noise feasibility study proposed residential development ... · noise feasibility study for a...
TRANSCRIPT
Noise Feasibility Study
Proposed Residential Development
47 – 75 Willow Road
Guelph, Ontario
Prepared for:
Black, Shoemaker, Robinson & Donaldson Limited 257 Woodlawn Road West, Unit 101
Guelph, Ontario N1H 8J1
Prepared by
Yvonne Lo, BASc, PEng
Reviewed by
Bill Gastmeier, MASc, PEng
November 29, 2019
Project No.: 01900657
Table of Contents
1 Introduction and Summary ............................................................................................................. 1
2 Site Description and Sources of Sound ........................................................................................... 2
2.1 Road Traffic Noise Criteria ..................................................................................................... 2
3 Traffic Noise Predictions ................................................................................................................ 4
3.1 Road Traffic Data .................................................................................................................... 4
3.2 Road Traffic Noise Predictions ............................................................................................... 5
4 Recommendations ........................................................................................................................... 6
4.1 Outdoor Living Areas .............................................................................................................. 6
4.2 Indoor Living Areas and Ventilation Requirements ................................................................ 6
4.3 Building Façade Constructions ................................................................................................ 7
4.4 Warning Clauses ...................................................................................................................... 8
5 Stationary Noise Assessment .......................................................................................................... 9
5.1 Criteria Governing Stationary (Industrial) Noise Sources ...................................................... 9
5.2 Sound Level Criteria at the Residential Receptors ................................................................ 10
5.3 Assessment of Noise Emissions from Existing Rooftop Mechanical Equipment at Adjacent Sensitive Receptors .......................................................................................................................... 11
5.4 Assessment of Stationary Noise Sources Associated with the Proposed Development at Existing Sensitive Receptors ............................................................................................................ 12
6 Impact of the Development on Itself ............................................................................................ 13
7 Summary and Recommendations ................................................................................................. 13
7.1 Implementation ...................................................................................................................... 15
Figure 1: Key Plan Figure 2: Proposed Site Plan Showing Prediction Locations Figure 3: Existing and Proposed Noise Source Locations Figure 4: Predicted Daytime Sound Level Contours at Proposed Sensitive Receptors from Existing Stationary Noise Sources, dBA Figure 5: Predicted Nighttime Sound Level Contours at Proposed Sensitive Receptors from Existing Stationary Noise Sources, dBA Figure 6: Predicted Daytime Sound Level Contours at Existing Sensitive Receptors from Proposed Stationary Noise Sources, dBA Figure 7: Predicted Nighttime Sound Level Contours at Existing Sensitive Receptors from Proposed Stationary Noise Sources, dBA Appendix A: Road Traffic Data Appendix B: Sample STAMSON 5.04 Output Appendix C: Manufacturer’s Sound Data
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 1 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
1 Introduction and Summary
HGC Engineering was retained by Black, Shoemaker, Robinson & Donaldson Limited to conduct a
noise feasibility study for a proposed mixed-use/residential development to be located at 47 – 75
Willow Road in the City of Guelph, Ontario. The proposed development will consist of two 6-storey
mixed-use/residential buildings with commercial uses on the ground floor and one level of
underground parking. The study is required by the Municipality as part of their rezoning and
approvals process.
The primary sources of transportation noise are road traffic on Willow Road and Dawson Road.
Relevant road traffic data was obtained from City of Guelph personnel. The data was used to predict
future traffic sound levels at the façades of the proposed buildings and in the outdoor amenity area.
The predicted sound levels were compared to the guidelines of the Ministry of the Environment,
Conservation and Parks (MECP) and the City.
The results of this study indicate that with suitable noise control measures integrated into the design
of the buildings, it is feasible to achieve the indoor MECP guideline sound levels from road traffic
sources. The recommended noise control measures include appropriate wall and window glazing
assemblies, and an alternative means of ventilation to open windows. Warning clauses will need to
be included in the property, tenancy and purchase and sale and/or rental agreements to warn
occupants of potentially audible transportation noise levels and of the nearby commercial uses.
An analysis was also conducted to determine the potential impact of noise from rooftop units on the
adjacent commercial building located at the west side of the site on the proposed residential units in
addition to the potential impact of mechanical equipment associated with the proposed buildings on
existing residential apartment units. Detailed information regarding the type or model of the
proposed mechanical equipment was not known at the time of the study, but reasonable estimates of
the sizes and tonnages have been used based on experience with similar projects. Manufacturer’s
sound power data was used to estimate sound levels associated with the proposed building on
existing dwelling units. Specifications and sound data for the existing rooftop units of the existing
commercial building were provided by the developer and used to estimate the impact of sound levels
associated with the existing building on proposed residences.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 2 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
The results indicate that the sound emissions from the rooftop equipment associated with the existing
commercial building on the proposed residential buildings, as well as the sound emissions
mechanical equipment associated with the proposed buildings on existing residential receptors in the
area will be within MECP sound level criteria without additional mitigation. Physical mitigation
measures are not required for mechanical equipment associated with the existing and proposed
buildings.
2 Site Description and Sources of Sound
Figure 1 shows a key plan which identifies the location of the proposed residential development at
the northwest corner of Dawson Road and Willow Road, specifically at 47 – 75 Willow Road in the
City of Guelph, Ontario. The site plan dated October 2, 2019 is included as Figure 2. The proposed
development will consist of two 6-storey mixed-use/residential buildings. The proposed buildings
will have commercial uses on the ground floor and one level of underground parking.
A site visit was conducted by HGC Engineering personnel in September 2019 to make observations
of the acoustic environment and to identify the significant noise sources in the vicinity. During the
site visit, it was noted that the primary sources of sound impacting the site are vehicular traffic on
Willow Road and Dawson Road. Highway 6 is located approximately 900 m away from the closest
proposed building façade and therefore has not been included in the analysis.
There are existing residential uses in the surrounding area. The site is currently occupied by a large
commercial building. With the exception of the western portion of the existing building, the
remaining structure will be demolished to make way for the proposed development. There is
mechanical equipment on the roof of the existing commercial building and these have been included
in the noise assessment. The area of the site is classified as a Class 1 area since the background
sound level is dominated by the activities of people and road traffic.
2.1 Road Traffic Noise Criteria
Guidelines for acceptable levels of road traffic noise impacting residential developments are given in
the MECP publication NPC-300 “Environment Noise Guideline Stationary and Transportation
sources – Approval and Planning”, release date October 21, 2013, and are listed in Table I below.
