mtp-jaya sma4 (network a3 13%)
DESCRIPTION
Network DiagramTRANSCRIPT
-
Days (210 Calendar Days/180Start: 5/19/14 ID: 1
Finish: 12/13/14 Dur: 180 days?
Res:
Total TimeStart: 5/19/14 ID: 2
Finish: 12/13/14 Dur: 180 days
Comp: 0%
GEDUNG BStart: 6/16/14 ID: 3
Finish: 10/4/14 Dur: 96 days
Comp: 0%
LANTAI 3Start: 6/16/14 ID: 5
Finish: 7/26/14 Dur: 36 days
Comp: 0%
I. Beton KolomStart: 6/16/14 ID: 6
Finish: 7/5/14 Dur: 18 days
Comp: 0%
- Type K1 - 40/50Start: 6/16/14 ID: 7
Finish: 7/5/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 6/30/14 ID: 8
Finish: 7/5/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 6/16/14 ID: 9
Finish: 7/5/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 6/16/14 ID: 10
Finish: 7/5/14 Dur: 18 days
Res:
- BekistingStart: 6/16/14 ID: 11
Finish: 7/5/14 Dur: 18 days
Res:
- Type K2 - 30/30Start: 6/16/14 ID: 12
Finish: 7/5/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 6/30/14 ID: 13
Finish: 7/5/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 6/16/14 ID: 14
Finish: 7/5/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 6/16/14 ID: 15
Finish: 7/5/14 Dur: 18 days
Res:
- BekistingStart: 6/16/14 ID: 16
Finish: 7/5/14 Dur: 18 days
Res:
- Type K3 - 20/80Start: 6/16/14 ID: 17
Finish: 7/5/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 6/30/14 ID: 18
Finish: 7/5/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 6/16/14 ID: 19
Finish: 7/5/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 6/16/14 ID: 20
Finish: 7/5/14 Dur: 18 days
Res:
- BekistingStart: 6/16/14 ID: 21
Finish: 7/5/14 Dur: 18 days
Res:
- Type K4 - 20/60Start: 6/16/14 ID: 22
Finish: 7/5/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 6/30/14 ID: 23
Finish: 7/5/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 6/16/14 ID: 24
Finish: 7/5/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 6/16/14 ID: 25
Finish: 7/5/14 Dur: 18 days
Res:
- BekistingStart: 6/16/14 ID: 26
Finish: 7/5/14 Dur: 18 days
Res:
II. Beton BalokStart: 7/7/14 ID: 27
Finish: 7/26/14 Dur: 18 days
Comp: 0%
- Type BR - 20/30Start: 7/7/14 ID: 28
Finish: 7/26/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/21/14 ID: 29
Finish: 7/26/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/7/14 ID: 30
Finish: 7/26/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/7/14 ID: 31
Finish: 7/26/14 Dur: 18 days
Res:
- BekistingStart: 7/7/14 ID: 32
Finish: 7/26/14 Dur: 18 days
Res:
Beton Plat LT.3Start: 7/7/14 ID: 33
Finish: 7/26/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/21/14 ID: 34
Finish: 7/26/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/7/14 ID: 35
Finish: 7/26/14 Dur: 18 days
Res:
- BekistingStart: 7/7/14 ID: 36
Finish: 7/26/14 Dur: 18 days
Res:
Beton Plat KanopiStart: 7/7/14 ID: 37
Finish: 7/26/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/21/14 ID: 38
Finish: 7/26/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/7/14 ID: 39
Finish: 7/26/14 Dur: 18 days
Res:
- BekistingStart: 7/7/14 ID: 40
Finish: 7/26/14 Dur: 18 days
Res:
B. PEKERJAAN ARSITEKTUStart: 6/23/14 ID: 41
Finish: 10/4/14 Dur: 90 days
Comp: 0%
B.1 LANTAI 3Start: 6/23/14 ID: 42
Finish: 10/4/14 Dur: 90 days
Comp: 0%
I. PEKERJAAN TANAHStart: 8/18/14 ID: 43
Finish: 8/23/14 Dur: 6 days
Comp: 0%
Urugan Pasir Bawah lantaiStart: 8/18/14 ID: 44
Finish: 8/23/14 Dur: 6 days
Res:
II. PEKERJAAN BETONStart: 7/7/14 ID: 45
Finish: 8/23/14 Dur: 42 days
Comp: 0%
Beton Lantai KerjaStart: 8/11/14 ID: 46
Finish: 8/23/14 Dur: 12 days
Res:
Beton Kolom PraktisStart: 7/7/14 ID: 47
Finish: 7/19/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 48
Finish: 7/19/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 7/7/14 ID: 49
Finish: 7/19/14 Dur: 12 days
Res:
- BekistingStart: 7/7/14 ID: 50
Finish: 7/19/14 Dur: 12 days
Res:
Beton Balok Latei 15/20Start: 7/7/14 ID: 51
Finish: 7/19/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 52
Finish: 7/19/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 7/7/14 ID: 53
Finish: 7/19/14 Dur: 12 days
Res:
- BekistingStart: 7/7/14 ID: 54
Finish: 7/19/14 Dur: 12 days
Res:
III. PEKERJAAN PASANGANStart: 7/7/14 ID: 55
Finish: 7/19/14 Dur: 12 days
Comp: 0%
Pasangan bata rollagStart: 7/7/14 ID: 56
Finish: 7/12/14 Dur: 6 days
Res:
Pasangan Batu Merah 1/2 baStart: 7/7/14 ID: 57
Finish: 7/19/14 Dur: 12 days
Res:
Pasangan Batu Merah 1/2 baStart: 7/7/14 ID: 58
Finish: 7/19/14 Dur: 12 days
Res:
IV. PEKERJAAN PLESTERAStart: 7/14/14 ID: 59
Finish: 8/2/14 Dur: 18 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 7/14/14 ID: 60
Finish: 7/26/14 Dur: 12 days
Res:
Plesteran Dinding 1PC : 6PsStart: 7/14/14 ID: 61
Finish: 7/26/14 Dur: 12 days
Res:
Plesteran Beton 1PC : 3Ps Start: 7/14/14 ID: 62
Finish: 7/26/14 Dur: 12 days
Res:
AcianStart: 7/21/14 ID: 63
Finish: 8/2/14 Dur: 12 days
Res:
Benangan Sudut, Plinkolt & Start: 7/21/14 ID: 64
Finish: 8/2/14 Dur: 12 days
Res:
Water Proofing Plat terasStart: 7/21/14 ID: 65
Finish: 8/2/14 Dur: 12 days
Res:
V. PEKERJAAN PELAPIS LAStart: 9/22/14 ID: 66
Finish: 10/4/14 Dur: 12 days
Comp: 0%
Pasang Keramik Lantai 40x4Start: 9/22/14 ID: 67
Finish: 10/4/14 Dur: 12 days
Res:
Pasang Keramik Lantai 30x3Start: 9/22/14 ID: 68
Finish: 10/4/14 Dur: 12 days
Res:
Pasang Keramik Tangga 30xStart: 9/22/14 ID: 69
Finish: 10/4/14 Dur: 12 days
Res:
Pasang Keramik Dinding 25xStart: 9/22/14 ID: 70
Finish: 10/4/14 Dur: 12 days
Res:
VI. PEKERJAAN KUSEN PINStart: 7/7/14 ID: 71
Finish: 7/19/14 Dur: 12 days
Comp: 0%
Pasang Kusen Aluminium 4"Start: 7/7/14 ID: 72
Finish: 7/19/14 Dur: 12 days
Res:
Pasang Daun Pintu Double TStart: 7/7/14 ID: 73
Finish: 7/19/14 Dur: 12 days
Res:
Pasang Daun Jendela Kaca AStart: 7/7/14 ID: 74
Finish: 7/19/14 Dur: 12 days
Res:
Pasang kusen dan pintu KMStart: 7/7/14 ID: 75
Finish: 7/19/14 Dur: 12 days
Res:
Pasang Aksesoris AluminiumStart: 7/7/14 ID: 76
Finish: 7/19/14 Dur: 12 days
Res:
VII. PEKERJAAN PENGGANTStart: 8/25/14 ID: 77
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasang Kunci PintuStart: 8/25/14 ID: 78
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Engsel Pintu 4"Start: 8/25/14 ID: 79
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Grendel TanamStart: 8/25/14 ID: 80
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Grendel Pintu BiasaStart: 8/25/14 ID: 81
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Engsel Jendela ModStart: 8/25/14 ID: 82
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Grendel JendelaStart: 8/25/14 ID: 83
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Railling Tangga PipaStart: 8/25/14 ID: 84
Finish: 9/6/14 Dur: 12 days
Res:
VIII. PEKERJAAN PLAFONDStart: 8/25/14 ID: 85
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasang Penutup Plafond GyStart: 8/25/14 ID: 86
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Lis Gypsum 15 cmStart: 8/25/14 ID: 87
Finish: 9/6/14 Dur: 12 days
Res:
IX. PEKERJAAN SANITASIStart: 6/23/14 ID: 88
Finish: 7/19/14 Dur: 24 days
Comp: 0%
Pasang FloordrainStart: 6/23/14 ID: 89
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Kloset JongkokStart: 6/23/14 ID: 90
Finish: 7/19/14 Dur: 24 days
Res:
Pasang WastafelStart: 6/23/14 ID: 91
Finish: 7/19/14 Dur: 24 days
Res:
X. PEKERJAAN PENGECATAStart: 9/8/14 ID: 92
Finish: 9/20/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding ExterioStart: 9/8/14 ID: 93
Finish: 9/20/14 Dur: 12 days
Res:
Pengecatan Dinding InteriorStart: 9/8/14 ID: 94
Finish: 9/20/14 Dur: 12 days
Res:
Pengecatan PlafondStart: 9/8/14 ID: 95
Finish: 9/20/14 Dur: 12 days
Res:
Politur Daun PintuStart: 9/8/14 ID: 96
Finish: 9/20/14 Dur: 12 days
Res:
B.3 LANTAI 3Start: 7/28/14 ID: 97
Finish: 8/23/14 Dur: 24 days
Comp: 0%
XI. PEKERJAAN ATAPStart: 7/28/14 ID: 98
Finish: 8/23/14 Dur: 24 days
Comp: 0%
Kuda-kuda WF-200.204.12.12Start: 7/28/14 ID: 99
Finish: 8/23/14 Dur: 24 days
Res:
Gording C-150,50,20,3,2Start: 7/28/14 ID: 100
Finish: 8/23/14 Dur: 24 days
Res:
Batang Tarik f 16 mmStart: 7/28/14 ID: 101
Finish: 8/23/14 Dur: 24 days
Res:
Ikatan Angin f 16 mmStart: 7/28/14 ID: 102
Finish: 8/23/14 Dur: 24 days
Res:
Jarum KerasStart: 7/28/14 ID: 103
Finish: 8/23/14 Dur: 24 days
Res:
Baja Siku Penopang GordingStart: 7/28/14 ID: 104
Finish: 8/23/14 Dur: 24 days
Res:
Plat Plendes, Simpul, StiffneStart: 7/28/14 ID: 105
Finish: 8/23/14 Dur: 24 days
Res:
Angkur Baut HTB 16Start: 7/28/14 ID: 106
Finish: 8/23/14 Dur: 24 days
