  • Monthly progress report No. 5 2017

    0

    Monthly progress report No. 5

    Design and Construction of a Medical Stores Warehouse- Chipata, Zambia.

    Submitted: S.H Mazakaza

    Designation: Project Manager

    Report Period: 1st - 31st December, 2017

  • Monthly progress report No. 5 2017

    1

    Contents 1.0.0 Project ................................................................................................................................................................. 2

    2.0.0 Project Data .......................................................................................................................................................... 2

    2.1 Time Management. ....................................................................................................................................... 3

    2.2 Defects Liability Period. ................................................................................................................................ 3

    3.0 Attendance ....................................................................................................................................................... 4

    4.0 Progress............................................................................................................................................................ 4

    A).Mobilization Activity ............................................................................................................................................... 5

    B). Site Establishment ............................................................................................................................................... 5

    C).Warehouse dispatch Building ............................................................................................................................... 5

    D). Warehouse External Activities ...................................................................................................................... 6

    4.2 Delayed Activities ......................................................................................................................................... 6

    4.3 Mitigation Measures ..................................................................................................................................... 7

    5.0 Resources ......................................................................................................................................................... 7

    5.1 Labour/Personnel ......................................................................................................................................... 7

    5.2.0 Plant and Equipment ......................................................................................................................................... 8

    6.0 Materials ........................................................................................................................................................... 9

    7.0 Quality Assessment (Works and Designs) ........................................................................................................ 9

    8.0 Health and Safety Plan .................................................................................................................................. 10

    9.0 Waste Management ............................................................................................................................................... 10

    10.0 Documents Submission .................................................................................................................................. 10

    Contractual/ Technical Matters .................................................................................................................................... 10

    13.0 Conclusion/Recommendation .......................................................................................................................... 12

    Photographs ................................................................................................................................................................. 13

  • Monthly progress report No. 5 2017

    2

    MONTHLY PROGRESS REPORT NO. 5

    1.0.0 Project: Design and Construction of a Proposed New Medical Stores Warehouse, Chipata, Zambia

    2.0.0 Project Data

    Participants

    2.01

    Employer:

    United National Development

    Programme (UNDP)

    2.02

    Beneficiary:

    Medical Stores Limited (MSL)

    2.03

    -

    -

    Supervisors

    Project Focal Person

    Project Manager

    (External Consultant)

    Assistant Project Manager

    (External Consultant)

    Clerk of Works

    (External Consultant)

    D. Kampamba (UNDP)

    S.H. Mazakaza (UNDP)

    D. Pfumbauta (UNDP)

    P.Mayembe (UNDP)

    2.04

    Contractor:

    Sunshare Construction Limited

    2.05

    -

    Design Consultants

    Architects

    A+Urban Technics Ltd

  • Monthly progress report No. 5 2017

    3

    -

    -

    -

    Quantity Surveyors

    Mechanical & Electrical Engineers

    Civil & Structural Engineers

    MNL Associates

    DH Engineering Consultants.

    Civilinks Engineering Designers

    Limited

    2.06

    Insurer

    Golden Lotus Infrastructure

    2.07

    Subcontractors:

    Appointment (outstanding)

    2.1 Time Management.

    2.1.1 Letter of Award Date: 17/07/2017

    2.1.1 Contract Signing Date: 18/07/2017

    2.1.3 Site Handover Date: 24/07/2017

    2.1.4 Possession of Site: 24/07/2017

    2.1.5 Contract Commencement Date: 18/07/2017

    2.1.6 Contract Period: Five (05) Months

    2.1.7 Contract Completion Date: 15/12/2017

    2.1.8 Extension to Contract: 16/02/2018

    2.1.9 Revised Contract Completion:

    2.2 Defects Liability Period.

    2.2.1 Start of the Defects Liability Period

    2.2.2 End of the Defects Liability Period

  • Monthly progress report No. 5 2017

    4

    2.3 Financials

    2.4 Performance

    3.0

    Attendance

    3.1 During the period under review, the United Nation Development Programme, Medical Stores Limited and

    Sunshare Construction Limited attended all site inspections and site meetings held during the month. The

    design consultants attended the last monthly site meeting which was held on 14th December, 2017.

