  • Days (210 Calendar Days/180Start: 5/19/14 ID: 1

    Finish: 12/13/14 Dur: 180 days?

    Res:

    Total TimeStart: 5/19/14 ID: 2

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    GEDUNG BStart: 6/16/14 ID: 3

    Finish: 10/4/14 Dur: 96 days

    Comp: 0%

    LANTAI 3Start: 6/16/14 ID: 5

    Finish: 7/26/14 Dur: 36 days

    Comp: 0%

    I. Beton KolomStart: 6/16/14 ID: 6

    Finish: 7/5/14 Dur: 18 days

    Comp: 0%

    - Type K1 - 40/50Start: 6/16/14 ID: 7

    Finish: 7/5/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 6/30/14 ID: 8

    Finish: 7/5/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 6/16/14 ID: 9

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 6/16/14 ID: 10

    Finish: 7/5/14 Dur: 18 days

    Res:

    - BekistingStart: 6/16/14 ID: 11

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Type K2 - 30/30Start: 6/16/14 ID: 12

    Finish: 7/5/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 6/30/14 ID: 13

    Finish: 7/5/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 6/16/14 ID: 14

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 6/16/14 ID: 15

    Finish: 7/5/14 Dur: 18 days

    Res:

    - BekistingStart: 6/16/14 ID: 16

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Type K3 - 20/80Start: 6/16/14 ID: 17

    Finish: 7/5/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 6/30/14 ID: 18

    Finish: 7/5/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 6/16/14 ID: 19

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 6/16/14 ID: 20

    Finish: 7/5/14 Dur: 18 days

    Res:

    - BekistingStart: 6/16/14 ID: 21

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Type K4 - 20/60Start: 6/16/14 ID: 22

    Finish: 7/5/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 6/30/14 ID: 23

    Finish: 7/5/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 6/16/14 ID: 24

    Finish: 7/5/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 6/16/14 ID: 25

    Finish: 7/5/14 Dur: 18 days

    Res:

    - BekistingStart: 6/16/14 ID: 26

    Finish: 7/5/14 Dur: 18 days

    Res:

    II. Beton BalokStart: 7/7/14 ID: 27

    Finish: 7/26/14 Dur: 18 days

    Comp: 0%

    - Type BR - 20/30Start: 7/7/14 ID: 28

    Finish: 7/26/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/21/14 ID: 29

    Finish: 7/26/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/7/14 ID: 30

    Finish: 7/26/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/7/14 ID: 31

    Finish: 7/26/14 Dur: 18 days

    Res:

    - BekistingStart: 7/7/14 ID: 32

    Finish: 7/26/14 Dur: 18 days

    Res:

    Beton Plat LT.3Start: 7/7/14 ID: 33

    Finish: 7/26/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/21/14 ID: 34

    Finish: 7/26/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/7/14 ID: 35

    Finish: 7/26/14 Dur: 18 days

    Res:

    - BekistingStart: 7/7/14 ID: 36

    Finish: 7/26/14 Dur: 18 days

    Res:

    Beton Plat KanopiStart: 7/7/14 ID: 37

    Finish: 7/26/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/21/14 ID: 38

    Finish: 7/26/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/7/14 ID: 39

    Finish: 7/26/14 Dur: 18 days

    Res:

    - BekistingStart: 7/7/14 ID: 40

    Finish: 7/26/14 Dur: 18 days

    Res:

    B. PEKERJAAN ARSITEKTUStart: 6/23/14 ID: 41

    Finish: 10/4/14 Dur: 90 days

    Comp: 0%

    B.1 LANTAI 3Start: 6/23/14 ID: 42

    Finish: 10/4/14 Dur: 90 days

    Comp: 0%

    I. PEKERJAAN TANAHStart: 8/18/14 ID: 43

    Finish: 8/23/14 Dur: 6 days

    Comp: 0%

    Urugan Pasir Bawah lantaiStart: 8/18/14 ID: 44

    Finish: 8/23/14 Dur: 6 days

    Res:

    II. PEKERJAAN BETONStart: 7/7/14 ID: 45

    Finish: 8/23/14 Dur: 42 days

    Comp: 0%

    Beton Lantai KerjaStart: 8/11/14 ID: 46

    Finish: 8/23/14 Dur: 12 days

    Res:

    Beton Kolom PraktisStart: 7/7/14 ID: 47

    Finish: 7/19/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 48

    Finish: 7/19/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 7/7/14 ID: 49

    Finish: 7/19/14 Dur: 12 days

    Res:

    - BekistingStart: 7/7/14 ID: 50

    Finish: 7/19/14 Dur: 12 days

    Res:

    Beton Balok Latei 15/20Start: 7/7/14 ID: 51

    Finish: 7/19/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 52

    Finish: 7/19/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 7/7/14 ID: 53

    Finish: 7/19/14 Dur: 12 days

    Res:

    - BekistingStart: 7/7/14 ID: 54

    Finish: 7/19/14 Dur: 12 days

    Res:

    III. PEKERJAAN PASANGANStart: 7/7/14 ID: 55

    Finish: 7/19/14 Dur: 12 days

    Comp: 0%

    Pasangan bata rollagStart: 7/7/14 ID: 56

    Finish: 7/12/14 Dur: 6 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 7/7/14 ID: 57

    Finish: 7/19/14 Dur: 12 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 7/7/14 ID: 58

    Finish: 7/19/14 Dur: 12 days

    Res:

    IV. PEKERJAAN PLESTERAStart: 7/14/14 ID: 59

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 7/14/14 ID: 60

    Finish: 7/26/14 Dur: 12 days

    Res:

    Plesteran Dinding 1PC : 6PsStart: 7/14/14 ID: 61

    Finish: 7/26/14 Dur: 12 days

    Res:

    Plesteran Beton 1PC : 3Ps Start: 7/14/14 ID: 62

    Finish: 7/26/14 Dur: 12 days

    Res:

    AcianStart: 7/21/14 ID: 63

    Finish: 8/2/14 Dur: 12 days

    Res:

    Benangan Sudut, Plinkolt & Start: 7/21/14 ID: 64

    Finish: 8/2/14 Dur: 12 days

    Res:

    Water Proofing Plat terasStart: 7/21/14 ID: 65

    Finish: 8/2/14 Dur: 12 days

    Res:

    V. PEKERJAAN PELAPIS LAStart: 9/22/14 ID: 66

    Finish: 10/4/14 Dur: 12 days

    Comp: 0%

    Pasang Keramik Lantai 40x4Start: 9/22/14 ID: 67

    Finish: 10/4/14 Dur: 12 days

    Res:

    Pasang Keramik Lantai 30x3Start: 9/22/14 ID: 68

    Finish: 10/4/14 Dur: 12 days

    Res:

    Pasang Keramik Tangga 30xStart: 9/22/14 ID: 69

    Finish: 10/4/14 Dur: 12 days

    Res:

    Pasang Keramik Dinding 25xStart: 9/22/14 ID: 70

    Finish: 10/4/14 Dur: 12 days

    Res:

    VI. PEKERJAAN KUSEN PINStart: 7/7/14 ID: 71

    Finish: 7/19/14 Dur: 12 days

    Comp: 0%

    Pasang Kusen Aluminium 4"Start: 7/7/14 ID: 72

    Finish: 7/19/14 Dur: 12 days

    Res:

    Pasang Daun Pintu Double TStart: 7/7/14 ID: 73

    Finish: 7/19/14 Dur: 12 days

    Res:

    Pasang Daun Jendela Kaca AStart: 7/7/14 ID: 74

    Finish: 7/19/14 Dur: 12 days

    Res:

    Pasang kusen dan pintu KMStart: 7/7/14 ID: 75

    Finish: 7/19/14 Dur: 12 days

    Res:

    Pasang Aksesoris AluminiumStart: 7/7/14 ID: 76

    Finish: 7/19/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PENGGANTStart: 8/25/14 ID: 77

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasang Kunci PintuStart: 8/25/14 ID: 78

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Engsel Pintu 4"Start: 8/25/14 ID: 79

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Grendel TanamStart: 8/25/14 ID: 80

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Grendel Pintu BiasaStart: 8/25/14 ID: 81

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Engsel Jendela ModStart: 8/25/14 ID: 82

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Grendel JendelaStart: 8/25/14 ID: 83

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Railling Tangga PipaStart: 8/25/14 ID: 84

    Finish: 9/6/14 Dur: 12 days

    Res:

    VIII. PEKERJAAN PLAFONDStart: 8/25/14 ID: 85

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasang Penutup Plafond GyStart: 8/25/14 ID: 86

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Lis Gypsum 15 cmStart: 8/25/14 ID: 87

    Finish: 9/6/14 Dur: 12 days

    Res:

    IX. PEKERJAAN SANITASIStart: 6/23/14 ID: 88

    Finish: 7/19/14 Dur: 24 days

    Comp: 0%

    Pasang FloordrainStart: 6/23/14 ID: 89

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Kloset JongkokStart: 6/23/14 ID: 90

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang WastafelStart: 6/23/14 ID: 91

    Finish: 7/19/14 Dur: 24 days

    Res:

    X. PEKERJAAN PENGECATAStart: 9/8/14 ID: 92

    Finish: 9/20/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding ExterioStart: 9/8/14 ID: 93

    Finish: 9/20/14 Dur: 12 days

    Res:

    Pengecatan Dinding InteriorStart: 9/8/14 ID: 94

    Finish: 9/20/14 Dur: 12 days

    Res:

    Pengecatan PlafondStart: 9/8/14 ID: 95

    Finish: 9/20/14 Dur: 12 days

    Res:

    Politur Daun PintuStart: 9/8/14 ID: 96

    Finish: 9/20/14 Dur: 12 days

    Res:

    B.3 LANTAI 3Start: 7/28/14 ID: 97

    Finish: 8/23/14 Dur: 24 days

    Comp: 0%

    XI. PEKERJAAN ATAPStart: 7/28/14 ID: 98

    Finish: 8/23/14 Dur: 24 days

    Comp: 0%

    Kuda-kuda WF-200.204.12.12Start: 7/28/14 ID: 99

    Finish: 8/23/14 Dur: 24 days

    Res:

