Course Objectives

Module 1 : Introduction

Module 2 : Planning the Project

Module 3: Task Entry and Task LinkingModule 4: Resources and Resource Management

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 3/56

Module 1 : Introduction

Start Project 2010.

Note the difference between Project Standard and Project

Professional editions and the new features available.

Open a Project File.

Use the ribbon interface and the new Timeline view.

Change the View of a Project.

Understand terms and procedures in project management and

planning.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 4/56

Fundamental of Project Management

Projects ± What are they?

� Inter-related tasks to achieve a goal

� Require resources to complete

� Within a certain time frame

Complex or Simple

� Task link to Task

� Project link to project

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 5/56

Why use Project Management Software?

Scheduling

Cost Control

Budget Management

Resource Allocation

Collaboration Software

Communication

Quality Management

Documentation

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 6/56

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 7/56

New Features and Edition Comparison

Professional

Project Server

Standard

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 8/56

Starting Project

Getting Help

Ms Project ± The Screen Quick Access Toolbar 

The Ribbon

The Timeline

Entry Bar 

Views and Tables

Status Bar 

Scroll Bar 

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 9/56

The Screen

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 10/56

View Ribbon / Tab

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 11/56

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 12/56

The Stages of Project Management

Defining the Project

Plan/Design Project

Determine Dependencies and Constraint

Monitoring and Adjusting

Track Progress

Evaluation

Reporting

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 13/56

How MS Project Helps«

 

The ³Black Box´(algorithm)

In ut 

Task Information Task NameDurationTask RelationshipsFixed CostsConstraints

ResourceInformation WhoAvailability Cost 

Output (Schedule)

 Gantt Network DiagramResource Graph

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 14/56

How MS Project Helps« 

Summary Task 

E A   The earliest possible time a task can start.

SS   The scheduled start time of the task.

S E The scheduled end time of the task.

LE The latest possible time a task can end.

Predecessor Task 

Task A

Task B

Successor Task 

EA SS  SE               LE

Total Slack Delay 

Free Slack 

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 15/56

A Work Breakdown Structure (WBS)

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 16/56

Project Management Terminology

C

ritical PathASAP

Baseline

Cost Variance

Lead/Lag

PERT ALAP

Float

Milestone

WBSCode

LoadingUniform)

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 17/56

Module 2 : Planning the Project

Define your own project.

Start to use MS Project.

Amend and create project calendars.

Save and close projects.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 18/56

Defining the Project

Setting out the Goal

Identify major phases of Project

Create tasks that represent a logical sequence of steps

Collect necessary information you need to define the

project¶s scope.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 19/56

Planning «

Plan tasks and resources

Resources

People, material, Machine or Equipment

Get input from team members to make sure you¶re using

the right combinations

Create different plans ± if time permits

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 20/56

Dependencies and Constraints«

Dependencies

� Relationship between tasks that affect timing of 

the project. Constraints

� Determine when a task must begin or end in

order to meet the deadline

� As soon as possible is the default

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 21/56

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 22/56

Set Critical Path

Outlines all critical tasks

These are the tasks that will cause a project

deadline to delay if they slip

Must be managed well to guarantee the success

of the entire project

Project 2010 can helps to navigate and explore

this CPM every effectively.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 23/56

Track Progress

Important to keep project on track

Planning is only the beginning ± Tracking

progress is the key to project management.

Solidify your tracking methods prior to starting the

project to avoid frustation ± as to who tracks what

where and when.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 24/56

Final : Reporting«

Reports are generated automatically as when

task, resources, costing and etc. are entered into

the project.

Report can be printed or shared across network

Project 2010 has many pre-set reports

Customization of reports are available too

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 25/56

Define the Project Start Date / End Date

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 26/56

DefiningWorking / Non Working Hours

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 27/56

Create New Calender 

Shift Start End

Morning 6am 10am

Break 10am 11am

Morning 11am 3pm

Evening 3pm 7pm

Break 7pm 8pm

Evening 8pm 12am

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 28/56

Saving Project Files«

A File name can contain up to 255 characters and will

automatically be given a file extension of .mpp.

If you open a project created in a previous version, it will openin compatibility mode and when you save it, it will be saved in

the previous file format.

Click the File tab and choose Save As if you amend or update

a project and wish to save a separately named copy of it.

Save as Project Template

Save as PDF Format / XPS Format

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 29/56

Module 3:T

ask Entr y andT

ask Linking

Understand the new Task Mode and how it affect the project

schedule

Enter, Delete and Edit Tasks.

Link Tasks.

Create a project outline using summary and subtasks

Insert milestone and recurring tasks

Understand how constraints and deadlines impact tasks

Use automatic features including AutoCorrect and AutoFill

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 30/56

Creating Tasks

The Title

The Objective of the Task

The time required to complete the task.

(Give an optimistic and pessimistic estimation.)

A note of any previous task or tasks that are associated with

this task.

The immediate subsequent tasks.