Res:
Mur Baut HTB 16Start: 7/28/14 ID: 107
Finish: 8/23/14 Dur: 24 days
Res:
PengelasanStart: 7/28/14 ID: 108
Finish: 8/23/14 Dur: 24 days
Res:
Usuk reng galvalumStart: 7/28/14 ID: 109
Finish: 8/23/14 Dur: 24 days
Res:
Penutup Atap genteng keramStart: 7/28/14 ID: 110
Finish: 8/23/14 Dur: 24 days
Res:
Lisplank double 3/25Start: 7/28/14 ID: 111
Finish: 8/23/14 Dur: 24 days
Res:
Papan Reuter 3/30Start: 7/28/14 ID: 112
Finish: 8/23/14 Dur: 24 days
Res:
BubunganStart: 7/28/14 ID: 113
Finish: 8/23/14 Dur: 24 days
Res:
C. PEKERJAAN PLUMBINGStart: 6/23/14 ID: 114
Finish: 7/19/14 Dur: 24 days
Comp: 0%
C.1 LANTAI 3Start: 6/23/14 ID: 115
Finish: 7/19/14 Dur: 24 days
Comp: 0%
Pasang Pipa Pengisi TandonStart: 6/23/14 ID: 116
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Pipa Induk DistribusStart: 6/23/14 ID: 117
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Pipa Air Bersih PVCStart: 6/23/14 ID: 118
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 6/23/14 ID: 119
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 6/23/14 ID: 120
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Pipa Induk Air KotorStart: 6/23/14 ID: 121
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Talang tegak PVC TyStart: 6/23/14 ID: 122
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Stop Kran dia 1" Start: 6/23/14 ID: 123
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Kran dia 1/2" DUPONStart: 6/23/14 ID: 124
Finish: 7/19/14 Dur: 24 days
Res:
Pasang Kran wastafel 1/2"Start: 6/23/14 ID: 125
Finish: 7/19/14 Dur: 24 days
Res:
Sumur Bor (Lengkap AksesoStart: 6/23/14 ID: 126
Finish: 7/19/14 Dur: 24 days
Res:
Tandon Air 4000 L SteinlessStart: 6/23/14 ID: 127
Finish: 7/19/14 Dur: 24 days
Res:
D. PEKERJAAN LISTRIKStart: 6/23/14 ID: 128
Finish: 8/2/14 Dur: 36 days
Comp: 0%
D.1 LANTAI 3Start: 6/23/14 ID: 129
Finish: 8/2/14 Dur: 36 days
Comp: 0%
Titik Instalasi Penerangan (NStart: 6/23/14 ID: 130
Finish: 8/2/14 Dur: 36 days
Res:
Titik Instalasi Stop Kontak (NStart: 6/23/14 ID: 131
Finish: 8/2/14 Dur: 36 days
Res:
Saklar tunggalStart: 6/23/14 ID: 132
Finish: 8/2/14 Dur: 36 days
Res:
Saklar SeriStart: 6/23/14 ID: 133
Finish: 8/2/14 Dur: 36 days
Res:
Lampu PLC 24 watt + fittingStart: 6/23/14 ID: 134
A. PEKERJAAN STRUKTURStart: 6/16/14 ID: 4
Finish: 7/26/14 Dur: 36 days
Comp: 0%
Page 1
-
Finish: 8/2/14 Dur: 36 days
Res:
Stop kontak 200 VAStart: 6/23/14 ID: 135
Finish: 8/2/14 Dur: 36 days
Res:
Pasang Panel Lantai IIIStart: 6/23/14 ID: 136
Finish: 8/2/14 Dur: 36 days
Res:
Pasang Kabel induk NYY 4x4Start: 6/23/14 ID: 137
Finish: 8/2/14 Dur: 36 days
Res:
Pasang Penangkal PetirStart: 6/23/14 ID: 138
Finish: 8/2/14 Dur: 36 days
Res:
GEDUNG CStart: 5/19/14 ID: 140
Finish: 12/13/14 Dur: 180 days
Comp: 0%
A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 141
Finish: 12/13/14 Dur: 180 days
Comp: 0%
A.1 LANTAI 1Start: 5/19/14 ID: 142
Finish: 12/13/14 Dur: 180 days
Comp: 0%
I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 143
Finish: 12/13/14 Dur: 180 days
Comp: 0%
Pengadaan Air KerjaStart: 5/19/14 ID: 144
Finish: 5/31/14 Dur: 12 days
Res:
Pembuatan Papan Nama KegStart: 5/19/14 ID: 145
Finish: 5/31/14 Dur: 12 days
Res:
Pembersihan LokasiStart: 5/19/14 ID: 146
Finish: 5/31/14 Dur: 12 days
Res:
Pembersihan AkhirStart: 12/1/14 ID: 147
Finish: 12/13/14 Dur: 12 days
Res:
MobStart: 5/19/14 ID: 148
Finish: 5/31/14 Dur: 12 days
Res:
DemobStart: 12/1/14 ID: 149
Finish: 12/13/14 Dur: 12 days
Res:
II. PEKERJAAN TANAHStart: 6/2/14 ID: 150
Finish: 7/5/14 Dur: 30 days
Comp: 0%
Galian Tanah lubang PondasStart: 6/2/14 ID: 151
Finish: 6/14/14 Dur: 12 days
Res:
Urugan Pasir Bawah PondasStart: 6/9/14 ID: 152
Finish: 6/14/14 Dur: 6 days
Res:
Urugan tanah kembaliStart: 6/23/14 ID: 153
Finish: 7/5/14 Dur: 12 days
Res:
Urugan tanahStart: 6/9/14 ID: 154
Finish: 6/14/14 Dur: 6 days
Res:
III. PEKERJAAN BETONStart: 6/2/14 ID: 155
Finish: 8/2/14 Dur: 54 days
Comp: 0%
1. Beton BalokStart: 7/14/14 ID: 156
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Type BLT - 15/20Start: 7/14/14 ID: 157
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 158
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 159
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 160
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 161
Finish: 8/2/14 Dur: 18 days
Res:
- Type BLK - 15/20Start: 7/14/14 ID: 162
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 163
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 164
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 165
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 166
Finish: 8/2/14 Dur: 18 days
Res:
- Type BL - 20/40Start: 7/14/14 ID: 167
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 168
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 169
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 170
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 171
Finish: 8/2/14 Dur: 18 days
Res:
- Type BL1- 30/60Start: 7/14/14 ID: 172
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 173
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 174
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 175
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 176
Finish: 8/2/14 Dur: 18 days
Res:
- Type BL2- 30/40Start: 7/14/14 ID: 177
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 178
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 179
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 180
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 181
Finish: 8/2/14 Dur: 18 days
Res:
- Type BA1 - 20/30Start: 7/14/14 ID: 182
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 183
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 184
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 185
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 186
Finish: 8/2/14 Dur: 18 days
Res:
- Type BA2 - 15/25Start: 7/14/14 ID: 187
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 188
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 7/14/14 ID: 189
Finish: 8/2/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 190
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 191
Finish: 8/2/14 Dur: 18 days
Res:
2. Beton Plat Lantai 2Start: 7/14/14 ID: 192
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 193
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 194
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 195
Finish: 8/2/14 Dur: 18 days
Res:
3. Beton Plat KanopiStart: 7/14/14 ID: 196
Finish: 8/2/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/28/14 ID: 197
Finish: 8/2/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 198
Finish: 8/2/14 Dur: 18 days
Res:
- BekistingStart: 7/14/14 ID: 199
Finish: 8/2/14 Dur: 18 days
Res:
4. Beton TanggaStart: 6/2/14 ID: 200
Finish: 7/12/14 Dur: 36 days
Comp: 0%
- Beton Pondasi TanggaStart: 6/2/14 ID: 201
Finish: 6/21/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 6/16/14 ID: 202
Finish: 6/21/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/2/14 ID: 203
Finish: 6/21/14 Dur: 18 days
Res:
- BekistingStart: 6/2/14 ID: 204
Finish: 6/21/14 Dur: 18 days
Res:
- Beton Plat TanggaStart: 6/23/14 ID: 205
Finish: 7/12/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 206
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 207
Finish: 7/12/14 Dur: 18 days
Res:
- BekistingStart: 6/23/14 ID: 208
Finish: 7/12/14 Dur: 18 days
Res:
- Beton Balok BordesStart: 6/23/14 ID: 209
Finish: 7/12/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 210
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 211
Finish: 7/12/14 Dur: 18 days
Res:
- BekistingStart: 6/23/14 ID: 212
Finish: 7/12/14 Dur: 18 days
Res:
- Beton Plat BordesStart: 6/23/14 ID: 213
Finish: 7/12/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 214
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 215
Finish: 7/12/14 Dur: 18 days
Res:
- BekistingStart: 6/23/14 ID: 216
Finish: 7/12/14 Dur: 18 days
Res:
- Beton K-250Start: 7/7/14 ID: 218
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 219
Finish: 7/12/14 Dur: 18 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 226
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 227
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 228
Finish: 8/23/14 Dur: 18 days
Res:
- Type K2 - 30/30Start: 8/4/14 ID: 229
