nbi 14-19 march 2002 the miniboone horn ioanis kourbanis for the miniboone collaboration

58
NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

Upload: eric-copeland

Post on 23-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

The MiniBooNE Horn

Ioanis Kourbanis

For

The MiniBooNE Collaboration

Page 2: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outline

List of people Horn characteristics Horn Power Supply Horn Striplines Highlights of Horn Construction and Assembly Horn Testing Horn Changeover Future Plans

Page 3: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

List of People• C. Anderson

• L. Bartotzek (Bartoszek Engineering)

• L. Bartelson

• L. Bugel

• C. Jensen

• H. Le

• B. Markel (Markel & Associates)

• J. Misek

• F. Nezrick

• H. Pfeffer

• R. Reilly

• D. Snee

• M. Sorel

• E. Zimmerman

Page 4: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Characteristics

We are using one horn with a narrow neck and a conical inner conductor (BNL Design) designed to run at a current of 170 KA.

The horn is made out of Al alloy 6061-T6 and is excited by a 143 sec current pulse. Keep the voltage at the PS below 10 KV (use solid state SCR’s

instead of thyristors) Reduce the current pulse width as much as possible to avoid

excessive heating of the horn . Keep the voltage at the horn as low as possible (small inductance).

The horn will operate at an average rep rate of 5 Hz. Total average power deposited in the horn is 2.4 KW.

Page 5: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

3-D Model of the Horn

Page 6: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Power Supply

The Power Supply consists of a Capacitor bank (1,344 F) discharged through an inductive load by an SCR switch. The system has a separate circuit for energy recovery.

The circuit is divided into 16 parallel capacitors, each with its own SCR switch.

Page 7: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn PS Parameters

DESIGN OPERATION

Pulse Amplitude(KA)

250 170

Rep. Rate(Hz)

7.5 5.0

Circuit Inductance(microH)

1.78 1.33

Operating Voltage(kV)

9.5 5.4

Average Power(kW)

62 19

Page 8: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Power Supply Schematic

Page 9: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Power Supply View (Front)

Page 10: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Power Supply View (Back)

Page 11: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Stripline Balanced design (odd number of conductors) to

minimize forces. The conductor spacing is 1 inch. Fluted alumina

insulators with a 2 inch creepage length were used to separate the conductors.

The test stripline piece, along with a clamped joint, were corona tested.

The inductance of the final stripline was measured to be 18.5 nH/m.

Page 12: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

View of the Long Stripline Section

Page 13: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

View of a Stripline Joint

Page 14: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

View of the Small Stripline Section

Page 15: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Construction and Assembly Highlights

Forged Outer Conductor The water sprayers were vibration isolated from

the Horn Outer Conductor. Solid connections from the striplines to the Horn. The Horn Inner Conductor was welded at

Fermilab using a programmable TIG welding machine.

Page 16: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outer Conductor after Forging

Page 17: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outer Conductor after Machining

Page 18: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outer Conductor after Welding

Page 19: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Manifolds

Page 20: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Truss

Page 21: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Truss and Water Manifolds

Page 22: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Truss Bellows Detail

Page 23: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Connection Detail

Page 24: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outer Conductor with Water Truss

Page 25: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Drain Connection

Page 26: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Water Nozzle Detail

Page 27: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Twist Transitions

Page 28: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Inner Conductor Before Welding

Page 29: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Hand Scraping before Welding

Page 30: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Welding Sample

Page 31: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Large Weld

Page 32: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Small Diameter Weld

Page 33: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Inspecting the Small Diameter Weld

Page 34: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Radiography of Weld

Page 35: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Radiography of Large Weld

Page 36: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Moving the Inner Conductor from The Welding Machine

Page 37: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Inserting the Inner into the Outer Conductor

Page 38: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Testing

The horn was pulsed for the first time on 07/27/01. The horn test was completed on 02/12/02 after completing 11M pulses

at full current. We completed horn magnetic field measurements. Completed a series of vibration measurements. Things we were monitoring:

Total current Current in the four striplines feeding the horn Total voltage Cooling water supply and return temperatures Horn temperatures

Page 39: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Overview of MI-8 Test Area

Page 40: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn module overview

Page 41: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Stripline Configuration at the TSB

Page 42: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Current and Voltage Profiles

Page 43: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Magnetic Field Measurement

Page 44: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Temperature Profiles with Different Sprayer Configurations

Page 45: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Correlation between Horn and Water Return Temperatures

Page 46: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Vibration Spectrum

Page 47: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Axial Displacement vs. Time

Page 48: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Changeover

The horn module is expected to be highly radioactive (30 Rad/hr at 2 ft).

In order to reduce the Radiation Exposure to under 100 mR/hr at 1 ft, the shielding requirement is 5” of steel on all sides.

Because of the crane lifting capacity, two separate coffins (an inner and an outer ) will be used.

The inner coffin has 1.5’’ thick walls except from the top cover and the front door (5” thick).

The outer coffin has 3.5” thick walls and is open at the top and the front.

Page 49: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Horn Changeover (2)

The radioactive horn module will be stored inside the two coffins in the Target Service Building in the old Proton Line.

Four coffins (two inner and two outer coffins) will be needed for a changeover.

A detailed procedure outlining all the steps for a changeover has been written and reviewed.

Total estimated time for a changeover is 2 weeks.

Page 50: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Inner Coffin

Page 51: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Outer Coffin

Page 52: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Initial Configuration

Page 53: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Inner and Outer Coffins

Page 54: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Open Inner Coffin Door

Page 55: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Position the Coffins next to the Horn Module

Page 56: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Pull the Horn Module in the Coffin

Page 57: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Close Inner Coffin Door

Page 58: NBI 14-19 March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration

NBI 14-19 March 2002

Future Plans

We have started disassembling the Power Supply and the Striplines.

The horn modules will be stored in the inner coffin. Plan to install the horn in the target pile on May 7. We estimate to be ready for a horn changeover test on May

15. We should be ready for beam on June 15. We have started ordering the large pieces for a spare horn.