M. Brooks April ‘00 Core Wee Muon Tracking Status •Mechanics •Chamber Building •Magnet Mods •Installation Plans •Schedule •FEE •Preparations for octant test •Recent FEE Review •Status of mechanical structures •Schedule

Upload: elin

Post on 14-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE Preparations for octant test Recent FEE Review Status of mechanical structures Schedule. Mechanics Status--Station 1. Doug Fields Nicki Bruner Bernd Bassalleck Benji Lewis R. Fraga - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Muon Tracking Status

•Mechanics•Chamber Building•Magnet Mods•Installation Plans•Schedule

•FEE•Preparations for octant test•Recent FEE Review•Status of mechanical structures•Schedule

Page 2: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Mechanics Status--Station 1

•All chambers completed (some time ago)•Expect to ship to BNL in May in preparation for installation•Mechanical support structures on order•Added tasks:

•All testing of Cathode Preamp Chips•Design, prototyping, production of LV distribution system•Presentation for upcoming FEE safety review

Doug FieldsNicki BrunerBernd BassalleckBenji LewisR. FragaD. KoehlerTim ThomasJohn Behrendt

Page 3: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Mechanics Status--Station 2

•All chambers completed•Still undergoing various performance, leak tests•Associated support structure under construction

Dave LeeRusty TowellWalter SondheimMyung-Shin ChungVal ArmijoBenny MontoyaGreg HartMatt ShawChris Kuberg

Ray SavinoBill Sandhoff

Korea Univ.WooYoung JangMinJung Kweon

Christos Velissaris

Page 4: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Mechanics Status--Station 3

•Last assembly shipped from NMSU 5-Apr-00•Expect last chamber to be complete next week•Still undergoing various performance, leak tests

Dave LeeRusty TowellWalter SondheimGreg HartMatt ShawChris Kuberg

Ray SavinoBill Sandhoff

KoreaWooYoung JangMinJung Kweon

Steve PateChristos VelissarisVassili PapavassiliouGary Kyle

Page 5: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Mechanics Status--Turning the muon magnet into Swiss Cheese

Mounting holes required at:•Station 1 teacup rib•Station 2 rib•Station 2, piston•Backplate•Reconfiguration of piston support finsFor:•Chamber mounting•FEE Mounting•Eyebrow mounting•Scaffolding

Expect holes, excluding scaffolding and eyebrow to be complete this week or next

Expect all drilling to be completed first or second week of May

Fins completed

Page 6: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

Mechanics Status--Installation Plans

•Integration Meeting to discuss installation and alignment plans•Installation scaffolding expected to be completed and shipped from NMSU May 1•Lifting fixtures in process•Station 2 mounting fixture (“spider”) being built

Installation Schedule:

•Install spider 6/8•Install St. 3 6/15•Install St. 2 6/27•Install St. 1 7/7•Install Align. 7/13•Trial fit Buss 7/20

READY for FEE 7/26

Page 7: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

FEE--Octant Test WorkSeptember TAC recommended larger-scale test of FEE system before full production--ergo, we now have an “octant test”

LV

Cal Pulse

Dick MischkeMing LiuMelynda BrooksPat McGaugheyMike LeitchMaureen CaffertyScott RobinsonGlenn ThorntonManny EchaveJake ArchuletaBernie ArchuletaGreg Hart

Andrew HooverGreg Moran, Steve Pate

Jack Fried

Page 8: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

FEE--Octant Test Work

•St. 2 Production Chamber•6 readout planes•960 channels

•4 chassis, fully populated•8 Control Boards•16 Cathode Readout Cards

•12 channels of HV, dist. system•10 channels of LV, dist. system

Page 9: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

FEE--Octant Test Work•Mechanical Structures:

•Chassis and cross-rib assemblies delivered to BNL some time ago. Assembly mostly complete, by Andrew, some plumbing still needs to be received.

•Board Status:•First control board (3rd round) received (LANL) and checked out o.k.; Full order placed.•First Readout Card (3rd round) expected this week; full order will follow

•Noise specs already achieved on large fraction of the channels; this latest version should have layout fixes required to meet specs on all channels

•Backplanes expected 17-April•HV

•Initial hookup complete•Will switch to latest version of distribution system over the next couple of weeks

•LV•Distribution system design completed by LANL/UNM•First production board expected this month, also real LV supplies

•DAQ•Hookup to GTM, DCM, associated software completed by Ming, Jamie, Mickey

•ARCNet:•Preamp, AMU/ADC, FPGA downloads available (Andrew). Also, board monitoring (T, I, V)

•Calibration System•Already had gone through few rounds (Pat and Mike); final or nearly final system expected available for octant test

Page 10: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

FEE--Other Work•Ancillary Systems:

•Full review of system completed by Steve Pate, Andrew Hoover. Orders of necessary VME modules begun

•Mechanics (AMC @ NMSU, Jake and Bernie @ LANL)•In-magnet mechanical structures to nearly complete•Eyebrow (platform for racks) completed

UNM: Preamp testing nearly complete, LV distribution sent out, much work for FEE safety review completed by NickiFPGA: Download via ARCNet worked on by Andrew, full production FPGA code worked on by Jack FriedRack Layout completed, cable layout begun (Jan B.)

Page 11: Muon Tracking Status Mechanics Chamber Building Magnet Mods Installation Plans Schedule FEE

M. Brooks

April ‘00 Core Week

FEE--Schedule

Order full set of production parts O.K. given 5-April following FEE reviewOctant test complete mid-MayOrder production boards May-Aug. (may be shorter)Install Mech. Support Structure Aug. 2Install Platform and Racks Aug. 9Test boards AugAssemble chassis, CRAs Aug-NovInstall chassis, CRAs Aug-Nov

FEE Installation complete Nov. 10

Activities to follow FEE Installation:•Roll-in•Connections to counting house, plumbing, etc.•Replacement of beam pipe•Installation of “collar”•Installation of Magnet Buss•Central arm work