mic universi ty of gaza -...
TRANSCRIPT
S
Comm
Schedulin
ISLAmunity Ser
Com
ng & Anboxes
En
AMIC UNrvices anmmunity
alysis thby Micr
PMotRab
Sung. Hesh
Gaza,
NIVERSInd Contin
Develop
he projecrosoft Pr
repared taz J. Aloah J. Ala
pervisedham Abu
, Pales n
ITY OF Gnuing Edupment Ins
ct of manroject an
by ostath ashqar
d by: El Qumb
ne 2017
GAZA ucation Dstitute
nufacturind Excel
boz
Deanship
ing seism
mic
Page 1 of 20
Table of Contents
1) Table of figures ........................................................................................................................ 3
2) Introduction ............................................................................................................................. 4
A) Project background ............................................................................................................. 4
i) Requirements Analysis: ................................................................................................... 4
ii) Design and concept: ........................................................................................................ 4
iii) Plan the project ............................................................................................................... 4
iv) Materials procurements .................................................................................................. 4
v) Boxes production ............................................................................................................. 4
vi) Boxes assembly ................................................................................................................ 4
B) Planning concept and software ........................................................................................... 4
i) Planning concept ............................................................................................................. 4
ii) External resources and software ..................................................................................... 4
3) Project scope statement .......................................................................................................... 5
A) Define project scope ............................................................................................................ 5
B) Project assumptions and constraints .................................................................................. 5
i) Quality ............................................................................................................................. 5
ii) Resources ........................................................................................................................ 5
iii) Scope ............................................................................................................................... 5
iv) Time ................................................................................................................................. 5
4) Work Breakdown Structure WBS ............................................................................................ 6
A) Decomposition .................................................................................................................... 6
B) WBS ..................................................................................................................................... 6
5) Project schedule ...................................................................................................................... 7
A) Define project activities ....................................................................................................... 7
B) Estimate activities duration ................................................................................................. 8
C) Schedule activities ............................................................................................................... 8
i) Sequence activities .......................................................................................................... 8
ii) Project Original Bar chart ................................................................................................ 9
iii) Project Revised Bar Chart .............................................................................................. 10
6) Resource management plan .................................................................................................. 10
A) Types of resources ............................................................................................................. 10
B) Quantities of each type of resource .................................................................................. 11
Page 2 of 20
C) Project organization chart ................................................................................................. 12
D) Project resource histogram ............................................................................................... 12
i) Primavera resource histogram ...................................................................................... 12
ii) Microsoft Excel resource histogram .............................................................................. 13
iii) Microsoft Excel revised resource histogram ................................................................. 13
7) Cost estimates ....................................................................................................................... 14
A) Determining Project Budget .............................................................................................. 14
i) Original project budget.................................................................................................. 14
ii) Revised project budget .................................................................................................. 14
B) Project cash flow ............................................................................................................... 15
i) Original Cash Flow ......................................................................................................... 15
ii) Revised Cash Flow ......................................................................................................... 15
8) Risk management plan .......................................................................................................... 16
A) Identify risks ...................................................................................................................... 16
B) Perform qualitative risk analysis ....................................................................................... 16
C) Perform quantitative risk analysis ..................................................................................... 17
D) Plan risk responses ............................................................................................................ 17
E) Monitor and control risks .................................................................................................. 17
9) Communications plan ............................................................................................................ 18
A) Project Stakeholders .......................................................................................................... 18
B) Communications groups .................................................................................................... 18
C) Communications Information needs ................................................................................. 18
10) Quality plan ....................................................................................................................... 19
A) Plan Quality ....................................................................................................................... 19
B) Quality Assurance .............................................................................................................. 19
C) Quality Control .................................................................................................................. 19
11) Conclusions and recommendations .................................................................................. 19
12) References ......................................................................................................................... 20
Page 3 of 20
1) Table of figures Figure 1(Scope Decomposing) ........................................................................................................ 6 Figure 2(Project WBS) .................................................................................................................... 7 Figure 3(Activity List) ..................................................................................................................... 7 Figure 4(Activity Duration) ............................................................................................................. 8 Figure 5(Activity Sequence) ............................................................................................................ 9 Figure 6(Bar Chart) ......................................................................................................................... 9 Figure 7(Revised Bar Chart).......................................................................................................... 10 Figure 8(Type of Resources) ......................................................................................................... 11 Figure 9(Resources Quantities) ..................................................................................................... 11 Figure 10(Organization Chart) ...................................................................................................... 12 Figure 11(Primavera Resource Histogram) ................................................................................... 12 Figure 12(Excel Resource Histogram) .......................................................................................... 13 Figure 13(Excel Revised Resource Histogram) ............................................................................ 13 Figure 14(Project Budget) ............................................................................................................. 14 Figure 15(Revised Project Budget) ............................................................................................... 14 Figure 16(Project Cash Flow) ....................................................................................................... 15 Figure 17(Project Revised Cash Flow) .......................................................................................... 15 Figure 18(Qualitative Risk Analysis) ............................................................................................ 16 Figure 19(Quantitative Risk Analysis) .......................................................................................... 17 Figure 20(Communications Information) ...................................................................................... 18
Page 4 of 20
2) Introduction A) Project background
Our company Flexible Models (FM) awarded a project for the Research and Development unit of the Property Development Department of the Government (PDDG). The project is part of Seismic Zone Residential Construction Improvement Program, and it is to manufacture and deliver boxes, which used on a foundation of buildings. In order to deliver the final product, the project will pass through the following stages:
i) Requirements Analysis: Interview the project stakeholders and Product detail analysis to define the project scope of work.
