Host City Transport Operations Plan

CITY OF CAPE TOWN

2010 FIFA WORLD CUP

Operations Plan&

Venue Transport Operations Plans

3 February 2008

Page 2: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

PROGRAMME

Page 3: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 4: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 5: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 6: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 7: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

CAPE TOWN CBD UPGRADES

Page 8: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

CAPE TOWN CBD UPGRADES

Page 9: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

INFRASTRUCTURE BUDGET

Page 10: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

SPECTATOR TRANSPORT SPECTATOR TRANSPORT

PLAN

Page 11: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

• Airport Shuttle Service

• Public Transport Service to CBD (incl Park ‘n Ride Facilities)

SPECTATOR TRANSPORT SERVICES

• Inner City Transport Service

• Green Point Stadium Shuttle Service (match days only)

• V&A Waterfront Shuttle Service (match days only)

Page 12: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

PARK ‘n RIDE SCHEDULED SERVICE

Page 13: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

Measures / Outcomes Basis Of Measure Target Group Impact On

2010 Implementation Ease Cost

Permanence Of Measure

Priority Rating

Wide Area Background Travel Demand Measures

Alignment of Scholar Holidays with busiest WC period

Reduction of school and associated trips

Background traffic V. High Easy Low WC Specific 1

Flexi-time and flexi-working on match days

Reduction of work and business trips

Background traffic V. High Mod Mod WC Specific 2

Encourage worker holidays Reduction of work and business trips

Background traffic High Mod Low WC Specific 3

Public Transport & Park and Ride Encourage HOV; reduce Background and WC

TRAVEL DEMAND MANAGEMENT MEASURES

Public Transport & Park and Ride promotion

Encourage HOV; reduce congestion

Background and WC traffic

Mod Mod High Permanent* 4

Car Sharing Scheme Traffic reduction Background traffic Mod Diff Mod Permanent* 5

Car Pooling Traffic reduction Background traffic Low Diff Mod Permanent* 6

Promotion of Metered Taxi to capture % of hire car market

Reduce SOV WC & business traffic Low Diff Mod Permanent* 7

Localised Measures (CBD and Stadia )

Increased focus on Match day flexi-working in CBD

Reduction of work and business trips

Background traffic V. High Mod Mod WC Specific 1a

Restricted vehicular access in CBD, pedestrian only routes

Traffic management Background and WC

traffic High Mod Low WC Specific 2a

Remote parking away from facilities Traffic management; support alt modes

Background and WC traffic

Mod Mod Mod WC Specific 3a

Communication plan to discourage local travel that is not necessary

Trip planning; trip reductions

Background and WC traffic

Mod Mod Mod WC Specific 4a

Concentrate accommodation into large facilities, close to city centre

Promote NMT; enhance Public transport viability

WC traffic Mod Mod Mod/High WC Specific 5a

CBD focussed car pooling schemes for large employers

Reduction of work and business trips

Background traffic Low Diff Mod Permanent* 6a

Page 14: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

GREEN POINT STADIUMGREEN POINT STADIUM

Page 15: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 16: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 17: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

CBD AND FAN PARKCBD AND FAN PARK

Page 18: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 19: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 20: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 21: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 22: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009
Page 23: Microsoft Power Point   Hctop Version 3 Presentation To Cpt Partnership   3 Feb 2009

Thank YouThank You

Enkosi

Dankie