ncdot ord implementation (draft) · part i part ii part iii readiness assessment department-wide...

18
NORTH CAROLINA Department of Transportation NCDOT ORD IMPLEMENTATION (DRAFT) Roger Kluckman, PE Roadway Design Unit December 2019

Upload: others

Post on 03-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NORTH CAROLINA

Department of Transportation

NCDOT ORD IMPLEMENTATION (DRAFT)

Roger Kluckman, PE Roadway Design UnitDecember 2019

Page 2: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NCDOT ORD Implementation Plan

PART I PART I I PART I I IReadiness

AssessmentDepartment-Wide

MigrationPlan

Unit-SpecificMigration

Recommendations

Page 3: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NCDOT Readiness Assessments

Hydraulics

Roadway Design

Feasibility Studies

Structures Management

Utilities

ITS and Signals

Geotechnical Engineering

Location and Surveys

Photogrammetry

Signing and Delineation

Work Zone Traffic Control

CADD Services

Plans and Standards Management

Roadside Environmental

Units Already Interviewed for Readiness Assessment

Page 4: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NCDOT Readiness AssessmentsAwareness

Understanding

Planning

Testing/Training

Implementing

Page 5: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NCDOT Readiness Assessments

It is important to understanding what current software applications are being used in order to establish a transition plan. It is also important to understand what hardware is currently being used to ensure that it is compatible with ORD.

HA R D WA R E & SOFTWA R E

Each unit has specific processes and workflows that are regularly used to get your work done. It is possible that the shift to ORD will require some of these processes to be reexamined.

WOR KFLOW

The team members within each unit are at the core of the NCDOT’s work. It is important to ensure that personnel understands what this ORD transition means for them. ORD education or training will be needed at various levels within the unit, ranging from production staff to management staff.

PER SONNEL

Page 6: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

NCDOT ORD Implementation Plan

PART I PART I I PART I I IReadiness

AssessmentDepartment-Wide

MigrationPlan

Unit-SpecificMigration

Recommendations

Page 7: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

Implementation vs Migration Implementation Approach Migration Approach

Finite Schedule / Focus on single dateFlexibility in Schedule / Focus on regular

cycle

All disciplines transition at same time Units/Disciplines can transition at varying

paces

All projects, all sizes transition at onceCertain types of projects may advance

before others

All milestones set at beginning of process Intermediate milestones set along the way

Page 8: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

Phased Migration Approach

Page 9: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Migration Roles

NCDOT Leadership

ORD Implementation Manager

ORD Working Group

ORD Working Group Facilitator

CADD Coordinators(Super Users, Representing each Unit/Division as needed)

ORD Implementation Team

(SMEs)

NCDOT Users(Relaying issues and experiences to CADD Coordinators)

Page 10: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

Role of the Working Group

Coordination and Communication

Disseminate technical information

Collect feedback

Discuss challenges and barriers

Track progress of development updates

Page 11: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Working Groups

Anticipated Frequency: Monthly

INTERNAL

EXTERNAL

Begins upon adoption

of ORD Implementation

Plan

Begins upon ORD

Rollout

Page 12: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Training Plan

Training Levels

Unit Training

Internal vs. External Training

• General Training – basic tasks, accessible to

anyone, navigation and familiarity

• Focused Training – discipline specific, more

detailed

Units will identify who they need to train and what

focused training they will need

The training plan will describe the approaches that

will be used for NCDOT staff and external

consultants based on trainees needs.

Page 13: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Training Plan

Live Classroom Sessions

TRAINING FORMATS

Webinars

Written Tutorials and Documents

Video Training Modules

3rd Party Training Options

Various formats will be considered for

the general and focused training. The

training plan will designate which

format is recommended for each

training

Page 14: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Testing Process

Pilot Projects Testing

• Already Underway

• Completed 25% Design

• Tangible Results

• Constrained to Project Schedule

• Dependent on Bentley ORD

Update Releases

• Full Regression Testing

• Hardware and Software

Testing

Page 15: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

Draft ORD Communications PlanInternal

Communications

External

Communications

Potential Methods of Communication

Monthly Digital

Newsletter

Progress Reports to

Senior Management

Fact Sheets

Memos

Presentations

Coordination Meetings

Page 16: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

ORD Workspaces

• Roadway

• Structures

• Hydraulics

• Geotechnical

• Traffic Control

• Signing

• ITS and Signals

• Photogrammetry

• Location

Complete or Nearing

Completion• Erosion Control

• Rail

• Environmental Analysis

• Utilities

Under Construction

Page 17: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

Soft Rollout

Completely Voluntary

Vetted through NCDOT Project

Manager and ORD Implementation

Team

Anticipated Soft Rollout Date: July

2020

Page 18: NCDOT ORD IMPLEMENTATION (DRAFT) · PART I PART II PART III Readiness Assessment Department-Wide ... Roadway Design Feasibility Studies Structures Management Utilities ITS and Signals

ncdot.gov

THANK YOU