msc.abst+
TRANSCRIPT
-
7/27/2019 Msc.Abst+
1/8
Supervision and delay in implementing construction projects
The role of owners supervisor
Abstract:The construction industry in Libya has grown with a remarkable increase during the previous
three decades after the discovery of oil and the rise of September revolution. As a sequence of that,
various industries were established, and the geographic change took place in the demography of the
population, as well as the growth in the economic activity, such elements represent the important
factors in the rising and development of prosperity movement in various spheres, starting from
infrastructure to investment projects, aiming to achieve economic incomes. Although such projects
have a significant and paramount role to play, most of them are subject to delay problems during their
several stages, which lead to a rational loss to all contracting parties, and cause many conflicts
between them. The probability of the construction project being subject to delay is due to its multiple
inputs and due to the various kinds of its resources, in addition to the special requirements and uniquenature that may characterize each construction project distinctly from another, and also because of the
numerous parties undertaking its execution.
The owners supervisor plays an important role in supervising the performance of the
contractor in order to achieve the three main goals of the owner project ( time, quality, and cost). In
this regard, the supervisor can follow specific procedures during his supervision for achieving two
goals: quality of accomplished work, and the execution of the project within the limits of the allocated
budget, while the associating process of the project schedule time is considered to be one of the most
difficult tasks which lead to problems occurrence. Such an issue requires a qualified supervisor with
high skills, well known and a good understanding of how such delay occurs, and the way to deal with
it, and a knowledge of modern techniques being used. Ultimately any supervisor shortcoming will
cause a project cost increase because of its delay in particular, and categorically due to the rarity of
studies dealing with the tasks of the owners supervisor.
Due to the general trend to assign supervisory tasks to Libyan nationals, and the absence of
information about the extent efficiency of the national supervisor, this research work was conducted
depending on information obtained from opinions field survey of national experts in the field of
executing construction projects, aiming to evaluate the efficiency degree of the national supervisor
both as an individual engineer or as an organization concerning the delay, and to detect the
shortcoming aspects as well as its/his role in the delay occurrence.
Suggested solution models which were approached and tested by Libyan supervision experts,
are :
1 The engineer performance evaluation model concerning the delay which was applied to Libyan
supervisor engineer, resulted 48.38% degree of current efficiency, while the minimum required
points should not be less than 51.08%.2 The organization quality procedures evaluation model concerning the delay which was applied to
Libyan organizations, resulted 53.6% degree of current efficiency, while the minimum required
points should not be less than 50.24%.
3 The supervision causing delay rate model showed 18.16% , with an increasing executing time
with 13% of the contractual duration.
4 The national supervisor engineer efficiency predicating model obtained was :
Y = 3.91 + 0.928x1 + 1.42x3 + 1.45x5 + 4.24x7 ,
and the causing delay rate was found as :
R = ( 1 Y ) * 7.02
The first three solution models mentioned above were consisting a Database, Statistical analysis, andSolution model system (DSS) in a software program which was attached with the thesis on a CD laser
disc together with a user manual.
-
7/27/2019 Msc.Abst+
2/8
This software was designed very simple to be used, with an ability for modification, develop and
possible to be used out side Libya with few changes in the local experts factors.
1. Introduction
The project life cycle goes through three main stages. These are design;
construction, and maintenance. The design stage encompasses scientific
principles and initiatives; technical knowledge and developments, and an
understanding of the users needs and requirements, taking into account both the
resulting physical and mental working environment.
The construction stage is the execution of the work in accordance with the
contractual agreement. To ensure that the construction project adheres to the
agreed contract, the owner has his own supervisor to monitor the work and
check its progress according to the plans.
The final stage of the project comes into effect once the construction is
completed. This stage according to specified time is the maintenance period
where any defects are remedied.
Once the decision has been made to proceed with the construction project,
the client will usually have three main goals.
- To complete the project within the budget.