    4.0 Progress

    4.1 The following are the major milestone activities and how they were carried out in the month under review as shown

    in the schedule of works (appendix i) attached:

    (i) Site establishment, continued.

    (ii) Mobilization activity, continued.

    (iii) Dispatch warehouse building, continued.

    (iv) Hazardous Store in progress.

    (v) Perimeter boundary block wall fence, Continued.

    (vi) Warehouse external works, continued.

    A breakdown of how each of the individual activities fared by the end of the month is as in the tables below.

    2.3.1 Contract Amount (USD): 1,685,307.73

    2.3.2 Approved Variations to Date (USD): N/A

    2.3.3 Revised Contract Amount(USD) : N/A

    2.3.4 Payment Certified (USD): 252,796.16 ( Paid if full)

    2.3.5 Penalties per day (USD): 500.00

    2.3.6 Maximum Retention to be Held (USD): 10% of Contract Sum

    2.4.1 Percentage of Contract Period Lapsed: 100.00%

    2.4.2 Percentage of Contract Value Certified out: 90.0%

    2.4.3 Percentage of Project Completed: 92.00%

  • Monthly progress report No. 5 2017

    5

    A).Mobilization Activity

    No. Activity State Date

    Finish Date

    Progress Comments

    i Contract Award 18/07/17 18/07/17 100% Done

    ii Compile & Submit Safety Plan

    21/07/17 21/07/17 100% Done

    iii Method Statement 21/07/17 21/07/17 100% Done

    iv Preliminary Drawings 21/07/17 23/07/17 100% Done

    v Detailed Set of Drawings 19/07/17 05/08/17 95% Detailing in progress

    B). Site Establishment

    No. Activity State Date

    Finish Date

    Progress Comments

    i Receive Access to Site 24/07/17 24/07/17 100% Done

    ii Erect Hoarding 25/07/17 02/08/17 100% Done

    Iii Clear Site & Bulk Excavation

    25/07/17 07/08/17 100% Done

    iv Erect Offices & Store room 26/07/17 09/08/17 100% Done

    v Installation & Connection of Services

    25/07/17 03/08/17 100% Borehole ( Water) done Generator ( Electricity) done

    vi Appointment of Subcontractors

    23/07/17 25/07/17 50% To be confirmed. Behind schedule.

    C).Warehouse dispatch Building

    No. Activity State Date Finish Date Progress Comments

    1 Setting Out 02/08/17 04/08/17 100% Done

    2 Excavate to Foundations 04/08/17 10/08/17 100% Done

    3 Blinding in foundations 10/08/17 12/08/17 100% Done

    4 Placing of reinforcement 12/08/17 19/08/17 100% Done

    5 Cast foundation concrete bases

    19/08/17 25/08/17 100% Done

    6 Foundation solid filled block work

    25/08/17 08/09/17 100% Done

    7 Fill and Compact 08/09/17 16/09/17 100% Done

    8 Indoor Floor reinforcement and concrete

    16/09/17 26/09/17 100% Done

    9 Cast concrete to external column

    16/09/17 100% Done

    10 Structural steel fabrication and erection

    26/09/17 07/10/17 99% Installation of canopies outstanding due to subsequent activities

    11 Structural roofing, re-Insulation and Covering

    09/10/2017 19/10/2017 78% Structural roofing done, insulation/sisalation being re done.