    Gording C-150,50,20,3,2Start: 7/28/14 ID: 100

    Finish: 8/23/14 Dur: 24 days

    Res:

    Batang Tarik f 16 mmStart: 7/28/14 ID: 101

    Finish: 8/23/14 Dur: 24 days

    Res:

    Ikatan Angin f 16 mmStart: 7/28/14 ID: 102

    Finish: 8/23/14 Dur: 24 days

    Res:

    Jarum KerasStart: 7/28/14 ID: 103

    Finish: 8/23/14 Dur: 24 days

    Res:

    Baja Siku Penopang GordingStart: 7/28/14 ID: 104

    Finish: 8/23/14 Dur: 24 days

    Res:

    Plat Plendes, Simpul, StiffneStart: 7/28/14 ID: 105

    Finish: 8/23/14 Dur: 24 days

    Res:

    Angkur Baut HTB 16Start: 7/28/14 ID: 106

    Finish: 8/23/14 Dur: 24 days

    Res:

    Mur Baut HTB 16Start: 7/28/14 ID: 107

    Finish: 8/23/14 Dur: 24 days

    Res:

    PengelasanStart: 7/28/14 ID: 108

    Finish: 8/23/14 Dur: 24 days

    Res:

    Usuk reng galvalumStart: 7/28/14 ID: 109

    Finish: 8/23/14 Dur: 24 days

    Res:

    Penutup Atap genteng keramStart: 7/28/14 ID: 110

    Finish: 8/23/14 Dur: 24 days

    Res:

    Lisplank double 3/25Start: 7/28/14 ID: 111

    Finish: 8/23/14 Dur: 24 days

    Res:

    Papan Reuter 3/30Start: 7/28/14 ID: 112

    Finish: 8/23/14 Dur: 24 days

    Res:

    BubunganStart: 7/28/14 ID: 113

    Finish: 8/23/14 Dur: 24 days

    Res:

    C. PEKERJAAN PLUMBINGStart: 6/23/14 ID: 114

    Finish: 7/19/14 Dur: 24 days

    Comp: 0%

    C.1 LANTAI 3Start: 6/23/14 ID: 115

    Finish: 7/19/14 Dur: 24 days

    Comp: 0%

    Pasang Pipa Pengisi TandonStart: 6/23/14 ID: 116

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Pipa Induk DistribusStart: 6/23/14 ID: 117

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Pipa Air Bersih PVCStart: 6/23/14 ID: 118

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 6/23/14 ID: 119

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 6/23/14 ID: 120

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Pipa Induk Air KotorStart: 6/23/14 ID: 121

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Talang tegak PVC TyStart: 6/23/14 ID: 122

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Stop Kran dia 1" Start: 6/23/14 ID: 123

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Kran dia 1/2" DUPONStart: 6/23/14 ID: 124

    Finish: 7/19/14 Dur: 24 days

    Res:

    Pasang Kran wastafel 1/2"Start: 6/23/14 ID: 125

    Finish: 7/19/14 Dur: 24 days

    Res:

    Sumur Bor (Lengkap AksesoStart: 6/23/14 ID: 126

    Finish: 7/19/14 Dur: 24 days

    Res:

    Tandon Air 4000 L SteinlessStart: 6/23/14 ID: 127

    Finish: 7/19/14 Dur: 24 days

    Res:

    D. PEKERJAAN LISTRIKStart: 6/23/14 ID: 128

    Finish: 8/2/14 Dur: 36 days

    Comp: 0%

    D.1 LANTAI 3Start: 6/23/14 ID: 129

    Finish: 8/2/14 Dur: 36 days

    Comp: 0%

    Titik Instalasi Penerangan (NStart: 6/23/14 ID: 130

    Finish: 8/2/14 Dur: 36 days

    Res:

    Titik Instalasi Stop Kontak (NStart: 6/23/14 ID: 131

    Finish: 8/2/14 Dur: 36 days

    Res:

    Saklar tunggalStart: 6/23/14 ID: 132

    Finish: 8/2/14 Dur: 36 days

    Res:

    Saklar SeriStart: 6/23/14 ID: 133

    Finish: 8/2/14 Dur: 36 days

    Res:

    Lampu PLC 24 watt + fittingStart: 6/23/14 ID: 134

    A. PEKERJAAN STRUKTURStart: 6/16/14 ID: 4

    Finish: 7/26/14 Dur: 36 days

    Comp: 0%

    Page 1

  • Finish: 8/2/14 Dur: 36 days

    Res:

    Stop kontak 200 VAStart: 6/23/14 ID: 135

    Finish: 8/2/14 Dur: 36 days

    Res:

    Pasang Panel Lantai IIIStart: 6/23/14 ID: 136

    Finish: 8/2/14 Dur: 36 days

    Res:

    Pasang Kabel induk NYY 4x4Start: 6/23/14 ID: 137

    Finish: 8/2/14 Dur: 36 days

    Res:

    Pasang Penangkal PetirStart: 6/23/14 ID: 138

    Finish: 8/2/14 Dur: 36 days

    Res:

    GEDUNG CStart: 5/19/14 ID: 140

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 141

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    A.1 LANTAI 1Start: 5/19/14 ID: 142

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 143

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    Pengadaan Air KerjaStart: 5/19/14 ID: 144

    Finish: 5/31/14 Dur: 12 days

    Res:

    Pembuatan Papan Nama KegStart: 5/19/14 ID: 145

    Finish: 5/31/14 Dur: 12 days

    Res:

    Pembersihan LokasiStart: 5/19/14 ID: 146

    Finish: 5/31/14 Dur: 12 days

    Res:

    Pembersihan AkhirStart: 12/1/14 ID: 147

    Finish: 12/13/14 Dur: 12 days

    Res:

    MobStart: 5/19/14 ID: 148

    Finish: 5/31/14 Dur: 12 days

    Res:

    DemobStart: 12/1/14 ID: 149

    Finish: 12/13/14 Dur: 12 days

    Res:

    II. PEKERJAAN TANAHStart: 6/2/14 ID: 150

    Finish: 7/5/14 Dur: 30 days

    Comp: 0%

    Galian Tanah lubang PondasStart: 6/2/14 ID: 151

    Finish: 6/14/14 Dur: 12 days

    Res:

    Urugan Pasir Bawah PondasStart: 6/9/14 ID: 152

    Finish: 6/14/14 Dur: 6 days

    Res:

    Urugan tanah kembaliStart: 6/23/14 ID: 153

    Finish: 7/5/14 Dur: 12 days

    Res:

    Urugan tanahStart: 6/9/14 ID: 154

    Finish: 6/14/14 Dur: 6 days

    Res:

    III. PEKERJAAN BETONStart: 6/2/14 ID: 155

    Finish: 8/2/14 Dur: 54 days

    Comp: 0%

    1. Beton BalokStart: 7/14/14 ID: 156

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Type BLT - 15/20Start: 7/14/14 ID: 157

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 158

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 159

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 160

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 161

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BLK - 15/20Start: 7/14/14 ID: 162

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 163

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 164

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 165

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 166

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BL - 20/40Start: 7/14/14 ID: 167

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 168

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 169

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 170

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 171

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BL1- 30/60Start: 7/14/14 ID: 172

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 173

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 174

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 175

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 176

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BL2- 30/40Start: 7/14/14 ID: 177

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 178

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 179

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 180

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 181

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BA1 - 20/30Start: 7/14/14 ID: 182

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 183

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 184

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 185

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 186

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Type BA2 - 15/25Start: 7/14/14 ID: 187

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 188

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 7/14/14 ID: 189

    Finish: 8/2/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 190

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 191

    Finish: 8/2/14 Dur: 18 days

    Res:

    2. Beton Plat Lantai 2Start: 7/14/14 ID: 192

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 193

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 194

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 195

    Finish: 8/2/14 Dur: 18 days

    Res:

    3. Beton Plat KanopiStart: 7/14/14 ID: 196

    Finish: 8/2/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/28/14 ID: 197

    Finish: 8/2/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 198

    Finish: 8/2/14 Dur: 18 days

    Res:

    - BekistingStart: 7/14/14 ID: 199

    Finish: 8/2/14 Dur: 18 days

    Res:

    4. Beton TanggaStart: 6/2/14 ID: 200

    Finish: 7/12/14 Dur: 36 days

    Comp: 0%

    - Beton Pondasi TanggaStart: 6/2/14 ID: 201

    Finish: 6/21/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 6/16/14 ID: 202

    Finish: 6/21/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/2/14 ID: 203

    Finish: 6/21/14 Dur: 18 days

    Res:

    - BekistingStart: 6/2/14 ID: 204

    Finish: 6/21/14 Dur: 18 days

    Res:

    - Beton Plat TanggaStart: 6/23/14 ID: 205

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 206

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 207

    Finish: 7/12/14 Dur: 18 days

    Res:

    - BekistingStart: 6/23/14 ID: 208

    Finish: 7/12/14 Dur: 18 days

    Res:

    - Beton Balok BordesStart: 6/23/14 ID: 209

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 210

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 211

    Finish: 7/12/14 Dur: 18 days

    Res:

    - BekistingStart: 6/23/14 ID: 212

    Finish: 7/12/14 Dur: 18 days

    Res:

    - Beton Plat BordesStart: 6/23/14 ID: 213

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 214

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 215

    Finish: 7/12/14 Dur: 18 days

    Res:

    - BekistingStart: 6/23/14 ID: 216

    Finish: 7/12/14 Dur: 18 days

    Res:

    - Beton K-250Start: 7/7/14 ID: 218

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 219

    Finish: 7/12/14 Dur: 18 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 226

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 227

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 228

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K2 - 30/30Start: 8/4/14 ID: 229