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 230
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 231
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 232
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 233
Finish: 8/23/14 Dur: 18 days
Res:
- Type K3 - 20/80Start: 8/4/14 ID: 234
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 235
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 236
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 237
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 238
Finish: 8/23/14 Dur: 18 days
Res:
- Type K4 - 20/60Start: 8/4/14 ID: 239
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 240
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 241
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 242
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 243
Finish: 8/23/14 Dur: 18 days
Res:
2. Beton BalokStart: 8/25/14 ID: 244
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Type BLT - 15/20Start: 8/25/14 ID: 245
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 246
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 247
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 248
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 249
Finish: 9/13/14 Dur: 18 days
Res:
- Type BLK - 15/20Start: 8/25/14 ID: 250
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 251
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 252
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 253
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 254
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL - 20/40Start: 8/25/14 ID: 255
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 256
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 257
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 258
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 259
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL1- 30/60Start: 8/25/14 ID: 260
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 261
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 262
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 263
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 264
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL2- 30/40Start: 8/25/14 ID: 265
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 266
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 267
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 268
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 269
Finish: 9/13/14 Dur: 18 days
Res:
- Type BA1 - 20/30Start: 8/25/14 ID: 270
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 271
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 272
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 273
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 274
Finish: 9/13/14 Dur: 18 days
Res:
- Type BA2 - 15/25Start: 8/25/14 ID: 275
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 276
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 277
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 278
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 279
Finish: 9/13/14 Dur: 18 days
Res:
3. Beton Plat Lantai 3Start: 8/25/14 ID: 280
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 281
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 282
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 283
Finish: 9/13/14 Dur: 18 days
Res:
4. Beton Plat KanopiStart: 8/25/14 ID: 284
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 285
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 286
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 287
Finish: 9/13/14 Dur: 18 days
Res:
5. Beton TanggaStart: 8/4/14 ID: 288
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton Plat TanggaStart: 8/4/14 ID: 289
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 290
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 291
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 292
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Balok BordesStart: 8/4/14 ID: 293
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 294
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 295
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 296
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 297
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Plat BordesStart: 8/4/14 ID: 298
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 299
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 300
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 301
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Anak TanggaStart: 8/4/14 ID: 302
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 303
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 304
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 305
Finish: 8/23/14 Dur: 18 days
Res:
A.3 LANTAI 3Start: 9/15/14 ID: 306
Finish: 10/25/14 Dur: 36 days
Comp: 0%
I. PEKERJAAN BETONStart: 9/15/14 ID: 307
Finish: 10/25/14 Dur: 36 days
Comp: 0%
1. Beton KolomStart: 9/15/14 ID: 308
Finish: 10/4/14 Dur: 18 days
Comp: 0%
- Type K1 - 40/50Start: 9/15/14 ID: 309
Finish: 10/4/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/29/14 ID: 310
Finish: 10/4/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 9/15/14 ID: 311
Finish: 10/4/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 9/15/14 ID: 312
Finish: 10/4/14 Dur: 18 days
Res:
- BekistingStart: 9/15/14 ID: 313
Finish: 10/4/14 Dur: 18 days
Res:
- Type K2 - 30/30Start: 9/15/14 ID: 314
Finish: 10/4/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/29/14 ID: 315
Finish: 10/4/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 9/15/14 ID: 316
Finish: 10/4/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 9/15/14 ID: 317
Finish: 10/4/14 Dur: 18 days
Res:
- BekistingStart: 9/15/14 ID: 318
Finish: 10/4/14 Dur: 18 days
Res:
- Type K3 - 20/80Start: 9/15/14 ID: 319
Finish: 10/4/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/29/14 ID: 320
Finish: 10/4/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 9/15/14 ID: 321
Finish: 10/4/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 9/15/14 ID: 322
Finish: 10/4/14 Dur: 18 days
Res:
- BekistingStart: 9/15/14 ID: 323
Finish: 10/4/14 Dur: 18 days
Res:
- Type K4 - 20/60Start: 9/15/14 ID: 324
Finish: 10/4/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/29/14 ID: 325
Finish: 10/4/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 9/15/14 ID: 326
Finish: 10/4/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 9/15/14 ID: 327
Finish: 10/4/14 Dur: 18 days
Res:
- BekistingStart: 9/15/14 ID: 328
Finish: 10/4/14 Dur: 18 days
Res:
2. Beton BalokStart: 10/6/14 ID: 329
Finish: 10/25/14 Dur: 18 days
Comp: 0%
- Type BR - 20/30Start: 10/6/14 ID: 330
Finish: 10/25/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 10/20/14 ID: 331
Finish: 10/25/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 10/6/14 ID: 332
Finish: 10/25/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 10/6/14 ID: 333
Finish: 10/25/14 Dur: 18 days
Res:
- BekistingStart: 10/6/14 ID: 334
Finish: 10/25/14 Dur: 18 days
Res:
3. Beton Plat LT.3Start: 10/6/14 ID: 335
Finish: 10/25/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 10/20/14 ID: 336
Finish: 10/25/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 10/6/14 ID: 337
Finish: 10/25/14 Dur: 18 days
Res:
- BekistingStart: 10/6/14 ID: 338
Finish: 10/25/14 Dur: 18 days
Res:
4. Beton Plat KanopiStart: 10/6/14 ID: 339
Finish: 10/25/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 10/20/14 ID: 340
Finish: 10/25/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 10/6/14 ID: 341
Finish: 10/25/14 Dur: 18 days
Res:
- BekistingStart: 10/6/14 ID: 342
Finish: 10/25/14 Dur: 18 days
Res:
B. PEKERJAAN ARSITEKTUStart: 6/16/14 ID: 343
Finish: 12/13/14 Dur: 156 days
Comp: 0%
B.1 LANTAI 1Start: 6/16/14 ID: 344
Finish: 9/13/14 Dur: 78 days
Comp: 0%
I. PEKERJAAN TANAHStart: 8/25/14 ID: 345
Finish: 8/30/14 Dur: 6 days
Comp: 0%
Urugan Pasir Bawah lantaiStart: 8/25/14 ID: 346
Finish: 8/30/14 Dur: 6 days
Res:
II. PEKERJAAN BETONStart: 7/14/14 ID: 347
Finish: 7/26/14 Dur: 12 days
Comp: 0%
1. Beton Lantai KerjaStart: 7/14/14 ID: 348
Finish: 7/26/14 Dur: 12 days
Res:
A.2 LANTAI 2Start: 8/4/14 ID: 221
Finish: 9/13/14 Dur: 36 days
Comp: 0%
I. PEKERJAAN BETONStart: 8/4/14 ID: 222