ii) Design and concept: Perform the project design and execution method statement in order to plan the project.
iii) Plan the project: Develop the project plan; scope statement, WBS, schedule, resources, cost, risks, communication, and quality plans as per the following sections.
iv) Materials procurements: As per the project management plan, and the design, the materials procurement should start to provide the materials required to manufacture the boxes.
v) Boxes production: As per the materials delivery schedule and the project plan, the manufacture should start to deliver the boxes on time.
vi) Boxes assembly: As per the production schedule, and the project management plan, the boxes should be delivered and assembled at the client's site as required.
B) Planning concept and software i) Planning concept Project planning concept is as per (Project Management Institute 2008) planning process groups, tools, and techniques. However, the author used his own experience to select the best techniques fits the project situation.
ii) External resources and software The author used Microsoft Excel, and Oracle Primavera to perform the required calculations and diagrams embedded in the final project document as figures.
Page 5 of 20
3) Project scope statement A) Define project scope
The project scope is to design, manufacture, deliver, and assembly cardboard or metal sheet boxes, which will be used in the foundation of PDDG program.
B) Project assumptions and constraints This section include the assumptions and the constrains, which considered during the project planning and execution as per the following:
i) Quality The size must be 300 x 250 x 200 cm with a slot of 10 x 10 x 25 cm. The tolerance on outer dimensions must be +/-2 cm. The tolerance on dimensions of the slot must be 0 to -3 mm in width. In
short, the slot cannot be more than 10 x 10 cm. It should be made of cardboard or metal sheet. It should be made of small cubes of dimensions 5 x 5 x 5 cm. It should be smooth in appearance.
ii) Resources
The following is the Labor rates:
Design department: USD 150 per day Cutting department: USD 90 per day Assembly department: USD 150 per day
Note: the given effort of resources is total number of resources to complete the task not the daily manpower,
The following is the Labor rates:
USD 20 per industrial cardboard sheet USD 25 per metal sheet USD 10 per Standard cubes
iii) Scope The boxes should be delivered and assembled at the client's site
iv) Time The project completion date was revised because of the risk management.
See section 8-D. The calendar used on oracle Primavera scheduling tool is standard 5-day
work per week except for task number A1150 “Shipment/Delivery” the calendar used is 7-day work per week.
Page 6 of 20
4) Work Breakdown Structure WBS A) Decomposition
“Decomposition is a technique for subdividing the project deliverables into smaller, manageable tasks called work packages” (Sanghera 2010, p97). The project scope of work decomposed into work packages and groups as per the following figure-1.
Boxes Project Decomposing
1 Requirements Analysis
1.1 Interview client stakeholders
1.2 Product detail analysis
1.3 Refinement of the final draft
2 Design and Concept
2.1 High level design
2.2 Details with operation designs
3 Production
3.1 Set up
3.2 Cutting and parts development
3.3 Sub-assembly 1
3.4 Sub-assembly 2
3.5 Sub-assembly 3
3.6 Assembly integration
4 Material
4.1 Cardboard sheet
4.1 Metal sheets
4.1 Cubes
5 Delivery
5.1 Pre-delivery
5.2 Shipment/Delivery—delivery takes 2 weeks by sea.
5.3 Implementation Figure 1(Scope Decomposing)
B
5) A
B) WBS After dPrimav
Figure 2(
ProjecA) Define
After thWBS a
Figure 3(
decomposingvera as per th
(Project WBS)
ct schedul project ache creation oas per the fo
(Activity List)
g the projeche following
le ctivities of the WBSllowing figu
Requiremen Interview Product de RefinemenDesign and High level Details witProduction Set up Cutting an Sub-assem Sub-assem Sub-assem Assembly Material Cardboard Metal shee CubesDelivery Pre-delive Shipment/ Implemen
Page 7 of 20
t into work g figure-2.
