New Stratford Middle School & New Wilson SchoolOptions for Completing within Funding Available School Board Work SessionOctober 6, 2015
Objectives
• Respond to School Board charge to present options to complete both Stratford and Wilson projects within funding available
• Obtain feedback from the School Board on how to proceed
2
Agenda
3
• Financial Overview• Funding Analysis • Stratford Building Options• Wilson Site Options• Summary of Options• Next Steps
Financial Overview
CIP ‐ 6/2014
5
MAJOR CONSTRUCTIONDescription
PreviousBonds
CapitalReserve FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 Total
Prior CIP
McKinley 12 Room Addition $ 12.6 $ 7.470 $ 20.1
Capacity Projects
New Elementary School $ 2.000 $ 17.500 $ 20.600 $ 10.150 $ 50.3
Abingon Addition/Renovation $ 3.400 $ 19.000 $ 6.350 $ 28.8
Secondary Seats to be determined * $ 5.0 $ 4.000 $ 41.600 $ 57.900 $ 17.500 $ 126.0
Career Center $ 1.000 $ 1.000 $ 9.300 $ 56.100 $ 49.400 $ 36.600 $ 153.4
Washington-Lee $ 3.000 $ 2.000 $ 5.0
Infrastructure Investments
HVAC & Roofing Projects $ 3.350 $ 3.100 $ 4.500 $ 2.600 $ 4.000 $ 4.100 $ 4.200 $ 4.300 $ 4.400 $ 4.500 $ 39.1
Infrastructure Projects ** $ 0.760 $ 3.100 $ 3.200 $ 3.300 $ 3.200 $ 3.300 $ 3.400 $ 3.500 $ 3.600 $ 3.700 $ 31.1
Grand Total Major Construction $ 12.6 $ 5.0 $ 23.980 $ 44.700 $ 77.250 $ 74.950 $ 34.000 $ 63.500 $ 57.000 $ 44.400 $ 8.000 $ 8.200 $ 453.6
2014 Bond 2016 Bond 2018 Bond 2020 Bond 2022 Bond
Referenda Total $ 105.810 $ 132.600 $ 166.000 $ 15.400 $ 16.200 $ 436.0
MINOR CONSTRUCTION/MAJOR MAINTENANCEDescription
PreviousBonds
CapitalReserve FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 Total
Current Revenues
Minor Construction/Major Maintenance $ 6.910 $ 7.240 $ 7.460 $ 7.680 $ 7.910 $ 8.150 $ 8.390 $ 8.650 $ 8.910 $ 9.170 $ 80.470
Grand Total All Projects $ 12.6 $ 5.0 $ 30.890 $ 51.940 $ 84.710 $ 82.630 $ 41.910 $ 71.650 $ 65.390 $ 53.050 $ 16.910 $ 17.370 $ 534.050
* $5 million for planning and design for secondary seats is funded from the Capital Reserve.
** Infrastructure Projects include replacement of lighting, electrical systems, and windows.
CIP ‐ 12/2014
6
Stratford Building– 1,000‐seat middle school – Addition(s) plus renovation– To open September 2019 – $29.2 M funding
Wilson Site– New building for H‐B and Stratford programs– 775 seats total (70 new seats)– To open September 2019– $80.2 M funding
Remaining CIP Secondary Seats– 230 seats at a location TBD– $16.6 M funding
Total CIP funding $126.0 M ($121.0 M bond + $5.0 M reserve)
CIP ‐ 4/2015
7
SPRING 2015 BOND ISSUANCE
$ in millions AS ADOPTED RECOMMENDED
DescriptionCapital
Reserve FY 2015Capital
Reserve FY 2015
Prior CIP
McKinley 12 Room Addition $ 7.5 $ 7.5
Capacity Projects
New Elementary School $ 2.0 $ 1.0
Abingdon Addition/Renovation $ 3.4 $ 3.4
Secondary Seats projects $ 5.0 $ 4.0 $ - $ 9.0
Washington-Lee $ 3.0 $ 5.0
Infrastructure Investments
HVAC & Roofing Projects $ 3.4 $ 3.4
Infrastructure Projects $ 0.8 $ 0.8
Additional Bond Issuance for Future Projects $ 34.3 $ -
Total Spring 2015 Bond Issuance $ 5.0 $ 58.3 $ - $ 30.0
Net Debt Service Savings in FY 2016 $ 1.4
Potential Funding Sources
1. Reserve Fund Balances in Millions – Capital Reserve: $9.9– Future Budget Years: $20.8– Undesignated Reserve: $2.0
2. APS bonding capacity will be reassessed this Spring as part of the FY 2017 CIP process
8
Total Project Cost Estimates Concept Design 8/2015
Stratford MS: –$43.3 ‐ $47.5 M / $14.1 ‐ $18.3 M over
Wilson: –$100.7 M / $20.5 M over
9
• Estimates prepared by professional cost estimators in conjunction with architect/engineering team.