- To complete the project on time.
- To ensure completion of the project in conformance with the contractspecifications.
For the successful completion of a project, the construction participants
must aim to work toward achieving the clients goals. Various contractual
arrangements are used to govern the construction process. These may take the
traditional approach as is the general rule in Libya, or use alternative systems
such as BOOT contract (build, own, operate, and transfer) and design and build
contracts. The client can appoint an engineering team from his own organization
-
7/27/2019 Msc.Abst+
3/8
or employ an independent team of engineers to carry out feasibility studies;
provide detailed design and contract documentation. After the decision to
proceed with the project has been made, tenders can be invited and a
competitive contractor selected.
The client may make three contracts.
- Client and contractor to implement the project.
- Client and consultant to carry out the preliminary study and design stage.
- The client and supervisor to monitor the contractors performance within theagreed contract. The contract for supervision may be made with the existing
design consultant or a separate body.
The owners supervisor (either an individual or an organization) represents
the owner on the construction site and ensures that the clients goals of quality,
cost, and time are achieved. To guarantee the achievement of these goals, the
supervisor devises appropriate procedures which also set out clear guidelines to
monitor the quality and the cost, but time monitoring and dealing with delays is
the main problem and is considered to be the most difficult task facing the
supervision team and the project manager.
Most of the construction projects in Libya are subject to delay during the
actual construction phase which increases the project costs; overrun costs,
acceleration costs, and delayed income from the finished project. The lack of
the supervisors efficiency and shortage of understanding of the problems and
failure to use new techniques does not allow the supervisor to protect the
owners interests.
The supervisor should have scientific and technical knowledge and the skills
to adjust to and take on new and future technical developments.
The supervisor needs to understand the contract procurement system as well
as have experience in record-keeping. The supervisor should also have
-
7/27/2019 Msc.Abst+
4/8
background knowledge in the legal complexities of owner/contractor
relationships, an understanding of the regulations involved in different
client/contractor contracts and types and forms as well as the rights and
obligations of both parties. This is to minimize the risk of claims made by the
contractor.
The supervisor needs these special skills when monitoring project schedules
and dealing with the variety of delay problems which are the most difficult
areas to control. At present, the construction industry is highly competitive, asother industries, and aims to minimize its costs. One way to minimize costs is to
minimize the consequences of delays in construction projects. Most
construction projects, if not all, are subject to delays. The construction industry
throughout the world faces a variety of challenges concerning delays and
Libyan construction projects face the same challenges; sometimes to a greater
degree. In this case the owner of most large construction projects in Libya is the
government. The Libyan supervisor needs to be armed with the required skills
to deal with these problems of delay. In spite of the important role of the
owners supervisor in protecting the owner from extra delay costs, - in the
construction industry worldwide - very little has been written about it. This
thesis is concerned with the owners supervisor and his efficiency and the
requirements to deal with delays on construction sites.
Problem Background.
Information concerning the problems of the owners supervisor in construction
projects in Libya has been gathered from the researchers experience in
supervising some construction projects and from discussions with supervising
engineers; and from the reports of The Public Committee of Projects
Monitoring and Follow-up The Division for Projects and Contract
-
7/27/2019 Msc.Abst+
5/8
Management (The Public Committee of Projects Monitoring and Follow-up,
1999) and also by the majority of court cases between contractors and clients.
Discussions and interviews have been carried out with Libyan owners,
contractors, and experts who have stated that the Libyan supervisor needs
improvement and is lacking in efficiency, especially as - apart from a few
exceptions - construction projects in Libya have Libyan supervisors.
2. Research Hypotheses- Libyan supervisor limitation in understanding the nature of delay problems
and his shortage in using modern techniques to determine and measure the delay
in the construction field.
- Participation of supervisors deficiency in overruns of delay problems in
Libya.
