navy manufacturing technology project s2306 - nsrp · electro-optics manufacturing technology...
TRANSCRIPT
1
John Mazurowski
Electro-Optics Manufacturing Technology Center
Navy Manufacturing Technology Project S2306
National Shipbuilding Research Program All Panel Meeting March 2015
DISTRIBUTION STATEMENT A: Approved for public release.
2
Technology Discussion
This project has developed a cable test system that incorporates all cable
media types- power, communications, digital, coaxial, and fiber optic.
Integrated Link Test System (ILTS) Paradigm
• Manual link-to-link tests take time / multiple personnel.
• Test results are handwritten and contain many transcription / hookup errors.
• ILTS coordinates testing and stores test results automatically.
• MRP database contains cable data, acceptance criteria, test results, and
certification record.
• Networked communication between database / system / remote test units.
3
Project Team
DISTRIBUTION STATEMENT A. Refer to cover page.
4
Project Team
COMPANY TELEPHONE
ONR ManTech Richard Henson
Penn State EOC David Ditto, John Mazurowski, Lucas
Cashdollar, Melissa McCandless
HII Newport News Dave Gruszkowski, Vannia Willis, Lisa
Maddrey, NP Rao, Jason Jaques, Billy
Marshall, Steve Harbick, Gordon Burr,
Bob Smole, Mark Dunford
DIT-MCO International John Kusek, Gregg Carder, Charlie
Jennings, Mike Reed, TJ Surgeon, Kurt
Morrison
General Dynamics
Land Systems
Steve Spurlin, Eric Clore, Greg Bagwell
DISTRIBUTION STATEMENT A. Refer to cover page.
5
Project Description
Participants and Roles
• Penn State Electro-Optics Center- Project Management and Systems
Engineering
• Huntington Ingalls Newport News- End User
• PMS 450- Program Representative
• NSWCDD- Technical Warrant Holder
• DIT-MCO International- System Supplier
• General Dynamics Land Systems- System Designer
Technical Deliverables
• Monthly Spend Plan, Project Schedule, Monthly Reports, EVM Report
• Technology Transition Plan, Risk Assessment
• Final Report, Demonstration
Period of Performance
• June 2010 – June 2015
DISTRIBUTION STATEMENT A. Refer to cover page.
6
ILTS System Features
Primary Customer:
PMS 450 Virginia Class Submarine
Requirements: • Must fit through 30 inch opening.
• Processor / Electrical: 16 in x 15 in x 5 in.
• RF: (Agilent 9918A): 12 in x 7 in x 3 in.
• Fiber Optic: 18 in x 13 in x 7 in.
• Weight < 25 pounds.
• Processor: 18 pounds.
• RF Unit: 6.6 pounds.
• Fiber Optic: 10 pounds.
• MRP database stores requirements and test data.
• Communications complies with Information Systems policies.
• Compliance with military test equipment specification (Mil-PRF-28800 Class 2).
DISTRIBUTION STATEMENT A. Refer to cover page.
7
ILTS System Features
Benefits:
• In shipbuilding, deck access time is valuable and highly choreographed. ILTS
measurement setup is done offline in order to minimize deck access.
• ILTS modular design supports electrical, RF, and fiber optic cable measurements in
accordance with recognized standards.
• ILTS is portable; hot-swappable batteries last >1 shift each.
• The ILTS supports a baseline MRP / EDA system, and can be adapted to others.
• ILTS system suppliers form the ILTS supply chain to provide downstream support.
BASELINE OPTIONAL
Electrical continuity 100 pin x 3 DC voltage to 600 volts
Electrical isolation 100 pin x 3 AC voltage to 500 volts
RF insertion loss to 26 GHz Resistance to 50 megohm
RF return loss / VSWR to 26 GHz Capacitance to 100 microfarad
Fiber Optic insertion loss SM / MM Time Domain Reflectometry (Electrical)
Fiber Optic return loss SM 200 MHz Oscilloscope
DISTRIBUTION STATEMENT A. Refer to cover page.