• Further verification and reconciliation will occur with independent estimates prepared by the Construction Managers at Risk.
Reasons for Increased Cost
• Substantial increase in construction costs, also affecting escalation, contingencies and other soft costs
• Custom educational specifications for the Stratford and H–B programs increase Wilson building areas
• Extent of community improvements identified during concept design
• APS Design & Construction staffing costsreassigned from operating to project costs
10
Stratford and Wilson – Summary of Options
11*Other Funding includes Non 20‐year Items (furniture, technology, equipment, etc.) and Community Improvements
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$109.4 $0.0 $109.4 1,070 230 $16.6
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$82.5 to $89.4 $8.3 $90.8 to $97.7 815 to 920 380 to 485 $36.6 to $44.5
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$109.1 to $114.1 $9.9 $119.0 to $124.0 1,050 to 1,070 230 to 250 $11.9 to $16.9
Options without an addition at Stratford MS
Options with an addition at Stratford MS
CIP as of 4/2015
Funding Analysis
Funding Sources for Capital Projects
1. Bond Sales2. Other
• Capital Reserve• Major Construction Reserve• Minor Capital/Major Maintenance (MC/MM)• Joint School Board/County Board Fund for Community Improvements
13
Funding Sources for Recent Capital Projects
14
Funding Source Project (Millions)Ashlawn
Approved CIP $14.9Project cost:
Adopted Bond Sales ‐Capital Reserve $16.4Major Construction Reserves $0.3Major Capital HVAC/Roofing Bonds $1.4MC/MM $0.9Joint SB/CB Fund $2.3
Total $21.3
Funding Sources for Recent Capital Projects
15
Funding Source Project (Millions)Ashlawn Discovery
Approved CIP $14.9 $43.1Project cost:
Adopted Bond Sales ‐ $25.8Capital Reserve $16.4 $14.9Major Construction Reserves $0.3 ‐Major Capital HVAC/Roofing Bonds $1.4 ‐MC/MM $0.9 ‐Joint SB/CB Fund $2.3 $3.1
Total $21.3 $43.8
Funding Sources for Recent Capital Projects
16
Funding Source Project (Millions)Ashlawn Discovery McKinley
Approved CIP $14.9 $43.1 $20.1Project cost:
Adopted Bond Sales ‐ $25.8 $17.6Capital Reserve $16.4 $14.9 $0.9Major Construction Reserves $0.3 ‐ ‐Major Capital HVAC/Roofing Bonds $1.4 ‐ $2.0MC/MM $0.9 ‐ $0.7Joint SB/CB Fund $2.3 $3.1 $0.8
Total $21.3 $43.8 $22.0
Funding Sources for Recent Capital Projects
17
* Abingdon is currently in design; Joint SB/CB Funding is estimated and has not be finalized.