Finish: 9/13/14 Dur: 36 days
Comp: 0%
- Type K1 - 40/50Start: 8/4/14 ID: 224
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 225
Finish: 8/23/14 Dur: 6 days
Res:
- BekistingStart: 6/23/14 ID: 220
Finish: 7/12/14 Dur: 18 days
Res:
- Beton Anak TanggaStart: 6/23/14 ID: 217
Finish: 7/12/14 Dur: 18 days
Comp: 0%
1. Beton KolomStart: 8/4/14 ID: 223
Finish: 8/23/14 Dur: 18 days
Comp: 0%
Page 2
-
2. Beton Kolom PraktisStart: 7/14/14 ID: 349
Finish: 7/26/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 7/14/14 ID: 350
Finish: 7/26/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 351
Finish: 7/26/14 Dur: 12 days
Res:
- BekistingStart: 7/14/14 ID: 352
Finish: 7/26/14 Dur: 12 days
Res:
3. Beton Balok Latei 15/20Start: 7/14/14 ID: 353
Finish: 7/26/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 7/14/14 ID: 354
Finish: 7/26/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 7/14/14 ID: 355
Finish: 7/26/14 Dur: 12 days
Res:
- BekistingStart: 7/14/14 ID: 356
Finish: 7/26/14 Dur: 12 days
Res:
III. PEKERJAAN PASANGANStart: 6/23/14 ID: 357
Finish: 7/26/14 Dur: 30 days
Comp: 0%
Pas. AanstampengStart: 6/23/14 ID: 358
Finish: 7/12/14 Dur: 18 days
Res:
Pas. Pondasi Batu kaliStart: 6/23/14 ID: 359
Finish: 7/12/14 Dur: 18 days
Res:
Pasangan bata rollagStart: 7/14/14 ID: 360
Finish: 7/19/14 Dur: 6 days
Res:
Pasangan Batu Merah 1/2 baStart: 7/14/14 ID: 361
Finish: 7/26/14 Dur: 12 days
Res:
Pasangan Batu Merah 1/2 baStart: 7/14/14 ID: 362
Finish: 7/26/14 Dur: 12 days
Res:
IV. PEKERJAAN PLESTERAStart: 7/21/14 ID: 363
Finish: 8/9/14 Dur: 18 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 7/21/14 ID: 364
Finish: 8/2/14 Dur: 12 days
Res:
Plesteran Dinding 1PC : 6PsStart: 7/21/14 ID: 365
Finish: 8/2/14 Dur: 12 days
Res:
Plesteran Beton 1PC : 3Ps Start: 7/21/14 ID: 366
Finish: 8/2/14 Dur: 12 days
Res:
AcianStart: 7/28/14 ID: 367
Finish: 8/9/14 Dur: 12 days
Res:
Benangan Sudut, Plinkolt & Start: 7/28/14 ID: 368
Finish: 8/9/14 Dur: 12 days
Res:
Water Proofing Plat terasStart: 7/28/14 ID: 369
Finish: 8/9/14 Dur: 12 days
Res:
V. PEKERJAAN PELAPIS LAStart: 8/25/14 ID: 370
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasang Keramik Lantai 40x4Start: 8/25/14 ID: 371
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Keramik Lantai 30x3Start: 8/25/14 ID: 372
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Keramik Tangga 30xStart: 8/25/14 ID: 373
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Keramik Dinding 25xStart: 8/25/14 ID: 374
Finish: 9/6/14 Dur: 12 days
Res:
VI. PEKERJAAN KUSEN PINStart: 7/14/14 ID: 375
Finish: 7/26/14 Dur: 12 days
Comp: 0%
Pasang Kusen Aluminium 4"Start: 7/14/14 ID: 376
Finish: 7/26/14 Dur: 12 days
Res:
Pasang Daun Pintu Double TStart: 7/14/14 ID: 377
Finish: 7/26/14 Dur: 12 days
Res:
Pasang Daun Jendela Kaca AStart: 7/14/14 ID: 378
Finish: 7/26/14 Dur: 12 days
Res:
Pasang kusen dan pintu KMStart: 7/14/14 ID: 379
Finish: 7/26/14 Dur: 12 days
Res:
Pasang Aksesoris AluminiumStart: 7/14/14 ID: 380
Finish: 7/26/14 Dur: 12 days
Res:
VII. PEKERJAAN PENGGANTStart: 9/1/14 ID: 381
Finish: 9/13/14 Dur: 12 days
Comp: 0%
Pasang Kunci PintuStart: 9/1/14 ID: 382
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Engsel Pintu 4"Start: 9/1/14 ID: 383
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Grendel TanamStart: 9/1/14 ID: 384
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Grendel Pintu BiasaStart: 9/1/14 ID: 385
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Engsel Jendela ModStart: 9/1/14 ID: 386
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Grendel JendelaStart: 9/1/14 ID: 387
Finish: 9/13/14 Dur: 12 days
Res:
Pasang Railling Tangga PipaStart: 9/1/14 ID: 388
Finish: 9/13/14 Dur: 12 days
Res:
VIII. PEKERJAAN PLAFONDStart: 8/4/14 ID: 389
Finish: 8/16/14 Dur: 12 days
Comp: 0%
Pasang Penutup Plafond GyStart: 8/4/14 ID: 390
Finish: 8/16/14 Dur: 12 days
Res:
Pasang Lis Gypsum 15 cmStart: 8/4/14 ID: 391
Finish: 8/16/14 Dur: 12 days
Res:
IX. PEKERJAAN SANITASIStart: 6/30/14 ID: 392
Finish: 7/26/14 Dur: 24 days
Comp: 0%
Pasang FloordrainStart: 6/30/14 ID: 393
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Kloset JongkokStart: 6/30/14 ID: 394
Finish: 7/26/14 Dur: 24 days
Res:
Pasang WastafelStart: 6/30/14 ID: 395
Finish: 7/26/14 Dur: 24 days
Res:
X. PEKERJAAN PENGECATAStart: 8/11/14 ID: 396
Finish: 8/23/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding ExterioStart: 8/11/14 ID: 397
Finish: 8/23/14 Dur: 12 days
Res:
Pengecatan Dinding InteriorStart: 8/11/14 ID: 398
Finish: 8/23/14 Dur: 12 days
Res:
Pengecatan PlafondStart: 8/11/14 ID: 399
Finish: 8/23/14 Dur: 12 days
Res:
Politur Daun PintuStart: 8/11/14 ID: 400
Finish: 8/23/14 Dur: 12 days
Res:
XI. PEKERJAAN SEPTICTANStart: 6/16/14 ID: 401
Finish: 7/19/14 Dur: 30 days
Comp: 0%
Galian TanahStart: 6/16/14 ID: 402
Finish: 6/28/14 Dur: 12 days
Res:
Urugan pasir urugStart: 6/16/14 ID: 403
Finish: 6/21/14 Dur: 6 days
Res:
Pas. IjukStart: 6/16/14 ID: 404
Finish: 6/21/14 Dur: 6 days
Res:
Pasir kerikilStart: 6/16/14 ID: 405
Finish: 6/21/14 Dur: 6 days
Res:
Lantai kerjaStart: 6/16/14 ID: 406
Finish: 6/21/14 Dur: 6 days
Res:
Pas. Bata merah 1:3Start: 6/16/14 ID: 407
Finish: 6/28/14 Dur: 12 days
Res:
Pas. Bata merah kosongStart: 6/16/14 ID: 408
Finish: 6/28/14 Dur: 12 days
Res:
Pekerjaan beton plat penutupStart: 6/23/14 ID: 409
Finish: 7/12/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 410
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 411
Finish: 7/12/14 Dur: 18 days
Res:
- BekistingStart: 6/23/14 ID: 412
Finish: 7/12/14 Dur: 18 days
Res:
Plesteran Start: 7/14/14 ID: 413
Finish: 7/19/14 Dur: 6 days
Res:
acianStart: 7/14/14 ID: 414
Finish: 7/19/14 Dur: 6 days
Res:
B.2 LANTAI 2Start: 8/11/14 ID: 415
Finish: 11/1/14 Dur: 72 days
Comp: 0%
I. PEKERJAAN TANAHStart: 10/6/14 ID: 416
Finish: 10/11/14 Dur: 6 days
Comp: 0%
Urugan Pasir Bawah lantaiStart: 10/6/14 ID: 417
Finish: 10/11/14 Dur: 6 days
Res:
II. PEKERJAAN BETONStart: 8/25/14 ID: 418
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Beton Kolom PraktisStart: 8/25/14 ID: 419
Finish: 9/6/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 420
Finish: 9/6/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 421
Finish: 9/6/14 Dur: 12 days
Res:
- BekistingStart: 8/25/14 ID: 422
Finish: 9/6/14 Dur: 12 days
Res:
Beton Balok Latei 15/20Start: 8/25/14 ID: 423
Finish: 9/6/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 424
Finish: 9/6/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 425
Finish: 9/6/14 Dur: 12 days
Res:
- BekistingStart: 8/25/14 ID: 426
Finish: 9/6/14 Dur: 12 days
Res:
III. PEKERJAAN PASANGANStart: 8/25/14 ID: 427
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 428
Finish: 9/6/14 Dur: 12 days
Res:
Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 429
Finish: 9/6/14 Dur: 12 days
Res:
IV. PEKERJAAN PLESTERAStart: 9/1/14 ID: 430
Finish: 9/20/14 Dur: 18 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 431
Finish: 9/13/14 Dur: 12 days
Res:
Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 432
Finish: 9/13/14 Dur: 12 days
Res:
Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 433
Finish: 9/13/14 Dur: 12 days
Res:
AcianStart: 9/8/14 ID: 434
Finish: 9/20/14 Dur: 12 days
Res:
Benangan Sudut, Plinkolt & Start: 9/8/14 ID: 435
Finish: 9/20/14 Dur: 12 days
Res:
Water Proofing Kanopi + potStart: 9/8/14 ID: 436
Finish: 9/20/14 Dur: 12 days
Res:
V. PEKERJAAN PELAPIS LAStart: 10/20/14 ID: 437
Finish: 11/1/14 Dur: 12 days
Comp: 0%
Pasang Keramik Lantai 40x4Start: 10/20/14 ID: 438
Finish: 11/1/14 Dur: 12 days
Res:
Pasang Keramik Lantai 30x3Start: 10/20/14 ID: 439
Finish: 11/1/14 Dur: 12 days
Res:
Pasang Keramik Tangga 30xStart: 10/20/14 ID: 440
Finish: 11/1/14 Dur: 12 days
Res:
Pasang Keramik Dinding 25xStart: 10/20/14 ID: 441
Finish: 11/1/14 Dur: 12 days
Res:
VI. PEKERJAAN KUSEN PINStart: 8/25/14 ID: 442
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasang Kusen Aluminium 4"Start: 8/25/14 ID: 443
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Daun Pintu Double TStart: 8/25/14 ID: 444
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Daun Jendela Kaca Start: 8/25/14 ID: 445
Finish: 9/6/14 Dur: 12 days
Res:
Pasang kusen dan pintu KMStart: 8/25/14 ID: 446
Finish: 9/6/14 Dur: 12 days
Res:
VII. PEKERJAAN PENGGANTStart: 10/13/14 ID: 447
