national institutes of health building 37 modernization katie l. mcgimpsey mechanical option the...
TRANSCRIPT
National Institutes of HealthBuilding 37 Modernization
Katie L. McGimpseyMechanical Option
The Pennsylvania State UniversityDepartment of Architectural
EngineeringSpring 2005 Thesis
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
General Project Information• Located in Bethesda, Maryland
on the National Institutes of Health (NIH) campus
• Began modernization phases in 1997
• $82.8 million
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Project Team• Owners:
– National Institutes of Health (NIH) – National Cancer Institute (NCI)
• Architects: – FLAD & Associates, Inc.– Louviere, Stratton & Yokel (LSY)
• Engineers: – AEPA Architects & Engineers, P.C.– Affiliated Engineers, Inc. (MEP)– James Posey Associates, Inc. (Consulting
Engineers)– Aerosol Monitoring & Analysis (Environmental)– Rathgeber/Goss Associates (Structural)– JBG Engineers (Audiovisual)
• General Contractor: – Whiting Turner
• CM: – Smith Management Construction, Inc.
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Existing Conditions
• Architectural Features– Two circulation towers– Four utility corridors
• Architectural Design– 21,889 m2 (235,613 ft2)– 6 stories above grade– Offices & laboratories– Mechanical penthouse
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Existing Conditions
• Electrical/Lighting– Underground duct system from Bldg 36– Main distribution: 4000A, 480Y/277V, 3-phase, 4-wire– Transformers: (3) 2500kVA, 13.8kV to 480Y/277V, 3-
phase, 4-wire– Fluorescent light fixtures: RF suppression ballasts– Laboratory lighting density = 2.5 W/m2
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Existing Conditions
• Structural– Steel column grid matrix– Pre-cast concrete panels– Pre-tensioned concrete floor
slabs
• Roof System– Concrete slab on metal roof
deck– Roof drains
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Existing Conditions
• Mechanical– (8) 100% OA AHUs supplying to a zoned VAV system
• Approximately 28,000-29,000 L/s (59,000-61,000 cfm)
– (8) Fume exhaust fans 32,000 L/s (68,000 cfm)– District heating/cooling
• Chilled water: 6ºC, (3) constant speed tertiary pumps• Steam: 20,000 lbs/hr, 165 psi
• Fire Protection– Passive System
• Corridors: 1 hour fire rating• Independent risers for fume hoods
– Active System • Zoned automatic sprinkler system
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Redesign Goals
• Mechanical– Energy Efficient – Decreased Cooling Load– Cost Savings– State-of-the-Art Laboratory and Research Facility
• Solar– Decrease Peak Electrical Load– Cost Efficient
• Structural– Support Additional Loads of New Equipment
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Redesign Goals
• Mechanical Design Conditions
Outdoor Design Conditions
Cooling DBT ºC WBT ºC
34.3 24.1
Heating -10.3 N/A
Indoor Design Conditions
Cooling DBT ºC % RH
23 50
Heating 21 50
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Mechanical Redesign
• Passive Desiccant Dehumidification – Energy Recovery– Cross-contamination concerns with fume hoods– Based on SEMCO model: EXCLU-SIEVE 3 Ǻ
molecular sieve desiccant coating
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Mechanical Redesign
• SEMCO EXCLU-SIEVE TE3-70 Model
AHU Face Velocity
Pressure Loss
Effectiveness Unit Effectiveness
Cooling
Unit Effectiveness
Heating
Purge Volume
Chiller Reduction Capacity
Boiler Reduction Capacity
Fpm In. wg % Supply Return Supply Return cfm tons boiler hp
AHU-1 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12
AHU-2 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03
AHU-3 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03
AHU-4 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12
