modernizing loran command and control

19
Modernizing Loran Command and Control U.S. Coast Guard Loran U.S. Coast Guard Loran Support Unit Support Unit 12001 Pacific Ave. 12001 Pacific Ave. Wildwood, NJ 08260-3232 Wildwood, NJ 08260-3232 Raymond Agostini Raymond Agostini James R. Betz James R. Betz International Loran International Loran Association Association Convention and Technical Convention and Technical Symposium Symposium Washington D.C., USA Washington D.C., USA 28-30 October 2002 28-30 October 2002

Upload: jaser

Post on 01-Feb-2016

63 views

Category:

Documents


0 download

DESCRIPTION

Modernizing Loran Command and Control. International Loran Association Convention and Technical Symposium Washington D.C., USA 28-30 October 2002. James R. Betz. Raymond Agostini. U.S. Coast Guard Loran Support Unit 12001 Pacific Ave. Wildwood, NJ 08260-3232. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Modernizing Loran Command and Control

Modernizing Loran Command and Control

U.S. Coast Guard Loran Support UnitU.S. Coast Guard Loran Support Unit

12001 Pacific Ave.12001 Pacific Ave.

Wildwood, NJ 08260-3232Wildwood, NJ 08260-3232

Raymond AgostiniRaymond AgostiniJames R. BetzJames R. Betz

International Loran Association International Loran Association Convention and Technical SymposiumConvention and Technical Symposium

Washington D.C., USAWashington D.C., USA28-30 October 200228-30 October 2002

Page 2: Modernizing Loran Command and Control

3. Remote Automated Integrated Loran (RAIL) Computer System

4. Locus Casualty Control Receiver Set

2. State-of-the Art Cisco Router Communications Equipment Suite

Out with the old and in with the new.

1. New Frame Relay Data Communication Network

5. RAIL Envelope Pulse Analyzer (EPA)

Page 3: Modernizing Loran Command and Control

Broad Functional Block

Frame RelayTCP/IP Protocol

MonitorSite

Page 4: Modernizing Loran Command and Control

The Network

Page 5: Modernizing Loran Command and Control

Communications Suite

DSU

Router

Network Switch

Redundant PowerSupply

Wireless Backup Comms Modem

Page 6: Modernizing Loran Command and Control

RAIL Computer System

RAIL ChassisWith ProtectiveFront Cover

Monitor

Keyboard

Locus

Printer

Page 7: Modernizing Loran Command and Control

RAIL Graphical User Interface

Home Screen – Shows a complete overview of equipment status and displays: alarms, data and access to equipment control screens

The GUI is the centerpiece of RAIL and allows the operatorTo command and control the Loran station’s equipment.

Equipment Control Screens for:

•Automatic Blink System (ABS)

•Locus Casualty Control Receiver Set (CCRS)

•Frequency Standard/Time of Transmission Monitor (TTM)

•RAIL Envelope Pulse Analyzer (EPA)

•Local Site Operating Set (LSOS)

•Remote Control Interface (RCI)

Page 8: Modernizing Loran Command and Control

RAIL GUI – Home Screen

Page 9: Modernizing Loran Command and Control

RAIL GUI – Local Charts

Page 10: Modernizing Loran Command and Control

RAIL GUI – CCRS Data

Page 11: Modernizing Loran Command and Control

RAIL GUI – ABS Control

Page 12: Modernizing Loran Command and Control

RAIL Envelope Pulse AnalyzerCompuscope 1250-1M A/D Digital Storage PCI Board

12-bit resolution

1 MB on-board memory2 Input ChannelsAnalog or TTL Trigger InputAnalog or TTL Ext Clock Input

Page 13: Modernizing Loran Command and Control

RAIL GUI – RAIL EPA Control

Page 14: Modernizing Loran Command and Control

RAIL GUI – Pulse Analysis

Page 15: Modernizing Loran Command and Control

RAIL GUI – Archive Screen

Page 16: Modernizing Loran Command and Control

Interim Equipment Rack Layout

Page 17: Modernizing Loran Command and Control

Immediate System ImprovementsThe RAIL system, Locus CCRS & Communications Equipment provides numerous benefits:

•Replaces antiquated command & control equipment withstate-of-the-art, highly reliable, fault tolerant equipment.

•Improves the local interface with the Loran Station.

•Improves reliability and availability of the Loran signal.

•Improves remote Command and Control to LCCS.

•Improves archiving functions and integrity of data.

Page 18: Modernizing Loran Command and Control

Future PlansThe RAIL system, along with the Communications Equipment willprovide the interface to two systems in development:

Graphical User Interface for TFE .

Graphical User Interface for the new TCS.

Local and Remote Electronic Interface for TFE.

Local and Remote Electronic Interface for TCS.

•Timing and Frequency Equipment (TFE)•Transmitter Control System (TCS) for the new SSX Transmitter

Page 19: Modernizing Loran Command and Control

End Presentation

Questions?