S, the activiture-3
Tasknts Analysis client stakehoetail analysisnt of the final Conceptdesign
th operation d
nd parts develombly 1mbly 2mbly 3
integration
d sheetets
ry/Delivery—detation
0
packages, t
ties were po
k Name
olders
draft
designs
opment
livery takes 2
the WBS is
opulated und
weeks by sea
created by O
der the relate
.
Oracle
ed
Page 8 of 20
B) Estimate activities duration In this process, the duration of each activity will be estimated. Since the “duration estimate is progressively elaborated” (Project Management Institute., 2013), this step could be revisited during the schedule activities, resource management, and risk management to achieve the project deadlines. See figure-4
Task Name Duration Requirements Analysis 12 days Interview client stakeholders 4 days Product detail analysis 6 days Refinement of the final draft 2 days Design and Concept 8 days High level design 4 days Details with operation designs 6 days Production 16 days Set up 4 days Cutting and parts development 3 days Sub-assembly 1 6 days Sub-assembly 2 6 days Sub-assembly 3 4 days Assembly integration 3 days Material 1 day Cardboard sheet 1 day Metal sheets 1 day Cubes 1 day Delivery 32 days Pre-delivery 2 days Shipment/Delivery—delivery takes 2 weeks by sea. 14 days Implementation 7 days
Figure 4(Activity Duration)
Page 9 of 20
C) Schedule activities i) Sequence activities The activities is sequenced assigning the predecessor and successor relationships as per figure-5 below.
Note: activity “Details with operation designs” has a start-to-start + 2 days lag relationship with activity “High level design” as per statement “The task 'Details with operation designs' starts with a 50% overlap with 'High level design'”
Task Name Duration Start Finish Requirements Analysis 12 days Mon 01-01-18 Tue 16-01-18 Interview client stakeholders 4 days Mon 01-01-18 Thu 04-01-18 Product detail analysis 6 days Sun 07-01-18 Sun 14-01-18 Refinement of the final draft 2 days Mon 15-01-18 Tue 16-01-18Design and Concept 8 days Wed 17-01-18 Sun 28-01-18 High level design 4 days Wed 17-01-18 Mon 22-01-18 Details with operation designs 6 days Sun 21-01-18 Sun 28-01-18Production 16 days Mon 29-01-18 Mon 19-02-18 Set up 4 days Mon 29-01-18 Thu 01-02-18 Cutting and parts development 3 days Sun 04-02-18 Tue 06-02-18 Sub-assembly 1 6 days Wed 07-02-18 Wed 14-02-18 Sub-assembly 2 6 days Wed 07-02-18 Wed 14-02-18 Sub-assembly 3 4 days Wed 07-02-18 Mon 12-02-18 Assembly integration 3 days Thu 15-02-18 Mon 19-02-18Material 1 day Sun 04-02-18 Sun 04-02-18 Cardboard sheet 1 day Sun 04-02-18 Sun 04-02-18 Metal sheets 1 day Sun 04-02-18 Sun 04-02-18 Cubes 1 day Sun 04-02-18 Sun 04-02-18Delivery 32 days Mon 05-02-18 Tue 20-03-18 Pre-delivery 2 days Mon 05-02-18 Tue 06-02-18 Shipment/Delivery—delivery takes 2 weeks by sea. 14 days Tue 20-02-18 Sun 11-03-18 Implementation 7 days Mon 12-03-18 Tue 20-03-18
Figure 5(Activity Sequence)
ii) ProjAfter sidentify
Figure 6(
ect Originalequencing tying the pro
(Bar Chart)
l Bar chartthe activitiesoject critical
Page 10 of 2
s, Oracle Prl path by the
20
rimavera repe red bars as
presents the s per figure-
bar chart w-6.