    12 Bond decking for the office (Mezzanine)

    13/10/2017 18/10/2017 100% Done

    13 Electrical Installations 19/10/2017 14/12/2017 75% In progress. Behind schedule

    14 Block work/walling to warehouse

    23/10/17 14/11/2017 100% Done

    15 Plastering internally and Externally

    10/11/2017 30/11/2017 100% In progress. Behind schedule

  • Monthly progress report No. 5 2017

    6

    16 Concrete to Mezzanine floor (Offices)

    12/11/2017 13/11/2017 100% Done

    17 Doors, Windows and Partitioning

    15/11/2017 30/11/2017 78% In progress. Behind schedule

    18 Painting externally 30/11/2017 4/12/2017 80% On hold due to subsequent activities. Behind schedule

    19 Floor Tiles 04/12/17 14/12/17 50% In progress. Behind schedule

    20 Ceiling installation to offices

    04/12/17 14/12/17 80% In progress. Behind schedule

    21 Plumbing, Electrical Data Airconditioning2nd Fix

    08/12/17

    14/12/17 60% In progress. Behind schedule

    22 Painting internal 11/12/2017 13/12/2017 65% In progress. Behind schedule

    D). Warehouse External Activities

    No. Activity State Date Finish Date

    Progress Comments

    1 Hazardous House 02/10/17 22/10/2017 95% In progress. Behind schedule

    2 Guardhouse building (Block work completed)

    04/10/17 30/11/17 95% On hold. Behind schedule awaiting materials from Lusaka

    3 Boundary block work (Perimeter Fencing)

    01/10/17 22/10/2017 95% On hold due to subsequent activities. Behind schedule

    4 Road works (Paving and Drainage)

    1/09/2017 4/12/2017 68% In progress. Behind schedule

    5 Sewer Reticulation 24/07/2017 31/11/2017 90% On hold. Delayed due to subsequent work. Behind schedule

    6 External Electrical and Water Reticulation

    24/07/2017 06/10/2017 75% On hold due to subsequent activities. Behind schedule

    7. Lunch shade 27/12/2017 5% In progress. Behind schedule

    The general progress on site mobilization, site establishment and works to the warehouse building as well as external

    works are as shown on the attached schedule (Program of works), Appendix i. Progress for the works is estimated at

    ninety-two (92%) against the planned one hundred percent (100%). The project is generally behind schedule and the

    contractors were asked to work more efficiently; engage more labour force, continue with overtime shifts and enhance

    material delivery to site in order for them to complete the works within the given extension time.

    4.2 Delayed Activities

    All activities are behind schedule on account of:

    (i) Erect hoarding (Substituted with permanent wall fence) in progress

    (ii) Late submission of method statement and quality assurance plan

  • Monthly progress report No. 5 2017

    7

    (iii) Some subsequent construction activities

    (iv) Improper and Inadequate operational and administrational planning by the contractor .

    4.3 Mitigation Measures

    The Contractor put up some measures such as employing more personnel and working overtime shifts. This is working

    well so far. The subcontractors’ nomination is still poor. The contractor has been asked to improve on this aspect.

    5.0 Resources

    5.1 Labour/Personnel

    The contractor had adequate personnel against planned activities during the period under review. The site crew

    comprised of both local and foreign personnel. Table 4.1 indicates the labour data as at 31stDecember, 2017.

    Table 5.1.0 - Personnel Data

    Description

    Number

    Males

    Females

    Disabled

    Foreign

    Local

    Contracts Manager

    Site Agents

    1

    Site Engineers

    1

    Surveyor

    Site Administrator

    2

    Safety/Environmental Officer

    Lab Technician

    Foreman

    5

    Operators (drivers)

    2

    Skilled Labour

    1

    Semi-skilled Labour

    60

    Unskilled Labour

    70

    Total Employees on Site

    142

  • Monthly progress report No. 5 2017

    8

    5.1.1 Some of the key personnel for the works stated in the technical proposal submission will not be available on

    the project. The contactor has been instructed to indicate the affected positions and provide alternative

    personnel whose credentials should be equal or better than for those initially proposed on the project.

    5.1.2 The Design Team is maintaining the key personnel stated in the contractor’s technical proposal

    5.2.0 Plant and Equipment

    The plant and equipment deployed on site is indicated in Table 5.2

    Table 5.2 Equipment on Site

    No.

    Description

    Plant No.

