Fallon Range Training Complex Modernization Environmental Impact Statement NATIONAL ENVIRONMENTAL POLICY ACT PROCESS AND TIMELINE MILESTONE DESCRIPTION CURRENT SCHEDULE Notice of Intent to Prepare an EIS X Starts the public involvement phase of the NEPA process Aug. 26, 2016 Scoping Period X Provides 90 days for an early and open public process for identifying environmental issues and potential viable alternatives to be evaluated in the EIS X Includes scoping meetings and other opportunities to learn more and submit comments Comment Period: Aug. 26, 2016 - Nov. 25, 2016 Scoping Meetings: Draft EIS X Presents analysis of potential environmental impacts for each identified alternative Winter 2018 Draft EIS Public Review and Comment Period X Provides 90 days for the public to comment on the analysis presented in the Draft EIS X Includes public meetings Public Meetings: Winter 2018 Final EIS X Includes updates to the Draft EIS and responses to public comments received during the Draft EIS comment period Fall 2019 Final EIS Public Review and Wait Period X Provides a 30-day wait period after the Final EIS is published before the Navy may take final action Fall 2019 Record of Decision X Follows the Final EIS public review and wait period, which includes consideration of public comments X Includes selection of an alternative by the Office of the Assistant Secretary of the Navy (Energy, Installations, and Environment) X After the Navy issues the Record of Decision, receives Congressional Approval, and based upon the availability of funding, the Navy would begin implementing the selected alternative Winter 2020 Public involvement is a fundamental part of the development of the Environmental Impact Statement. The Navy welcomes your comments. Cooperating agencies will provide early review of the Proposed Action. Opportunities for Public Review and Comment www.FRTCModernization.com Fallon, NV: Oct. 3, 2016 Lovelock, NV: Oct. 4, 2016 Reno, NV: Oct. 4, 2016 Austin, NV: Oct. 5, 2016 Eureka, NV: Oct. 6, 2016 Hawthorne, NV: Oct. 7, 2016 Gabbs, NV: Oct. 7, 2016

Upload: others

Post on 30-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NATIONAL ENVIRONMENTAL POLICY ACT PROCESS AND …€¦ · Fallon Range Training Complex Modernization Environmental Impact Statement NATIONAL ENVIRONMENTAL POLICY ACT PROCESS AND

Fallon Range Training Complex Modernization Environmental Impact Statement

NATIONAL ENVIRONMENTAL POLICY ACT PROCESS AND TIMELINE

MILESTONE DESCRIPTION CURRENT SCHEDULENotice of Intent to Prepare an EIS

XX Starts the public involvement phase of the NEPA process Aug. 26, 2016

Scoping Period XX Provides 90 days for an early and open public process for identifying environmental issues and potential viable alternatives to be evaluated in the EIS

XX Includes scoping meetings and other opportunities to learn more and submit comments

Comment Period:Aug. 26, 2016 - Nov. 25, 2016

Scoping Meetings:

Draft EIS XX Presents analysis of potential environmental impacts for each identified alternative

Winter 2018

Draft EIS Public Review and Comment Period

XX Provides 90 days for the public to comment on the analysis presented in the Draft EIS

XX Includes public meetings

Public Meetings:Winter 2018

Final EIS XX Includes updates to the Draft EIS and responses to public comments received during the Draft EIS comment period

Fall 2019

Final EIS Public Review and Wait Period

XX Provides a 30-day wait period after the Final EIS is published before the Navy may take final action

Fall 2019

Record of Decision XX Follows the Final EIS public review and wait period, which includes consideration of public comments

XX Includes selection of an alternative by the Office of the Assistant Secretary of the Navy (Energy, Installations, and Environment)

XX After the Navy issues the Record of Decision, receives Congressional Approval, and based upon the availability of funding, the Navy would begin implementing the selected alternative

Winter 2020

Public involvement is a fundamental part of the development of the Environmental Impact Statement. The Navy welcomes your comments.

Cooperating agencies will provide early review of the Proposed Action.

Opportunities for Public Review and Comment

www.FRTCModernization.com

Fallon, NV: Oct. 3, 2016Lovelock, NV: Oct. 4, 2016Reno, NV: Oct. 4, 2016Austin, NV: Oct. 5, 2016

Eureka, NV: Oct. 6, 2016Hawthorne, NV: Oct. 7, 2016Gabbs, NV: Oct. 7, 2016