The City of Guelph Noise Control Guidelines version 1.0 effective January 1, 2019 were also used in
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 3 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
conjunction with NPC-300. The values in Table I are energy equivalent (average) sound levels [LEQ]
in units of A-weighted decibels [dBA].
Table I: Road Noise Criteria (dBA)
Daytime LEQ(16 hour)
Road Nighttime LEQ(8 hour)
Road
Outdoor Living Areas 55 dBA -- Inside Living/Dining Rooms 45 dBA 40 dBA
Inside Bedrooms 45 dBA 40 dBA
Daytime refers to the period between 07:00 and 23:00, while nighttime refers to the period between
23:00 and 07:00. The term "Outdoor Living Area" (OLA) is a noise sensitive space intended for the
quiet enjoyment of the outdoor environment and is readily accessible from the building. OLA’s
include backyard and side yard areas of single family, semi-detached and townhouse dwellings,
gardens, terraces and patios, balconies and elevated terraces (e.g. Rooftops) that are not enclosed
with a minimum depth of 4 meters and common outdoor areas associated with high-rise and other
multi-unit buildings and passive recreational areas such as parks if identified by the City. Front yards
areas are not OLA’s.
The target sound level in an OLA is 55 dBA. The guidelines in the MECP publication allow the
sound level in an Outdoor Living Area to be exceeded by up to 5 dBA, without mitigation, if
warning clauses are placed in the purchase and rental agreements to the property. Where OLA sound
levels exceed 60 dBA, physical mitigation is required to reduce the OLA sound level to 55 dBA.
Where mitigation is not technically, economically and administratively feasible, an excess above the
limit of 55 dBA is acceptable with the use of a noise warning clause with some justification.
A central air conditioning system as an alternative means of ventilation to open windows is required
for dwellings where nighttime sound levels outside bedroom or living/dining room windows exceed
60 dBA or daytime sound levels outside bedroom or living/dining room windows exceed 65 dBA.
Forced-air ventilation with ducts sized to accommodate the future installation of air conditioning is
required when nighttime sound levels at bedroom or living/dining room windows are in the range of
51 to 60 dBA or when daytime sound levels at bedroom or living/dining room windows are in the
range of 56 to 65 dBA.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 4 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
Building components such as walls, windows and doors must be designed to achieve indoor sound
level criteria when the plane of window nighttime sound level is greater than 60 dBA or the daytime
sound level is greater than 65 dBA due to road traffic noise.
Warning clauses are required to notify future residents of possible sound level excesses when
nighttime sound levels exceed 50 dBA at the plane of the bedroom window and/or daytime sound
levels exceed 55 dBA in the outdoor living area and at the plane of the bedroom or living/dining
room window due to road traffic.
3 Traffic Noise Predictions
3.1 Road Traffic Data
Road traffic data for Willow Road and Dawson Road was obtained from the City of Guelph in the
form of turning movement counts from 2013 and is provided in Appendix A. The data was projected
to the year 2030 using a conservative estimate of 2.5% growth per year. A commercial vehicle
percentage of 1.2% medium trucks and 0.8% heavy trucks was applied for Willow Road. A
commercial vehicle percentage of 1.2% medium trucks and 0.8% heavy trucks was applied for
Dawson Road.
A posted speed limit of 50 km/h and a day-night split of 90%/10% was used for all roadways, as per
ORNAMENT (Ontario Road Noise Analysis Method for Environment and Transportation), a
document describing modelling procedures for the prediction of road traffic noise prepared by the
MECP, for municipal roadways. Table II below indicates the road traffic data used in the analysis.
Road traffic information is included in Appendix A.
Table II: Projected Road Traffic Data (2030)
Road Name Cars Medium Trucks
Heavy Trucks
Total
Willow Road Daytime 13 483 167 250 13 900 Nighttime 1 498 19 28 1 544 Total 14 981 185 278 15 444
Dawson Road Daytime 9 777 121 181 10 079 Nighttime 1 086 13 20 1 120 Total 10 863 134 202 11 199
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 5 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
3.2 Road Traffic Noise Predictions
To assess the levels of road traffic noise which will impact the site in the future, predictions were
made using STAMSON version 5.04, a computer algorithm developed by the MECP. Sample
STAMSON output is included in Appendix B.
The predictions were performed at the top storey of the proposed buildings during daytime and
nighttime hours to investigate ventilation requirements and in the outdoor amenity area to determine
acoustic barrier requirements. The upper storeys typically represent a worst case location in terms of
traffic noise as they are potentially exposed to more of the roadway being less shielded by adjacent
structures and there is no surplus attenuation due to ground effects. The distance setbacks of the
proposed buildings from the roads indicated on the site plan and aerial photos were used in the
analysis. Reflective ground has been applied in the STAMSON calculations for A to I. The results
of these predictions are summarized in Table III. The acoustic requirements may be subject to
modifications if the site plan is changed significantly.
Table III: Daytime and Nighttime Future Road Traffic Sound Levels, [dBA]
Prediction Location
Building Location Daytime at
Façade LEQ-16 hr
Nighttime at Façade LEQ-8 hr
A
1
South Façade 66 59 B East Façade 66 59 C North Façade 60 54 D West Façade 62 55 E
2
South Façade 62 59 F East Façade 64 57 G North Façade 60 54 H West Façade 55 <50 I -- Common Amenity Area 58 --
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 6 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
4 Recommendations
The predictions indicate that road traffic sound levels will exceed MECP limits at both proposed
buildings in the development. Recommendations are provided in the following sections.
4.1 Outdoor Living Areas
The predicted daytime sound level in the common amenity area located at the northwest corner of the
subject site (Prediction Location [I]) will be 58 dBA, 3 dBA in excess of the MECP’s limit. The 3
dBA sound level excess is within the discretionary range acceptable to the MECP and the City with
the use of a noise warning clause. Physical mitigation would typically not be required.
The residential units may have balconies less than 4 m in depth. These balconies are not considered
as outdoor living areas under MECP guidelines, and therefore are exempt from traffic noise
assessment.
4.2 Indoor Living Areas and Ventilation Requirements
Central Air Conditioning
The predicted sound levels at some of the façades of Building 1 with exposure to Dawson Road and
Willow Road will be greater than 60 dBA during the nighttime and 65 dBA during the daytime. To
address these excesses, the MECP guidelines recommend that the proposed buildings be equipped
with central air conditioning systems.