The resource(s) that are required to complete the task. Any time constraints that apply.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 31/56

Entering aT

askD

uration

Min = Minutes

Hr = Hours

D = Days

W = Weeks

M = Months

0 days = Milestone

? = Estimated

E prefix = Elapsed Time

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 32/56

Inserting aT

ask and Summar y T

ask

Like Microsoft Excel, when editing an entry in a

cell the field entry bar is active and you can

choose         or 

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 33/56

Task Information

Dialog Box

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 34/56

Deleting

Task and Undo Changes

By pressing del button

Clear a cell

Restore default value

To remove a Task Click on Task ID, press del button

Combination key Ctrl Minus

Undo level limited to 20 changes [default]

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 35/56

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 36/56

Milestone in Project

The end of a stage

Marks the completion of work package or phase

Signify an important decision made

With PERT or CPM, more accurately determine whether or not

the project is on schedule.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 37/56

RecurringT

asks

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 38/56

Other T

asks¶s Options Adding a Note

Cell Formatting

Roll up Bars

Manual or Automatic Scheduling

Scheduling Ignore Resource Calendars

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 39/56

Task Relationships and

Type of Links

Predecessor

Successor

Four linkage types

� Finish to Start (FS)

� Start to Start (SS)

� Finish to Finish (FF)

� Start to Finish (SF)

Lag and Lead Time

Splitting Tasks

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 40/56

Creating Constraints for T

asksConstraint type Description

As Late as Possible Starts the task as late as possible, depending on other task constraints and relationships.  You do

not need to enter a date to use this constraint

As Soon as Possible Starts the task as soon as possible, depending on other task constraints and relationships.  You

do not need to enter a date to use this constraint.  This is thedefault and is equivalent to having 

no constraint 

Finish No earlier than Constrains the task to finish on or after the date that you enter in the Date box. You can manually

enter this constraint by typing a date in the Finish field in the Gantt table

Finish no later than Constrains the task to finish on or before the date that you enter in the Date box

Must Finish on Constrains the task to finish on the date that you enter in the Date box.

Must Start On Constrains the task to start on the date that you enter in the Date box.

Start No Earlier than Constrains the task to start on or after the date that you enter in the Date box. You can manually

enter this constraint by typing a date in the Start field

Start No Later than Constrains the task to start on or before the date that you enter in the Date box

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 41/56

Resolving Scheduling Conflicts

Manual vs Automatic Scheduling

Respect Links

Inspect Tasks

Move Tasks

Setting a deadline on a task 

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 42/56

Module 4: Resources and Resource Management An understanding of the various information required to enter 

resources

Assigned resources to the tasks

Changed individual resource calendars/availability

Modified task assignments

Completed the end of the design and planning stage and

baselined the project.

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 43/56

Creating Resources You are able to track the whereabouts of resources

You can identify potential resource shortages or overallocation

that could force you to miss scheduled deadlines and which, in

turn, could possibly extend the duration of your project.

You can identify under-utilised resources ± and if you reassign

these resources, you may be able to shorten the project¶s

duration.

Project uses a resource calendar to automatically schedule the

working / non-working times of a resource

Overallocated resources will show red person icon

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 44/56

Entering Resources

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 45/56

Resource Availability D

ates

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 46/56

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 47/56

UnderstandingH

ow Cost per use is calculated

For example allocating Peter Pan with Max Units = 100%,

Standard Rate of Rm100/hr to a 5 day task. Total Cost will

result in the following

Duration 5 day

Work 5 * 8 hours

= 40 hrs

Total Cost 100% * 100/hr * 40 hrs

= RM4000

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 48/56

UnderstandingH

owT

otal Cost is calculated

For example allocating a Peter Pan with Max Units = 50%,

Standard Rate of Rm100/hr to a 5 day task. Total Cost will

result in the following

Duration 5 day

Work 40 hours

Total Cost 50% * 100/hr * 40 hrs

= RM 2000

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 49/56

UnderstandingH

owT

otal Cost is calculated

For example allocating a Samuel with Max Units = 75%, Standard

Rate of Rm100/hr and Cost/Use = RM500 to 2 days task. Total

Cost will result in the following

Duration 2 days

Work 16 hours

Total Hourly Cost 75% * 100/hr * 16 hrs

= RM1200

Cost/Use 75% * Rm500= RM 375

Total Cost RM1200 + RM 375

= RM 1575

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 50/56

UnderstandingH

owT

otal Cost is calculated

For example allocating a Resource with Units = 500%, Standard

Rate of Rm30/hr to 3 days task. Total Cost will result in the

following

Duration 3 days

Work 3 * 8 hours

= 24 hrs

Total Hourly Cost 500% * 30/hr * 24 hrs

= RM 3600

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 51/56

UnderstandingH

owT

otal Cost is calculated

For example allocating Samuel and 10 workers to a 5 days Task..

Total Cost will result in the following

Duration 5 days

Work 5 * 8 hours

= 40 hrs

Total Hourly Cost for Workers 1000% * 30 /hr * 40 hrs

= RM 12000Total Hourly Cost + Cost/Use

for Samuel

(100% * 100 /hr * 40 hrs) +

RM500

= RM 4500

Total Cost RM12000 + RM 4500

= RM16500

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 52/56

UnderstandingH

ow Overtime Rate is calculatedFor example allocating Samuel Angel to a 10 days task and ask to

work for 40 hrs OT with Std Rate ± 100/hr Ovt Rate ± 150/hr.

Total Cost will result in the following

Duration 10 days

Ovt Work 40 hrs

Shorten New

Duration

10 d ((40h / 80h )* 10 d)

= 5 days

Total Cost (Normal Hrs*Std Rate)+(OT Hrs*OT Rate)+(Cost/use)

(40*100) + (40*150) + (500)

= 4000 + 6000 + 500

= RM 10500

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 53/56

Team Planner (

New Features in 2010)

8/7/2019 MSProject 2010 Essential

http://slidepdf.com/reader/full/msproject-2010-essential 54/56

More Resources Options

Assigning Additional Resources to reduce task duration

Effort Driven and Manually Scheduled

Fixed Duration / Fixed Units / Fixed Works

Update the Task Completion Percentage