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 230

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 231

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 232

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 233

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K3 - 20/80Start: 8/4/14 ID: 234

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 235

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 236

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 237

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 238

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K4 - 20/60Start: 8/4/14 ID: 239

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 240

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 241

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 242

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 243

    Finish: 8/23/14 Dur: 18 days

    Res:

    2. Beton BalokStart: 8/25/14 ID: 244

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Type BLT - 15/20Start: 8/25/14 ID: 245

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 246

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 247

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 248

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 249

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BLK - 15/20Start: 8/25/14 ID: 250

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 251

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 252

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 253

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 254

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL - 20/40Start: 8/25/14 ID: 255

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 256

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 257

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 258

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 259

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL1- 30/60Start: 8/25/14 ID: 260

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 261

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 262

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 263

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 264

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL2- 30/40Start: 8/25/14 ID: 265

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 266

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 267

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 268

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 269

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BA1 - 20/30Start: 8/25/14 ID: 270

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 271

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 272

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 273

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 274

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BA2 - 15/25Start: 8/25/14 ID: 275

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 276

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 277

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 278

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 279

    Finish: 9/13/14 Dur: 18 days

    Res:

    3. Beton Plat Lantai 3Start: 8/25/14 ID: 280

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 281

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 282

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 283

    Finish: 9/13/14 Dur: 18 days

    Res:

    4. Beton Plat KanopiStart: 8/25/14 ID: 284

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 285

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 286

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 287

    Finish: 9/13/14 Dur: 18 days

    Res:

    5. Beton TanggaStart: 8/4/14 ID: 288

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton Plat TanggaStart: 8/4/14 ID: 289

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 290

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 291

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 292

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Balok BordesStart: 8/4/14 ID: 293

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 294

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 295

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 296

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 297

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Plat BordesStart: 8/4/14 ID: 298

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 299

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 300

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 301

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Anak TanggaStart: 8/4/14 ID: 302

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 303

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 304

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 305

    Finish: 8/23/14 Dur: 18 days

    Res:

    A.3 LANTAI 3Start: 9/15/14 ID: 306

    Finish: 10/25/14 Dur: 36 days

    Comp: 0%

    I. PEKERJAAN BETONStart: 9/15/14 ID: 307

    Finish: 10/25/14 Dur: 36 days

    Comp: 0%

    1. Beton KolomStart: 9/15/14 ID: 308

    Finish: 10/4/14 Dur: 18 days

    Comp: 0%

    - Type K1 - 40/50Start: 9/15/14 ID: 309

    Finish: 10/4/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/29/14 ID: 310

    Finish: 10/4/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 9/15/14 ID: 311

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 9/15/14 ID: 312

    Finish: 10/4/14 Dur: 18 days

    Res:

    - BekistingStart: 9/15/14 ID: 313

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Type K2 - 30/30Start: 9/15/14 ID: 314

    Finish: 10/4/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/29/14 ID: 315

    Finish: 10/4/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 9/15/14 ID: 316

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 9/15/14 ID: 317

    Finish: 10/4/14 Dur: 18 days

    Res:

    - BekistingStart: 9/15/14 ID: 318

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Type K3 - 20/80Start: 9/15/14 ID: 319

    Finish: 10/4/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/29/14 ID: 320

    Finish: 10/4/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 9/15/14 ID: 321

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 9/15/14 ID: 322

    Finish: 10/4/14 Dur: 18 days

    Res:

    - BekistingStart: 9/15/14 ID: 323

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Type K4 - 20/60Start: 9/15/14 ID: 324

    Finish: 10/4/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/29/14 ID: 325

    Finish: 10/4/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 9/15/14 ID: 326

    Finish: 10/4/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 9/15/14 ID: 327

    Finish: 10/4/14 Dur: 18 days

    Res:

    - BekistingStart: 9/15/14 ID: 328

    Finish: 10/4/14 Dur: 18 days

    Res:

    2. Beton BalokStart: 10/6/14 ID: 329

    Finish: 10/25/14 Dur: 18 days

    Comp: 0%

    - Type BR - 20/30Start: 10/6/14 ID: 330

    Finish: 10/25/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 10/20/14 ID: 331

    Finish: 10/25/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 10/6/14 ID: 332

    Finish: 10/25/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 10/6/14 ID: 333

    Finish: 10/25/14 Dur: 18 days

    Res:

    - BekistingStart: 10/6/14 ID: 334

    Finish: 10/25/14 Dur: 18 days

    Res:

    3. Beton Plat LT.3Start: 10/6/14 ID: 335

    Finish: 10/25/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 10/20/14 ID: 336

    Finish: 10/25/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 10/6/14 ID: 337

    Finish: 10/25/14 Dur: 18 days

    Res:

    - BekistingStart: 10/6/14 ID: 338

    Finish: 10/25/14 Dur: 18 days

    Res:

    4. Beton Plat KanopiStart: 10/6/14 ID: 339

    Finish: 10/25/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 10/20/14 ID: 340

    Finish: 10/25/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 10/6/14 ID: 341

    Finish: 10/25/14 Dur: 18 days

    Res:

    - BekistingStart: 10/6/14 ID: 342

    Finish: 10/25/14 Dur: 18 days

    Res:

    B. PEKERJAAN ARSITEKTUStart: 6/16/14 ID: 343

    Finish: 12/13/14 Dur: 156 days

    Comp: 0%

    B.1 LANTAI 1Start: 6/16/14 ID: 344

    Finish: 9/13/14 Dur: 78 days

    Comp: 0%

    I. PEKERJAAN TANAHStart: 8/25/14 ID: 345

    Finish: 8/30/14 Dur: 6 days

    Comp: 0%

    Urugan Pasir Bawah lantaiStart: 8/25/14 ID: 346

    Finish: 8/30/14 Dur: 6 days

    Res:

    II. PEKERJAAN BETONStart: 7/14/14 ID: 347

    Finish: 7/26/14 Dur: 12 days

    Comp: 0%

    1. Beton Lantai KerjaStart: 7/14/14 ID: 348

    Finish: 7/26/14 Dur: 12 days

    Res:

    A.2 LANTAI 2Start: 8/4/14 ID: 221

    Finish: 9/13/14 Dur: 36 days

    Comp: 0%

    I. PEKERJAAN BETONStart: 8/4/14 ID: 222

    Finish: 9/13/14 Dur: 36 days

    Comp: 0%

    - Type K1 - 40/50Start: 8/4/14 ID: 224

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 225

    Finish: 8/23/14 Dur: 6 days

    Res:

    - BekistingStart: 6/23/14 ID: 220

    Finish: 7/12/14 Dur: 18 days

    Res:

    - Beton Anak TanggaStart: 6/23/14 ID: 217

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    1. Beton KolomStart: 8/4/14 ID: 223

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    Page 2

  • 2. Beton Kolom PraktisStart: 7/14/14 ID: 349

    Finish: 7/26/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 7/14/14 ID: 350

    Finish: 7/26/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 351

    Finish: 7/26/14 Dur: 12 days

    Res:

    - BekistingStart: 7/14/14 ID: 352

    Finish: 7/26/14 Dur: 12 days

    Res:

    3. Beton Balok Latei 15/20Start: 7/14/14 ID: 353

    Finish: 7/26/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 7/14/14 ID: 354

    Finish: 7/26/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 7/14/14 ID: 355

    Finish: 7/26/14 Dur: 12 days

    Res:

    - BekistingStart: 7/14/14 ID: 356

    Finish: 7/26/14 Dur: 12 days

    Res:

    III. PEKERJAAN PASANGANStart: 6/23/14 ID: 357

    Finish: 7/26/14 Dur: 30 days

    Comp: 0%

    Pas. AanstampengStart: 6/23/14 ID: 358

    Finish: 7/12/14 Dur: 18 days

    Res:

    Pas. Pondasi Batu kaliStart: 6/23/14 ID: 359

    Finish: 7/12/14 Dur: 18 days

    Res:

    Pasangan bata rollagStart: 7/14/14 ID: 360

    Finish: 7/19/14 Dur: 6 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 7/14/14 ID: 361

    Finish: 7/26/14 Dur: 12 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 7/14/14 ID: 362

    Finish: 7/26/14 Dur: 12 days

    Res:

    IV. PEKERJAAN PLESTERAStart: 7/21/14 ID: 363

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 7/21/14 ID: 364

    Finish: 8/2/14 Dur: 12 days

    Res:

    Plesteran Dinding 1PC : 6PsStart: 7/21/14 ID: 365

    Finish: 8/2/14 Dur: 12 days

    Res:

    Plesteran Beton 1PC : 3Ps Start: 7/21/14 ID: 366

    Finish: 8/2/14 Dur: 12 days

    Res:

    AcianStart: 7/28/14 ID: 367

    Finish: 8/9/14 Dur: 12 days

    Res:

    Benangan Sudut, Plinkolt & Start: 7/28/14 ID: 368

    Finish: 8/9/14 Dur: 12 days

    Res:

    Water Proofing Plat terasStart: 7/28/14 ID: 369

    Finish: 8/9/14 Dur: 12 days

    Res:

    V. PEKERJAAN PELAPIS LAStart: 8/25/14 ID: 370

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasang Keramik Lantai 40x4Start: 8/25/14 ID: 371

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Keramik Lantai 30x3Start: 8/25/14 ID: 372

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Keramik Tangga 30xStart: 8/25/14 ID: 373

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Keramik Dinding 25xStart: 8/25/14 ID: 374

    Finish: 9/6/14 Dur: 12 days

    Res:

    VI. PEKERJAAN KUSEN PINStart: 7/14/14 ID: 375

    Finish: 7/26/14 Dur: 12 days

    Comp: 0%

    Pasang Kusen Aluminium 4"Start: 7/14/14 ID: 376

    Finish: 7/26/14 Dur: 12 days

    Res:

    Pasang Daun Pintu Double TStart: 7/14/14 ID: 377

    Finish: 7/26/14 Dur: 12 days

    Res:

    Pasang Daun Jendela Kaca AStart: 7/14/14 ID: 378

    Finish: 7/26/14 Dur: 12 days

    Res:

    Pasang kusen dan pintu KMStart: 7/14/14 ID: 379

    Finish: 7/26/14 Dur: 12 days

    Res:

    Pasang Aksesoris AluminiumStart: 7/14/14 ID: 380

    Finish: 7/26/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PENGGANTStart: 9/1/14 ID: 381

    Finish: 9/13/14 Dur: 12 days

    Comp: 0%

    Pasang Kunci PintuStart: 9/1/14 ID: 382

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Engsel Pintu 4"Start: 9/1/14 ID: 383

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Grendel TanamStart: 9/1/14 ID: 384

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Grendel Pintu BiasaStart: 9/1/14 ID: 385

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Engsel Jendela ModStart: 9/1/14 ID: 386

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Grendel JendelaStart: 9/1/14 ID: 387

    Finish: 9/13/14 Dur: 12 days

    Res:

    Pasang Railling Tangga PipaStart: 9/1/14 ID: 388

    Finish: 9/13/14 Dur: 12 days

    Res:

    VIII. PEKERJAAN PLAFONDStart: 8/4/14 ID: 389

    Finish: 8/16/14 Dur: 12 days

    Comp: 0%

    Pasang Penutup Plafond GyStart: 8/4/14 ID: 390

    Finish: 8/16/14 Dur: 12 days

    Res:

    Pasang Lis Gypsum 15 cmStart: 8/4/14 ID: 391

    Finish: 8/16/14 Dur: 12 days

    Res:

    IX. PEKERJAAN SANITASIStart: 6/30/14 ID: 392

    Finish: 7/26/14 Dur: 24 days

    Comp: 0%

    Pasang FloordrainStart: 6/30/14 ID: 393

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Kloset JongkokStart: 6/30/14 ID: 394

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang WastafelStart: 6/30/14 ID: 395

    Finish: 7/26/14 Dur: 24 days

    Res:

    X. PEKERJAAN PENGECATAStart: 8/11/14 ID: 396

    Finish: 8/23/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding ExterioStart: 8/11/14 ID: 397

    Finish: 8/23/14 Dur: 12 days

    Res:

    Pengecatan Dinding InteriorStart: 8/11/14 ID: 398

    Finish: 8/23/14 Dur: 12 days

    Res:

    Pengecatan PlafondStart: 8/11/14 ID: 399

    Finish: 8/23/14 Dur: 12 days

    Res:

    Politur Daun PintuStart: 8/11/14 ID: 400

    Finish: 8/23/14 Dur: 12 days

    Res:

    XI. PEKERJAAN SEPTICTANStart: 6/16/14 ID: 401

    Finish: 7/19/14 Dur: 30 days

    Comp: 0%

    Galian TanahStart: 6/16/14 ID: 402

    Finish: 6/28/14 Dur: 12 days

    Res:

    Urugan pasir urugStart: 6/16/14 ID: 403

    Finish: 6/21/14 Dur: 6 days

    Res:

    Pas. IjukStart: 6/16/14 ID: 404

    Finish: 6/21/14 Dur: 6 days

    Res:

    Pasir kerikilStart: 6/16/14 ID: 405

    Finish: 6/21/14 Dur: 6 days

    Res:

    Lantai kerjaStart: 6/16/14 ID: 406

    Finish: 6/21/14 Dur: 6 days

    Res:

    Pas. Bata merah 1:3Start: 6/16/14 ID: 407

    Finish: 6/28/14 Dur: 12 days

    Res:

    Pas. Bata merah kosongStart: 6/16/14 ID: 408

    Finish: 6/28/14 Dur: 12 days

    Res:

    Pekerjaan beton plat penutupStart: 6/23/14 ID: 409

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 410

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 411

    Finish: 7/12/14 Dur: 18 days

    Res:

    - BekistingStart: 6/23/14 ID: 412

    Finish: 7/12/14 Dur: 18 days

    Res:

    Plesteran Start: 7/14/14 ID: 413

    Finish: 7/19/14 Dur: 6 days

    Res:

    acianStart: 7/14/14 ID: 414

    Finish: 7/19/14 Dur: 6 days

    Res:

    B.2 LANTAI 2Start: 8/11/14 ID: 415

    Finish: 11/1/14 Dur: 72 days

    Comp: 0%

    I. PEKERJAAN TANAHStart: 10/6/14 ID: 416

    Finish: 10/11/14 Dur: 6 days

    Comp: 0%

    Urugan Pasir Bawah lantaiStart: 10/6/14 ID: 417

    Finish: 10/11/14 Dur: 6 days

    Res:

    II. PEKERJAAN BETONStart: 8/25/14 ID: 418

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Beton Kolom PraktisStart: 8/25/14 ID: 419

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 420

    Finish: 9/6/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 421

    Finish: 9/6/14 Dur: 12 days

    Res:

    - BekistingStart: 8/25/14 ID: 422

    Finish: 9/6/14 Dur: 12 days

    Res:

    Beton Balok Latei 15/20Start: 8/25/14 ID: 423

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 424

    Finish: 9/6/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 425

    Finish: 9/6/14 Dur: 12 days

    Res:

    - BekistingStart: 8/25/14 ID: 426

    Finish: 9/6/14 Dur: 12 days

    Res:

    III. PEKERJAAN PASANGANStart: 8/25/14 ID: 427

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 428

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 429

    Finish: 9/6/14 Dur: 12 days

    Res:

    IV. PEKERJAAN PLESTERAStart: 9/1/14 ID: 430

    Finish: 9/20/14 Dur: 18 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 431

    Finish: 9/13/14 Dur: 12 days

    Res:

    Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 432

    Finish: 9/13/14 Dur: 12 days

    Res:

    Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 433

    Finish: 9/13/14 Dur: 12 days

    Res:

    AcianStart: 9/8/14 ID: 434

    Finish: 9/20/14 Dur: 12 days

    Res:

    Benangan Sudut, Plinkolt & Start: 9/8/14 ID: 435

    Finish: 9/20/14 Dur: 12 days

    Res:

    Water Proofing Kanopi + potStart: 9/8/14 ID: 436

    Finish: 9/20/14 Dur: 12 days

    Res:

    V. PEKERJAAN PELAPIS LAStart: 10/20/14 ID: 437

    Finish: 11/1/14 Dur: 12 days

    Comp: 0%

    Pasang Keramik Lantai 40x4Start: 10/20/14 ID: 438

    Finish: 11/1/14 Dur: 12 days

    Res:

    Pasang Keramik Lantai 30x3Start: 10/20/14 ID: 439

    Finish: 11/1/14 Dur: 12 days

    Res:

    Pasang Keramik Tangga 30xStart: 10/20/14 ID: 440

    Finish: 11/1/14 Dur: 12 days

    Res:

    Pasang Keramik Dinding 25xStart: 10/20/14 ID: 441

    Finish: 11/1/14 Dur: 12 days

    Res:

    VI. PEKERJAAN KUSEN PINStart: 8/25/14 ID: 442

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasang Kusen Aluminium 4"Start: 8/25/14 ID: 443

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Daun Pintu Double TStart: 8/25/14 ID: 444

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Daun Jendela Kaca Start: 8/25/14 ID: 445

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang kusen dan pintu KMStart: 8/25/14 ID: 446

    Finish: 9/6/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PENGGANTStart: 10/13/14 ID: 447

    Finish: 10/25/14 Dur: 12 days

    Comp: 0%

    Pasang Kunci PintuStart: 10/13/14 ID: 448

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Engsel Pintu 4"Start: 10/13/14 ID: 449

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel TanamStart: 10/13/14 ID: 450

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel Pintu BiasaStart: 10/13/14 ID: 451

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Engsel Jendela ModStart: 10/13/14 ID: 452

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel JendelaStart: 10/13/14 ID: 453

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Railling Tangga PipaStart: 10/13/14 ID: 454

    Finish: 10/25/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PLAFONDStart: 9/29/14 ID: 455

    Finish: 10/11/14 Dur: 12 days

    Comp: 0%

    Pasang Penutup Plafond GyStart: 9/29/14 ID: 456

    Finish: 10/11/14 Dur: 12 days

    Res:

    Pasang Lis Gypsum 12 cmStart: 9/29/14 ID: 457

    Finish: 10/11/14 Dur: 12 days

    Res:

    VIII. PEKERJAAN SANITASIStart: 8/11/14 ID: 458

    Finish: 9/6/14 Dur: 24 days

    Comp: 0%

    Pasang FloordrainStart: 8/11/14 ID: 459

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kloset JongkokStart: 8/11/14 ID: 460

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang WastafelStart: 8/11/14 ID: 461

    Finish: 9/6/14 Dur: 24 days

    Res:

    IX. PEKERJAAN PENGECATAStart: 10/6/14 ID: 462

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding ExterioStart: 10/6/14 ID: 463

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pengecatan Dinding InteriorStart: 10/6/14 ID: 464

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pengecatan PlafondStart: 10/6/14 ID: 465

    Finish: 10/18/14 Dur: 12 days

    Res:

    Politur Daun PintuStart: 10/6/14 ID: 466

    Finish: 10/18/14 Dur: 12 days

    Res:

    B.3 LANTAI 3Start: 9/22/14 ID: 467

    Finish: 12/13/14 Dur: 72 days

    Comp: 0%

    I. PEKERJAAN TANAHStart: 11/17/14 ID: 468

    Finish: 11/22/14 Dur: 6 days

    Comp: 0%

    Urugan Pasir Bawah lantaiStart: 11/17/14 ID: 469

    Finish: 11/22/14 Dur: 6 days

    Res:

    II. PEKERJAAN BETONStart: 10/6/14 ID: 470

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    Beton Kolom PraktisStart: 10/6/14 ID: 471

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 10/6/14 ID: 472

    Finish: 10/18/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 10/6/14 ID: 473

    Finish: 10/18/14 Dur: 12 days

    Res:

    - BekistingStart: 10/6/14 ID: 474

    Finish: 10/18/14 Dur: 12 days

    Res:

    Beton Balok Latei 15/20Start: 10/6/14 ID: 475

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 10/6/14 ID: 476

    Finish: 10/18/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 10/6/14 ID: 477

    Finish: 10/18/14 Dur: 12 days

    Res:

    - BekistingStart: 10/6/14 ID: 478

    Finish: 10/18/14 Dur: 12 days

    Res:

    III. PEKERJAAN PASANGANStart: 10/6/14 ID: 479

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    Pasangan Batu Merah 1/2 baStart: 10/6/14 ID: 480

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 10/6/14 ID: 481

    Finish: 10/18/14 Dur: 12 days

    Res:

    IV. PEKERJAAN PLESTERAStart: 10/13/14 ID: 482

    Finish: 11/1/14 Dur: 18 days

    Plesteran Dinding 1PC : 3PsStart: 10/13/14 ID: 483

    Finish: 10/25/14 Dur: 12 days

    Plesteran Dinding 1PC : 6PsStart: 10/13/14 ID: 484

    Finish: 10/25/14 Dur: 12 days

    Page 3

  • Comp: 0% Res: Res:

    Plesteran Beton 1PC : 3Ps Start: 10/13/14 ID: 485

    Finish: 10/25/14 Dur: 12 days

    Res:

    AcianStart: 10/20/14 ID: 486

    Finish: 11/1/14 Dur: 12 days

    Res:

    Benangan Sudut, Plinkolt & Start: 10/20/14 ID: 487

    Finish: 11/1/14 Dur: 12 days

    Res:

    Water Proofing Kanopi + potStart: 10/20/14 ID: 488

    Finish: 11/1/14 Dur: 12 days

    Res:

    V. PEKERJAAN PELAPIS LAStart: 12/1/14 ID: 489

    Finish: 12/13/14 Dur: 12 days

    Comp: 0%

    Pasang Keramik Lantai 40x4Start: 12/1/14 ID: 490

    Finish: 12/13/14 Dur: 12 days

    Res:

    Pasang Keramik Lantai 30x3Start: 12/1/14 ID: 491

    Finish: 12/13/14 Dur: 12 days

    Res:

    Pasang Keramik Dinding 25xStart: 12/1/14 ID: 492

    Finish: 12/13/14 Dur: 12 days

    Res:

    VI. PEKERJAAN KUSEN PINTStart: 10/6/14 ID: 493

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    Pasang Kusen Aluminium 4"Start: 10/6/14 ID: 494

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pasang Daun Pintu Double TStart: 10/6/14 ID: 495

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pasang Daun Jendela Kaca Start: 10/6/14 ID: 496

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pasang kusen dan pintu KMStart: 10/6/14 ID: 497

    Finish: 10/18/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PENGGANTStart: 11/24/14 ID: 498

    Finish: 12/6/14 Dur: 12 days

    Comp: 0%

    Pasang Kunci PintuStart: 11/24/14 ID: 499

    Finish: 12/6/14 Dur: 12 days

    Res:

    Pasang Engsel Pintu 4"Start: 11/24/14 ID: 500

    Finish: 12/6/14 Dur: 12 days

    Res:

    Pasang Grendel TanamStart: 11/24/14 ID: 501

    Finish: 12/6/14 Dur: 12 days

    Res:

    Pasang Grendel Pintu BiasaStart: 11/24/14 ID: 502

    Finish: 12/6/14 Dur: 12 days

    Res:

    Pasang Engsel Jendela ModStart: 11/24/14 ID: 503

    Finish: 12/6/14 Dur: 12 days

    Res:

    Pasang Grendel JendelaStart: 11/24/14 ID: 504

    Finish: 12/6/14 Dur: 12 days

    Res:

    VIII. PEKERJAAN SANITASIStart: 9/22/14 ID: 505

    Finish: 10/18/14 Dur: 24 days

    Comp: 0%

    Pasang FloordrainStart: 9/22/14 ID: 506

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Kloset JongkokStart: 9/22/14 ID: 507

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang WastafelStart: 9/22/14 ID: 508

    Finish: 10/18/14 Dur: 24 days

    Res:

    IX. PEKERJAAN PENGECATStart: 11/17/14 ID: 509

    Finish: 11/29/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding ExterioStart: 11/17/14 ID: 510

    Finish: 11/29/14 Dur: 12 days

    Res:

    Pengecatan Dinding InteriorStart: 11/17/14 ID: 511

    Finish: 11/29/14 Dur: 12 days

    Res:

    Pengecatan PlafondStart: 11/17/14 ID: 512

    Finish: 11/29/14 Dur: 12 days

    Res:

    Politur Daun PintuStart: 11/17/14 ID: 513

    Finish: 11/29/14 Dur: 12 days

    Res:

    X. PEKERJAAN PLAFONDStart: 11/10/14 ID: 514

    Finish: 11/22/14 Dur: 12 days

    Comp: 0%

    Pasang Penutup Plafond GyStart: 11/10/14 ID: 515

    Finish: 11/22/14 Dur: 12 days

    Res:

    Pasang Lis Gypsum 15 cmStart: 11/10/14 ID: 516

    Finish: 11/22/14 Dur: 12 days

    Res:

    XI. PEKERJAAN ATAPStart: 10/13/14 ID: 517

    Finish: 11/8/14 Dur: 24 days

    Comp: 0%

    Kuda-kuda WF-200.204.12.12Start: 10/13/14 ID: 518

    Finish: 11/8/14 Dur: 24 days

    Res:

    Gording C-150,50,20,3,2Start: 10/13/14 ID: 519

    Finish: 11/8/14 Dur: 24 days

    Res:

    Batang Tarik f 16 mmStart: 10/13/14 ID: 520

    Finish: 11/8/14 Dur: 24 days

    Res:

    Ikatan Angin f 16 mmStart: 10/13/14 ID: 521

    Finish: 11/8/14 Dur: 24 days

    Res:

    Jarum KerasStart: 10/13/14 ID: 522

    Finish: 11/8/14 Dur: 24 days

    Res:

    Baja Siku Penopang GordingStart: 10/13/14 ID: 523

    Finish: 11/8/14 Dur: 24 days

    Res:

    Plat Plendes, Simpul, StiffneStart: 10/13/14 ID: 524

    Finish: 11/8/14 Dur: 24 days

    Res:

    Angkur Baut HTB 16Start: 10/13/14 ID: 525

    Finish: 11/8/14 Dur: 24 days

    Res:

    Mur Baut HTB 16Start: 10/13/14 ID: 526

    Finish: 11/8/14 Dur: 24 days

    Res:

    PengelasanStart: 10/13/14 ID: 527

    Finish: 11/8/14 Dur: 24 days

    Res:

    Usuk reng galvalumStart: 10/13/14 ID: 528

    Finish: 11/8/14 Dur: 24 days

    Res:

    Penutup Atap genteng keramStart: 10/13/14 ID: 529

    Finish: 11/8/14 Dur: 24 days

    Res:

    Lisplank double 3/25Start: 10/13/14 ID: 530

    Finish: 11/8/14 Dur: 24 days

    Res:

    Papan Reuter 3/30Start: 10/13/14 ID: 531

    Finish: 11/8/14 Dur: 24 days

    Res:

    BubunganStart: 10/13/14 ID: 532

    Finish: 11/8/14 Dur: 24 days

    Res:

    C. PEKERJAAN PLUMBINGStart: 6/30/14 ID: 533

    Finish: 10/18/14 Dur: 96 days

    Comp: 0%

    C.1 LANTAI IStart: 6/30/14 ID: 534

    Finish: 7/26/14 Dur: 24 days

    Comp: 0%

    Pasang Pipa Pengisi TandonStart: 6/30/14 ID: 535

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Pipa Induk DistribusStart: 6/30/14 ID: 536

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Pipa Air Bersih PVCStart: 6/30/14 ID: 537

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 6/30/14 ID: 538

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 6/30/14 ID: 539

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Pipa Induk Air KotorStart: 6/30/14 ID: 540

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Talang tegak PVC TyStart: 6/30/14 ID: 541

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Stop Kran dia 1" Start: 6/30/14 ID: 542

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Kran dia 1/2" DUPONStart: 6/30/14 ID: 543

    Finish: 7/26/14 Dur: 24 days

    Res:

    Pasang Kran wastafel 1/2"Start: 6/30/14 ID: 544

    Finish: 7/26/14 Dur: 24 days

    Res:

    Sumur Bor (Lengkap AksesoStart: 6/30/14 ID: 545

    Finish: 7/26/14 Dur: 24 days

    Res:

    C.2 LANTAI 2Start: 8/11/14 ID: 546

    Finish: 9/6/14 Dur: 24 days

    Comp: 0%

    Pasang Pipa Pengisi TandonStart: 8/11/14 ID: 547

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Induk DistribusStart: 8/11/14 ID: 548

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Bersih PVCStart: 8/11/14 ID: 549

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 550

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 551

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Induk Air KotorStart: 8/11/14 ID: 552

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Talang tegak PVC TyStart: 8/11/14 ID: 553

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Stop Kran dia 1" Start: 8/11/14 ID: 554

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kran dia 1/2" DUPONStart: 8/11/14 ID: 555

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kran wastafel 1/2"Start: 8/11/14 ID: 556

    Finish: 9/6/14 Dur: 24 days

    Res:

    C.3 LANTAI 3Start: 9/22/14 ID: 557

    Finish: 10/18/14 Dur: 24 days

    Comp: 0%

    Pasang Pipa Induk DistribusStart: 9/22/14 ID: 558

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Pipa Air Bersih PVCStart: 9/22/14 ID: 559

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 9/22/14 ID: 560

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 9/22/14 ID: 561

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Talang tegak PVC TyStart: 9/22/14 ID: 562

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Stop Kran dia 1" Start: 9/22/14 ID: 563