    Date on Site

    Qty

    1 15t Tipper Truck 21/08/2017 01

    2 380 liters Concrete mixer 25/08/2017 01

    3 32KW Output power Generator 25/08/2017 01

    4 2000L Water storage tank 25/08/2017 01

    5 Small Generator 25/08/2017 01

    6 12ton roller compactor Off hired 2/10/2017 01

    7 Front end loader Off hired 2/10/2017 00

    8 25t Mobile crane Off hired 6/10/2017 00

    9 Concrete Poker Vibrator 25/08/2017 03

    10 500 liters Concrete mixer 01/12/2017 01

    The plant is not adequate for the current activities. The contractor has therefore, been instructed to bring in plants like

    Grader or Front end loader for road works and drainages.

  • Monthly progress report No. 5 2017

    9

    6.0 Materials

    Materials deployed for warehouse works are inadequate. The contractor has been instructed to improve on the

    procurement and quick delivery of materials to site. The quantity of materials available on site is adequate for the

    current activities but the contractor has been urged to continue ensuring availability of the materials for efficient

    operations.

    In terms of quality, kerb stones manufactured by the contractor on site were found to be of poor quality. Therefore,

    contractor was instructed to get rid of all the kerb stones on site by 20th December, 2017 and buy good ones directly

    from reputable suppliers in Lusaka.

    7.0 Quality Assessment (Works and Designs)

    The quality of mobilization infrastructure namely, site offices, storage, warehouse building and associated services –

    water and electricity installation meet the minimum expected specifications for quality standards. Also the plant and

    equipment deployed on site are in good working condition. In addition, the quality of drawings and associated detailing

    has also met the minimum quality standard based on the latest revised drawings.

    Item No. Materials Description Qty/Unit

    1. River sand 150 tons

    2. 19 mm stones 200 tons

    3. 50kgs cement bags 1200 pockets

    4. Building sand 50 tons

    5. Structural Steel members 100% delivered to site

    6 500micronable DPM 05Rolls

    7 257 Mesh Wire 10Rolls

    8 DPC 15 Rolls

    9 Roofing sheets 100% delivered to site

    10 8” Concrete blocks 500 No

    11 6” Concrete blocks 1000 No

    12 4” Concrete blocks 500 No

    13 Concrete paving bricks 5000No

    14 Clear view material 100% delivered to site

    15 Door frames 100% delivered to site

    16 Neelkanth cables 7 rolls

    17 Durkeesox air dispenser system 4 boxes

    18 Glazed wall tiles 45 boxes

    19 DB 10 units

    20 Solid core flash doors 45No.

  • Monthly progress report No. 5 2017

    10

    8.0 Health and Safety Plan

    Generally Health and Safety Site requirements are satisfactory. Borehole water has been tested for human

    consumption and the results submitted to the Engineers for calcification of quality. Ablution facility construction is

    completed and water born toilets provided with fair sanitation which is enhanced with regular disinfection. The Healthy

    Plan has been submitted and the Contractor has First Aid Kit on site.

    Safety management, in terms of ensuring all workers on site have requisite safety clothing, safety shoes and helmets

    had been breached on a number of occasions before. The contractor was however, instructed to adhere to safety

    clothing provisions as stated in the safety plan. This instruction is being adhered to and safety monitoring is continuing

    on a daily basis. The contractor is to ensure Safety and Health standards on site are adhered to as postulated in the

    contract. This requires employment of a Safety Officer. The contractor has been asked to employ a new safety officer

    although no accident was recorded in the month of December.

    9.0 Waste Management

    The Waste Management Plan is in place and implementation. The contractor is abiding to the control measures basing

    on general guidelines. The environment is generally clean, disinfection is regularly done to the toilets and rubbish bins

    have been brought on site for waste disposal.

    10.0 Documents Submission

    11.0 Financial Matters

    The project manager confirms that stage one to three has been paid.