which
Page 11 of 20
6) Resource management plan A) Types of resources
The following figure-8 defines the type of resources associated with each activity
Boxes Project Decomposing Task Duration
Resource Type 1 Requirements Analysis
1.1 Interview client stakeholders 4 days Design
1.2 Product detail analysis 6 days Design & Assembly
1.3 Refinement of the final draft 2 days Design
2 Design and Concept
2.1 High level design 4 days Design
2.2 Details with operation designs 6 days Design
3 Production
3.1 Set up 4 days Assembly
3.2 Cutting and parts development 3 days Cutting
3.3 Sub-assembly 1 6 days Assembly
3.4 Sub-assembly 2 6 days Assembly
3.5 Sub-assembly 3 4 days Assembly
3.6 Assembly integration 3 days Assembly
4 Material
4.1 Cardboard sheet sheets
4.1 Metal sheets sheets
4.1 Cubes pieces
5 Delivery
5.1 Pre-delivery 2 days
5.2 Shipment/Delivery—delivery takes 2 weeks by sea. 14 days
5.3 Implementation 7 days Design & Assembly
B
Figure 8(
B) QuantiAfter dresourc
Figure 9(
(Type of Resour
ities of eacdefining the ce is calcula
(Resources Qua
rces)
ch type oftype of reso
ated as per fi
antities)
Page 12 of 2
resource ources assocfigure-9.
20
ciated with ttasks, quanttity of each
C
D
C) ProjectFigure-
Figu
D) ProjectThe aucalculausing M
i) Prim
Figure 11
t organizat-10 represen
ure 10(Organiza
t resource uthor populate the requirMicrosoft Ex
mavera resou
1(Primavera Re
tion chartnt the projec
ation Chart)
histogramlated the Ored work foxcel for bett
urce histogr
esource Histogr
Page 13 of 2
ct organizati
m Oracle primrce per weekter presentat
am
ram)
20
ion chart as
mavera withk, and then tion.
mentioned
h the activicreate the re
in the case
ities resourcesource hist
study
ces to ogram
ii) Micr
Figure 12
iii) MicrBecausmitigat13
Figure 13
rosoft Exce
2(Excel Resourc
rosoft Excese of the riskte the risks.
3(Excel Revised
l resource h
ce Histogram)
l revised resk response Accordingl
d Resource Histo
Page 14 of 2
histogram
source histoin section 8ly, the resou
ogram)
20
ogram 8-D, the projurce histogra
oject duratioam was revi
on was chanised as per f
nged to figure-
7) A
Cost eA) Determ
i) OrigThe autusing M
Figure 1
ii) ReviBecausmitigatper figu
Figure 15
estimates mining Proginal projectthor estimat
Microsoft Ex
14(Project Budg
ised projectse of the riste the risks ure-15
5(Revised Proje
oject Budgt budget ted the cost xcel. The pr
get)
t budget sk response associated w
ect Budget)
Page 15 of 2
get
of each actiroject budge
plan in secwith the pro
20
ivity, and acet is 36,960
ction 8-D, Poject. The r
ccordingly t$ as per fig
Project budgrevised budg
the project bgure-14
get was reviget is 37,81
budget
ised to 5 $ as
B
B) Projecti) OrigThe auto calcuExcel f
Figure 1
ii) ReviBecausmitigatfigure-
Figure 17
t cash flowginal Cash Futhor populaulate the wefor better pr
16(Project Cash
ised Cash Fse of the riskte the risks 17
7(Project Revise
w Flow ated the Oraeekly cash fesentation a
h Flow)
Flow k response passociated
ed Cash Flow)
Page 16 of 2
acle primaveflow, and thas per figure
plan in sectiwith the p
20
era with thehen create the-16
ion 8-D, Proroject. The
e budget coshe cash flow
oject cash flrevised ca
st of each aw using Mic
ow was revsh flow is
ctivity crosoft
ised to as per
8) A
B
Risk mA) Identify
In ordethe riskproject
B) Perform
The fol
Figure 1
managemfy risks er to establiks as the firs
manager id
Risk Id R1very skilledRisk ID R2Risk ID R3
m qualitatiRisk R1 haday of delaRisk R2 haRisk R3 haand Cutting
llowing figu
18(Qualitative R
ment plan
sh the risk st stage (Wydentified the
: The Cuttind resource t2: Project m3: change in
ive risk ans a 0.7 proba
ay in this tasas a 0.3 probas assumed pg and parts d
ure-18 repre
Risk Analysis)
Page 17 of 2
managemenysocki 2012,e following r
ng and partso meet the q
materials coun client requi
nalysis ability and wsk, which cobability and probability developmen
esent the qua
20
nt plan, the , p77). Accorisks:
s developmequality requ
uld be damagirements aft
will delays thonsider high0.3 impact of 0.5 and hnt) by 1
alitative risk
project teamordingly, pro
ent task id Auirements. ged during ster the cuttin
he project bh impact asson the task
has impact o
k analysis.
m should idoject team a
A1060 requi
shipment. ng stage.
y 6 days forsumed by 0.6cost.
on tasks (Set
dentify and the
red a
r every 6.
t up,
C
D
E
C) PerformReferen0.4 to 0risks. Tbelow
Figure 19
From thtask du2, and plan.