AHU-5 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12
AHU-6 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12
AHU-7 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03
AHU-8 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Mechanical Redesign
• Performance Data– Velocity: 900 fpm– Wheel efficiency: 76%– Pressure drop: 0.94 in. wg– Wheel model size: 70– Airflow rate: 29,900 L/s
(63,360 cfm)
• Unit Dimensions– Net weight: 4680 lbs– Flow area/side: 70.4 ft2
– Nominal airflow: 26,500 L/s (56,000 cfm)
A = 171.5 in
C = 89.4 in
B = 79.1 in
D = 84.3 in
W = 23.0 in
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Mechanical RedesignAHU-# Equipment
First Cost ($)Installation
Cost ($)First Cost Savings
($)
Immediate Payback w/
Positive PCV ($)
Cooling Capacity Required
(tons)
Existing Cooling
Load (tons)
Heating Capacity Required
(MBH)
Existing Heating
Load (MBH)
AHU-1 45,000 22,500 60,362 233,838 161.59 178.6 1165 415.7
AHU-2 45,000 22,500 64,030 241,280 168.02 204 1217 105.8
AHU-3 45,000 22,500 64,030 241,280 168.02 175 1217 104.1
AHU-4 45,000 22,500 60,362 233,838 161.59 168.2 1165 87.1
AHU-5 45,000 22,500 60,362 233,838 161.59 167.8 1165 80.3
AHU-6 45,000 22,500 60,362 233,838 161.59 167.1 1165 72.4
AHU-7 45,000 22,500 64,030 241,280 168.02 167.4 1217 74.3
AHU-8 45,000 22,500 64,030 241,280 168.02 165.7 1217 80.9
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Solar Analysis
• Photovoltaic (PV) Solar Cells– Converts solar radiation into electric power– Feasibility
• 4-5kWh/m2/day
– Peak Electric Load• 5,846,644 kWh
– BP Solar 4160 S• 62.7”x31.1”• 2480 modules• 512,216 kWh
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Solar AnalysisPhotovoltaic Project Cumulative Cash FlowsNIH Building 37 Modern., Bethesda, Maryland
Renewable energy delivered (MWh/yr): 512.216 Total Initial Costs: $ 3,424,712 Net average GHG reduction (tCO2/yr): 241.47
IRR and ROI: 52.2% Year-to-positive cash flow: 2.1 yr Net Present Value: $ 8,150,422
Cu
mu
lati
ve C
ash
Flo
ws (
$)
(5,000,000)
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Years
Total Initial Costs = $3,424,712
2.1 years
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Structural Impact Analysis
• Increased Loading
Mechanical Equip. 4,680 lbs
PV Solar Modules 84,320 lbs
Total 121,760 lbs = 121.8 kips
• ASCE 7-98– Roof Live Load (Lr=20R1R2=16 psf)
– Reduction in Live Load
• LRFD– Member sizing (Columns and Composite Beams)
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Structural Impact Analysis
1040 kips
833 kips
778 kips
623 kips
516 kips
413 kips
253 kips
203kips
Non-composite 1.3C24 with t=3.3” LW concrete slab
165N4k Joist Girder
16K2 Joists with 2 Rows Bridging
W12x26 Composite Beam
Composite 3VLI17 with t=6.5” NW concrete slabs
Column DesignRoof Design
Mechanical Floor Design
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Conclusions
• Recommendations
Equipment First Cost ($)
Installation Cost ($)
First Cost Savings ($)
Immediate Payback w/ Positive PCV ($)
Cooling Capacity Required (tons)
Existing Cooling Load (tons)
Heating Capacity Required (MBH)
Existing Heating Load (MBH)
Total 360,000 180,000 497,568 1,900,472 1318.44 1393.8 9530 10206
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Presentation Outline
• General Project Information
• Project Team• Existing Conditions• Redesign Goals• Mechanical
Redesign• Solar Analysis• Structural Analysis• Conclusions• Acknowledgements• Questions
Katie L. McGimpseyMechanical Option
NIH Building 37 ModernizationSpring 2005
The PennsylvaniaState University
Acknowledgements
• Special Thanks to…– The AE Department, Staff & Faculty– AEI sponsor: Michael Soong– LSY sponsors: James Louviere and Christine Ward– Smith Management sponsor: Randy Baer– Mechanical Professors, especially Dr. Jim Freihaut– My Family and Friends– AE Class of 2005