national aeronautics and space administration installation details minimize/eliminate field welds...
TRANSCRIPT
National Aeronautics and Space Administration
www.nasa.gov
Installation Details
• Minimize/eliminate field welds (and grinding and cutting)
• All pipe work to be done to ASME B31.3, all documentation shall be supplied (including but not limited to material certs, welding qualification, hydro test?, and NDE)
• Piping ASTM A-285 Sch. 40 (.375” wall)
• ¼” NPT couplings (10 per elbow)
• Insulation: Armacell AP Armaflex
• Insulation paint: Devflex HP Semi-gloss color NASA blue
• Using demoed bypass pipe fabricate bypass per drawing (preferably at shop mimimize/eliminate field welds)
• All piping, ID shall be painted with: Devoe 235 Epoxy per manufacturers instructions
• All piping, OD shall be painted with: Rustoleum damp proof primer color red per manufacturers instructions
• Facilities Division performing support analysis and design (including basement column)
1
National Aeronautics and Space Administration
www.nasa.gov
Relocate Pipe Support
2
relocate pipe support to original location
National Aeronautics and Space Administration
www.nasa.gov
Demolition
3
National Aeronautics and Space Administration
www.nasa.gov
Installation
4
install long radius elbows, bypass, and turn valve
National Aeronautics and Space Administration
www.nasa.gov
Installation
5
V-Cone flow meter
relocated pipe support at long spool mid-point
long spool
CRV or short spool TBD
National Aeronautics and Space Administration
www.nasa.gov
Updated Facility
6
V-Cone
Cheng Rotational Vane
Plenum
Long Radius Elbows
Valve to be turned so that as leading edge closes it points towards extrados of elbow