Funding Source Project (Millions)Ashlawn Discovery McKinley Abingdon*
Approved CIP $14.9 $43.1 $20.1 $28.8Project cost:
Adopted Bond Sales ‐ $25.8 $17.6 $28.8Capital Reserve $16.4 $14.9 $0.9 ‐Major Construction Reserves $0.3 ‐ ‐ ‐Major Capital HVAC/Roofing Bonds $1.4 ‐ $2.0 $1.6MC/MM $0.9 ‐ $0.7 $0.5Joint SB/CB Fund $2.3 $3.1 $0.8 $0.8
Total $21.3 $43.8 $22.0 $31.7
Stratford Building Options
Cost Saving Strategies
19
• Reduce area of addition from 45,000 SF to 35,000 SF– 3,000 SF Support spaces– 1,000 SF Locker rooms reductions– 600 SF Omit student activity center– 1,100 SF Gym storage & office reductions– 600 SF Omit two SPED resource rooms– 700 SF Omit drama classroom– 3,000 SF Retain existing media center
• Reduce scope of renovation to minimum• Use “Existing Facility” only
MS ‐ Gross Square Feet (GSF)/Seat Comparison
20
School GSF Capacity* GSF/SeatGunston** 209,212 932 224Jefferson** 219,070 982 223Kenmore 206,188 985 209Stratford MS (45,000 SF addition) 183,000 1,000 183Stratford MS (35,000 SF addition) 173,000 1,000 173Williamsburg 170,865 997 171Stratford MS (Entire Existing Building) 138,000 ~850*** ~162Swanson 132,158 948 139
* Excludes relocatable classrooms** Includes some square footage for shared use facilities*** Will require relocatable classrooms
“Link” & “West” Concept Design
21
1,000‐seat Middle School
• 35,000 SF addition• Renovations• To open September 2019
“West“ concept design has not been discussed, selected, or endorsed by either the BLPC or the PFRC
Funding SourceStratford (Millions)
CIP Estimate Over (Under)
Bond Sales $29.2 $27.1 ($2.1)
Other* $0 $4.2 $4.2
Total Cost $29.2 $31.3 $2.1*Includes $0.8 in Revenue / Reserves and $3.4 in Joint SB/CB Fund
“Existing Facility” and Stratford Program Remains
22
~750‐seat Middle School,45‐seat Stratford Program Remains in Current SF
• No addition • Renovations• To open September 2019• May not fully comply with
APS Ed Specifications• Requires use of relocatable
classrooms
Funding SourceStratford (Millions)
CIP Estimate Over (Under)
Bond Sales $29.2 $2.4 ($26.8)
Other* $0 $2.6 $2.6
Total Cost $29.2 $5.0 ($24.2)*Includes $0.7 in Revenue / Reserves and $1.9 in Joint SB/CB Fund
“Existing Facility” and Stratford Program Moves
23
~ 850‐seat Middle School
• No addition • Renovations• To open September 2019• May not fully comply with
APS Ed Specifications• Requires use of relocatable
classrooms
Funding SourceStratford (Millions)
CIP Estimate Over (Under)
Bond Sales $29.2 $2.4 ($26.8)
Other* $0 $2.6 $2.6
Total Cost $29.2 $5.0 ($24.2)*Includes $0.7 in Revenue / Reserves and $1.9 in Joint SB/CB Fund
Stratford MS: 8/11/15 School Board Work Session
24
• 45,000 SF addition• Renovations• To open September 2019• Total cost includes optional
enclosed courtyard
1000‐seat Middle School “Link” concept design Enclosed courtyard creates commemorative space to honor events of February 2, 1959
Funding SourceStratford (Millions)
CIP Estimate Over
Bond Sales $29.2 $36.6 $7.4
Other* $0 $10.9 $10.9
Total Cost $29.2 $47.5 $ 18.3*Includes $0.9 in Revenue / Reserves, $3.8 in Joint SB/CB Fund, and $6.2 for Enclosed Courtyard
Design Alternatives for an Addition (1,000 seats)
25
Terrace West
EastLink (w/o Enclosed Courtyard)
$27.1 M Bond$4.2 M Other$31.3 M Total
$32.2 M Bond$4.2 M Other$36.4 M Total
$27.1 M Bond$4.2 M Other$31.3 M Total
$33.9 M Bond$4.2 M Other$38.1 M Total
Stratford MS – Summary of Options
26
*Other Funding includes Non 20‐year Items (furniture, technology, equipment, etc.) and Community Improvements
OptionEstimate (Millions) Total
SeatsGSF per Seat
New Seats
Cost per New SeatBond
FundingOther
Funding* Total
“Link” Addition $27.1 $4.2 $31.3 1,000 173 295 $106,100“West” Addition $27.1 $4.2 $31.3 1,000 173 295 $106,100
“Existing Facility” with Stratford Program $2.4 $2.6 $5.0 ~750 ~168 ~45 $111,100