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Kran dia 1/2" DUPONStart: 9/22/14 ID: 564

    Finish: 10/18/14 Dur: 24 days

    Res:

    Pasang Kran wastafel 1/2"Start: 9/22/14 ID: 565

    Finish: 10/18/14 Dur: 24 days

    Res:

    Tandon Air 4000 L SteinlessStart: 9/22/14 ID: 566

    Finish: 10/18/14 Dur: 24 days

    Res:

    D. PEKERJAAN LISTRIKStart: 6/30/14 ID: 567

    Finish: 11/1/14 Dur: 108 days

    Comp: 0%

    D.1 LANTAI IStart: 6/30/14 ID: 568

    Finish: 8/9/14 Dur: 36 days

    Comp: 0%

    Titik Instalasi Penerangan (NStart: 6/30/14 ID: 569

    Finish: 8/9/14 Dur: 36 days

    Res:

    Titik Instalasi Stop Kontak (NStart: 6/30/14 ID: 570

    Finish: 8/9/14 Dur: 36 days

    Res:

    Saklar tunggalStart: 6/30/14 ID: 571

    Finish: 8/9/14 Dur: 36 days

    Res:

    Saklar SeriStart: 6/30/14 ID: 572

    Finish: 8/9/14 Dur: 36 days

    Res:

    Lampu PLC 24 watt + fittingStart: 6/30/14 ID: 573

    Finish: 8/9/14 Dur: 36 days

    Res:

    Stop kontak 200 VAStart: 6/30/14 ID: 574

    Finish: 8/9/14 Dur: 36 days

    Res:

    Pasang Panel Lantai IStart: 6/30/14 ID: 575

    Finish: 8/9/14 Dur: 36 days

    Res:

    PentanahanStart: 6/30/14 ID: 576

    Finish: 8/9/14 Dur: 36 days

    Res:

    Pasang Kabel induk NYY 4x4Start: 6/30/14 ID: 577

    Finish: 8/9/14 Dur: 36 days

    Res:

    Pemasangan Panel Listrik BStart: 6/30/14 ID: 578

    Finish: 8/9/14 Dur: 36 days

    Res:

    D.2 LANTAI IIStart: 8/11/14 ID: 579

    Finish: 9/20/14 Dur: 36 days

    Comp: 0%

    Titik Instalasi Penerangan (NStart: 8/11/14 ID: 580

    Finish: 9/20/14 Dur: 36 days

    Res:

    Titik Instalasi Stop Kontak (NStart: 8/11/14 ID: 581

    Finish: 9/20/14 Dur: 36 days

    Res:

    Saklar tunggalStart: 8/11/14 ID: 582

    Finish: 9/20/14 Dur: 36 days

    Res:

    Saklar SeriStart: 8/11/14 ID: 583

    Finish: 9/20/14 Dur: 36 days

    Res:

    Lampu PLC 24 watt + fittingStart: 8/11/14 ID: 584

    Finish: 9/20/14 Dur: 36 days

    Res:

    Stop kontak 200 VAStart: 8/11/14 ID: 585

    Finish: 9/20/14 Dur: 36 days

    Res:

    Pasang Panel Lantai 2Start: 8/11/14 ID: 586

    Finish: 9/20/14 Dur: 36 days

    Res:

    Pasang Kabel induk NYY 4x4

    Page 4

  • Start: 8/11/14 ID: 587

    Finish: 9/20/14 Dur: 36 days

    Res:

    D.3 LANTAI IIIStart: 9/22/14 ID: 588

    Finish: 11/1/14 Dur: 36 days

    Comp: 0%

    Titik Instalasi Penerangan (NStart: 9/22/14 ID: 589

    Finish: 11/1/14 Dur: 36 days

    Res:

    Titik Instalasi Stop Kontak (NStart: 9/22/14 ID: 590

    Finish: 11/1/14 Dur: 36 days

    Res:

    Saklar tunggalStart: 9/22/14 ID: 591

    Finish: 11/1/14 Dur: 36 days

    Res:

    Saklar SeriStart: 9/22/14 ID: 592

    Finish: 11/1/14 Dur: 36 days

    Res:

    Lampu PLC 24 watt + fittingStart: 9/22/14 ID: 593

    Finish: 11/1/14 Dur: 36 days

    Res:

    Stop kontak 200 VAStart: 9/22/14 ID: 594

    Finish: 11/1/14 Dur: 36 days

    Res:

    Pasang Panel Lantai 3Start: 9/22/14 ID: 595

    Finish: 11/1/14 Dur: 36 days

    Res:

    Penangkal petir Start: 9/22/14 ID: 596

    Finish: 11/1/14 Dur: 36 days

    Res:

    Pasang Kabel induk NYY 4x4Start: 9/22/14 ID: 597

    Finish: 11/1/14 Dur: 36 days

    Res:

    PAGAR dan TURAPStart: 5/19/14 ID: 599

    Finish: 10/4/14 Dur: 120 days

    Comp: 0%

    I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 600

    Finish: 5/24/14 Dur: 6 days

    Comp: 0%

    Pembersihan LokasiStart: 5/19/14 ID: 601

    Finish: 5/24/14 Dur: 6 days

    Res:

    Uitset / BowplankStart: 5/19/14 ID: 602

    Finish: 5/24/14 Dur: 6 days

    Res:

    II. PEKERJAAN TANAHStart: 6/16/14 ID: 603

    Finish: 7/26/14 Dur: 36 days

    Comp: 0%

    Galian Tanah lubang PondasStart: 6/16/14 ID: 604

    Finish: 6/28/14 Dur: 12 days

    Res:

    Urugan Tanah Bekas GalianStart: 7/21/14 ID: 605

    Finish: 7/26/14 Dur: 6 days

    Res:

    Urugan Pasir Bawah PondasStart: 6/16/14 ID: 606

    Finish: 6/28/14 Dur: 12 days

    Res:

    Buang Tanah Bekas GalianStart: 6/30/14 ID: 607

    Finish: 7/5/14 Dur: 6 days

    Res:

    III. PEKERJAAN BETONStart: 6/30/14 ID: 608

    Finish: 8/30/14 Dur: 54 days

    Comp: 0%

    Beton Lantai Kerja t = 5 cmStart: 6/30/14 ID: 609

    Finish: 7/5/14 Dur: 6 days

    Res:

    Beton Strouss f 20 cmStart: 6/30/14 ID: 610

    Finish: 7/5/14 Dur: 6 days

    Res:

    Beton Foot Plat 1.00x1.00mStart: 6/30/14 ID: 611

    Finish: 7/19/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/14/14 ID: 612

    Finish: 7/19/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/30/14 ID: 613

    Finish: 7/19/14 Dur: 18 days

    Res:

    - BekistingStart: 6/30/14 ID: 614

    Finish: 7/19/14 Dur: 18 days

    Res:

    Beton Sloof 15/20Start: 7/21/14 ID: 615

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/4/14 ID: 616

    Finish: 8/9/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/21/14 ID: 617

    Finish: 8/9/14 Dur: 18 days

    Res:

    - BekistingStart: 7/21/14 ID: 618

    Finish: 8/9/14 Dur: 18 days

    Res:

    Beton Kolom Praktis 30/30Start: 7/21/14 ID: 619

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/4/14 ID: 620

    Finish: 8/9/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/21/14 ID: 621

    Finish: 8/9/14 Dur: 18 days

    Res:

    - BekistingStart: 7/21/14 ID: 622

    Finish: 8/9/14 Dur: 18 days

    Res:

    Beton Balok 15/20Start: 8/11/14 ID: 623

    Finish: 8/30/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 624

    Finish: 8/30/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/11/14 ID: 625

    Finish: 8/30/14 Dur: 18 days

    Res:

    - BekistingStart: 8/11/14 ID: 626

    Finish: 8/30/14 Dur: 18 days

    Res:

    Beton Balok 15/15Start: 8/11/14 ID: 627

    Finish: 8/30/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 628

    Finish: 8/30/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/11/14 ID: 629

    Finish: 8/30/14 Dur: 18 days

    Res:

    - BekistingStart: 8/11/14 ID: 630

    Finish: 8/30/14 Dur: 18 days

    Res:

    Saluran BetonStart: 7/21/14 ID: 631

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/4/14 ID: 632

    Finish: 8/9/14 Dur: 6 days

    Res:

    - BekistingStart: 7/21/14 ID: 633

    Finish: 8/9/14 Dur: 18 days

    Res:

    IV. PEKERJAAN PASANGANStart: 8/11/14 ID: 634

    Finish: 8/30/14 Dur: 18 days

    Comp: 0%

    Pasangan Batu Belah 1 PC :Start: 8/11/14 ID: 635

    Finish: 8/30/14 Dur: 18 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 8/11/14 ID: 636

    Finish: 8/30/14 Dur: 18 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 8/11/14 ID: 637

    Finish: 8/30/14 Dur: 18 days

    Res:

    Pasangan Batu Alur Start: 8/11/14 ID: 638

    Finish: 8/30/14 Dur: 18 days

    Res:

    V. PEKERJAAN PLESTERANStart: 9/1/14 ID: 639

    Finish: 9/20/14 Dur: 18 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 640

    Finish: 9/20/14 Dur: 18 days

    Res:

    Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 641

    Finish: 9/20/14 Dur: 18 days

    Res:

    Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 642

    Finish: 9/20/14 Dur: 18 days

    Res:

    Plesteran CipratStart: 9/1/14 ID: 643

    Finish: 9/20/14 Dur: 18 days

    Res:

    AcianStart: 9/1/14 ID: 644

    Finish: 9/20/14 Dur: 18 days

    Res:

    Setrikan / SiarStart: 9/1/14 ID: 645

    Finish: 9/20/14 Dur: 18 days

    Res:

    Benangan SudutStart: 9/1/14 ID: 646

    Finish: 9/20/14 Dur: 18 days

    Res:

