enter amount (yet to be invoiced) into the “PO Accrued O/Cur” (object currency) Or you can enter “Value of Work Done” as a percentage, system will automatically calculate “PO Accrued O/Cur” value
Managing Cost Accruals
When finished click “Confirm”
Managing Cost Accruals
The Accrued Cost amount is copied into the aggregated view from Detailed Forecasting This Value will be saved in PS Info System Note. You don’t have to use “Detailed Forecasting”. You can enter value of accrued costs in “Forecast” tab
Managing Cost Accruals
From the Workbench you can go to PS Hierarchy reports
Managing Cost Accruals
This hierarchy report is delivered with Noveco ePM package
Managing Cost Accruals
Cost Accruals appear in PS report
Now you can report on total value of Accrued Costs for all your projects for a specific Period (in our case it was June 2015) !!! IDEA: If your Finance Dept. needs to see this amount in P&L report for the reported month you can make a journal posting to a special GL account crediting a special “Accrual” Internal Order. This way you leave project costs out of accrual postings and reversals cycle made by the finance.
Managing Cost Accruals
Accrual Costs will be automatically reduced next time the Invoice for our Purchase Order is posted
Managing Cost Accruals
We post GR and IR for the amount of 15,000 USD for our PO
Managing Cost Accruals
When Project forecasts are recalculated (click “Refresh”) the Accrued Cost is reduced automatically In our example they are wiped out to zero by actual costs
Revenue Planning
Managing Cost Accruals
Cross Project budget Adjustments (variations)
New Project tree
Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
Cross Project Adjustments
You can now create cross project Adjustment Variations. The system issues a warning message when WBS elements (or Network activities) belong to different projects
Revenue Planning
Managing Cost Accruals
Cross Project budget Adjustments (variations)
New Project tree Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
New Project Tree
The new ALV Tree is set for the Workbench with configurable Layouts
New Project Tree
… and there are more fields to choose from
Revenue Planning
Managing Cost Accruals
Cross Project budget Adjustments (variations)
New Project tree
Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
Plan By Period enhancements
Two splitters are now in place to manually modify sizes of the sub-screens by dragging them.
Plan By Period enhancements
To Copy Distribution pattern from Budget to Cost To Complete, you now must select a year (does not matter if you select line with ‘%’ or ‘$’) To copy all years, select all lines
Revenue Planning
Managing Cost Accruals
Cross Project budget Adjustments (variations)
New Project tree
Enhancements to Plan by Period
Enhancements to Detailed Forecasting
New Functionality in Release 3.0 support pack 01:
Detailed Forecasting
To Perform Detail Forecasting in the WB you must activate it in the Noveco Configuration for your project Planning Profile As default, this indicator is not selected
Detailed Forecasting enhancements
Two splitters are now in place to manually modify sizes of the sub-screens by dragging them.
Detailed Forecasting enhancements
Now you can plan detailed forecast from different Project WBS or NWA, different cost elements etc. You can now navigate the tree and the Detailed Forecasting tab is updated as you navigate
Detailed Forecasting enhancements
Dynamic filters are now available to filter out only those line items that you want to work with. For Example, if you want to work with Purchase Orders Only, click “Filter = PO” button
Detailed Forecasting enhancements
Example, Filter “Filter = PO” is applied
Detailed Forecasting enhancements
If you want to work with Detailed Forecasting and don’t need Detail Distribution screen click on “Expand Screen” button
The Detailed Forecasting Screen is expanded. Note that splitters are still available, they were set to the bottom of the screen. You can still drag them up. If you want to restore screen to its default structure, click “Restore Screen”
For more information visit Noveco Systems on www.novecosystems.com