Finish: 10/25/14 Dur: 12 days
Comp: 0%
Pasang Kunci PintuStart: 10/13/14 ID: 448
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Engsel Pintu 4"Start: 10/13/14 ID: 449
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel TanamStart: 10/13/14 ID: 450
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel Pintu BiasaStart: 10/13/14 ID: 451
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Engsel Jendela ModStart: 10/13/14 ID: 452
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel JendelaStart: 10/13/14 ID: 453
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Railling Tangga PipaStart: 10/13/14 ID: 454
Finish: 10/25/14 Dur: 12 days
Res:
VII. PEKERJAAN PLAFONDStart: 9/29/14 ID: 455
Finish: 10/11/14 Dur: 12 days
Comp: 0%
Pasang Penutup Plafond GyStart: 9/29/14 ID: 456
Finish: 10/11/14 Dur: 12 days
Res:
Pasang Lis Gypsum 12 cmStart: 9/29/14 ID: 457
Finish: 10/11/14 Dur: 12 days
Res:
VIII. PEKERJAAN SANITASIStart: 8/11/14 ID: 458
Finish: 9/6/14 Dur: 24 days
Comp: 0%
Pasang FloordrainStart: 8/11/14 ID: 459
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kloset JongkokStart: 8/11/14 ID: 460
Finish: 9/6/14 Dur: 24 days
Res:
Pasang WastafelStart: 8/11/14 ID: 461
Finish: 9/6/14 Dur: 24 days
Res:
IX. PEKERJAAN PENGECATAStart: 10/6/14 ID: 462
Finish: 10/18/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding ExterioStart: 10/6/14 ID: 463
Finish: 10/18/14 Dur: 12 days
Res:
Pengecatan Dinding InteriorStart: 10/6/14 ID: 464
Finish: 10/18/14 Dur: 12 days
Res:
Pengecatan PlafondStart: 10/6/14 ID: 465
Finish: 10/18/14 Dur: 12 days
Res:
Politur Daun PintuStart: 10/6/14 ID: 466
Finish: 10/18/14 Dur: 12 days
Res:
B.3 LANTAI 3Start: 9/22/14 ID: 467
Finish: 12/13/14 Dur: 72 days
Comp: 0%
I. PEKERJAAN TANAHStart: 11/17/14 ID: 468
Finish: 11/22/14 Dur: 6 days
Comp: 0%
Urugan Pasir Bawah lantaiStart: 11/17/14 ID: 469
Finish: 11/22/14 Dur: 6 days
Res:
II. PEKERJAAN BETONStart: 10/6/14 ID: 470
Finish: 10/18/14 Dur: 12 days
Comp: 0%
Beton Kolom PraktisStart: 10/6/14 ID: 471
Finish: 10/18/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 10/6/14 ID: 472
Finish: 10/18/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 10/6/14 ID: 473
Finish: 10/18/14 Dur: 12 days
Res:
- BekistingStart: 10/6/14 ID: 474
Finish: 10/18/14 Dur: 12 days
Res:
Beton Balok Latei 15/20Start: 10/6/14 ID: 475
Finish: 10/18/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 10/6/14 ID: 476
Finish: 10/18/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 10/6/14 ID: 477
Finish: 10/18/14 Dur: 12 days
Res:
- BekistingStart: 10/6/14 ID: 478
Finish: 10/18/14 Dur: 12 days
Res:
III. PEKERJAAN PASANGANStart: 10/6/14 ID: 479
Finish: 10/18/14 Dur: 12 days
Comp: 0%
Pasangan Batu Merah 1/2 baStart: 10/6/14 ID: 480
Finish: 10/18/14 Dur: 12 days
Res:
Pasangan Batu Merah 1/2 baStart: 10/6/14 ID: 481
Finish: 10/18/14 Dur: 12 days
Res:
IV. PEKERJAAN PLESTERAStart: 10/13/14 ID: 482
Finish: 11/1/14 Dur: 18 days
Plesteran Dinding 1PC : 3PsStart: 10/13/14 ID: 483
Finish: 10/25/14 Dur: 12 days
Plesteran Dinding 1PC : 6PsStart: 10/13/14 ID: 484
Finish: 10/25/14 Dur: 12 days
Page 3
-
Comp: 0% Res: Res:
Plesteran Beton 1PC : 3Ps Start: 10/13/14 ID: 485
Finish: 10/25/14 Dur: 12 days
Res:
AcianStart: 10/20/14 ID: 486
Finish: 11/1/14 Dur: 12 days
Res:
Benangan Sudut, Plinkolt & Start: 10/20/14 ID: 487
Finish: 11/1/14 Dur: 12 days
Res:
Water Proofing Kanopi + potStart: 10/20/14 ID: 488
Finish: 11/1/14 Dur: 12 days
Res:
V. PEKERJAAN PELAPIS LAStart: 12/1/14 ID: 489
Finish: 12/13/14 Dur: 12 days
Comp: 0%
Pasang Keramik Lantai 40x4Start: 12/1/14 ID: 490
Finish: 12/13/14 Dur: 12 days
Res:
Pasang Keramik Lantai 30x3Start: 12/1/14 ID: 491
Finish: 12/13/14 Dur: 12 days
Res:
Pasang Keramik Dinding 25xStart: 12/1/14 ID: 492
Finish: 12/13/14 Dur: 12 days
Res:
VI. PEKERJAAN KUSEN PINTStart: 10/6/14 ID: 493
Finish: 10/18/14 Dur: 12 days
Comp: 0%
Pasang Kusen Aluminium 4"Start: 10/6/14 ID: 494
Finish: 10/18/14 Dur: 12 days
Res:
Pasang Daun Pintu Double TStart: 10/6/14 ID: 495
Finish: 10/18/14 Dur: 12 days
Res:
Pasang Daun Jendela Kaca Start: 10/6/14 ID: 496
Finish: 10/18/14 Dur: 12 days
Res:
Pasang kusen dan pintu KMStart: 10/6/14 ID: 497
Finish: 10/18/14 Dur: 12 days
Res:
VII. PEKERJAAN PENGGANTStart: 11/24/14 ID: 498
Finish: 12/6/14 Dur: 12 days
Comp: 0%
Pasang Kunci PintuStart: 11/24/14 ID: 499
Finish: 12/6/14 Dur: 12 days
Res:
Pasang Engsel Pintu 4"Start: 11/24/14 ID: 500
Finish: 12/6/14 Dur: 12 days
Res:
Pasang Grendel TanamStart: 11/24/14 ID: 501
Finish: 12/6/14 Dur: 12 days
Res:
Pasang Grendel Pintu BiasaStart: 11/24/14 ID: 502
Finish: 12/6/14 Dur: 12 days
Res:
Pasang Engsel Jendela ModStart: 11/24/14 ID: 503
Finish: 12/6/14 Dur: 12 days
Res:
Pasang Grendel JendelaStart: 11/24/14 ID: 504
Finish: 12/6/14 Dur: 12 days
Res:
VIII. PEKERJAAN SANITASIStart: 9/22/14 ID: 505
Finish: 10/18/14 Dur: 24 days
Comp: 0%
Pasang FloordrainStart: 9/22/14 ID: 506
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Kloset JongkokStart: 9/22/14 ID: 507
Finish: 10/18/14 Dur: 24 days
Res:
Pasang WastafelStart: 9/22/14 ID: 508
Finish: 10/18/14 Dur: 24 days
Res:
IX. PEKERJAAN PENGECATStart: 11/17/14 ID: 509
Finish: 11/29/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding ExterioStart: 11/17/14 ID: 510
Finish: 11/29/14 Dur: 12 days
Res:
Pengecatan Dinding InteriorStart: 11/17/14 ID: 511
Finish: 11/29/14 Dur: 12 days
Res:
Pengecatan PlafondStart: 11/17/14 ID: 512
Finish: 11/29/14 Dur: 12 days
Res:
Politur Daun PintuStart: 11/17/14 ID: 513
Finish: 11/29/14 Dur: 12 days
Res:
X. PEKERJAAN PLAFONDStart: 11/10/14 ID: 514
Finish: 11/22/14 Dur: 12 days
Comp: 0%
Pasang Penutup Plafond GyStart: 11/10/14 ID: 515
Finish: 11/22/14 Dur: 12 days
Res:
Pasang Lis Gypsum 15 cmStart: 11/10/14 ID: 516
Finish: 11/22/14 Dur: 12 days
Res:
XI. PEKERJAAN ATAPStart: 10/13/14 ID: 517
Finish: 11/8/14 Dur: 24 days
Comp: 0%
Kuda-kuda WF-200.204.12.12Start: 10/13/14 ID: 518
Finish: 11/8/14 Dur: 24 days
Res:
Gording C-150,50,20,3,2Start: 10/13/14 ID: 519
Finish: 11/8/14 Dur: 24 days
Res:
Batang Tarik f 16 mmStart: 10/13/14 ID: 520
Finish: 11/8/14 Dur: 24 days
Res:
Ikatan Angin f 16 mmStart: 10/13/14 ID: 521
Finish: 11/8/14 Dur: 24 days
Res:
Jarum KerasStart: 10/13/14 ID: 522
Finish: 11/8/14 Dur: 24 days
Res:
Baja Siku Penopang GordingStart: 10/13/14 ID: 523
Finish: 11/8/14 Dur: 24 days
Res:
Plat Plendes, Simpul, StiffneStart: 10/13/14 ID: 524
Finish: 11/8/14 Dur: 24 days
Res:
Angkur Baut HTB 16Start: 10/13/14 ID: 525
Finish: 11/8/14 Dur: 24 days
Res:
Mur Baut HTB 16Start: 10/13/14 ID: 526
Finish: 11/8/14 Dur: 24 days
Res:
PengelasanStart: 10/13/14 ID: 527
Finish: 11/8/14 Dur: 24 days
Res:
Usuk reng galvalumStart: 10/13/14 ID: 528
Finish: 11/8/14 Dur: 24 days
Res:
Penutup Atap genteng keramStart: 10/13/14 ID: 529
Finish: 11/8/14 Dur: 24 days
Res:
Lisplank double 3/25Start: 10/13/14 ID: 530
Finish: 11/8/14 Dur: 24 days
Res:
Papan Reuter 3/30Start: 10/13/14 ID: 531
Finish: 11/8/14 Dur: 24 days
Res:
BubunganStart: 10/13/14 ID: 532
Finish: 11/8/14 Dur: 24 days
Res:
C. PEKERJAAN PLUMBINGStart: 6/30/14 ID: 533
Finish: 10/18/14 Dur: 96 days
Comp: 0%
C.1 LANTAI IStart: 6/30/14 ID: 534
Finish: 7/26/14 Dur: 24 days
Comp: 0%
Pasang Pipa Pengisi TandonStart: 6/30/14 ID: 535
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Pipa Induk DistribusStart: 6/30/14 ID: 536
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Pipa Air Bersih PVCStart: 6/30/14 ID: 537
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 6/30/14 ID: 538
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 6/30/14 ID: 539
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Pipa Induk Air KotorStart: 6/30/14 ID: 540
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Talang tegak PVC TyStart: 6/30/14 ID: 541
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Stop Kran dia 1" Start: 6/30/14 ID: 542
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Kran dia 1/2" DUPONStart: 6/30/14 ID: 543
Finish: 7/26/14 Dur: 24 days
Res:
Pasang Kran wastafel 1/2"Start: 6/30/14 ID: 544
Finish: 7/26/14 Dur: 24 days
Res:
Sumur Bor (Lengkap AksesoStart: 6/30/14 ID: 545
Finish: 7/26/14 Dur: 24 days
Res:
C.2 LANTAI 2Start: 8/11/14 ID: 546
Finish: 9/6/14 Dur: 24 days
Comp: 0%
Pasang Pipa Pengisi TandonStart: 8/11/14 ID: 547
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Induk DistribusStart: 8/11/14 ID: 548