Provision of Central Air Conditioning
The predicted sound levels at some of the façades of Building 2 with exposure to Dawson Road and
Willow Road will be between 51 dBA and 60 dBA and/or between 55 dBA and 65 dBA during the
daytime. To address these excesses, the MECP guidelines recommend that the building be equipped
with forced air ventilation systems with ducts sized to accommodate the future installation of air
conditioning by the occupant. The use of central air conditioning will exceed this requirement.
Typical window or through-the-wall air conditioning units are not recommended for any residential
units because of the noise they produce and because the units penetrate through the exterior wall
which degrades the overall noise insulating properties of the envelope. Acceptable air conditioning
systems for individual dwelling units are those that are housed in their own closet with an access
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 7 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
door for maintenance. The location, installation and sound ratings of the outdoor air conditioning
devices should minimize noise impacts and comply with criteria of MECP publication NPC-300, as
applicable.
4.3 Building Façade Constructions
Future traffic sound levels at some of the façades of Building 1 (Prediction Locations [A] and [B])
with exposure to Willow Road will exceed 65 dBA during the daytime due to road traffic. MECP
guidelines recommend that the windows, walls and doors be designed so that the indoor sound levels
comply with MECP noise criteria.
Calculations have been performed to determine the building envelope constructions likely to be
required to maintain indoor sound levels within MECP guidelines. The calculation methods were
developed by the National Research Council (NRC). They are based on the predicted future sound
levels at the building facades and the anticipated area of the facade components (walls, windows and
doors) relative to the floor area of the adjacent room.
The minimum necessary specification for the building envelope is Acoustical Insulation Factor,
AIF-26 for living/dining rooms at the south and east façades of Building 1 (Prediction Locations [A]
and [B]), based on the possibility of sound entering the dwellings through the walls and windows.
Any well sealed thermopane unit have a Sound Transmission Class (STC) rating of 30, that is two 3
mm panes and a 13 mm inter-pane gap will provide sufficient noise insulation as long as the window
to floor area ratio is less than 63% for living/dining rooms. Any building construction meeting the
minimum requirements of the Ontario Building Code (OBC) will provide sufficient acoustical
insulation for the bedrooms.
The remaining façades will have predicted sound levels less than 65 dBA during the nighttime and
less than 60 dBA during daytime. Thus, any exterior wall and double glazed window construction
meeting the minimum requirements of the OBC will provide adequate sound insulation.
Further Analysis
When detailed floor plans and elevations are available for the proposed building, the glazing
requirements should be verified based on actual window to floor area ratios. If patio doors are to be
used in the dwellings, they must be included in the window area.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 8 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
4.4 Warning Clauses
The MECP guidelines recommend that warning clauses be included in the property and tenancy
agreements and offers of purchase and sale for all units with anticipated road traffic sound levels
excesses. Examples are provided below.
The suggested wording for proposed dwellings with sound level excesses is given below.
Type A: Purchasers/tenants are advised that despite the inclusion of noise control features in the development and within the building units, sound levels due to increasing road traffic may occasionally interfere with some activities of the dwelling occupants as the sound levels exceed the noise criteria of the Municipality and the Ministry of the Environment, Conservation and Parks.
Suitable wording for future dwellings requiring forced air ventilation systems is given below.
Type B: This dwelling unit has been fitted with a forced air heating system and the ducting etc., was sized to accommodate central air conditioning. Installation of central air conditioning will allow windows and exterior doors to remain closed, thereby ensuring that the indoor sound levels are within the criteria of the Municipality and the Ministry of the Environment, Conservation and Parks. (Note: The location and installation of the outdoor air conditioning device should be done so as to minimize the noise impacts and comply with criteria of MECP publication NPC-300 as applicable.)
The suggested wording for proposed dwellings requiring central air conditioning systems is given
below.
Type C: This dwelling unit has been supplied with a central air conditioning system which will allow windows and exterior doors to remain closed, thereby ensuring that the indoor sound levels are within the Municipality’s and the Ministry of the Environment, Conservation and Parks’ noise criteria.
The suggested wording for proposed dwellings in close proximity to existing commercial facilities is
given below.
Type D: Purchasers are advised that due to the proximity of an existing commercial facility, sound levels from the facilities may be at times be audible.
These sample clauses are provided by the MECP as examples and can be modified by the
Municipality as required.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 9 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
5 Stationary Noise Assessment
5.1 Criteria Governing Stationary (Industrial) Noise Sources
An industrial or commercial facility is classified in MECP guidelines as a stationary source of sound
(as compared to sources such as traffic or construction, for example) for noise assessment purposes.
The existing rooftop mechanical equipment on the roof of the commercial building located to the
west of the site can be classified as stationary sources of sound. Also, the proposed building may be
serviced by roof mounted make up air units which are also classified as stationary sources of sound.
The stationary noise source locations and receptor locations (R1 to R7) are shown in Figure 3.
The Ministry of the Environment, Conservation and Parks (MECP) provides guidelines for the
assessment of stationary noise sources. NPC-300 “Environment Noise Guideline Stationary and
Transportation sources – Approval and Planning” referenced with regard to traffic noise is also
intended for use in the planning of noise sensitive land uses adjacent to residential buildings.
The criteria is based on the background sound level at sensitive points of reception (which are
typically residences) in the quietest hour that the source can be in operation. Background sound
includes sound from road traffic and natural sounds, but excludes the sources under assessment. For
relatively quiet areas where background sound may fall to low levels during some hours, NPC-300
stipulates various minimum limits. As per NPC-300, this area is considered a Class 1 area since the
background sound level is dominated by the activities of people and road traffic. In class 1 areas,
these limits are 50 dBA for daytime periods (07:00 to 23:00) and 45 dBA at night (23:00 to 07:00).
Sources sound levels for typical rooftop mechanical units and assumed operational information
(outlined below) were used as input to a predictive computer model (Cadna-A version 2019 MR2 (32
bit) : build 173.4905), in order to estimate the sound levels from the existing commercial building at
the proposed development and the sound levels from the proposed building on existing sensitive
receptors. The computer model is based on the methods from ISO Standard 9613-2.2, “Acoustic –
Attenuation of Sound During Propagation Outdoors”, which accounts for reduction in sound level
with distance due to geometrical spreading, air absorption, ground attenuation and acoustical
shielding by intervening structures. Worst case assumptions regarding the operating duty cycles of
the equipment (100% during the daytime, and 50% during the night-time) were included based on
our experience with other projects.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 10 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
5.2 Sound Level Criteria at the Residential Receptors
Typical ambient sound levels can be determined through prediction of road traffic volumes in areas
where traffic sound is dominant. Where it can be demonstrated that the hourly ambient sound levels
are greater than the exclusionary minimum limits listed above, the criterion becomes the lowest
predicted one-hour LEQ sound level during each respective period.