3. Research Objective
3.1 Developing a technique that aims to help the Libyan consultant
organizations to assess the supervisors engineer, and improve his skills and
abilities (dealing with the delays). This will include:
- Employing new supervisor engineers.
- Selecting of planning and control teams and supervisor engineers to work
in the construction site.
- Determine the efficiency shortage in engineers who are working for the
consultant office.
- Preparing training plans
3.2 Determining the supervisor role in the occurrence of delay in Libya.
-
7/27/2019 Msc.Abst+
6/8
This research will contribute in bridging the gap between academic research and
practical work experience in the construction industry. It also provide a model
which could be used in assisting the efficiency of supervising engineers.
The Limits of the Research.
This study is based on the opinions of Libyan engineering experts who have
experience in the supervising of medium scale and large scale government-
owned construction projects within the city of Tripoli which, like the majorityof construction projects in Libya follow a traditional procurement system.
4. Research Methodology
4.1 Preliminary Study
- Reviewing of new related references
- Exploration study for some consultant offices to list the variables and
develop the questionnaire.
- Developing of Solution Model
4.2 Questionnaire model developing:
- Assessment of questionnaire model that assess owners supervisor
efficiency degree by performing a pilot study.
- Developing the questionnaire model and conducting the survey.
4.3 Analysis system developing
- Preliminary study and primary development for the analysis system.
- Assess the analysis system which has been preliminary developed by
discussing specialist in statistics, mathematics and information technology.
4.4 Model or technique developing
4.5 Testing the developed model (technique) by designing a questionnaire
about solution validity.
-
7/27/2019 Msc.Abst+
7/8
4.6 Applying the supervisor assessment model to the supervisors.
4.7 Results
- Determine supervisor efficiency degree (individual and average)
- Determine efficient subjects variables and rank their importance
- Produce a regression equation (model) which will be used to predict the
supervisor efficiency degree.
- Determine the correlation between supervisor efficiency degree and his role
in delays occurring.
5. Thesis Organization.
This thesis presents the research work conducted in five chapters. The first
chapter covers the main phases of construction projects, the parties involved
and contracts that may be made between them during these phases. The role of
the owners supervisor on site in ensuring the achievement of the three main
goals of the owner. What knowledge, experience and skills are required to
enable him to perform this role. How the supervisor deals with delays, which
are a major aspect of most construction projects.
The awareness and identification of problems are also covered in this
chapter, as well as determining the research hypotheses and objectives and how
it will contribute academically and practically in assessing the efficiency of the
owners supervisor in dealing with delays in construction projects. Determining
the existing efficiency and ways to improve this efficiency.
The second chapter shows and discusses what has been written in relation
to this subject. It provides: a general overview of project management and the
construction industry in Libya and abroad. The requirements needed by the
supervisor in order to perform effectively. American, British and Libyan
-
7/27/2019 Msc.Abst+
8/8
conditions and regulations relating to delays. Project programs and schedules.
Delay problems and their effects on quality and costs of construction projects.
The causes, types and costs of delay. How to measure it. Determining which
party is responsible for the delays, delay claims and the way record keeping
and management systems help to deal with these claims.
Chapter three explains the procedures adopted in developing the
questionnaire and conducting the survey. It includes the process of selecting the
survey method, determining the variables, defining the subjects to be coveredby the questions. Conducting a pilot study and adjusting the questionnaire.
Making software analysis for the data obtained by the questionnaire. Selecting
the survey sample and describing the administration of the questionnaire.
The fourth chapter presents the rates of responses obtained. The
classification of responses. It also presents in detail the analysis of data obtained
together with a discussion of results. It describes the procedure for preparing the
research data for the analysis process. A summing-up of the main points
stemming from analyzing and discussing the results.
Chapter five presents the results and details of conclusions and the
recommendations made from this research. It also provides the solution models
and their subsequent use. Testing the model validation.
At the end of the thesis a number of appendices relating to the different
chapters introduced above, are presented together with a list of references used
in the literature review.