Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 1 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
Create Multi Counter Maintenance Plan IP43 This guide explains how to create a multi counter maintenance plan.
In the case of a multiple counter plan, there are no individual packages as there are for performance-based and time-based maintenance plans. When a cycle is due, all the operations from the assigned task list are automatically due.
Activities include:
Create a multi counter maintenance plan.
1. Enter the transaction code IP43 in the SAP Command box. Click to start the transaction. OR Drill down to the transaction through the SAP Menu: Logistics Plant Maintenance Preventive Maintenance Maintenance Planning Maintenance Plans Create Multiple Counter Plan.
Create Maintenance Plan: Initial
2. As required, complete/review the following fields:
Field Name Description
Maint. plan cat. Enter the maintenance plan category.
In most cases this will be Maintenance order. If notifications are used as the category these notifications will have to be processed into Work Orders. If using Maintenance orders as the category, work orders will be automatically generated.
Example: Maintenance order
3. Click .
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 2 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
Create Maintenance Plan: Multiple cntr plan
Multi counter plans enable the creation of maintenance plans that are triggered by different cycles. For example, where maintenance needs to be performed either 3 monthly or 150 hourly
4. As required, complete/review the following fields:
Field Name Description
Maintenance plan Enter the Maintenance plan description. Example: Primary Service Back Hoe
Cycle Enter the cycle. Example: 3
U.. Enter the unit of measure. Example: MON
Maintenance cycle text Enter the maintenance cycle text. Example: 3 Monthly
Cycle Enter another Cycle on the next line. Example: 150
U Enter the Unit of measure. Example: H
Maintenance cycle text Enter the Maintenance cycle text. Example: 150 Hourly
Counter Enter the Counter.
The counter in this case would be recording the operating hours of the unit and is entered against all cycles.
Example: 100140
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 3 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
5. Scroll down to view all maintenance item fields.
Create Maintenance Plan: Multiple cntr plan
6. Complete the following fields under the tab:
Field Name Description
Maintenance Item Enter the Maintenance Item description. Example: Primary Service Back Hoe
Functional loc Enter the Functional location. Example: 219047901
7. Click to populate the fields under the Planning data area with the defaults from the functional location that has been selected.
8. As required, complete/review the following field:
Field Name Description
Priority Enter the Priority of the task.
The Priority should be determined by the criticality of the task to be performed on the scheduled date. If the task must be performed on the date which is set when the plan call is generated then the priority should be High. Example: Medium
MaintActivityType Enter the Maintenance Activity Type.
For example: 110 Routine Service 140 Component Lubrication 150 - Calibration Example: 110
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 4 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
9. Double-click the Functional loc. field to display the master data.
10. Click the tab to display the Construction type (Assembly).
Display Functional Location: Master data
The Assembly number for the functional location is required to locate the appropriate task list. Make note of the construction type for the selected functional location.
11. Click .
12. Click in the Task list area.
Display Task Lists: Task List Selection
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 5 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
13. Complete the following fields:
Field Name Description
Usage Enter 01 to limit the selection to primary maintenance task lists only.
Example: 01
Assembly Enter the assembly code.
The Assembly is the Construction type assigned to the functional location.
Example: 60028111
14. Click .
Create Maintenance Plan: Multiple cntr plan
15. Scroll up to view the packages associated with the task list.
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 6 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
Create Maintenance Plan: Multiple cntr plan
16. Click .
Create Maintenance Plan: Multiple cntr plan
17. As required, complete/review the following fields:
Field Name Description
Sort field Enter the Sort field.
The sort field is used to manage the deadline monitoring process which automatically reschedules maintenance plans and creates maintenance orders (or notifications).
Example: CAL Weipa Activity Based
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 7 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
18. Click .
Create Maintenance Plan: Multiple cntr plan
Multi counter plans accommodate situations where regular maintenance is to be scheduled at one parameter, cycle and package, or any other parameter with an and/or relationship. For example, every 6 months or 4000 hours. These parameters are assigned in the maintenance plan header, and this type of maintenance plan can have one or more items, so the cycle and package assigned in the header is applied to all maintenance plan items.
19. As required, complete/review the following fields:
Field Name Description
Scheduled Period Enter the Scheduled Period.
The scheduling period determines the length of time for which the system creates maintenance calls during initial maintenance plan scheduling.
Example: 30
20. Click .
Refer to MPA_IP10 Schedule Maintenance Plan for information in relation to the scheduling of maintenance plans.
-
Create Multi Counter Maintenance Plan Manage Physical Assets
Activity Instruction Last Modified: 05 May 2010 Page 8 of 11 Business Solution 2009 Rio Tinto Create Multi Counter Maintenance Plan_AI
Start time
21. Select .
22. Click .
The system displays the message, "Maintenance plan xxxx created."
23. You have completed this transaction.
Result
You have created a multi counter Maintenance plan, ready for scheduling.