mrp-based detailed scheduling and subcontracting
DESCRIPTION
MRP-based Detailed Scheduling and SubcontractingTRANSCRIPT
-
MRP-based Detailed Scheduling and Subcontracting Subcontracting Without Source Location in PP/DS with subcontracting components (materials provided to the subcontractor) Do we need the Transportation lane for the ordered product and the Production process model (PPM) or the Production Data Structure (PDS) in the destination location?
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
2
Applies to:
SAP Advanced Planning and Optimization (SAP APO) SAP APO 7.0.
Summary
The paper is a case study on the combination of Subcontracting Without Source Location in PP/DS with subcontracting components (materials provided to the subcontractor) with MRP-based Detailed Scheduling. It describes a demo business process where the following master data are not created in the SAP APO system:
Transportation lane for the ordered product
Production process model (PPM) or the Production Data Structure (PDS) in the destination location
Author: Dr. Frank Horlacher Company: SAP AG, Walldorf Created on: 13 February 2013
Author Bio
Name: Dr. Frank Horlacher Company: SAP AG Product Expert, Solution Area Architect Supply Chain Management, SAaP Solution Package Build More than 10 years experience in SAP APO development and solution management in supply chain management production planning, detailed scheduling, manufacturing execution and optimization system integration. Area of Expertise:SAP APO Modules: DP, SNP, PP/DS, ATP, CIF;Characteristic Dependent Planning; SAP ERP Modules: SD, MM, PP, VC, FI-CO
SAP SCM Best Practices SAP Rapid Deployment Solutions for SAP APO
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
3
TABLE OF CONTENTS
INTRODUCTION ............................................................................................................................................... 4
MASTER DATA IN SAP ERP ........................................................................................................................... 4 Bill of Material F126 ......................................................................................................................................... 4 Subcontracting components (materials provided to the subcontractor) for Material S23 ...................... 4 Purchasing Info Record Subcontracting....................................................................................................... 4 Material Master - Special Procurement Key 30 Subcontracting ................................................................. 6 Integration to Advanced Planning and Optimization via Core Interface (CIF) .......................................... 6
MASTER DATA IN SAP APO ........................................................................................................................... 7
BUSINESS PROCESS DOCUMENTATION ..................................................................................................... 8 Sales Order Entry ............................................................................................................................................ 8 Material Requirements Planning at Plant Level ........................................................................................... 8 Evaluation of the Stock/Requirement List .................................................................................................... 8 Product View in SAP APO ............................................................................................................................ 10 Execute Heuristic Rescheduling: Bottom Up ............................................................................................. 12 Evaluation of the Stock/Requirement List after Rescheduling ................................................................. 13
CONCLUSION ................................................................................................................................................. 14
RELATED CONTENT ..................................................................................................................................... 14
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
4
INTRODUCTION
Recently I was approached from a partner with the following question:
We have a project with MRP-based Detailed Scheduling and Subcontracting Without Source Location in PP/DS with subcontracting components (materials provided to the subcontractor). Do we need the Transportation lane for the ordered product and the Production process model (PPM) or the Production Data Structure (PDS) in the destination location or are these data obsolete because the Material Requirements Planning is run in SAP ERP? So I took the opportunity to test the business process in our Online Reference System (ORS) for SAP Advanced Production Scheduling Rapid-Deployment-Solution. MASTER DATA IN SAP ERP
The SAP Best Practices scenario MRP-Based Scheduling (S80) reuses master data of existing SAP Best Practices scenarios that have an MRP run in SAP ERP. You can find a detailed description of the master data in SAP BEST PRACTICES BASELINE PACKAGE - BUILDING BLOCKS Central Master Data (for Library - Manufacturing) (143) and Subcontracting (138). Bill of Material F126 We have a material finished good F126 in plant 1000 and a Bill of Material for that finished good with a component S23 that is procured from a subcontractor.
Subcontracting components (materials provided to the subcontractor) for Material S23 The component S23 has two subcontracting components R13 and R14 which are provided from plant 1000 to the subcontractor who assembles them to S23 and sends them back to plant 1000.
Purchasing Info Record Subcontracting A purchasing info record for subcontracting exists for material S23 and vendor 300007.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
5
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
6
Material Master - Special Procurement Key 30 Subcontracting Material S23 has special procurement key 30 for subcontracting.
Integration to Advanced Planning and Optimization via Core Interface (CIF) The following master data is integrated to SAP APO: Plants
Plant 1000 Plant-Dependent Material Masters Material F126 S23 R13 R14 And several other materials contained in the BOM of material F126. Transactional data planned order, production orders and purchase requisitions and orders are also integrated via CIF.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
7
MASTER DATA IN SAP APO
Only the plant and the materials are integrated master data in SAP APO. For scheduling we of course also integrated the resources to produce F126. We did not model a resource for the subcontractor. The vendor 300007 is neither a vendor location nor a subcontractor location. It is not integrated!