Using the existing traffic volumes from 2013 provided by the City, the traffic data was applied to a
generic 24 hour traffic pattern developed by the US Department of Transportation, Federal Highways
Administration contained in the report titled “Summary of National and Regional Travel Trends
1970 – 1995” dated May 1996. The traffic volumes were then used to predict sound levels at the
building facades during the day/nighttime hours to determine the minimum hourly background sound
levels at those locations due to the traffic on the public roadways.
The sound level predictions and the recommended criteria during the daytime and nighttime at the
existing and proposed receptors are shown in Tables IV and V. To assess the levels of background
road traffic noise, noise predictions were made using a numerical computer modelling package
(Cadna/A version 2019 MR2 (32 bit) build: 173.4905). The model is based on the methods from ISO
Standard 9613-2.2, “Acoustics – Attenuation of Sound During Propagation Outdoors”, which
account for reduction in sound level with distance due to geometrical spreading, air absorption
attenuation and acoustical shielding by intervening structures.
Table IV: Predicted Minimum Hourly Sound Levels and Noise Level Criteria at Existing Sensitive Receptors [dBA]
Receptor Daytime
(07:00-23:00) Nighttime
(23:00-07:00)
R1 (existing 2.5-storey residence) 60 54
R2 (existing 2.5-storey residence) 60 54
R3 (existing 2.5-storey residence) 61 54
R4 (existing 2.5-storey residence) 61 55
R5 (existing apartment building) 58 51
R6 (existing apartment building) 61 55 R7 (existing apartment building) 61 54 R8 (existing apartment building) 58 52
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 11 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
Table V: Predicted Minimum Hourly Sound Levels and Noise Level Criteria at Proposed Sensitive Receptors [dBA]
Building Façade Daytime
(07:00-23:00) Nighttime
(23:00-07:00)
1
South Façade 61 56
East Façade 63 56
North Façade 59 52
West Façade 57 51
2
South Façade 59 52
East Façade 63 57
North Façade 59 52
West Façade 50 45
Compliance with MECP criteria generally results in acceptable levels of sound at sensitive receptors
although there may be residual audibility during periods of low background sound.
5.3 Assessment of Noise Emissions from Existing Rooftop
Mechanical Equipment at Adjacent Sensitive Receptors
Information regarding the specifications and sound power levels of the existing rooftop mechanical
equipment at the commercial building located at the west of the subject site were provided and
included in Appendix C. The sound levels due to the existing rooftop mechanical equipment at the
existing commercial building are summarized in the following table and shown graphically in
Figures 4 and 5.
Table VI: Predicted Sound Levels from the Existing Noise Sources at the Proposed Residences [dBA]
Building Façade Criteria
(Day/Night) Day Night
1
South Façade 61/56 <35 <30 East Façade 63/56 <35 <30 North Façade 59/52 38 35 West Façade 57/51 38 35
2
South Façade 59/52 37 34 East Façade 63/58 <35 <30 North Façade 59/52 <35 <30 West Façade 50/45 39 36
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 12 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
It is concluded that sounds from the existing rooftop mechanical equipment associated with the
adjacent commercial building are anticipated to be below background sound levels at the proposed
buildings and physical mitigation is not required.
5.4 Assessment of Stationary Noise Sources Associated with the
Proposed Development at Existing Sensitive Receptors
Sound power levels for rooftop makeup air units and the air conditioning systems for individual
dwelling units were estimated based upon manufacturer’s data for similar mechanical equipment
used in similar past projects, since the details of the equipment were not known at the time of this
report. Two make-up air units on the rooftop of the building with sound power ratings of 90 dBA
were assumed in the analysis. The individual unit air conditioning systems were assumed to have a
sound power level of 66 dBA. Proposed noise source locations are shown in Figure 3. The sound
levels created by this equipment at the closest neighbouring residences are summarized in the
following table and shown graphically in Figures 6 and 7.
Table VII: Predicted Sound Levels from the Proposed Building at the Existing Residences [dBA]
Receptor Criteria
(Day/Night) Day Night
R1 (existing 2.5-storey residence) 60/54 43 39 R2 (existing 2.5-storey residence) 60/54 42 38 R3 (existing 2.5-storey residence) 61/54 43 39 R4 (existing 2.5-storey residence) 61/55 42 39 R5 (existing apartment building) 58/51 45 41 R6 (existing apartment building) 61/55 48 43 R7 (existing apartment building) 61/55 50 46 R8 (existing apartment building) 58/52 50 45
These predicted sound levels at the existing residences are less than background sound levels, based
on this typical worst-case operating scenario. Noise mitigation measures are not required.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 13 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
6 Impact of the Development on Itself
Section 5.9.1 of the Ontario Building Code (OBC) specifies the minimum required sound insulation
characteristics for demising partitions, in terms of Sound Transmission Class (STC) values. In order
to maintain adequate acoustical privacy between separate suites in a multi-tenant building, inter-suite
walls must meet or exceed STC-50. Walls separating a suite from a noisy space such as a refuse
chute, or elevator shaft, must meet or exceed STC-55. In addition, it is recommended that the
floor/ceiling constructions separating suites from any amenity or commercial spaces also meet or
exceed STC-55. Tables 1 and 2 in Section SB-3 of the Supplementary Guideline to the OBC provide
a comprehensive list of constructions that will meet the above requirements.
Information for Builder/Developer:
Tarion’s Builder Bulletin B19R requires the internal design of condominium projects to integrate
suitable acoustic features to insulate the suites from noise from each other and amenities in
accordance with the OBC, and limit the potential intrusions of mechanical and electrical services of
the building on its residents. It is expected that if Building 19 Certification is needed, an acoustical
consultant will review in greater detail the mechanical and electrical drawings and details of
demising constructions and mechanical/electrical equipment, during design development, to help
ensure that the noise impact of the development on itself is maintained within acceptable levels.
7 Summary and Recommendations
The following list and Table VIII summarize the recommendations made in this report. The reader is
referred to the previous sections of the report where these recommendations are discussed in more
detail.
For transportation noise sources
1. Building 1 should be equipped with central air conditioning systems that will allow the windows
to remain closed. Building 2 should be equipped with forced air ventilation systems with ducts
sized to accommodate the future installation of air conditioning by the occupant. The use of
central air conditioning will exceed this requirement. The location, installation and sound ratings
of the air conditioning devices should comply with NPC-300, as applicable.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 14 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
2. Upgraded glazing constructions are required for some of the façades of the proposed building, as
indicated in Section 4.3.
