module production t. bowcock. substrates twist problem –further understanding of the warp/weft and...
TRANSCRIPT
![Page 1: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/1.jpg)
Module Production
T. Bowcock
![Page 2: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/2.jpg)
Substrates
• Twist problem– Further understanding of the warp/weft and layup problem
• Chirality of the twist– Looks like it can be controlled
• It looks like it is a function of the 45°layer.
– The current layup is good ~0.5° (Limit about 3°)
• Pressure identified as part of problem– Reproduce twist at Liverpool by increasing pressure >90psi– Note nominal maximum pressure ~300psi
• Determine the CF/Epoxy ratios– For our modules ~ 9.9g/Weight (module)– Should be approx 60-68% CF by weight.
• PAC still quotes at 10/week.
![Page 3: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/3.jpg)
K-05
• (Re)-Processing almost complete– Last batch were untestable through
overetching
• Circuits should be ready to laminate next week at Stevenage
![Page 4: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/4.jpg)
Pitch Adaptors
• All pitch adaptors sent back to CERN for plasma cleaning
• Current ones not testable– 2 controls done in old pa’s– Damage/deposit on needle
![Page 5: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/5.jpg)
Sensors
• 8 arrived at Liverpool– Currents ~uA and 0<0.5% percent strips bad.– One with no bad strips
• “Perfect” cutting
• 2 returned to Micron for remeasurement (3 others high in dB)– One recleaned at Micron did not change
current
![Page 6: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/6.jpg)
Sensor Testing Problem
• On new batch of sensors on some detectors measure substantially higher current than micron
• Complete halt and check for damage to sensors– Inspection of old sensors– Running tests with mechanicals– Tests with “quartz”
• Repeat of tests using chuck/kapton– Currents confirmed
![Page 7: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/7.jpg)
Sensor Testing
• Limited evidence of microscopic liquid from vacuum holes
• Hypothesis that the jigs were contaminating the sensors (Noryl)
• 2nd and 3rd tier of cleaning of jigs• Tests underway• 8 Pairs of new (cleaner) jigs under
construction for Liverpool and Micron– Acetal rather than Noryl
![Page 8: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/8.jpg)
Bonding & Jigs
• Now have 4 double sided bonding jigs– 1 for backend– 2 for frontend– 1 for laser system
• 2 handling frames created (expect about 10 at the end)
![Page 9: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/9.jpg)
Module Production
• Feet and Bases still in production
• Paddle Moulds (3 off) still to be made
![Page 10: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/10.jpg)
Testing Equipment
• Laser rig plate finalized and submitted
• Thermograph equipment designed (to be reviewed)
• Gluing equipment expect to start the metrology and programming next week
![Page 11: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/11.jpg)
Summary
• K-05 circuits close to delivery• Twist story still approx 2 weeks from resolution
– Living with the twist?
• Pitch adaptor problems again. Need cleaning?• Sensor testing issues uncovered
– Micron results look OK
• All mechanics except the thermograph system and the final paddle-hybrid assembly (twist) ready by July.
![Page 12: Module Production T. Bowcock. Substrates Twist problem –Further understanding of the warp/weft and layup problem Chirality of the twist –Looks like it](https://reader036.vdocuments.site/reader036/viewer/2022082701/5516020b550346a2308b4c5c/html5/thumbnails/12.jpg)
Timeline
• No prototype modules will be completed until end Aug 05 based on current status of K-05 and twist (guesstimate)– 4 double sided modules
• Look for “real” production start ~ Oct ‘05