There is also no transportation lane existing between plant 1000 and the subcontractor vendor
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
8
BUSINESS PROCESS DOCUMENTATION
Sales Order Entry
SAP ERP menu Logistics Sales and Distribution Sales Order Create
Transaction code VA01
I created a sales order with the quantity of 5000 EA for the finished good material F126. Material Requirements Planning at Plant Level Single-item multi-level requirement planning is carried out for material F126 and plant 1000.
SAP ECC menu Logistics Production MRP Planning Multilevel Single-Item Planning
Transaction code MD02
Evaluation of the Stock/Requirement List After the requirement planning has been carried out I display the stock/requirements situation for the Finished Good MTS (F126) in the stock/requirements list.
SAP ECC menu Logistics Production MRP Evaluations Stock/Requirements List
Transaction code MD04
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
9
There is a customer order and a planned order with 5000 EA. I also check the list of material S23.
There is a dependent requirement and purchase requisition. We can also see the subcontracting requirements of the purchase requisition.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
10
Product View in SAP APO Now I wanted to check the results of the MRP in ERP in SAP APO.
SAP SCM menu path Advanced Planning and Optimization Production Planning Interactive Production Planning Product View
Transaction code /n/SAPAPO/RRP3
The sales order and the planned order for material F126 are transferred to SAP APO.
In the pegging context for the sales order we can identify the purchase requisition and the corresponding planned order for subcontracting material S23 with the subcontracting requirements for components R13 and R14.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
11
The output of the purchase requisition is in the Make-To-Stock segment.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
12
The input of the purchase requisition as stock transport requisition from the subcontractor and the planned order are in the Subcontracting segment.
The subcontracting requirements for the components are in plant 1 location 1000. Execute Heuristic Rescheduling: Bottom Up The purpose of the service heuristic Rescheduling: Bottom Up is to provide a feasible material flow/pegging as a starting point for the scheduling heuristics and sequence optimization also based on the subcontracting requirements.
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
13
I choose component check also for all other components.
After the rescheduling the pegging context is adjusted. Evaluation of the Stock/Requirement List after Rescheduling After rescheduling in SAP APO I wanted to check the new dates in SAP ERP integrated from SAP APO via CIF.
SAP ECC menu Logistics Production MRP Evaluations Stock/Requirements List
Transaction code MD04
-
MRP-BASED DETAILED SCHEDULING AND SUBCONTRACTING
14
The subcontracting purchase requisition has an updated date. CONCLUSION
I demonstrated that the combination of Subcontracting Without Source Location in PP/DS with subcontracting components (materials provided to the subcontractor) with MRP-based Detailed Scheduling does not need the following master data in the SAP APO system:
Transportation lane for the ordered product
Production process model (PPM) or the Production Data Structure (PDS) in the destination location MRP-based Detailed Scheduling allows you to derive the benefits of detailed scheduling in SAP APO and continuing to use your existing subcontracting process in SAP ERP without requiring additional master data in SAP APO. RELATED CONTENT
SAP ADVANCED PRODUCTION SCHEDULING RAPID-DEPLOYMENT SOLUTION SAP BEST PRACTICES BASELINE PACKAGE - BUILDING BLOCKS MRP-based Detailed Scheduling Subcontracting Without Source Location in PP/DS
-
2013 SAP AG. All rights reserved.
SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP
BusinessObjects Explorer, StreamWork, SAP HANA, and other SAP
products and services mentioned herein as well as their respective
logos are trademarks or registered trademarks of SAP AG in Germany
and other countries.
Business Objects and the Business Objects logo, BusinessObjects,
Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and
other Business Objects products and services mentioned herein as
well as their respective logos are trademarks or registered trademarks
of Business Objects Software Ltd. Business Objects is an SAP
company.
Sybase and Adaptive Server, iAnywhere, Sybase 365, SQL
Anywhere, and other Sybase products and services mentioned herein
as well as their respective logos are trademarks or registered
trademarks of Sybase Inc. Sybase is an SAP company.
Crossgate, m@gic EDDY, B2B 360, and B2B 360 Services are
registered trademarks of Crossgate AG in Germany and other
countries. Crossgate is an SAP company.
All other product and service names mentioned are the trademarks of
their respective companies. Data contained in this document serves
informational purposes only. National product specifications may vary.
These materials are subject to change without notice. These materials
are provided by SAP AG and its affiliated companies ("SAP Group")
for informational purposes only, without representation or warranty of
any kind, and SAP Group shall not be liable for errors or omissions
with respect to the materials. The only warranties for SAP Group
products and services are those that are set forth in the express
warranty statements accompanying such products and services, if
any. Nothing herein should be construed as constituting an additional
warranty.
www.sap.com