3. Warning clauses should be included in the property and tenancy agreements and offers of
purchase or sale to inform future owners/occupants of the noise issues and the presence of the
roadways, as indicated in Section 4.4.
Table VIII: Summary of Noise Control Requirements and Noise Warning Clauses
Prediction Location
Building Location Acoustic Barrier
Ventilation Requirements*
Warning Clause
Upgraded Building
Constructions +
A
1
South Façade
-- Central A/C A, C, D
BR: OBC LR/DR: AIF-26+
B East Façade BR: OBC
LR/DR: AIF-26+
C North Façade OBC
D West Façade OBC
E
2
South Façade
-- Forced Air A, B, D
OBC
F East Façade OBC
G North Façade OBC
H West Façade OBC
I -- Common
Amenity Area -- -- -- --
Notes: -- no specific requirement * The location, installation and sound rating of the air conditioning condensers must be compliant with MECP Guideline NPC-300, as applicable. +When floor plans and building elevations are available, an acoustical consultant should refine glazing constructions based on actual window to floor area ratios. LR/DR – Living Room/Dining Room BR – Bedroom OBC – Ontario Building Code
For stationary noise sources
1. Two make-up air units were assumed for each proposed mixed-use building. This rooftop
equipment should be selected to have a sound power level rating of 90 dBA or less.
Noise Feasibility Study, Proposed Mixed-Use/Residential Development Page 15 47 – 75 Willow Road, Guelph, Ontario November 29, 2019
2. If alternate rooftop units are chosen or the location of the mechanical units are modified, an
acoustical engineer should verify that with the selected HVAC equipment and locations
acceptable sound levels will result at all offsite residential receptors.
3. Tarion Builder’s Bulletin B19R requires that the internal design of condominium projects
integrates suitable acoustic features to insulate the suites from noise from each other and
amenities in accordance with the OBC, and limit the potential intrusions of mechanical and
electrical services of the buildings on its residents. If B19R certification is needed, an acoustical
consultant is required to review the mechanical and electrical drawings and details of demising
constructions and mechanical/electrical equipment, when available, to help ensure that the noise
impact of the development on itself are maintained within acceptable levels.
7.1 Implementation
To ensure that the sound control recommendations outlined above are properly implemented in the
site design, it is recommended that:
1) Prior to the issuance of building permits for this development, a Professional Engineer qualified
to perform acoustical engineering services in the Province of Ontario should review the
mechanical drawings and specifications for the mechanical equipment to certify that the MECP
sound levels will be met at all offsite noise sensitive receptors.
2) Prior to the issuance of occupancy permits for this development, the Municipality’s building
inspector or a Professional Engineer qualified to provide acoustical engineering services in the
Province of Ontario to certify that the suggested noise control measures have been properly
installed and constructed.
3) Prior to the issuance of building permits for this development, a Professional Engineer qualified
to perform acoustical engineering services in the Province of Ontario should review the
architectural plans and building elevations to refine glazing requirements based on actual
window to floor areas ratios.
EX
ISTI
NG
CO
NC
RETE
SID
EW
ALK
EX
ISTI
NG
LA
ND
SC
AP
E A
REA
EXISTING CONCRETE SIDEWALK
EXISTING LANDSCAPE AREA
N44°50'50"E 93.982
EXISTING CONCRETE SIDEWALK
EXISTING LANDSCAPE AREA
EX
ISTI
NG
CO
NC
RETE
SID
EW
ALK
EX
ISTI
NG
LA
ND
SC
APE A
REA
N44°50'50"E 80.772
N4
5°1
5'0
0"W
27
.43
2
18.29
N44°50'50"E 13.216
PR
OP
OSED
LA
ND
SCA
PE A
REA
EXISTING LANDSCAPE AREA
EXISTING
COMMERCIAL 509.0 S.M.
(5,479 S.F.)
DA
WSO
N R
OA
D
WILLOW ROAD
6
FIRE ROUTE
BLDG. TO PROPERTY LINE5757
PROPERTY LINE
ENTRANCE
ENTRANCE
EXIT EXIT
RAMP DOWN TO UNDERGROUND
P1 PARKING
PROPOSED CONCRETE SIDEWALK
56000
56000
1
1
PR
OP
OSED
CO
MM
ON
AM
EN
ITY
AR
EA
3
62
.5 S
.M.
(3,9
02
S.F
.)
PROPOSED CONCRETE SIDEWALKPROPOSED CONCRETE SIDEWALK
EXIT EXIT
BLD
G. FR
OM
PR
OP
ER
TY L
INE
220
24
BLD
G. FR
OM
PR
OP
ER
TY L
INE
810
24
190
00
= AREA OF WORK
= EXISTING BUILDING TO REMAIN
= EXISTING BUILDING TO BE REMOVED
EXTENT OF EXISTING BUILDING REMOVAL
BLDG.-1
PROPOSED 6-STOREY
RESIDENTIAL BUILDING
BFA = 1,064.0 sm (11,453 sf)
GFA = 6,384 sm (68,717 sf)
BLDG.-2
PROPOSED 6-STOREY
RESIDENTIAL BUILDING
BFA = 1,064.0 sm (11,453 sf)
GFA = 6,384 sm (68,717 sf)
DRIVEWAY VISIBILITY TRIANGLE 4.0m x 5.0m
DEEP WELL WASTE STORAGE
1 10 1 20
1 20
1 3
7
20
1 17
1
1
1
1 11
11
152000
5500
7000
110
00
7000
5500
2000
9000 2000
BLDG. FROM PROPERTY LINE
32199
FIR
E R
OU
TE
BLDG. TO PROPERTY LINE
34956
± 7
897
5500
± 1
928
± 1530
5500 7000 5500
2000
2000 400
6100
400
7000 16500 3751 15550 7000
BLD
G. TO
BLD
G.
400
00
EXISTING TREE TO BE REMOVED
CORNER LOT SIGHT LINE 9.0m x 9.0m
BLD
G. TO
PR
OP
. L I
NE
3608
BLDG TO PROPERTY LINE3000
PROPOSED CONCRETE SIDEWALK
BLDG. TO PROPERTY LINE
5789
190
00
BLD
G. TO
PR
OP
ER
TY L
INE
626
08
PR
OP
OSED
CO
NC
RETE
SID
EW
ALK
1608
2000
2000
2024
5500
7000
5500
2000
190
00
2123 27500 2000 57365 5000
7500
209
00
5600
9348
211
52
2000
TYPE A
3400 2000
TYP.
