MIS5102: Process Improvement and Innovation

Project ManagementProject Planning

Steve [email protected]

http://community.mis.temple.edu/ssclarow

Why is the distinction between what a project is and what it is not important?

What is a project?

The Triple Constraint

Scope

Describe a scenario where changing one affects the others.

Role of the project manager?

In writing the spec?

In managing the triple constraint?

In navigating the organization?

What is Project Portfolio Management (PPM)?

Five Questions(Pennypacker and Retna)

• Are we investing in the right things?

• Are we optimizing our capacity?• How well are we executing?• Can we absorb all the changes?• Are we realizing the promised

benefits?

Are we talking about “singular” or “comparative” evaluations?

What’s the difference?

Two broad approaches

Quantitative Qualitative

There are pros and cons of each approach…

Quantifying Options Using a Decision Tree

http://en.wikipedia.org/wiki/Project_portfolio_management

Each project has an associated

• Cost• Revenue• Risk

Project Investment #1

-$3,500,000

Project Revenues$4,275,000

Opt. 50%$4,750,000

50%$1,250,000

Pess. 50%$3,800,000

50%$300,000

Project Investment #2

-$2,800,000

Project Revenues$3,250,000

Opt. 50%$3,900,000

0%$1,100,000

Pess. 50%$2,600,000

0%-$200,000

A Closer Look

TRUE

FALSE

= $4,750,000 * .5 + $3,800,000 * .5

= -$3,500,000 + $4,750,000

= -$3,500,000 + $3,800,000

= -$2,800,000+ $3,900,000

= -$2,800,000+ $2,600,000

Expected value of this part of the project portfolio:

$1,250,000 * .5 + $300,000 * .5 + $1,100,000 * .0 + -$200,000 * .0 = $775,000

What are the pitfalls of this approach?

= $3,900,000 * .5 + $2,600,000 * .5

A more qualitative approach

Decision Points for PPM(Wikipedia)

• The criteria for filtering and ranking

• Which criteria are most important

• Which project ideas are worth developing

• Which projects should be considered as part of the portfolio

• Which projects to fundhttp://en.wikipedia.org/wiki/Project_portfolio_management

But how do you prioritize?

Some of the Big Questions

How can you blend quantitative and qualitative approaches? Should you?

How can a “do nothing” option help?

When doesn’t any of this matter?

Project Planning

Recall our party planning exercise from the beginning of

the semester…

What do you do?

When do you do it?

Who does what?

Elements of a Project Plan

What do you do?

When do you do it?

Who does what?

• Process decomposition• Swim lane diagrams• RACI charts

We already have some tools we can use

You may not use these specific tools, but many of the

concepts are the same!

Work Breakdown Structure (WBS)

Aircraft System

Air Vehicle

Receiver Fire Control Communication

Training

Equipment Services

Peculiar Support Equipment

Depot

How is this like process

decomposition?

How is it different?

What do you learn from this?

http://en.wikipedia.org/wiki/Work_breakdown_structure

WBS Design principles• 100% rule

• Mutual exclusivity

• Outcomes, not actions

• Level of detail

http://workbreakdownstructure.com/

Why is each principle important in building a useful WBS?

How far should you break down a project?

What is the “problem” with estimation?

Understanding Dependencies

What are task dependencies?

Why is it important to understand them?

How are they usedto turn a WBS into

a project plan?

Critical Path Analysisusing PERT (Program Evaluation and Review Technique)

Design

Create module 1

Createmodule 2

Buy hardware

SoftwareUnit Testing

Software Unit Testing

Hardware Config.

SystemTest

WriteManual

15 days

10 days

15 days

7 days

36 days

15 days

5 days

30 days

15 days

Hardware Testing

3 days

The work units on the longest path through the

diagram are on the critical path.

What does it mean for the task to be on the

critical path?

Allocating Work

Assigning people to tasks

Build off of the work breakdown structure

What can a RACI chart tell you about allocation?

What can a Swim Lane Diagram tell you about allocation?

Communications

Hardware Team

Allocating Work and the Critical Path

Design

Create module 1

Createmodule 2

Buy hardware

SoftwareUnit Testing

Software Unit Testing

Hardware Config.

SystemTest

WriteManual

15 days

10 days

15 days

7 days

36 days

15 days

5 days

30 days

15 days

Hardware Testing

3 days

How does adding this information help the

planning process?

Software Team 2

Software Team 1

Entire Team

Some moreabout estimating

“Few people enjoy estimating complex things that they will be accountable for.” (Berkun, Chapter 2.4.3.1)

What can go wrong with estimation?

• For the triple constraint?• For allocating resources?

What are the implications for project planning?