Page 1: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

MoA and M&O-B

Pigi Paolucci

Page 2: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 2

Introduction

• The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long experience regarding M&O-B.

• In the 2009 we asked all the institution to contribute with at least 5 KCHF

• All gave 5 KCHF• Ghent and Brussels 7.5 KCHF. • I.N.F.N. 163 KCHF

16/3/10

Page 3: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 3

M&O-B 20092009 contributions  

Institution CHFINFN (old account) 63.147INFN (new account) 60.308INFN Napoli 4.000INFN PS spare 29.974

INFN GGM spare 6.042Korea 5.000

Inre Univ 5.000

Sofia Univ 5.000Ghent Univ 7.500China 5.000India 5.000Pakistan 0Brussel Univ 7.712Total Input 198.683

16/3/10

Page 4: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 4

M&O-B 2009 balance

Manpower descriptionManpower

CostHardware maintencance

description Hardware maintencance Gas comp. Description Gas comp.

   PINTO from 07.06.2009 to 20.06.2009 2.000,00 2009 contract for CAEN site up 9.952,00 interface board for RH sensors 1.100,00  

SHAHZAD from 10.07.2009 to 09.08.2009 4.128,00 Repair of CAEN crates 2.570,00Accessoires Magasins (gas/power/cooling) 494,00  

VIVIANI from 03.08.2009 to 02.09.2009 4.128,00 Upgrade Endcap Mainframes 7.125,00 Temperature probes racks 3.138,00  

SHAHZAD from 10.08.2009 to 09.09.2009 4.128,00Accessoires Magasins (new account) 2.700,00

Analysis for the CMS Muon RPC Detector 4.758,00  

POLESE from 01.09.2009 to 30.09.2009 4.128,00 interface board for RH sensors 1.050,00  MUHAMMAD from 01.09.2009 to 30.09.2009 4.128,00 EASY crate Power Calbe 208,00  LOMIDZE from 10.09.2009 to 09.10.2009 4.000,00 CAEN Reparation 2.060,00  MUHAMMAD from 01.10.2009 to 31.10.2009 4.128,00 Rental Pool (2009) 5.675,00  POLESE from 01.10.2009 to 31.10.2009 4.128,00 GSM operation phone 4.983,00  MUHAMMAD from 01.11.2009 to 30.11.2009 4.128,00 Hum. Plug sensors 995,00  POLESE from 01.11.2009 to 30.11.2009 4.128,00  MUHAMMAD from 01.12.2009 to 31.12.2009 4.128,00  POLESE from 01.12.2009 to 31.12.2009 4.128,00  POLESE Conference 720,00 PS CAEN board spare 29.974,00    GGM CAEN board spare 6.042,00  

OLD ACCOUNT 2008/2009 balance 40.000,00   manpower   hardware   gas comp. Total Output

TOTAL 52.128   113.334  9.490 174.952

16/3/10

Page 5: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 5

Questions addressed I

• How is the M&O-B budget constructed (what are the items taken into account, are there cost items outside M&O-B budget):

2010 Budget is based on what we needed in the 2009 and taking into account the small number of spares we need and the short time for hardware reparation and maintenance (2 months).

For the first time we are asking the institutions to contribute proportionally to the FTE (2010). Until now only Belgium and Italy gave a positive feedback. No answer from the other institutions.

16/3/10

Page 6: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 6

Questions addressed II

• What is the manpower component of the budget and what are the plans for moving towards the MoA system

In the 2009 the manpower component was about 50 KCHF (1/4 of the total) and for the 2010 we are planning to have 180 KCHF (need to pay few experts in DCS, DQM, Electr. and DPG)

Part of the services could be covered by MoA but mostly for short period and not for high-level expert.

RPC project still need some high-level experts (DQM, DCS, Database, Power…) that are not easily replaceable by the institution.

This number of experts must be reduced in the next years using the MoA

16/3/10

Page 7: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 7

Questions addressed III

• What is the long-term budgetary plan (e.g. is the Sub- system self-sufficient in a 10-15 year perspective)

2010 will be our first real test about the MOFB and only after that we could answer to this. In any case I don’t think we will be self-sufficient unless new institutions will not joint our project.

• Are Upscope/Upgrade costs built into the M&O-B budget

No it is not in the budget, but it will be in the 2011.16/3/10

Page 8: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli

2010 material details

Shall we contribute to the LB upgrade/spare ?

16/3/10 8

MATERIALS      Keuro KCHF

Server (5 DCS + 3 DQM + RC) upgrade (every 2 years) 5,3 8,0

HV-LV spares (10HV+6LV) 102,7 154,0

HV-LV-ADC CAEN maintenance 21,3 32,0

HV-LV-ADC cable, connect. distrib 5,3 8,0

P5 Lab infrastr. 5,3 8,0

ISR gas & infrastr. 10,7 16,0

GIF detector test (SJ) 5,3 8,0

Gas Monitoring materials 5,3 8,0

Gas Monitoring spares 11,0 16,5

CERN store 11,0 16,5

Sensors upgrade endcap sensor on fiber 10,7 16,0

Electronic Pool CERN 12,7 19,0

Communication telephone for shifters and experts 2,0 3

LB upgrade and spare contribution ? (50.0)