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Bersih PVCStart: 8/11/14 ID: 549
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 550
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 551
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Induk Air KotorStart: 8/11/14 ID: 552
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Talang tegak PVC TyStart: 8/11/14 ID: 553
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Stop Kran dia 1" Start: 8/11/14 ID: 554
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kran dia 1/2" DUPONStart: 8/11/14 ID: 555
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kran wastafel 1/2"Start: 8/11/14 ID: 556
Finish: 9/6/14 Dur: 24 days
Res:
C.3 LANTAI 3Start: 9/22/14 ID: 557
Finish: 10/18/14 Dur: 24 days
Comp: 0%
Pasang Pipa Induk DistribusStart: 9/22/14 ID: 558
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Pipa Air Bersih PVCStart: 9/22/14 ID: 559
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 9/22/14 ID: 560
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 9/22/14 ID: 561
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Talang tegak PVC TyStart: 9/22/14 ID: 562
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Stop Kran dia 1" Start: 9/22/14 ID: 563
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Kran dia 1/2" DUPONStart: 9/22/14 ID: 564
Finish: 10/18/14 Dur: 24 days
Res:
Pasang Kran wastafel 1/2"Start: 9/22/14 ID: 565
Finish: 10/18/14 Dur: 24 days
Res:
Tandon Air 4000 L SteinlessStart: 9/22/14 ID: 566
Finish: 10/18/14 Dur: 24 days
Res:
D. PEKERJAAN LISTRIKStart: 6/30/14 ID: 567
Finish: 11/1/14 Dur: 108 days
Comp: 0%
D.1 LANTAI IStart: 6/30/14 ID: 568
Finish: 8/9/14 Dur: 36 days
Comp: 0%
Titik Instalasi Penerangan (NStart: 6/30/14 ID: 569
Finish: 8/9/14 Dur: 36 days
Res:
Titik Instalasi Stop Kontak (NStart: 6/30/14 ID: 570
Finish: 8/9/14 Dur: 36 days
Res:
Saklar tunggalStart: 6/30/14 ID: 571
Finish: 8/9/14 Dur: 36 days
Res:
Saklar SeriStart: 6/30/14 ID: 572
Finish: 8/9/14 Dur: 36 days
Res:
Lampu PLC 24 watt + fittingStart: 6/30/14 ID: 573
Finish: 8/9/14 Dur: 36 days
Res:
Stop kontak 200 VAStart: 6/30/14 ID: 574
Finish: 8/9/14 Dur: 36 days
Res:
Pasang Panel Lantai IStart: 6/30/14 ID: 575
Finish: 8/9/14 Dur: 36 days
Res:
PentanahanStart: 6/30/14 ID: 576
Finish: 8/9/14 Dur: 36 days
Res:
Pasang Kabel induk NYY 4x4Start: 6/30/14 ID: 577
Finish: 8/9/14 Dur: 36 days
Res:
Pemasangan Panel Listrik BStart: 6/30/14 ID: 578
Finish: 8/9/14 Dur: 36 days
Res:
D.2 LANTAI IIStart: 8/11/14 ID: 579
Finish: 9/20/14 Dur: 36 days
Comp: 0%
Titik Instalasi Penerangan (NStart: 8/11/14 ID: 580
Finish: 9/20/14 Dur: 36 days
Res:
Titik Instalasi Stop Kontak (NStart: 8/11/14 ID: 581
Finish: 9/20/14 Dur: 36 days
Res:
Saklar tunggalStart: 8/11/14 ID: 582
Finish: 9/20/14 Dur: 36 days
Res:
Saklar SeriStart: 8/11/14 ID: 583
Finish: 9/20/14 Dur: 36 days
Res:
Lampu PLC 24 watt + fittingStart: 8/11/14 ID: 584
Finish: 9/20/14 Dur: 36 days
Res:
Stop kontak 200 VAStart: 8/11/14 ID: 585
Finish: 9/20/14 Dur: 36 days
Res:
Pasang Panel Lantai 2Start: 8/11/14 ID: 586
Finish: 9/20/14 Dur: 36 days
Res:
Pasang Kabel induk NYY 4x4
Page 4
-
Start: 8/11/14 ID: 587
Finish: 9/20/14 Dur: 36 days
Res:
D.3 LANTAI IIIStart: 9/22/14 ID: 588
Finish: 11/1/14 Dur: 36 days
Comp: 0%
Titik Instalasi Penerangan (NStart: 9/22/14 ID: 589
Finish: 11/1/14 Dur: 36 days
Res:
Titik Instalasi Stop Kontak (NStart: 9/22/14 ID: 590
Finish: 11/1/14 Dur: 36 days
Res:
Saklar tunggalStart: 9/22/14 ID: 591
Finish: 11/1/14 Dur: 36 days
Res:
Saklar SeriStart: 9/22/14 ID: 592
Finish: 11/1/14 Dur: 36 days
Res:
Lampu PLC 24 watt + fittingStart: 9/22/14 ID: 593
Finish: 11/1/14 Dur: 36 days
Res:
Stop kontak 200 VAStart: 9/22/14 ID: 594
Finish: 11/1/14 Dur: 36 days
Res:
Pasang Panel Lantai 3Start: 9/22/14 ID: 595
Finish: 11/1/14 Dur: 36 days
Res:
Penangkal petir Start: 9/22/14 ID: 596
Finish: 11/1/14 Dur: 36 days
Res:
Pasang Kabel induk NYY 4x4Start: 9/22/14 ID: 597
Finish: 11/1/14 Dur: 36 days
Res:
PAGAR dan TURAPStart: 5/19/14 ID: 599
Finish: 10/4/14 Dur: 120 days
Comp: 0%
I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 600
Finish: 5/24/14 Dur: 6 days
Comp: 0%
Pembersihan LokasiStart: 5/19/14 ID: 601
Finish: 5/24/14 Dur: 6 days
Res:
Uitset / BowplankStart: 5/19/14 ID: 602
Finish: 5/24/14 Dur: 6 days
Res:
II. PEKERJAAN TANAHStart: 6/16/14 ID: 603
Finish: 7/26/14 Dur: 36 days
Comp: 0%
Galian Tanah lubang PondasStart: 6/16/14 ID: 604
Finish: 6/28/14 Dur: 12 days
Res:
Urugan Tanah Bekas GalianStart: 7/21/14 ID: 605
Finish: 7/26/14 Dur: 6 days
Res:
Urugan Pasir Bawah PondasStart: 6/16/14 ID: 606
Finish: 6/28/14 Dur: 12 days
Res:
Buang Tanah Bekas GalianStart: 6/30/14 ID: 607
Finish: 7/5/14 Dur: 6 days
Res:
III. PEKERJAAN BETONStart: 6/30/14 ID: 608
Finish: 8/30/14 Dur: 54 days
Comp: 0%
Beton Lantai Kerja t = 5 cmStart: 6/30/14 ID: 609
Finish: 7/5/14 Dur: 6 days
Res:
Beton Strouss f 20 cmStart: 6/30/14 ID: 610
Finish: 7/5/14 Dur: 6 days
Res:
Beton Foot Plat 1.00x1.00mStart: 6/30/14 ID: 611
Finish: 7/19/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/14/14 ID: 612
Finish: 7/19/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/30/14 ID: 613
Finish: 7/19/14 Dur: 18 days
Res:
- BekistingStart: 6/30/14 ID: 614
Finish: 7/19/14 Dur: 18 days
Res:
Beton Sloof 15/20Start: 7/21/14 ID: 615
Finish: 8/9/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/4/14 ID: 616
Finish: 8/9/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/21/14 ID: 617
Finish: 8/9/14 Dur: 18 days
Res:
- BekistingStart: 7/21/14 ID: 618
Finish: 8/9/14 Dur: 18 days
Res:
Beton Kolom Praktis 30/30Start: 7/21/14 ID: 619
Finish: 8/9/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/4/14 ID: 620
Finish: 8/9/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/21/14 ID: 621
Finish: 8/9/14 Dur: 18 days
Res:
- BekistingStart: 7/21/14 ID: 622
Finish: 8/9/14 Dur: 18 days
Res:
Beton Balok 15/20Start: 8/11/14 ID: 623
Finish: 8/30/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 624
Finish: 8/30/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/11/14 ID: 625
Finish: 8/30/14 Dur: 18 days
Res:
- BekistingStart: 8/11/14 ID: 626
Finish: 8/30/14 Dur: 18 days
Res:
Beton Balok 15/15Start: 8/11/14 ID: 627
Finish: 8/30/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 628
Finish: 8/30/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/11/14 ID: 629
Finish: 8/30/14 Dur: 18 days
Res:
- BekistingStart: 8/11/14 ID: 630
Finish: 8/30/14 Dur: 18 days
Res:
Saluran BetonStart: 7/21/14 ID: 631
Finish: 8/9/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/4/14 ID: 632
Finish: 8/9/14 Dur: 6 days
Res:
- BekistingStart: 7/21/14 ID: 633
Finish: 8/9/14 Dur: 18 days
Res:
IV. PEKERJAAN PASANGANStart: 8/11/14 ID: 634
Finish: 8/30/14 Dur: 18 days
Comp: 0%
Pasangan Batu Belah 1 PC :Start: 8/11/14 ID: 635
Finish: 8/30/14 Dur: 18 days
Res:
Pasangan Batu Merah 1/2 baStart: 8/11/14 ID: 636
Finish: 8/30/14 Dur: 18 days
Res:
Pasangan Batu Merah 1/2 baStart: 8/11/14 ID: 637
Finish: 8/30/14 Dur: 18 days
Res:
Pasangan Batu Alur Start: 8/11/14 ID: 638
Finish: 8/30/14 Dur: 18 days
Res:
V. PEKERJAAN PLESTERANStart: 9/1/14 ID: 639
Finish: 9/20/14 Dur: 18 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 640
Finish: 9/20/14 Dur: 18 days
Res:
Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 641
Finish: 9/20/14 Dur: 18 days
Res:
Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 642
Finish: 9/20/14 Dur: 18 days
Res:
Plesteran CipratStart: 9/1/14 ID: 643
Finish: 9/20/14 Dur: 18 days
Res:
AcianStart: 9/1/14 ID: 644
Finish: 9/20/14 Dur: 18 days
Res:
Setrikan / SiarStart: 9/1/14 ID: 645
Finish: 9/20/14 Dur: 18 days
Res:
Benangan SudutStart: 9/1/14 ID: 646
Finish: 9/20/14 Dur: 18 days
Res:
VI. PEKERJAAN BESIStart: 9/1/14 ID: 647
Finish: 9/20/14 Dur: 18 days
Comp: 0%
Tiang Kawat Duri L-50.50.5Start: 9/1/14 ID: 648
Finish: 9/20/14 Dur: 18 days
Res:
Kawat Duri 5 LapisStart: 9/1/14 ID: 649
Finish: 9/20/14 Dur: 18 days
Res:
VII. PEKERJAAN PENGECATStart: 9/22/14 ID: 650
Finish: 10/4/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding denganStart: 9/22/14 ID: 651
Finish: 10/4/14 Dur: 12 days
Res:
PENGURUGANStart: 5/19/14 ID: 653
Finish: 5/31/14 Dur: 12 days
Comp: 0%
A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 654
Finish: 5/31/14 Dur: 12 days
Comp: 0%
