Project Progress – 4thAug,2014
MY HOME VIHANGA BLOCK-“01” AS ON 4th Aug, 2014
Basement –II, Basement-I, Ground, First, Second , Third, Forth, Fifth , Sixth, Seventh Floor Slabs Completed
MY HOME VIHANGA BLOCK - “02” AS ON 4th Aug, 2014
Basement –II, Basement-I, Ground, First, Second , Third, Forth, Fifth Floor Slabs Completed
MY HOME VIHANGA BLOCK- “03” AS ON 4th Aug, 2014
Basement II Slab Completed
MY HOME VIHANGA BLOCK- “04” AS ON 4th Aug, 2014
Basement II Slab Completed, Basement-I Columns work completed
MY HOME VIHANGA BLOCK- “05” AS ON 4th Aug, 2014
PCC Work Completed, Footing Work Completed, Preparing for Grade Slab
MY HOME VIHANGA BLOCK- “06” AS ON 4th Aug, 2014
Basement II Slab Completed
MY HOME VIHANGA BLOCK-“07” AS ON 4th Aug, 2014
PCC Work In Progress
MY HOME VIHANGA BLOCK-“08” AS ON 4th Aug, 2014
Earth Work Completed
MY HOME VIHANGA BLOCK- “09 & 10” AS ON 4th Aug, 2014
Earth Work In Progress
MY HOME VIHANGA Block- “11 & 12” AS ON 4th Aug, 2014
Earth Work In Progress
MY HOME VIHANGA BLOCK-“13 & 14” AS ON 4th Aug, 2014
Footings-Work In Progress
MY HOME VIHANGA BLOCK-“15” AS ON 4th Aug, 2014
Basement-II Slab Completed, Basement-I Slab shuttering work in Progress
MY HOME VIHANGA BLOCK-“16” AS ON 4th Aug, 2014
Basement II Slab Completed
MY HOME VIHANGA BLOCK-“17” AS ON 4th Aug, 2014
Grade Slab Completed
MY HOME VIHANGA BLOCK-“18” AS ON 4th Aug, 2014
Grade Slab Bar bending work in progress
MY HOME VIHANGA BLOCK-“19”AS ON 4th Aug, 2014
Basement –II Slab Completed
MY HOME VIHANGA BLOCK-“20” AS ON 4th Aug, 2014
Basement II Slab Completed