TOTAL (maintenance and reparation)   208,7 313,0

Page 9: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 9

2010 M&O-B manpower

MANPOWER    months   FTE  Keuro   KCHF

Detector reparation 6 tech 0,50 16,8 25,2

Electronic (TTU+FEB+CB) reparation 1 tech 0,08 2,8 4,2

HV-LV repar. And maint. 2 tech 0,17 5,6 8,4

HV-LV firmware upgrade 2 ing 0,17 5,6 8,4

DCS - DQM - DB software upgrade 6 ing 0,50 16,8 25,2

DCS - DQM machine maint. 2 ing 0,17 5,6 8,4

Sensors upgrade endcap upgrade endcap 2 ing 0,17 5,6 8,4

Gas gas test and reparation 4 tech 0,33 11,2 16,8

Gas Monitoring repair and maint. 2 tech 0,17 5,6 8,4

Cooling repar. and maint. 2 tech 0,17 5,6 8,4

TOTAL     29,0  2,42 81,2 121,8

16/3/10

Page 10: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 10

MoA 2010data tacking shut-down data tacking shut-down

10 2 10 2FTE FTE needed months needed months

Detector Hardwarechamber 2 3 20 6electronics 0,5 2 5 4services 1 2 10 4 49

Electronic and DAQ Power system 1 2 10 4DCS-DSS 1 1 10 2TTU 0 1 0 2XDAQ 0,5 0,5 5 1 34

Software and DQM Raw Data/DQM 2 2 20 4 Reconstructed 2 2 20 4 Prompt Analysys-Run valid 2 2 20 4 TTU 0,4 0,6 4 1,2 77,2

Operation P5 shift 3 1 30 2CAF shift 2 1 20 2Shift leader 1 1 10 2 66

Managment LV2 and LV3 21 21 42

Up Scope Simulation 0,3 0,3 3 0,6R&D 0,6 0,6 6 1,2Chamber production 2 2 20 4Front-end electronic 0,5 0,5 5 1Trigger electronic 0,5 0,5 5 1 46,8

TOTALE months 47,3 244 71 31516/3/10

Page 11: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 11

2010 M&O-B per institutionM&O 2010 # M&O Amount due (KCHF)Peking univ 3 17,9

SKK Univ (Korea) 6 35,7

Korea Univ (Korea) 11 65,5

Chonnam (Korea) 0 0,0

Mumbai-Barc (India) 2 11,9

Ghent (Belgium) 9 53,6

Brussel Univ (Blgium) 1 6,0

Uniandes 2 11,9

Pakistan 3 17,9

Bari 10 59,6

LNF 4 29,8

Napoli 6 35,7

Pavia 3 17,9

Sofia Univ 6 35,7

Sofia INRE 6 35,7

INFN 23 142,9

RPC TOTAL 72 434,8

16/3/10

Page 12: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 12

Proposal for 2010 M&OB budget sharing

• At least 50% of the amount due in cash for subsistence, material and spares: 217 KCHF – M&OB material budget foreseen = 313 KCHF– Part of the cash can be used for materials/spare

• 50% in manpower to cover the 2010 MoA– FTE/month = 4 KCHF– Total is 217/4 = 54 months– Needed MoA = 315 FTE (all covered by RPC institutions)

• Example: Sofia INRE amount due 36 KCHF– 18 KCHF in cash (material/spare/subsistence)– 18 KCHF ==> 5 months of MoA

16/3/10

Page 13: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 13

2010 M&O-B per institutionM&O 2010 # M&O Amount due (KCHF)

Cash/Materials (KCHF) Manpower (KCHF)

Peking univ 2 12,1 6,04 6,04

SKK Univ (Korea) 6 36,2 18,12 18,12

Korea Univ (Korea) 11 66,4 33,21 33,21

Chonnam (Korea) 0 0,0 0,00 0,00

Mumbai-Barc (India) 2 12,1 6,04 6,04

Ghent (Belgium) 9 54,4 27,18 27,18

Brussel Univ (Blgium) 1 6,0 3,02 3,02

Uniandes 2 12,1 6,04 6,04

Pakistan 3 18,1 9,06 9,06

Bari 10 60,4 30,19 30,19

LNF 4 24,2 12,08 12,08

Napoli 6 36,2 18,12 18,12

Pavia 3 18,1 9,06 9,06

Sofia Univ 6 36,2 18,12 18,12

Sofia INRE 7 42,3 21,14 21,14

INFN 23 138,9 69,45 69,45

RPC TOTAL 72 434,8 108,70 108,70

In red the already confirmed contributions16/3/10

Page 14: MoA and M & O-B Pigi Paolucci. Introduction The RPC endcap and barrel project were merged in an unique project in the 2009 and so we don’t have a long

Pigi Paolucci - INFN Napoli 14

Conclusions 15 institutions, 72 FTE M&OB = 435 KCHF MoA = 47 FTE = 315 months

• We need to quantify our Cash/manpower contribution for 2010 M&O in March (50%)

• CMS FB will approve it and then will prepare invoices for the institutions

• CMS FB will follow the invoice payments as for the other subsystem.• We need make a proposal for the RPC MoA via email and approve

the distribution• Then write pledge letters for the end April• 2011 budget and 2012-2013-2014 for RRB

16/3/10