8
ILTS System Integration
External Network
(ILTS Portable Test System)
HII Domain
(ILTS Central Database Manager)
HII DB Server
HII Domain
Computer
HII Web
Service
FIREWALL
ILTS Portable Test System
ILTS
Analyzer
Network
Node
ILTS Tablet
RF Module Optical Module
DISTRIBUTION STATEMENT A. Refer to cover page.
9
ILTS Supply Chain
ADAPTERS
BASELINE SYSTEM
CUSTOMER
REQUIREMENTS
NEW FUNCTIONS
DATA STRUCTURES
ILTS SYSTEM SUPPLIER
DIT-MCO BASIC
FEATURES
GDLS
DISTRIBUTION STATEMENT A. Refer to cover page.
10
Metrics
• Estimated cost avoidance 7200 hours X $65/hour = $468,000 per hull.
• The project goal is a reduction in labor connected with cable measurement
and fault diagnosis.
PARAMETER
BASELINE
GOAL
CURRENT
Cost Metric:
VCS Cable Measurements
36,000
Hours
28,800
Hours
36,000
Hours
Performance Metric:
Requirements Defined 0%
376
(100%)
534
(>100%)
Performance Metric:
Verification Complete 0%
534/534
(100%)
520/534
(97%)
DISTRIBUTION STATEMENT A. Refer to cover page.
11
Progress
Administrative Progress: Award received from ONR June 2010
Subcontract awarded October 2011
Technology Transition Plan submitted May 2012
Task 2.1 – 2.4 complete June 2012
Task 2.5 Test System Supplier identified and PO placed January 2013
Weekly teleconferences begun May 2013
Review meeting and requirements review (PDR) June 2013
Task 2.5 – 2.12 complete July 2014
System requirements verification (CDR) July 2014
Technology Transition Plan update submitted July 2014
System demonstration August 2014
Final Review December 2014
Risk and Mitigation: Risk assessment completed each review in accordance with Navy ManTech guidance.
Technical Progress: Requirements and Specification June 2012
Requirements reviewed June 2013
Design activities begun July 2013
Preliminary design review August 2013
Critical design review July 2014
System demonstration August 2014
Software task list finalized November 2014
DISTRIBUTION STATEMENT A. Refer to cover page.
12
Project Schedule
DISTRIBUTION STATEMENT A. Refer to cover page.
13
Transition
TRANSITION STRATEGY: Documented in ManTech Technology
Transition Plan (TTP), submitted May 2012 and updated July 2014.
IMPLEMENTING ORGANIZATION: Ingalls Shipbuilding Newport News.
SUPPLY CHAIN: Future product of DIT-MCO International and General
Dynamics Land Systems.
FUNDING SOURCES: Ingalls Shipbuilding Newport News transition
funding ($50K) and capital acquisition ($50K). In-Kind: RF network
analyzer.
DEMONSTRATION: System verification held July 15-17 at GDLS.
System demonstration August 2014 aboard future SSN 785 USS John
Warner.
DISTRIBUTION STATEMENT A. Refer to cover page.
14
Related Projects
• PROJECTS:
• NAVAIR N00421-03-D-0044 Fiber Optic Network Development
• NSWC Crane N00164-09-C-GR34 Task V Copper Replacement
• COLLABORATIVE INTERACTIONS:
• Army Stryker Vehicle- General Dynamics Land Systems
• National Shipbuilding Research Program “Flexible Interface for
Automated Circuit Tester”
• INDUSTRY:
• HII-NNS ACCS System
• DIT-MCO International internal product development for air platforms
DISTRIBUTION STATEMENT A. Refer to cover page.
15
Future Actions
Close software task list.
Integration of ILTS into HII-NNS shipyard.
Future: Adapt for use at other shipyards / platforms.
Future: Merge functionality with ship cabling EDA tool.
Future: Enhance fiber optic measurement function.
DISTRIBUTION STATEMENT A. Refer to cover page.
16
Jointness
17
Acknowledgements
This material was supported by the Office of Naval
Research under contract N00014-05-D-0275 / 0002.
Any opinions, findings, conclusions, or recommendations
expressed in this presentation are those of the authors
and do not necessarily reflect the views of the Office of
Naval Research.
DISTRIBUTION STATEMENT A. Refer to cover page.