A.1 LANTAI 1Start: 5/19/14 ID: 655
Finish: 5/31/14 Dur: 12 days
Comp: 0%
I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 656
Finish: 5/31/14 Dur: 12 days
Comp: 0%
Pembongkaran Bangunan LaStart: 5/19/14 ID: 657
Finish: 5/31/14 Dur: 12 days
Res:
Pembersihan LokasiStart: 5/19/14 ID: 658
Finish: 5/31/14 Dur: 12 days
Res:
II. PEKERJAAN TANAHStart: 5/19/14 ID: 659
Finish: 5/31/14 Dur: 12 days
Comp: 0%
Urugan SirtuStart: 5/19/14 ID: 660
Finish: 5/31/14 Dur: 12 days
Res:
PemadatanStart: 5/19/14 ID: 661
Finish: 5/31/14 Dur: 12 days
Res:
LAPANGAN BASKETStart: 5/19/14 ID: 663
Finish: 8/23/14 Dur: 84 days
Comp: 0%
I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 664
Finish: 5/24/14 Dur: 6 days
Comp: 0%
Uitset / BowplankStart: 5/19/14 ID: 665
Finish: 5/24/14 Dur: 6 days
Res:
II. PEKERJAAN TANAHStart: 6/16/14 ID: 666
Finish: 7/26/14 Dur: 36 days
Comp: 0%
Galian Tanah Start: 6/16/14 ID: 667
Finish: 6/28/14 Dur: 12 days
Res:
Urugan Tanah Bekas GalianStart: 7/21/14 ID: 668
Finish: 7/26/14 Dur: 6 days
Res:
Urugan Pasir Bawah PondasStart: 6/16/14 ID: 669
Finish: 6/28/14 Dur: 12 days
Res:
Buang Tanah Bekas GalianStart: 6/30/14 ID: 670
Finish: 7/5/14 Dur: 6 days
Res:
III. PEKERJAAN PASANGANStart: 7/21/14 ID: 671
Finish: 8/9/14 Dur: 18 days
Comp: 0%
Pasangan AanstampengStart: 7/21/14 ID: 672
Finish: 8/9/14 Dur: 18 days
Res:
Pasangan Bt Belah 1 Pc : 6 PStart: 7/21/14 ID: 673
Finish: 8/9/14 Dur: 18 days
Res:
Pasangan Batu Tempel DiagStart: 7/21/14 ID: 674
Finish: 8/9/14 Dur: 18 days
Res:
Pasangan Buis Beton Dia. 30Start: 7/21/14 ID: 675
Finish: 8/9/14 Dur: 18 days
Res:
Pasangan Paving Persegi K-Start: 7/21/14 ID: 676
Finish: 8/9/14 Dur: 18 days
Res:
IV. PEKERJAAN BETONStart: 6/30/14 ID: 677
Finish: 8/9/14 Dur: 36 days
Comp: 0%
Beton Lantai Kerja t = 5 cmStart: 6/30/14 ID: 678
Finish: 7/5/14 Dur: 6 days
Res:
Beton PoerStart: 6/30/14 ID: 679
Finish: 7/19/14 Dur: 18 days
Comp: 0%
- Pile cap type 1Start: 6/30/14 ID: 680
Finish: 7/19/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/14/14 ID: 681
Finish: 7/19/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/30/14 ID: 682
Finish: 7/19/14 Dur: 18 days
Res:
- BekistingStart: 6/30/14 ID: 683
Finish: 7/19/14 Dur: 18 days
Res:
Beton Balok 20/30Start: 6/30/14 ID: 684
Finish: 7/19/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/14/14 ID: 685
Finish: 7/19/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/30/14 ID: 686
Finish: 7/19/14 Dur: 18 days
Res:
- BekistingStart: 6/30/14 ID: 687
Finish: 7/19/14 Dur: 18 days
Res:
Beton Plat Lantai t = 10 cmStart: 7/21/14 ID: 688
Finish: 8/9/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/4/14 ID: 689
Finish: 8/9/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 7/21/14 ID: 690
Finish: 8/9/14 Dur: 18 days
Res:
- BekistingStart: 7/21/14 ID: 691
Finish: 8/9/14 Dur: 18 days
Res:
V. PEKERJAAN PLESTERANStart: 8/11/14 ID: 692
Finish: 8/16/14 Dur: 6 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 8/11/14 ID: 693
Finish: 8/16/14 Dur: 6 days
Res:
VI. PEKERJAAN PENGECATAStart: 8/18/14 ID: 694
Finish: 8/23/14 Dur: 6 days
Comp: 0%
Pengecatan LapanganStart: 8/18/14 ID: 695
Finish: 8/23/14 Dur: 6 days
Res:
GEDUNG EStart: 5/19/14 ID: 697
Finish: 12/13/14 Dur: 180 days
Comp: 0%
A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 698
Finish: 12/13/14 Dur: 180 days
Comp: 0%
A.1 LANTAI 1Start: 5/19/14 ID: 699
Finish: 12/13/14 Dur: 180 days
Comp: 0%
I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 700
Finish: 12/13/14 Dur: 180 days
Comp: 0%
Pembersihan LokasiStart: 5/19/14 ID: 701
Finish: 5/31/14 Dur: 12 days
Res:
Pembersihan AkhirStart: 12/1/14 ID: 702
Finish: 12/13/14 Dur: 12 days
Res:
A.2 LANTAI 2Start: 8/4/14 ID: 703
Finish: 9/13/14 Dur: 36 days
Comp: 0%
I. PEKERJAAN BETONStart: 8/4/14 ID: 704
Finish: 9/13/14 Dur: 36 days
Comp: 0%
1. Beton KolomStart: 8/4/14 ID: 705
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Type K1 - 40/50Start: 8/4/14 ID: 706
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 707
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 708
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 709
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 710
Finish: 8/23/14 Dur: 18 days
Res:
- Type K2 - 30/30Start: 8/4/14 ID: 711
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 712
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 714
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 715
Finish: 8/23/14 Dur: 18 days
Res:
- Type K3 - 20/80Start: 8/4/14 ID: 716
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 717
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 718
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 719
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 720
Finish: 8/23/14 Dur: 18 days
Res:
- Type K4 - 20/60Start: 8/4/14 ID: 721
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 722
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 723
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 724
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 725
Finish: 8/23/14 Dur: 18 days
Res:
2. Beton BalokStart: 8/25/14 ID: 726
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Type BLT - 15/20Start: 8/25/14 ID: 727
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 728
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 729
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 730
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 731
Finish: 9/13/14 Dur: 18 days
Res:
- Type BLK - 15/20Start: 8/25/14 ID: 732
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 733
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 734
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 735
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 736
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL - 20/40Start: 8/25/14 ID: 737
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 738
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 739
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 740
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 741
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL1- 30/60Start: 8/25/14 ID: 742
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 743
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 744
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 745
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 746
Finish: 9/13/14 Dur: 18 days
Res:
- Type BL2- 30/40Start: 8/25/14 ID: 747
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 748
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 749
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 750
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 751
Finish: 9/13/14 Dur: 18 days
Res:
- Type BA1 - 20/30Start: 8/25/14 ID: 752
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 753
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 754
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 755
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 756
Finish: 9/13/14 Dur: 18 days
Res:
- Type BA2 - 15/25Start: 8/25/14 ID: 757
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 758
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/25/14 ID: 759
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 760
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 761
Finish: 9/13/14 Dur: 18 days
Res:
3. Beton Plat Lantai 3Start: 8/25/14 ID: 762
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 763
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 764
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 765
Finish: 9/13/14 Dur: 18 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 713
Finish: 8/23/14 Dur: 18 days
Res:
Page 5
-
4. Beton Plat KanopiStart: 8/25/14 ID: 766
Finish: 9/13/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 9/8/14 ID: 767
Finish: 9/13/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 768
Finish: 9/13/14 Dur: 18 days
Res:
- BekistingStart: 8/25/14 ID: 769
Finish: 9/13/14 Dur: 18 days
Res:
5. Beton TanggaStart: 8/4/14 ID: 770
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton Plat TanggaStart: 8/4/14 ID: 771
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 772
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 773
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 774