2750
5500 T
YP
.
TYPE B
2400 2000
5500 T
YP
.
V V V V V V V V V V V V V
V V V V V V VV V V V V V
ENTRANCE
ENTRANCE
15
.24
N45
°15
'00
"W1
31
.06
4
N4
5°1
5'0
0"W
10
3.6
32
9.0
9.0
SCALE: 1 : 700
SITE PLAN
A1.017045 - 47 WILLOW MULTI-RES DEVELOPMENT
2019.10.02
R1
R2
R3
R4
R5
R6
R7
R8
17558650
17558650
17558700
17558700
17558750
17558750
17558800
17558800
4821
450
4821
450
4821
500
4821
500
4821
550
4821
550
4821
600
4821
600
4821
650
4821
650
FRAME COORDINATES ARE UTM IN METRES
Figure 3: Existing and Proposed Noise Source Locations
40
35
30
17558620
17558620
17558640
17558640
17558660
17558660
17558680
17558680
17558700
17558700
17558720
17558720
17558740
17558740
4821
460
4821
460
4821
480
4821
480
4821
500
4821
500
4821
520
4821
520
4821
540
4821
540
4821
560
4821
560
4821
580
4821
580
4821
600
4821
600
4821
620
4821
620
FRAME COORDINATES ARE UTM IN METRES
Figure 4: Predicted Daytime Sound Level Contours at Proposed Sensitive Receptors from Existing Stationary Noise Sources, dBA
40
35
30
17558620
17558620
17558640
17558640
17558660
17558660
17558680
17558680
17558700
17558700
17558720
17558720
17558740
17558740
4821
460
4821
460
4821
480
4821
480
4821
500
4821
500
4821
520
4821
520
4821
540
4821
540
4821
560
4821
560
4821
580
4821
580
4821
600
4821
600
4821
620
4821
620
FRAME COORDINATES ARE UTM IN METRES
Figure 5: Predicted Nighttime Sound Level Contours at Proposed Sensitive Receptors from Existing Stationary Noise Sources, dBA
50
55
50
44
50
45
55
45
45
40
R1
R2
R3
R4
R5
R6
R7
R8
17558650
17558650
17558700
17558700
17558750
17558750
17558800
17558800
4821
450
4821
450
4821
500
4821
500
4821
550
4821
550
4821
600
4821
600
4821
650
4821
650
FRAME COORDINATES ARE UTM IN METRES
Figure 6: Predicted Daytime Sound Level Contours at Existing Sensitive Receptors from Stationary Noise Sources, dBA
45
50 50
40
50
50
45
40
35
45
45
40
35
30
R1
R2
R3
R4
R5
R6
R7
R8
17558650
17558650
17558700
17558700
17558750
17558750
17558800
17558800
4821
450
4821
450
4821
500
4821
500
4821
550
4821
550
4821
600
4821
600
4821
650
4821
650
FRAME COORDINATES ARE UTM IN METRES
Figure 7: Predicted Nighttime Sound Level Contours at Existing Sensitive Receptors from Stationary Noise Sources, dBA
Dawson Road & Willow Road
Morning Peak Diagram Specified PeriodFrom:To:
7:00:00
9:00:00
One Hour PeakFrom:To:
8:00:00
9:00:00
Municipality:Site #:Intersection:TFR File #:Count date:
Guelph
0000001316
Willow Road & Dawson Road
2
17-Apr-2013
Weather conditions:Clear
Person(s) who counted:
** Signalized Intersection ** Major Road: Willow Road runs W/E
North Leg Total:
North Entering:
North Peds:
Peds Cross:
413
181
0
Cyclists
Trucks
Cars
Totals
0
5
73
78
1
3
99
103
1
8
172
Cyclists
Trucks
Cars
Totals
0
4
228
232
Cyclists Trucks Cars Totals
2 15 355 372
Cyclists Trucks Cars Totals
0 1 125 126
1 9 341 351
1 10 466
Peds Cross:
West Peds:
West Entering:
West Leg Total:
56
477
849
Dawson Road
Willow RoadW
N
E
S
Willow Road
East Leg Total:
East Entering:
East Peds:
Peds Cross:
854
400
10
Cars Trucks Cyclists Totals
103 3 0 106
282 10 2 294
385 13 2
Cars Trucks Cyclists Totals
440 12 2 454
Comments
Dawson Road & Willow Road
Mid-day Peak Diagram Specified PeriodFrom:To:
11:00:00
14:00:00
One Hour PeakFrom:To:
12:00:00
13:00:00
Municipality:Site #:Intersection:TFR File #:Count date:
Guelph
0000001316
Willow Road & Dawson Road
2
17-Apr-2013
Weather conditions:Clear
Person(s) who counted:
** Signalized Intersection ** Major Road: Willow Road runs W/E
North Leg Total:
North Entering:
North Peds:
Peds Cross:
465
249
7
Cyclists
Trucks
Cars
Totals
0
1
140
141
0
0
108
108
0
1
248
Cyclists
Trucks
Cars
Totals
2
8
206
216
Cyclists Trucks Cars Totals
1 6 433 440
Cyclists Trucks Cars Totals
1 3 131 135
0 9 288 297
1 12 419
Peds Cross:
West Peds:
West Entering:
West Leg Total:
10
432
872
Dawson Road
Willow RoadW
N
E
S
Willow Road
East Leg Total:
East Entering:
East Peds:
Peds Cross:
785
380
7
Cars Trucks Cyclists Totals
75 5 1 81
293 5 1 299
368 10 2
Cars Trucks Cyclists Totals
396 9 0 405
Comments
Dawson Road & Willow Road
Afternoon Peak Diagram Specified PeriodFrom:To:
15:00:00
18:00:00
One Hour PeakFrom:To:
16:15:00
17:15:00
Municipality:Site #:Intersection:TFR File #:Count date:
Guelph
0000001316
Willow Road & Dawson Road
2
17-Apr-2013
Weather conditions:Clear
Person(s) who counted:
** Signalized Intersection ** Major Road: Willow Road runs W/E
North Leg Total:
North Entering:
North Peds:
Peds Cross:
736
547
8
Cyclists
Trucks
Cars
Totals
0
0
207
207
1
4
335
340
1
4
542
Cyclists
Trucks
Cars
Totals
0
4
185
189
Cyclists Trucks Cars Totals