“Existing Facility” without Stratford Program $2.4 $2.6 $5.0 ~850 ~162 ~145 $34,500
CIP $29.2 $0.0 $29.2 1,000 N/A 295 $99,000
Wilson Site Options
• Simplify building design to “Box”: ~$2.5 M savings • Consider alternative parking strategies: ~$7.4M Savings• Reduce area of building
– More efficient layout/building system: ~$1.7 M savings– Omit black box theater: ~$0.8 M savings– Smaller classrooms/labs: ~$0.3M savings
• Reduce number of seats for Stratford Program– Reduce to 25 seats: ~$0.9M savings– Stratford Program not moved to Wilson: ~$5.1M savings
Cost Saving Strategies
28
“Fanning Bars”5 levels above ground
“Box”7 levels above ground
Consider Alternative Parking Strategies
Alternatives to 92 structured parking spaces included in “Fanning Bars” and “Box” concept designs:• Parking structure $7.4M• Omit parking structure / lease spaces in adjacent commercial parking structures
• Share parking with Penzance• Penzance funds three levels of parking below entire site to reduce rock excavation on its site
• APS spaces fully funded by Penzance, or• APS receives compensation and then leases spaces from Penzance
29
Reduce Area of Building & Relocate Stratford Program
30
“Fanning Bars” & Stratford Program remains at Stratford MS or is co‐located at existing MS/HS
150,000 SF
• 150,000 SF new building• 725 seats• To open September 2019• Alternative parking strategy• Includes black box theater
Funding SourceWilson (Millions)
CIP Estimate Over (Under)
Bond Sales $80.2 $80.1 ($0.1)
Other* $0 $5.7 $5.7
Total Cost $80.2 $85.8 $5.6*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Reduce Area of Building & Program
31
Image of Reduced area perhaps pie chart159,000 SF
• 159,000 SF new building• 750 seats• To open September 2019• Alternative parking strategy• Omit black box theater• Smaller classrooms/labs (each 25 SF less than Ed Specs)
“Fanning Bars” H‐B 725 Seats with area reductions, Stratford Program reduced from 50 to 25 Seats
11,000 SF
Funding SourceWilson (Millions)
CIP Estimate Over
Bond Sales $80.2 $83.1 $2.9
Other* $0 $5.7 $5.7
Total Cost $80.2 $88.8 $8.6*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Reduce Area of Building & Stratford Program Seats
32
“Fanning Bars” H‐B 725 SeatsStratford Program reduced from 50 to 25 Seats
Image of Reduced area perhaps pie chart163,000 SF
• 163,000 SF new building• 750 seats• To open September 2019• Alternative parking strategy
Funding SourceWilson (Millions)
CIP Estimate Over
Bond Sales $80.2 $85.7 $5.5
Other* $0 $5.7 $5.7
Total Cost $80.2 $91.4 $11.2*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Reduce Area of Building
33
“Fanning Bars” H‐B 725 Seats Stratford 50 Seats167,000 SF
• 167,000 SF new building • 775 seats• To open September 2019• Alternative parking strategy• More efficient layout/building system
Funding SourceWilson (Millions)
CIP Estimate Over
Bond Sales $80.2 $87.0 $6.8
Other* $0 $5.7 $5.7
Total Cost $80.2 $92.7 $12.5*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Simplified Building Design without Parking
34
• 167,000 SF new building• 775 seats• To open September 2019• Alternative parking strategy
“Box” concept design7 levels above ground / $2.5M savings over “Fanning Bars”
Funding SourceWilson (Millions)
CIP Estimate Over
Bond Sales $80.2 $84.5 $4.3
Other* $0 $5.7 $5.7
Total Cost $80.2 $90.2 $10.0*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Wilson: 8/13/15 School Board Work Session
35
• 170,000 SF new building• 775 seats• Structured parking for 92 cars• To open September 2019
“Fanning Bars” 5 levels above groundStepped design creates outside space at every level to compensate for limited site areaEndorsed by BLPC and PFRC
Image of current Design
Funding SourceWilson (Millions)
CIP Estimate Over
Bond Sales $80.2 $95.0 $14.8
Other* $0 $5.7 $5.7
Total Cost $80.2 $100.7 $20.5*Includes $1.8 in Revenue / Reserves and $3.9 in Joint SB/CB Fund