    Contractual/ Technical Matters

    12.1 Subcontracting

    The following works have been subcontracted and the Subcontractors are as follows:

    - Electrical Installation- sun share( internally)

    - Fire Protection Systems-outstanding

    - Air Conditioning Installation

    - Mechanical - Ndykay Limited

    - Security Installation – Win-Link Limited

    - Chiller installation – BJ Cooling

    - Gen set installation-outstanding PM to provide guidance

  • Monthly progress report No. 5 2017

    11

    - Telephone ( outstanding)

    - Turnstiles, electrical boom and access control outstanding.

    It is reported that the contracts are for labour only as the two parties could not agree on final rates for supply and fix.

    12.2 Designs

    The Design Team was working on the various disciplines with the following anticipated milestone to be achieved;

    Activity

    Architectural and Structural Foundation preliminary layout drawings with

    associated details completion and subsequent approval by the Project

    Manager. Completed

    Submission of architectural and structural drawings to the Local

    Authorities and lodging of an application-in- principle to commence

    construction works prior to drawings approval. Submitted and approved.

    Submission of final detailed architectural drawings to the Project Manager.

    Done

    Mechanical drawings were submitted

    Bills of Quantities to be finalized upon receipt of detailed and final

    drawings from the Architects and Engineers.

    12.3 Insurance

    The total insurable cover for project is equivalent to the total contract value.

    12.4 Communication

    12.4.1

    All communication to be managed effectively, between the client, the contractor, and the design team

    and vice versa, and it should be channeled through the Project Manager. The contractor and their design team have

    been advised to fully read the entire contract to avoid unnecessary assumptions, which might have negative impact on

    the project in terms of expected deliverables.

  • Monthly progress report No. 5 2017

    12

    12.5 Construction Activity Progress Projection Plan (CAPPP)

    Work planned for next two weeks

    I. Sisalation/ insulation and covering will be completed 100%

    II. Hazardous store will be completed 100%

    III. Sewer reticulation will be completed 100%

    IV. Boundary block work ( perimeter fencing )will be completed 100%

    V. Tile fixing to offices and ceiling will be 100%

    VI. External and internal wall painting to be completed 100%

    VII. Road works (Paving and drainage) to be completed 100%

    VIII. Guard house to be completed 100%

    IX. Electrical installations to continue

    X. Doors and windows installation to be completed 100%

    XI. Lunch shade to continue.

    XII. Electrical reticulation to be done 100%

    XIII. Plumbing, Electrical Data Air-conditioning fix1 to continue

    XIV. Floor Tiling to be completed 100%

    XV. Ceiling installation to offices to be completed 100%

    XVI. Painting internal to be completed 100%

    XVII. Air Condition works to continue

    XVIII. External Electrical and Water reticulation to be completed 100%

    Note: The Contractor to submit a recovery plan and follow it and level the delay in a weeks’ time.

    13.0 Conclusion/Recommendation

    The overall project progress stands at 92% against 100%. Recovery measures should include: the contractor to revise

    the Programme for the outstanding works, timely ordering and delivering of outstanding materials, continue increasing

    labour/personnel and introducing overtime on selected activities. The contractor is however, reminded to ensure there

    is adequate lighting in all work places in times of overtime shifts. Rain coats should also be availed to workers to

    promote productivity during light rains. In addition, more equipment is to be brought on site as demand increases.

    The Project Manager and Clerk of Works will closely monitor the delayed activities and ensure that the delays are

    worked over in the stipulated time frame without further delays.

  • Monthly progress report No. 5 2017

    13

    Photographs

    The pictures below show the latest progress of the works on site as at 31/12/17.

    Figure 1. South Eastern side elevation- (painting, and road civil /concrete works)

  • Monthly progress report No. 5 2017

    14

    Figure 2: Mezzanine floor passage Window or door frames /ceiling.

  • Monthly progress report No. 5 2017

    15

    Figure 3. Roof insulation- new layer being added

  • Monthly progress report No. 5 2017

    16

    Figure 4: Paving road works -Northern side of the warehouse building