D) Plan risBecausdate, bchange
E) MonitoMonitoplannedidentify
AlthouRisks Rthe promonito
m quantitance to (Berm0.6 medium,The impact
9(Quantitative R
he quantitaturation for ta3 days resp
sk responsse of the qubar chart, reed and name
or and conoring and cod metrics. Ty new risks
gh, risk R2 R1 and R3 soject if theyoring the thre
ative risk aman 2007) p, and belowof the high
Risk Analysis)
tive risk anaasks (Set uppectively. T
ses uantitative aesources hi
ed “revised”
ntrol risksntrolling ofThis procesduring the p
is low risk,should be my occurs. Proee risks iden
Page 18 of 2
analysis p167 risk as0.4 low, the
h and mediu
alysis, the prp, and Cutti
These chang
and qualitatiistogram, b”.
f risks is requs could resuprogress of
but it shouldmonitored car
oject team ntified.
20
ssessment, rie qualitativeum risks are
roject budgeing and part
ges reflected
ive risk anaudget cost,
uired to evalult a develothe project.
d be monitorefully becashould iden
isks above 0e risk analyse calculated
et increasedts developmd on the pro
alysis, the pr, and cash
luate the riskopment on (Kerzner 20
ored to avoidause they hantify any ne
0.6 high andis ignored th
d as per figu
d by 855$, ament) increasoject manag
roject compflow plans
k response athe risk pla
009) p788
d its impact.ave a big effew risks and
d from he low ure-19
and the sed by
gement
pletion s were
against an and
. Other fect on d keep
Page 19 of 20
9) Communications plan A) Project Stakeholders
In addition to the project team identified on the organization chart in section 6-C, other external stakeholders is identified. Joseph Bukhmann, the chief editor of Construction Consortium Journal.
B) Communications groups The project consist of three main groups:
FM Company group Client Group External stakeholders group.
C) Communications Information needs The following figure-20 represent the communication information between the stakeholders on the project.
S.N
Stakeholder Name
Stakeholder Group
Type of information
Sequence of Communicat
ion
Information Delivery Method
1 Roy Benjamin
FM Company group product design alternate day Email
2 Michael Gartner
FM Company group
detailed drawings assembly drawings
Weekly Email & Hard
Copy
3 Philip Cloony
FM Company group design drawings Weekly
Email & Hard Copy
4
Jim Stanford
FM Company group
vendor management,
market analysis, contracting, and
procuring required resources
Weekly
5
John Morris
FM Company
group
information on the progress
project management processes
Daily
Web-based project tracking
system Reports, and
Memo's
6 Caroline Smith
FM Company group
budget
Weekly
one-on-one meetings, and telephone calls
7
Joseph Bukhmann
External stakeholders
group
Progress, photos, and project status
Monthly
Email & Hard Copy
8
Paul Lee
Client Group
progress of the technical design
Progress presentation
Weekly report
biweekly call
Email Phone Call
Figure 20(Communications Information)
Page 20 of 20
10) Quality plan A) Plan Quality
The boxes manufacture project has a very tight scope constrains with very limited tolerances. Therefore, the boxes quality should meet the quality constrains and tolerances mentioned in section 3-B-i. In addition, a mockup of the boxes to be manufactured in early stage of the project to perform a quality test, experiment the manufacture quality procedures and to avoid risks of bad quality in the production stage.
B) Quality Assurance During the manufacture process, and before proceeding with the second stage of the manufacture, the first stage should be checked via inspection request and verified by the QA engineer. This procedure will reduce the probabilities of quality defects and if any defects discovered during the manufacture will be fixed in early stage, rather than waiting the assembly stage to find out that there is a problem in the boxes.
C) Quality Control During the manufacture process, the QA engineer should physically check the quality of the product and sign inspection request for each stage of the manufacture.
11) Conclusions and recommendations The boxes manufacture project represent a high value to the FM company reputation since it is part of well-known program, and followed by the Construction Consortium Journal chief editor Joseph Bukhmann.
The project quality requirement is very high, and therefore, the quality should be effectively managed. The risks associated with the project increased the project budget and duration. Accordingly, all the project management plan components were revised to accommodate the risk response.
Project communication involves different parties. Therefore, the communication information log is effective way of informing the stakeholders the required information, by the time they need to know, and with the preferred communication method. This communication plan will ensure the information flow, and will keep all the project stakeholders updated.
The project management plan is a progressively elaborated document. It is expected to be modified, and updated. Each change or update should be reflected on the other elements of the project management plan.