Wilson – Summary of Options
36
*All options assume alternative parking strategy and more efficient layout/building systems. Many other combinations of options are possible. **Other Funding includes Non 20‐year Items (furniture, technology, equipment, etc.) and Community Improvements
Option*Estimate (Millions)
GSF Seats GSF per Seat
Cost per SeatBond
FundingOther
Funding** Total
“Fanning Bars” Relocate Stratford Program $80.1 $5.7 $85.8 150,000 725 207 $118,300
“Fanning Bars” Omit Black box Theater and Reduce
Classrooms SF, Reduce Stratford Program Seats
$83.1 $5.7 $88.8 159,000 750 212 $118,400
“Box” $84.5 $5.7 $90.2 167,000 775 215 $116,400 “Fanning Bars” Reduce Stratford Program Seats $85.7 $5.7 $91.4 163,000 750 217 $121,900
“Fanning Bars” $87.0 $5.7 $92.7 167,000 775 215 $119,600
CIP $80.2 $0.0 $80.2 N/A 775 N/A $103,500
Summary of Options
Stratford MS Wilson School
Stratford and Wilson – Summary of Options
38*Other Funding includes Non 20‐year Items (furniture, technology, equipment, etc.) and Community Improvements
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$109.4 $0.0 $109.4 1,070 230 $16.6
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$82.5 to $89.4 $8.3 $90.8 to $97.7 815 to 920 380 to 485 $36.6 to $44.5
Estimate (Millions)New Seats
Remaining Seats
Needed
Remaining Bond Funds (Millions)Bond Funding
(Stratford & Wilson)Other
Funding* Total
$109.1 to $114.1 $9.9 $119.0 to $124.0 1,050 to 1,070 230 to 250 $11.9 to $16.9
Options without an addition at Stratford MS
Options with an addition at Stratford MS
CIP as of 4/2015
Start Finish 2015 2016 2017 2018 2019Design (22 months) Apr‐2015 Dec‐2016SB Approves CMR Pre‐construction Contract Sep‐2015 Sep‐2015SB Approves Concept Design Nov‐2015 Nov‐2015SB Approves Schematic Design Feb‐2016 Feb‐2016Use Permit Approval Jun‐2016 Jun‐2016SB Approves Final Design Jan‐2017 Jan‐2017GMP/Procurement (4 months) Feb‐2017 May‐2017SB Approves CMR Construction Contract May‐2017May‐2017Construction (25 months) Jun‐2017 Jun‐2019Furniture/Technology Jul‐2019 Aug‐2019School Opening Sep‐2019 Sep‐2019
Preliminary Milestone Schedules
39
Start Finish 2015 2016 2017 2018 2019Design (22 months) Apr‐2015 Jan‐2017SB Approves CMR Pre‐construction Contract Oct‐2015 Oct‐2015SB Approves Concept Design Nov‐2015 Nov‐2015SB Approves Schematic Design Feb‐2016 Feb‐2016Use Permit Approval Jun‐2016 Jun‐2016SB Approves Final Design Jan‐2017 Jan‐2017GMP/Procurement (4 months) Feb‐2017 May‐2017SB Approves CMR Construction Contract May‐2017May‐2017Construction (26 months) Jun‐2017 Jul‐2019Furniture/Technology Aug‐2019 Aug‐2019School Opening Sep‐2019 Sep‐2019
Wilson School
Today
Stratford Middle School
Next Steps
Next Steps
• Stakeholder Meetings – Stratford MS BLPC meetings: Oct. 13 & 26 – Wilson BLPC meeting: Oct. 14 & 28– Stratford MS & Wilson PFRC meetings: Oct. 15 – FAC meeting: Oct. 19
• School Board Items• Stratford MS and Wilson Concept Design Info: Nov. 5• Stratford MS & Wilson Concept Design Action: Nov. 16
41
Gross Square Feet (GSF)/Student Comparison
42
School GSF Capacity* GSF/studentGunston** 209,212 932 224Jefferson** 219,070 982 223Kenmore 206,188 985 209Stratford (35,000 SF addition) 173,000 1,000 173Williamsburg 170,865 997 171Swanson 132,158 948 139
Wakefield*** 404,000 1,903 / 2,200 212 / 184Yorktown*** 364,142 1,879 / 2,200 194 / 166Washington‐Lee*** 329,376 1,900 / 2,200 173 / 150
H‐B (Existing) 118,700 660 180H‐B (at Wilson) 150,000 725 207H‐B (at Wilson w/o black box and w/ smaller classrooms) 146,000 725 201
* Excludes relocatable classrooms. High school capacity illustrates both current capacity and anticipated capacity after planned interior space modifications.** Includes some square footage for shared use facilities*** Includes square footage for pool facilities