0 3 603 606
Cyclists Trucks Cars Totals
0 1 99 100
0 8 301 309
0 9 400
Peds Cross:
West Peds:
West Entering:
West Leg Total:
32
409
1015
Dawson Road
Willow RoadW
N
E
S
Willow Road
East Leg Total:
East Entering:
East Peds:
Peds Cross:
1137
488
7
Cars Trucks Cyclists Totals
86 3 0 89
396 3 0 399
482 6 0
Cars Trucks Cyclists Totals
636 12 1 649
Comments
Dawson Road & Willow Road
Total Count Diagram
Municipality:Site #:Intersection:TFR File #:Count date:
Guelph
0000001316
Willow Road & Dawson Road
2
17-Apr-2013
Weather conditions:Clear
Person(s) who counted:
** Signalized Intersection ** Major Road: Willow Road runs W/E
North Leg Total:
North Entering:
North Peds:
Peds Cross:
3881
2225
132
Cyclists
Trucks
Cars
Totals
0
22
1053
1075
3
12
1135
1150
3
34
2188
Cyclists
Trucks
Cars
Totals
8
50
1598
1656
Cyclists Trucks Cars Totals
5 73 3448 3526
Cyclists Trucks Cars Totals
1 22 909 932
7 65 2223 2295
8 87 3132
Peds Cross:
West Peds:
West Entering:
West Leg Total:
253
3227
6753
Dawson Road
Willow RoadW
N
E
S
Willow Road
East Leg Total:
East Entering:
East Peds:
Peds Cross:
6620
3175
131
Cars Trucks Cyclists Totals
689 28 7 724
2395 51 5 2451
3084 79 12
Cars Trucks Cyclists Totals
3358 77 10 3445
Comments
Dawson Road & Willow RoadTraffic Count Summary
Intersection: Willow Road & Dawson Road Count Date: 17-Apr-2013 Municipality: Guelph
North Approach Totals South Approach Totals
East Approach Totals West Approach Totals
Includes Cars, Trucks, & Cyclists Includes Cars, Trucks, & Cyclists
Includes Cars, Trucks, & Cyclists Includes Cars, Trucks, & Cyclists
Hour Hour
Hour Hour
Ending Ending
Ending Ending
Left Left
Left Left
Thru Thru
Thru Thru
Right Right
Right Right
Grand Grand
Grand Grand
Total Total
Total Total
Total Total
Total Total
Peds Peds
Peds Peds
North/South
East/West
Total
Total
Approaches
Approaches
Calculated Values for Traffic Crossing Major StreetHours Ending:Crossing Values:
Totals:
Totals:
7:00:00 0 0 0 0 0 0 7:00:00 0 0 0 0 08:00:00 45 0 66 111 0 111 8:00:00 0 0 0 0 09:00:00 103 0 78 181 0 181 9:00:00 0 0 0 0 0
11:00:00 0 0 0 0 0 0 11:00:00 0 0 0 0 012:00:00 111 0 129 240 10 240 12:00:00 0 0 0 0 013:00:00 108 0 141 249 7 249 13:00:00 0 0 0 0 014:00:00 122 0 117 239 17 239 14:00:00 0 0 0 0 015:00:00 0 0 0 0 0 0 15:00:00 0 0 0 0 016:00:00 192 0 192 384 65 384 16:00:00 0 0 0 0 017:00:00 315 0 201 516 21 516 17:00:00 0 0 0 0 018:00:00 154 0 151 305 12 305 18:00:00 0 0 0 0 0
7:00:00 0 0 0 0 0 0 7:00:00 0 0 0 0 08:00:00 0 149 87 236 19 517 8:00:00 135 146 0 281 179:00:00 0 294 106 400 10 877 9:00:00 126 351 0 477 56
11:00:00 0 2 0 2 0 3 11:00:00 0 1 0 1 012:00:00 0 269 114 383 10 726 12:00:00 126 217 0 343 4313:00:00 0 299 81 380 7 812 13:00:00 135 297 0 432 1014:00:00 0 276 103 379 16 781 14:00:00 135 267 0 402 1515:00:00 0 0 0 0 0 0 15:00:00 0 0 0 0 016:00:00 0 411 82 493 38 971 16:00:00 99 379 0 478 6017:00:00 0 376 98 474 14 881 17:00:00 115 292 0 407 2918:00:00 0 375 53 428 17 834 18:00:00 61 345 0 406 23
8:00 9:00 12:00 13:00 14:00 16:00 17:00 18:0081 169 164 125 153 290 358 194
1150 0 1075 2225 132 2225 0 0 0 0 0
0 2451 724 3175 131 6402 932 2295 0 3227 253
Dawson Road & Willow RoadCount Date: 17-Apr-2013
Intersection: Willow Road & Dawson Road
Major Road: Willow Road
Operating Speed of Major Road: 50 km/hr
Municipality: Guelph
Major Road Runs: E/W two lanes each way
Operating under restricted flow conditions
Warrant #1: Minimum Vehicular Volumes.
A. All Approaches.
B. Minor Street Both Approaches.
Minimum RequirementsNo. ofLanes 1 Lane Each Way 2 Lanes Each Way 3 Lanes Hours Ending
FlowCondition
1 Lane 1 Lane 2 Lane 2 Lane or MoreF. Flow F. FlowR. Flow R. Flow R. Flow
(Code 1) (Code 2) (Code 3) (Code 4) (Code 5)
100%
100%
80%
80%
AllApproa-
ches
100% Fulfilled
100% Fulfilled
80% Fulfilled
80% Fulfilled
Actual % if Below 80%
Actual % if Below 80%
MinorStreetBoth
Approa-ches
Total:
Total:
Actual Average (Total/8):
Actual Average (Total/8):
PercentageWarrant
100%
100%
Yes:
Yes:
No:
No:
480 720 600 900 1125
385 575 480 720 900
120 170 120 255 170
95 135 95 203 135
8:00 9:00 12:00 13:00 14:00 16:00 17:00 18:00
628 1058 966 1061 1020 1355 1397 1139
100 100 100 100 100 100 100
70
111 181 240 249 239 384 516 305
100 100 100
80 80 80
44 71
X
700
0
70
770
96%
X
300
240
115
655
82%
80% Satisfied
Dawson Road & Willow RoadCount Date: 17-Apr-2013
Intersection: Willow Road & Dawson Road
Major Road: Willow Road
Operating Speed of Major Road: 50 km/hr
Municipality: Guelph
Major Road Runs: E/W two lanes each way
Operating under restricted flow conditions
Warrant #2: Delay to Cross Traffic.