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Balok BordesStart: 8/4/14 ID: 775
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 776
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan DeformStart: 8/4/14 ID: 777
Finish: 8/23/14 Dur: 18 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 778
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 779
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Plat BordesStart: 8/4/14 ID: 780
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 781
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 782
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 783
Finish: 8/23/14 Dur: 18 days
Res:
- Beton Anak TanggaStart: 8/4/14 ID: 784
Finish: 8/23/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 8/18/14 ID: 785
Finish: 8/23/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 8/4/14 ID: 786
Finish: 8/23/14 Dur: 18 days
Res:
- BekistingStart: 8/4/14 ID: 787
Finish: 8/23/14 Dur: 18 days
Res:
B. PEKERJAAN ARSITEKTUStart: 5/19/14 ID: 788
Finish: 10/25/14 Dur: 138 days
Comp: 0%
XI. PEKERJAAN SEPTICTANStart: 5/19/14 ID: 789
Finish: 7/19/14 Dur: 54 days
Comp: 0%
Galian TanahStart: 5/19/14 ID: 790
Finish: 5/31/14 Dur: 12 days
Res:
Urugan pasir urugStart: 5/19/14 ID: 791
Finish: 5/24/14 Dur: 6 days
Res:
Pas. IjukStart: 6/16/14 ID: 792
Finish: 6/21/14 Dur: 6 days
Res:
Pasir kerikilStart: 6/16/14 ID: 793
Finish: 6/21/14 Dur: 6 days
Res:
Lantai kerjaStart: 6/16/14 ID: 794
Finish: 6/21/14 Dur: 6 days
Res:
Pas. Bata merah 1:3Start: 6/16/14 ID: 795
Finish: 6/28/14 Dur: 12 days
Res:
Pas. Bata merah kosongStart: 6/16/14 ID: 796
Finish: 6/28/14 Dur: 12 days
Res:
Pekerjaan beton plat penutupStart: 6/23/14 ID: 797
Finish: 7/12/14 Dur: 18 days
Comp: 0%
- Beton K-250Start: 7/7/14 ID: 798
Finish: 7/12/14 Dur: 6 days
Res:
- Baja Tulangan PolosStart: 6/23/14 ID: 799
Finish: 7/12/14 Dur: 18 days
Res:
- BekistingStart: 6/23/14 ID: 800
Finish: 7/12/14 Dur: 18 days
Res:
Plesteran Start: 7/14/14 ID: 801
Finish: 7/19/14 Dur: 6 days
Res:
acianStart: 7/14/14 ID: 802
Finish: 7/19/14 Dur: 6 days
Res:
B.2 LANTAI 2Start: 8/11/14 ID: 803
Finish: 10/25/14 Dur: 66 days
Comp: 0%
I. PEKERJAAN TANAHStart: 10/6/14 ID: 804
Finish: 10/11/14 Dur: 6 days
Comp: 0%
Urugan Pasir Bawah lantaiStart: 10/6/14 ID: 805
Finish: 10/11/14 Dur: 6 days
Res:
II. PEKERJAAN BETONStart: 8/25/14 ID: 806
Finish: 9/6/14 Dur: 12 days
Comp: 0%
1. Beton Kolom PraktisStart: 8/25/14 ID: 807
Finish: 9/6/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 808
Finish: 9/6/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 809
Finish: 9/6/14 Dur: 12 days
Res:
- BekistingStart: 8/25/14 ID: 810
Finish: 9/6/14 Dur: 12 days
Res:
2. Beton Balok Latei 15/20Start: 8/25/14 ID: 811
Finish: 9/6/14 Dur: 12 days
Comp: 0%
- Beton K-250Start: 8/25/14 ID: 812
Finish: 9/6/14 Dur: 12 days
Res:
- Baja Tulangan PolosStart: 8/25/14 ID: 813
Finish: 9/6/14 Dur: 12 days
Res:
- BekistingStart: 8/25/14 ID: 814
Finish: 9/6/14 Dur: 12 days
Res:
III. PEKERJAAN PASANGANStart: 8/25/14 ID: 815
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 816
Finish: 9/6/14 Dur: 12 days
Res:
Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 817
Finish: 9/6/14 Dur: 12 days
Res:
IV. PEKERJAAN PLESTERAStart: 9/1/14 ID: 818
Finish: 9/20/14 Dur: 18 days
Comp: 0%
Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 819
Finish: 9/13/14 Dur: 12 days
Res:
Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 820
Finish: 9/13/14 Dur: 12 days
Res:
Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 821
Finish: 9/13/14 Dur: 12 days
Res:
AcianStart: 9/8/14 ID: 822
Finish: 9/20/14 Dur: 12 days
Res:
Benangan Sudut, Plinkolt & Start: 9/8/14 ID: 823
Finish: 9/20/14 Dur: 12 days
Res:
Water Proofing Kanopi + potStart: 9/8/14 ID: 824
Finish: 9/20/14 Dur: 12 days
Res:
V. PEKERJAAN PELAPIS LAStart: 10/13/14 ID: 825
Finish: 10/25/14 Dur: 12 days
Comp: 0%
Pasang Keramik Lantai 40x4Start: 10/13/14 ID: 826
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Keramik Lantai 30x3Start: 10/13/14 ID: 827
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Keramik Tangga 30xStart: 10/13/14 ID: 828
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Keramik Dinding 25xStart: 10/13/14 ID: 829
Finish: 10/25/14 Dur: 12 days
Res:
VI. PEKERJAAN KUSEN PINTStart: 8/25/14 ID: 830
Finish: 9/6/14 Dur: 12 days
Comp: 0%
Pasang kusen dan pintu KMStart: 8/25/14 ID: 831
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Daun Pintu Double TStart: 8/25/14 ID: 832
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Daun jendela DoubleStart: 8/25/14 ID: 833
Finish: 9/6/14 Dur: 12 days
Res:
Pasang Kusen dan Pintu KM/Start: 8/25/14 ID: 834
Finish: 9/6/14 Dur: 12 days
Res:
VII. PEKERJAAN PENGGANTStart: 10/13/14 ID: 835
Finish: 10/25/14 Dur: 12 days
Comp: 0%
Pasang Kunci PintuStart: 10/13/14 ID: 836
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Engsel Pintu 4"Start: 10/13/14 ID: 837
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel TanamStart: 10/13/14 ID: 838
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel Pintu BiasaStart: 10/13/14 ID: 839
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Engsel Jendela ModStart: 10/13/14 ID: 840
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Grendel JendelaStart: 10/13/14 ID: 841
Finish: 10/25/14 Dur: 12 days
Res:
Pasang Railling Tangga PipaStart: 10/13/14 ID: 842
Finish: 10/25/14 Dur: 12 days
Res:
VII. PEKERJAAN PLAFONDStart: 9/29/14 ID: 843
Finish: 10/11/14 Dur: 12 days
Comp: 0%
Pasang Penutup Plafond GyStart: 9/29/14 ID: 844
Finish: 10/11/14 Dur: 12 days
Res:
Pasang Lis Gypsum 12 cmStart: 9/29/14 ID: 845
Finish: 10/11/14 Dur: 12 days
Res:
VIII. PEKERJAAN SANITASIStart: 8/11/14 ID: 846
Finish: 9/6/14 Dur: 24 days
Comp: 0%
Pasang FloordrainStart: 8/11/14 ID: 847
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kloset JongkokStart: 8/11/14 ID: 848
Finish: 9/6/14 Dur: 24 days
Res:
Pasang WastafelStart: 8/11/14 ID: 849
Finish: 9/6/14 Dur: 24 days
Res:
IX. PEKERJAAN PENGECATAStart: 10/6/14 ID: 850
Finish: 10/18/14 Dur: 12 days
Comp: 0%
Pengecatan Dinding ExterioStart: 10/6/14 ID: 851
Finish: 10/18/14 Dur: 12 days
Res:
Pengecatan Dinding InteriorStart: 10/6/14 ID: 852
Finish: 10/18/14 Dur: 12 days
Res:
Pengecatan PlafondStart: 10/6/14 ID: 853
Finish: 10/18/14 Dur: 12 days
Res:
C. PEKERJAAN PLUMBINGStart: 8/11/14 ID: 854
Finish: 9/6/14 Dur: 24 days
Comp: 0%
C.2 LANTAI 2Start: 8/11/14 ID: 855
Finish: 9/6/14 Dur: 24 days
Comp: 0%
Pasang Pipa Pengisi TandonStart: 8/11/14 ID: 856
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Induk DistribusStart: 8/11/14 ID: 857
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Bersih PVCStart: 8/11/14 ID: 858
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 859
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 860
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Pipa Induk Air KotorStart: 8/11/14 ID: 861
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Talang tegak PVC TyStart: 8/11/14 ID: 862
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Stop Kran dia 1" Start: 8/11/14 ID: 863
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kran dia 1/2" DUPONStart: 8/11/14 ID: 864
Finish: 9/6/14 Dur: 24 days
Res:
Pasang Kran wastafel 1/2"Start: 8/11/14 ID: 865
Finish: 9/6/14 Dur: 24 days
Res:
Sumur Bor (Lengkap AksesoStart: 8/11/14 ID: 866
Finish: 9/6/14 Dur: 24 days
Res:
Tandon Air 4000 L SteinlessStart: 8/11/14 ID: 867
Finish: 9/6/14 Dur: 24 days
Res:
D. PEKERJAAN LISTRIKStart: 8/11/14 ID: 868
Finish: 9/20/14 Dur: 36 days
Comp: 0%
D.2 LANTAI IIStart: 8/11/14 ID: 869
Finish: 9/20/14 Dur: 36 days
Comp: 0%
Titik Instalasi Penerangan (NStart: 8/11/14 ID: 870
Finish: 9/20/14 Dur: 36 days
Res:
Titik Instalasi Stop Kontak (NStart: 8/11/14 ID: 871
Finish: 9/20/14 Dur: 36 days
Res:
Saklar tunggalStart: 8/11/14 ID: 872
Finish: 9/20/14 Dur: 36 days
Res:
Saklar SeriStart: 8/11/14 ID: 873
Finish: 9/20/14 Dur: 36 days
Res:
Lampu PLC 24 watt + fittingStart: 8/11/14 ID: 874
Finish: 9/20/14 Dur: 36 days
Res:
Stop kontak 200 VAStart: 8/11/14 ID: 875
Finish: 9/20/14 Dur: 36 days
Res:
Pasang Panel Lantai 2Start: 8/11/14 ID: 876
Finish: 9/20/14 Dur: 36 days
Res:
Pasang Kabel induk NYY 4x4Start: 8/11/14 ID: 877
Finish: 9/20/14 Dur: 36 days
Res:
Page 6
-
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 7
Project: SMA4 Project 2007Date: Wed 4/30/14