milton s. hershey medical center biomedical research building joshua zolko, structural option

24
Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Upload: geoffrey-carroll

Post on 22-Dec-2015

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Milton S. Hershey Medical Center Biomedical Research Building

Joshua Zolko, Structural Option

Page 2: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Introduction• The Biomedical Research Building (BMR)

is located in Hershey, Pennsylvania.• 245000 sq. ft, in 7 stories above grade• Built between 1991-1993• Cost $49 million• Used a Bid-Build project delivery method• Used for Education and Laboratory space

Table of Contents• Introduction• Architecture• Existing Structure• Process• Cost Comparison• Conclusion

Page 3: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Introduction• Site soil is considered poor, and as such,

columns were designed as pinned at the bottom.• Goal of this proposal is to determine if a

steel structure is more cost effective than a concrete structure.

Table of Contents• Introduction• Architecture• Existing Structure• Process• Cost Comparison• Conclusion

Page 4: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Architecture• Façade of the BMR consists of long

horizontal concrete and limestone slabs, and black glazing• Façade designed to relate to buildings

already existing on campus• Cylinder and Planar wall on corners add

to the otherwise flat building

Table of Contents• Introduction• Architecture• Existing Structure• Process• Cost Comparison• Conclusion

Page 5: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Existing Structure• The BMR is a monolithic concrete

structure, using a two-way flat plate system with the average column size about 22” by 22”• Building sits on a deep foundation

system of caissons 3 to 7 feet in diameter

Table of Contents• Introduction• Architecture• Existing Structure• Process• Cost Comparison• Conclusion

Page 6: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Assumed gravity loads were to be:• 45 PSF dead• 40 PSF snow• 20 PSF superimposed• 125 PSF live core, 100 PSF live offices

Typical Floor PlanTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 7: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Dead Load is from 3.5” slab (t = 3”) using

1.0CSV Conform decking from Vulcraft assuming 5’ joist spacing.• Gives 45 psf, plus 20 psf superimposed

for 65 psf dead.

Preliminary LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 8: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Using 1.2D + 1.6L, loading is 278 PSF

core.• Loading for joist is 1.4 KLF with 5’

tributary width.• Requires a W14x22 joist size.• Deflection under this loading is .63”,

satisfying L/360.

Preliminary LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 9: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Beam loading with a tributary width of

21’ is 5.8klf.• Braced at every 5’, under this load,

requires a w12x120.• Beams deflects .47”, satisfying L/360.

Preliminary LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 10: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Gravity columns have a tributary area of

21’ by 33’. Total of 693 sq ft.• Due to the large live load, live load

reduction does not apply to members supporting only one floor, and those that do, maximum of 20% reduction.

Preliminary LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 11: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Axial load per floor is 192.7 Kips.• After LLR, load is 165 kips.• With alternate loading of bays, and axial

loads, gravity column sizes range from W14x90 to W14x159.

Gravity Column ShapesTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Story Shape7 w14x906 w14x995 w14x1094 w14x1203 w14x1452 w14x1451 w14x159

Page 12: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Analysis was repeated for the office

spaces, and no changes were made.• Column sizes were the same aside from

the third story where a reduction to a W14x132 could have been made, but it was decide to keep it uniform with the core.

Preliminary LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity

• Cost Comparison• Conclusion

Page 13: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Goal of Lateral Design was to keep the

drift of the building under 2.6”, or H/400, with H = 88’• Hall/office spaces to have minimal drift

as they attach to an adjacent building.

Initial LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 14: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Initial Lateral design consisted of only

Moment Frames.• Frames were assumed to be equally stiff,

and checked via RAM.• Equal stiffness allowed for individual

frame design.

Initial LayoutTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 15: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Using ASCE 7-10, Wind loads were

derived.• Loads were then divided amongst the

moment frames.• Portal method was used to estimate

loads.

Wind LoadsTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Y (Kips) X (Kips)7 37.7 23.16 36.1 22.25 34.1 21.04 32.6 20.03 29.8 18.32 27.4 16.81 24.8 15.2

Page 16: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Loads from both lateral and gravity

forces were combined using interaction equations, including biaxial forces from overlapping lateral frames.• Drifts from the initial design were too

high, and frames were rearranged, and braced frames were added.

Final Frame DesignTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 17: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Loads from both lateral and gravity

forces were combined using interaction equations, including biaxial forces from overlapping lateral frames.• Drifts from the initial design were too

high, and frames were rearranged, and braced frames were added.

Biaxial Lateral ColumnsTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 18: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Braced Frames were designed in order to

decrease the drift caused by torsion.• A specific rigidity was found in order to

move the center of rigidity to the center of mass, and braces were sized in order to acquire this rigidity in order to decrease torsional effects.

Braced FrameTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Story Shape7 HSS6.625X0.2506 HSS6.625X0.2505 HSS7.0X0.2504 HSS7.5X0.2503 HSS8.625X0.2502 HSS8.625X0.3221 HSS9.625xX.250

Page 19: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Problem with this braced frame being

placed at the north side, is that the braced frame will be placed directly in front of the glazing.

Braced FrameTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Story Shape7 HSS6.625X0.2506 HSS6.625X0.2505 HSS7.0X0.2504 HSS7.5X0.2503 HSS8.625X0.2502 HSS8.625X0.3221 HSS9.625xX.250

Page 20: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Loads from both lateral and gravity

forces were combined using interaction equations, including biaxial forces from overlapping lateral frames.• Drifts from the initial design were too

high, and frames were rearranged, and braced frames were added.

Braced FrameTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 21: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Braced Frames were placed in order to

not block entrances into maintenance shafts• Halls go through center bay

Braced FrameTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 22: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Overturning was checked, and was not

an issue in either direction under controlling loads of either wind or seismic.

Overturning TablesTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 23: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Process• Braced Frames were placed in order to

not block entrances into maintenance shafts• Halls go through center bay

Final Frame DesignTable of Contents• Introduction• Architecture• Existing Structure• Process• Gravity• Lateral

• Cost Comparison• Conclusion

Page 24: Milton S. Hershey Medical Center Biomedical Research Building Joshua Zolko, Structural Option

Cost Comparison

• Original Plan costs $49 million• Proposal costs $.... million

CalculationsTable of Contents

• Introduction• Architecture• Structure• Process• Cost Comparison• Conclusion