A. Major Street Both Approaches.
B. Traffic Crossing Major Street.
Minimum RequirementsNo. ofLanes 1 Lane Each Way 2 Lanes Each Way 3 Lanes Hours Ending
FlowCondition
1 Lane 1 Lane 2 Lane 2 Lane or MoreF. Flow F. FlowR. Flow R. Flow R. Flow
(Code 1) (Code 2) (Code 3) (Code 4) (Code 5)
100%
100%
80%
80%
AllApproa-
ches
100% Fulfilled
100% Fulfilled
80% Fulfilled
80% Fulfilled
Actual % if Below 80%
Actual % if Below 80%
AllApproa-
ches
Total:
Total:
Actual Average (Total/8):
Actual Average (Total/8):
PercentageWarrant
100%
100%
Yes:
Yes:
No:
No:
480 720 600 900 1125
385 575 480 720 900
50 75 50 113 75
40 60 40 90 60
8:00 9:00 12:00 13:00 14:00 16:00 17:00 18:00
517 877 726 812 781 971 881 834
100
80 80 80 80 80 80
57
81 169 164 125 153 290 358 194
100 100 100 100 100 100 100
72
X
100
480
57
637
80%
X
700
0
72
772
96%
Not Satisfied
Dawson Road & Willow RoadCount Date: 17-Apr-2013
Intersection: Willow Road & Dawson Road
Major Road: Willow Road
Operating Speed of Major Road: 50 km/hr
Municipality: Guelph
Major Road Runs: E/W two lanes each way
Operating under restricted flow conditions
Warrant #3: Accident Experience.
Not Satisfied
A. Reportable accidents within a twelve month period averaged over 36 consequtive months susceptible to correctionby a traffic signal.
Minimum Requirements Actual Number of Accidents Average Number of Accidents Fulfilled
5 0 in 0 years Invalid 0%
B. Adequate trial of less restrictive remedies has failed to reduce accident frequency. No
C. Either Warrant 1 (Minimum Vehicular Volume) or Warrant 2 (Delay to Cross Traffic) satisfied 80% or more. Yes
Warrant #4: Combination Warrant.(Used if no warrant satisfied 100%)
Not Satisfied
Minimum Requirements Warrant Satisfied 80% or More Fulfilled
Two WarrantsSatisfied 80%
Warrant 1 (Minimum Vehicular Volume) YesWarrant 2 (Delay to Cross Traffic) NoWarrant 3 (Accident Experience) No
Conclusion: Traffic signal not warranted.
Page 1 of 3 Appendix B: Prediction Location [A] STAMSON 5.0 NORMAL REPORT Date: 28-11-2019 14:48:29 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: a.te Time Period: Day/Night 16/8 hours Description: Predicted daytime and nighttime sound levels at the south façade of Building 1, Prediction Location [A]. Road data, segment # 1: Willow (day/night) ------------------------------------------ Car traffic volume : 13483/1498 veh/TimePeriod * Medium truck volume : 167/19 veh/TimePeriod * Heavy truck volume : 250/28 veh/TimePeriod * Posted speed limit : 50 km/h Road gradient : 0 % Road pavement : 1 (Typical asphalt or concrete) * Refers to calculated road volumes based on the following input: 24 hr Traffic Volume (AADT or SADT): 10150 Percentage of Annual Growth : 2.50 Number of Years of Growth : 17.00 Medium Truck % of Total Volume : 1.20 Heavy Truck % of Total Volume : 1.80 Day (16 hrs) % of Total Volume : 90.00 Data for Segment # 1: Willow (day/night) ---------------------------------------- Angle1 Angle2 : -90.00 deg 90.00 deg Wood depth : 0 (No woods.) No of house rows : 0 / 0 Surface : 2 (Reflective ground surface) Receiver source distance : 16.00 / 17.00 m Receiver height : 1.50 / 1.50 m Topography : 3 (Elevated; no barrier) Elevation : 15.00 m Reference angle : 0.00 Road data, segment # 2: Dawson (day/night) ------------------------------------------ Car traffic volume : 9777/1086 veh/TimePeriod * Medium truck volume : 121/13 veh/TimePeriod * Heavy truck volume : 181/20 veh/TimePeriod * Posted speed limit : 50 km/h Road gradient : 0 % Road pavement : 1 (Typical asphalt or concrete) * Refers to calculated road volumes based on the following input: 24 hr Traffic Volume (AADT or SADT): 7360 Percentage of Annual Growth : 2.50 Number of Years of Growth : 17.00 Medium Truck % of Total Volume : 1.20 Heavy Truck % of Total Volume : 1.80
Page 2 of 3 Appendix B: Prediction Location [A] Day (16 hrs) % of Total Volume : 90.00 Data for Segment # 2: Dawson (day/night) ---------------------------------------- Angle1 Angle2 : -90.00 deg 0.00 deg Wood depth : 0 (No woods.) No of house rows : 0 / 0 Surface : 2 (Reflective ground surface) Receiver source distance : 17.00 / 17.00 m Receiver height : 1.50 / 1.50 m Topography : 3 (Elevated; no barrier) Elevation : 15.00 m Reference angle : 0.00 Results segment # 1: Willow (day) --------------------------------- Source height = 1.16 m ROAD (0.00 + 64.77 + 0.00) = 64.77 dBA Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 90 0.00 65.05 0.00 -0.28 0.00 0.00 0.00 0.00 64.77 ---------------------------------------------------------------------------- Segment Leq : 64.77 dBA Results segment # 2: Dawson (day) --------------------------------- Source height = 1.16 m ROAD (0.00 + 60.10 + 0.00) = 60.10 dBA Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 0 0.00 63.65 0.00 -0.54 -3.01 0.00 0.00 0.00 60.10 ---------------------------------------------------------------------------- Segment Leq : 60.10 dBA Total Leq All Segments: 66.04 dBA Results segment # 1: Willow (night) ----------------------------------- Source height = 1.16 m ROAD (0.00 + 58.00 + 0.00) = 58.00 dBA Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 90 0.00 58.55 0.00 -0.54 0.00 0.00 0.00 0.00 58.00 ---------------------------------------------------------------------------- Segment Leq : 58.00 dBA
Page 3 of 3 Appendix B: Prediction Location [A] Results segment # 2: Dawson (night) ----------------------------------- Source height = 1.16 m ROAD (0.00 + 53.55 + 0.00) = 53.55 dBA Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 0 0.00 57.10 0.00 -0.54 -3.01 0.00 0.00 0.00 53.55 ---------------------------------------------------------------------------- Segment Leq : 53.55 dBA Total Leq All Segments: 59.33 dBA TOTAL Leq FROM ALL SOURCES (DAY): 66.04 (NIGHT): 59.33