    VI. PEKERJAAN BESIStart: 9/1/14 ID: 647

    Finish: 9/20/14 Dur: 18 days

    Comp: 0%

    Tiang Kawat Duri L-50.50.5Start: 9/1/14 ID: 648

    Finish: 9/20/14 Dur: 18 days

    Res:

    Kawat Duri 5 LapisStart: 9/1/14 ID: 649

    Finish: 9/20/14 Dur: 18 days

    Res:

    VII. PEKERJAAN PENGECATStart: 9/22/14 ID: 650

    Finish: 10/4/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding denganStart: 9/22/14 ID: 651

    Finish: 10/4/14 Dur: 12 days

    Res:

    PENGURUGANStart: 5/19/14 ID: 653

    Finish: 5/31/14 Dur: 12 days

    Comp: 0%

    A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 654

    Finish: 5/31/14 Dur: 12 days

    Comp: 0%

    A.1 LANTAI 1Start: 5/19/14 ID: 655

    Finish: 5/31/14 Dur: 12 days

    Comp: 0%

    I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 656

    Finish: 5/31/14 Dur: 12 days

    Comp: 0%

    Pembongkaran Bangunan LaStart: 5/19/14 ID: 657

    Finish: 5/31/14 Dur: 12 days

    Res:

    Pembersihan LokasiStart: 5/19/14 ID: 658

    Finish: 5/31/14 Dur: 12 days

    Res:

    II. PEKERJAAN TANAHStart: 5/19/14 ID: 659

    Finish: 5/31/14 Dur: 12 days

    Comp: 0%

    Urugan SirtuStart: 5/19/14 ID: 660

    Finish: 5/31/14 Dur: 12 days

    Res:

    PemadatanStart: 5/19/14 ID: 661

    Finish: 5/31/14 Dur: 12 days

    Res:

    LAPANGAN BASKETStart: 5/19/14 ID: 663

    Finish: 8/23/14 Dur: 84 days

    Comp: 0%

    I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 664

    Finish: 5/24/14 Dur: 6 days

    Comp: 0%

    Uitset / BowplankStart: 5/19/14 ID: 665

    Finish: 5/24/14 Dur: 6 days

    Res:

    II. PEKERJAAN TANAHStart: 6/16/14 ID: 666

    Finish: 7/26/14 Dur: 36 days

    Comp: 0%

    Galian Tanah Start: 6/16/14 ID: 667

    Finish: 6/28/14 Dur: 12 days

    Res:

    Urugan Tanah Bekas GalianStart: 7/21/14 ID: 668

    Finish: 7/26/14 Dur: 6 days

    Res:

    Urugan Pasir Bawah PondasStart: 6/16/14 ID: 669

    Finish: 6/28/14 Dur: 12 days

    Res:

    Buang Tanah Bekas GalianStart: 6/30/14 ID: 670

    Finish: 7/5/14 Dur: 6 days

    Res:

    III. PEKERJAAN PASANGANStart: 7/21/14 ID: 671

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    Pasangan AanstampengStart: 7/21/14 ID: 672

    Finish: 8/9/14 Dur: 18 days

    Res:

    Pasangan Bt Belah 1 Pc : 6 PStart: 7/21/14 ID: 673

    Finish: 8/9/14 Dur: 18 days

    Res:

    Pasangan Batu Tempel DiagStart: 7/21/14 ID: 674

    Finish: 8/9/14 Dur: 18 days

    Res:

    Pasangan Buis Beton Dia. 30Start: 7/21/14 ID: 675

    Finish: 8/9/14 Dur: 18 days

    Res:

    Pasangan Paving Persegi K-Start: 7/21/14 ID: 676

    Finish: 8/9/14 Dur: 18 days

    Res:

    IV. PEKERJAAN BETONStart: 6/30/14 ID: 677

    Finish: 8/9/14 Dur: 36 days

    Comp: 0%

    Beton Lantai Kerja t = 5 cmStart: 6/30/14 ID: 678

    Finish: 7/5/14 Dur: 6 days

    Res:

    Beton PoerStart: 6/30/14 ID: 679

    Finish: 7/19/14 Dur: 18 days

    Comp: 0%

    - Pile cap type 1Start: 6/30/14 ID: 680

    Finish: 7/19/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/14/14 ID: 681

    Finish: 7/19/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/30/14 ID: 682

    Finish: 7/19/14 Dur: 18 days

    Res:

    - BekistingStart: 6/30/14 ID: 683

    Finish: 7/19/14 Dur: 18 days

    Res:

    Beton Balok 20/30Start: 6/30/14 ID: 684

    Finish: 7/19/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/14/14 ID: 685

    Finish: 7/19/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/30/14 ID: 686

    Finish: 7/19/14 Dur: 18 days

    Res:

    - BekistingStart: 6/30/14 ID: 687

    Finish: 7/19/14 Dur: 18 days

    Res:

    Beton Plat Lantai t = 10 cmStart: 7/21/14 ID: 688

    Finish: 8/9/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/4/14 ID: 689

    Finish: 8/9/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 7/21/14 ID: 690

    Finish: 8/9/14 Dur: 18 days

    Res:

    - BekistingStart: 7/21/14 ID: 691

    Finish: 8/9/14 Dur: 18 days

    Res:

    V. PEKERJAAN PLESTERANStart: 8/11/14 ID: 692

    Finish: 8/16/14 Dur: 6 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 8/11/14 ID: 693

    Finish: 8/16/14 Dur: 6 days

    Res:

    VI. PEKERJAAN PENGECATAStart: 8/18/14 ID: 694

    Finish: 8/23/14 Dur: 6 days

    Comp: 0%

    Pengecatan LapanganStart: 8/18/14 ID: 695

    Finish: 8/23/14 Dur: 6 days

    Res:

    GEDUNG EStart: 5/19/14 ID: 697

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    A. PEKERJAAN STRUKTURStart: 5/19/14 ID: 698

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    A.1 LANTAI 1Start: 5/19/14 ID: 699

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    I. PEKERJAAN PERSIAPANStart: 5/19/14 ID: 700

    Finish: 12/13/14 Dur: 180 days

    Comp: 0%

    Pembersihan LokasiStart: 5/19/14 ID: 701

    Finish: 5/31/14 Dur: 12 days

    Res:

    Pembersihan AkhirStart: 12/1/14 ID: 702

    Finish: 12/13/14 Dur: 12 days

    Res:

    A.2 LANTAI 2Start: 8/4/14 ID: 703

    Finish: 9/13/14 Dur: 36 days

    Comp: 0%

    I. PEKERJAAN BETONStart: 8/4/14 ID: 704

    Finish: 9/13/14 Dur: 36 days

    Comp: 0%

    1. Beton KolomStart: 8/4/14 ID: 705

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Type K1 - 40/50Start: 8/4/14 ID: 706

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 707

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 708

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 709

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 710

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K2 - 30/30Start: 8/4/14 ID: 711

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 712

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 714

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 715

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K3 - 20/80Start: 8/4/14 ID: 716

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 717

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 718

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 719

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 720

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Type K4 - 20/60Start: 8/4/14 ID: 721

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 722

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 723

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 724

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 725

    Finish: 8/23/14 Dur: 18 days

    Res:

    2. Beton BalokStart: 8/25/14 ID: 726

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Type BLT - 15/20Start: 8/25/14 ID: 727

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 728

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 729

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 730

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 731

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BLK - 15/20Start: 8/25/14 ID: 732

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 733

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 734

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 735

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 736

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL - 20/40Start: 8/25/14 ID: 737

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 738

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 739

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 740

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 741

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL1- 30/60Start: 8/25/14 ID: 742

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 743

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 744

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 745

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 746

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BL2- 30/40Start: 8/25/14 ID: 747

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 748

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 749

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 750

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 751

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BA1 - 20/30Start: 8/25/14 ID: 752

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 753

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 754

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 755

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 756

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Type BA2 - 15/25Start: 8/25/14 ID: 757

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 758

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/25/14 ID: 759

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 760

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 761

    Finish: 9/13/14 Dur: 18 days

    Res:

    3. Beton Plat Lantai 3Start: 8/25/14 ID: 762

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 763

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 764

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 765

    Finish: 9/13/14 Dur: 18 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 713

    Finish: 8/23/14 Dur: 18 days

    Res:

    Page 5

  • 4. Beton Plat KanopiStart: 8/25/14 ID: 766

    Finish: 9/13/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 9/8/14 ID: 767

    Finish: 9/13/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 768

    Finish: 9/13/14 Dur: 18 days

    Res:

    - BekistingStart: 8/25/14 ID: 769

    Finish: 9/13/14 Dur: 18 days

    Res:

    5. Beton TanggaStart: 8/4/14 ID: 770

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton Plat TanggaStart: 8/4/14 ID: 771

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 772

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 773

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 774

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Balok BordesStart: 8/4/14 ID: 775

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 776

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan DeformStart: 8/4/14 ID: 777

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 778

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 779

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Plat BordesStart: 8/4/14 ID: 780

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 781

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 782

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 783

    Finish: 8/23/14 Dur: 18 days

    Res:

    - Beton Anak TanggaStart: 8/4/14 ID: 784

    Finish: 8/23/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 8/18/14 ID: 785

    Finish: 8/23/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 8/4/14 ID: 786

    Finish: 8/23/14 Dur: 18 days

    Res:

    - BekistingStart: 8/4/14 ID: 787

    Finish: 8/23/14 Dur: 18 days

    Res:

    B. PEKERJAAN ARSITEKTUStart: 5/19/14 ID: 788

    Finish: 10/25/14 Dur: 138 days

    Comp: 0%

    XI. PEKERJAAN SEPTICTANStart: 5/19/14 ID: 789

    Finish: 7/19/14 Dur: 54 days

    Comp: 0%

    Galian TanahStart: 5/19/14 ID: 790

    Finish: 5/31/14 Dur: 12 days

    Res:

    Urugan pasir urugStart: 5/19/14 ID: 791

    Finish: 5/24/14 Dur: 6 days

    Res:

    Pas. IjukStart: 6/16/14 ID: 792

    Finish: 6/21/14 Dur: 6 days

    Res:

    Pasir kerikilStart: 6/16/14 ID: 793

    Finish: 6/21/14 Dur: 6 days

    Res:

    Lantai kerjaStart: 6/16/14 ID: 794

    Finish: 6/21/14 Dur: 6 days

    Res:

    Pas. Bata merah 1:3Start: 6/16/14 ID: 795

    Finish: 6/28/14 Dur: 12 days

    Res:

    Pas. Bata merah kosongStart: 6/16/14 ID: 796

    Finish: 6/28/14 Dur: 12 days

    Res:

    Pekerjaan beton plat penutupStart: 6/23/14 ID: 797

    Finish: 7/12/14 Dur: 18 days

    Comp: 0%

    - Beton K-250Start: 7/7/14 ID: 798

    Finish: 7/12/14 Dur: 6 days

    Res:

    - Baja Tulangan PolosStart: 6/23/14 ID: 799

    Finish: 7/12/14 Dur: 18 days

    Res:

    - BekistingStart: 6/23/14 ID: 800

    Finish: 7/12/14 Dur: 18 days

    Res:

    Plesteran Start: 7/14/14 ID: 801

    Finish: 7/19/14 Dur: 6 days

    Res:

    acianStart: 7/14/14 ID: 802

    Finish: 7/19/14 Dur: 6 days

    Res:

    B.2 LANTAI 2Start: 8/11/14 ID: 803

    Finish: 10/25/14 Dur: 66 days

    Comp: 0%

    I. PEKERJAAN TANAHStart: 10/6/14 ID: 804

    Finish: 10/11/14 Dur: 6 days

    Comp: 0%

    Urugan Pasir Bawah lantaiStart: 10/6/14 ID: 805

    Finish: 10/11/14 Dur: 6 days

    Res:

    II. PEKERJAAN BETONStart: 8/25/14 ID: 806

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    1. Beton Kolom PraktisStart: 8/25/14 ID: 807

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 808

    Finish: 9/6/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 809

    Finish: 9/6/14 Dur: 12 days

    Res:

    - BekistingStart: 8/25/14 ID: 810

    Finish: 9/6/14 Dur: 12 days

    Res:

    2. Beton Balok Latei 15/20Start: 8/25/14 ID: 811

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    - Beton K-250Start: 8/25/14 ID: 812

    Finish: 9/6/14 Dur: 12 days

    Res:

    - Baja Tulangan PolosStart: 8/25/14 ID: 813

    Finish: 9/6/14 Dur: 12 days

    Res:

    - BekistingStart: 8/25/14 ID: 814

    Finish: 9/6/14 Dur: 12 days

    Res:

    III. PEKERJAAN PASANGANStart: 8/25/14 ID: 815

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 816

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasangan Batu Merah 1/2 baStart: 8/25/14 ID: 817

    Finish: 9/6/14 Dur: 12 days

    Res:

    IV. PEKERJAAN PLESTERAStart: 9/1/14 ID: 818

    Finish: 9/20/14 Dur: 18 days

    Comp: 0%

    Plesteran Dinding 1PC : 3PsStart: 9/1/14 ID: 819

    Finish: 9/13/14 Dur: 12 days

    Res:

    Plesteran Dinding 1PC : 6PsStart: 9/1/14 ID: 820

    Finish: 9/13/14 Dur: 12 days

    Res:

    Plesteran Beton 1PC : 3Ps Start: 9/1/14 ID: 821

    Finish: 9/13/14 Dur: 12 days

    Res:

    AcianStart: 9/8/14 ID: 822

    Finish: 9/20/14 Dur: 12 days

    Res:

    Benangan Sudut, Plinkolt & Start: 9/8/14 ID: 823

    Finish: 9/20/14 Dur: 12 days

    Res:

    Water Proofing Kanopi + potStart: 9/8/14 ID: 824

    Finish: 9/20/14 Dur: 12 days

    Res:

    V. PEKERJAAN PELAPIS LAStart: 10/13/14 ID: 825

    Finish: 10/25/14 Dur: 12 days

    Comp: 0%

    Pasang Keramik Lantai 40x4Start: 10/13/14 ID: 826

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Keramik Lantai 30x3Start: 10/13/14 ID: 827

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Keramik Tangga 30xStart: 10/13/14 ID: 828

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Keramik Dinding 25xStart: 10/13/14 ID: 829

    Finish: 10/25/14 Dur: 12 days

    Res:

    VI. PEKERJAAN KUSEN PINTStart: 8/25/14 ID: 830

    Finish: 9/6/14 Dur: 12 days

    Comp: 0%

    Pasang kusen dan pintu KMStart: 8/25/14 ID: 831

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Daun Pintu Double TStart: 8/25/14 ID: 832

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Daun jendela DoubleStart: 8/25/14 ID: 833

    Finish: 9/6/14 Dur: 12 days

    Res:

    Pasang Kusen dan Pintu KM/Start: 8/25/14 ID: 834

    Finish: 9/6/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PENGGANTStart: 10/13/14 ID: 835

    Finish: 10/25/14 Dur: 12 days

    Comp: 0%

    Pasang Kunci PintuStart: 10/13/14 ID: 836

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Engsel Pintu 4"Start: 10/13/14 ID: 837

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel TanamStart: 10/13/14 ID: 838

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel Pintu BiasaStart: 10/13/14 ID: 839

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Engsel Jendela ModStart: 10/13/14 ID: 840

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Grendel JendelaStart: 10/13/14 ID: 841

    Finish: 10/25/14 Dur: 12 days

    Res:

    Pasang Railling Tangga PipaStart: 10/13/14 ID: 842

    Finish: 10/25/14 Dur: 12 days

    Res:

    VII. PEKERJAAN PLAFONDStart: 9/29/14 ID: 843

    Finish: 10/11/14 Dur: 12 days

    Comp: 0%

    Pasang Penutup Plafond GyStart: 9/29/14 ID: 844

    Finish: 10/11/14 Dur: 12 days

    Res:

    Pasang Lis Gypsum 12 cmStart: 9/29/14 ID: 845

    Finish: 10/11/14 Dur: 12 days

    Res:

    VIII. PEKERJAAN SANITASIStart: 8/11/14 ID: 846

    Finish: 9/6/14 Dur: 24 days

    Comp: 0%

    Pasang FloordrainStart: 8/11/14 ID: 847

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kloset JongkokStart: 8/11/14 ID: 848

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang WastafelStart: 8/11/14 ID: 849

    Finish: 9/6/14 Dur: 24 days

    Res:

    IX. PEKERJAAN PENGECATAStart: 10/6/14 ID: 850

    Finish: 10/18/14 Dur: 12 days

    Comp: 0%

    Pengecatan Dinding ExterioStart: 10/6/14 ID: 851

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pengecatan Dinding InteriorStart: 10/6/14 ID: 852

    Finish: 10/18/14 Dur: 12 days

    Res:

    Pengecatan PlafondStart: 10/6/14 ID: 853

    Finish: 10/18/14 Dur: 12 days

    Res:

    C. PEKERJAAN PLUMBINGStart: 8/11/14 ID: 854

    Finish: 9/6/14 Dur: 24 days

    Comp: 0%

    C.2 LANTAI 2Start: 8/11/14 ID: 855

    Finish: 9/6/14 Dur: 24 days

    Comp: 0%

    Pasang Pipa Pengisi TandonStart: 8/11/14 ID: 856

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Induk DistribusStart: 8/11/14 ID: 857

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Bersih PVCStart: 8/11/14 ID: 858

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 859

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Air Kotor PVC TStart: 8/11/14 ID: 860

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Pipa Induk Air KotorStart: 8/11/14 ID: 861

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Talang tegak PVC TyStart: 8/11/14 ID: 862

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Stop Kran dia 1" Start: 8/11/14 ID: 863

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kran dia 1/2" DUPONStart: 8/11/14 ID: 864

    Finish: 9/6/14 Dur: 24 days

    Res:

    Pasang Kran wastafel 1/2"Start: 8/11/14 ID: 865

    Finish: 9/6/14 Dur: 24 days

    Res:

    Sumur Bor (Lengkap AksesoStart: 8/11/14 ID: 866

    Finish: 9/6/14 Dur: 24 days

    Res:

    Tandon Air 4000 L SteinlessStart: 8/11/14 ID: 867

    Finish: 9/6/14 Dur: 24 days

    Res:

    D. PEKERJAAN LISTRIKStart: 8/11/14 ID: 868

    Finish: 9/20/14 Dur: 36 days

    Comp: 0%

    D.2 LANTAI IIStart: 8/11/14 ID: 869

    Finish: 9/20/14 Dur: 36 days

    Comp: 0%

    Titik Instalasi Penerangan (NStart: 8/11/14 ID: 870

    Finish: 9/20/14 Dur: 36 days

    Res:

    Titik Instalasi Stop Kontak (NStart: 8/11/14 ID: 871

    Finish: 9/20/14 Dur: 36 days

    Res:

    Saklar tunggalStart: 8/11/14 ID: 872

    Finish: 9/20/14 Dur: 36 days

    Res:

    Saklar SeriStart: 8/11/14 ID: 873

    Finish: 9/20/14 Dur: 36 days

    Res:

    Lampu PLC 24 watt + fittingStart: 8/11/14 ID: 874

    Finish: 9/20/14 Dur: 36 days

    Res:

    Stop kontak 200 VAStart: 8/11/14 ID: 875

    Finish: 9/20/14 Dur: 36 days

    Res:

    Pasang Panel Lantai 2Start: 8/11/14 ID: 876

    Finish: 9/20/14 Dur: 36 days

    Res:

    Pasang Kabel induk NYY 4x4Start: 8/11/14 ID: 877

    Finish: 9/20/14 Dur: 36 days

    Res:

    Page 6

  • Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical

    Page 7

    Project: SMA4 Project 2007Date: Wed 4/30/14