netapp building 4 pilot project -...
TRANSCRIPT
NetApp Building 4
Pilot Project
Accenture Smart Building Solutions (ASBS)
1 Copyright Accenture 2012.
Copyright Accenture 2012. 2
Objectives
Building Profile and BMS Profile
Analysis and Improvements
Agenda
Costs Savings Opportunities
Impact of Interventions
Appendix
Objectives
Why ASBS?
ISO 14001 Target Objective to reduce energy consumption
Discover hidden savings opportunities
Optimize equipment operation
Make incremental improvements to already efficient buildings
Reduce building drift that occurs over time
Leverage existing instrumentation to make buildings Smarter through
analytics
3 NetApp Confidential
NetApp Building 4
Copyright Accenture 2012. 4
Building Profile
121,185 sf. 3-Story Class A office building
Constructed in 2004
2 mW Engineering Lab
$2.7 Million/year energy spend
Energy Star Building
Chilled Water Plant
Lighting Controls/Day-lighting
CO2 Monitoring
Good Instrumentation – A data rich environment
BMS Controls
~ 33,000 BMS points
5,147 BACnet Points
2 - Main Service Entrances, 2 main meters with PQ
35 submeters, 9 points/submeter
2 - 600 Ton Chillers, 41 points/Chiller
2 Roof Top AHU’s, 12 points/AHU
50 VAVs, 5 points/VAV
18 CRAH’s, 10 points/CRAH
218 points/VFD
15 zone dampers, 8 points/damper
Used Gateway to push BACnet data
Used XML SOAP to push Non-BACnet points
Copyright Accenture 2012. 5
Operational Improvements in AHUs
Copyright Accenture 2012. 6
Through the following AHU improvements we have decreased the warm-up period by
~50% 1) Increased unoccupied SAT - Closing outside air damper when building is unoccupied
2) Increased SAT in AHU2 to match AHU1 - Calibrated dampers and sensors to adjust control and outside air leakage
3) Increased maximum SAT - Increased max SAT setpoint
4) Increased heating input to AHUs - Matched boiler run time to AHU supply fan enable time
5) Reduced instability in RAF - Loop tuned to not be so sensitive to small pressure changes in the building
1 1
2 2
3 3
5 5
4 4
Chiller Analysis Results
Both chillers in Building 4 are operating at efficiencies 40% below
manufacturer specifications
The NetApp chillers require ~42% more electricity then specified in manufacturer
ratings (0.68 vs 0.48 kW/ton at 72% load).
Chiller efficiency is below specification even when operating with a load well below the
rated capacity (which should make the chiller more efficient).
Both chillers in Building 4 are operating with a evaporator flow from 20% to 30% above
the chillers’ design flow. This is likely causing the chiller refrigerant pressure in the
evaporator tube bundle to exceed manufacturer specification.
Unstable chiller load due to cycling of the CRAH cooling valves was a likely contributor
to this issue.
Copyright Accenture 2012. 7
Operating Parameter Manufacturer
Specification
NetApp Operating
Conditions
Evaporator Pressure (PSI) 39.5 36.4
Condenser Pressure (PSI) 74.6 87.2
Difference 35.1 50.8 (1.45 X Base)
Impact of ASBS Recommendations to Date
Copyright Accenture 2012. 8
The interventions identified by the ASBS service have significantly improved
the performance of the HVAC system in Building 4.
Accomplishments
Decreased the building’s required warmup time by ~50% (between 2-4 hours reduction
per day, depending on outside air temperature)
Coordinated separate systems to drive efficiency (Boiler and AHU schedules)
Identified malfunctioning components (AHU economizer actuator)
Reduced cycling and instability of controls logic (FCU cooling coils, AHU return fan)
Contributed to best practice in BAS setup and controls logic across other NetApp
buildings
Identified limitations of the current controls system setup (PID loops for VAVs, Chiller
supply temperature, AHU individual control, etc.)
Overview of Recommendations to Date
Copyright Accenture 2012. 9
2) Implemented to support reducing simultaneous heating and cooling
5a) Removed minimum (electric) heating CFM from VAV control
5b) Selective testing of lowering max heating CFM on subset of VAV units to be closer
to 50% of max cooling CFM
1) Implemented to support efficiency during heating mode
1) Coordinated start times of AHUs and Boiler (now matched to 3am)
2a) Fixed stuck damper on AHU1
2b) Lower below 30% the minimum outside air damper position when building is
unoccupied (both heating and cooling modes)
2c) Match outside air supply on AHUs when the economizer is in the same position
(leaking damper on AHU1)
2d) Lowered min damper position to 30%
3) Raise supply air temperature setpoint from 68 to 75 degrees when building is in
warm up mode
4) Damper lockout setpoint lowered from 75 to 70 degrees
3) Recommended to support cooling efficiency
6) Reduce chiller primary flow to be limited to manufacturer maximum recommendation
Energy Use, Costs and CO2 Reductions
Implementing Accenture recommended changes would drive energy savings of
$119,202 (eq. 658,891 lbs CO2) per year, representing a total NPV of $458,588
Copyright Accenture 2012. 10
Issue System Energy
(kWh)
Energy
(Therms)
$/
year NPV $
C02
(lbs/yr)
1) Boiler/AHU Startup Time Match N/A
2a) Stuck Damper Heating 2,409 2,409 2,409 32,395
Cooling 9,035 1,081 1,081 4,734 2b) Min Damper Unoccupied Setpoint Heating 2,891 2,891 16,966 38,874
Cooling 9,637 1,153 6,764 5,050 2c) Unmatched Damper Airflow N/A
2d) Min Damper Occupied Position
Setpoint Heating 2,409 2,409 14,139 32,395
Cooling 12,046 1,441 8,455 6,312
3) AHU SAT Setpoint Heating 2,409 2,409 14,139 32,395 4) Economizer Lockout Temp Setpoint Cooling 28,911 3,458 20,292 15,149 5ab) VAV Max Heating CFM Heating 4,954 4,954 29,074 66,616
Cooling 24,772 2,963 17,386 12,980 6) Chiller Efficiency Improvement Cooling 786,240 94,034 327,884 411,990
Total 870,641 15,073 $119,202 $458,588 658,891
Copyright Accenture 2012. 11
Operational Guidelines – Exception Report
AFDD
Appendix
AFDD – Portal View