metropolitan sewer district of greater cincinnati muddy ... creek wwtp aeration system efficiency...
TRANSCRIPT
Muddy Creek WWTP Aeration System Efficiency Upgrade
Metropolitan Sewer District of Greater Cincinnati
June 19 | 2013
Muddy Creek WWTP Aeration System Efficiency Upgrade Brian Mumy, P.E., Brown and Caldwell
Ryan Welsh, P.E., Metropolitan Sewer District of Greater Cincinnati
MSDGC Overview
• Serves the City of Cincinnati and most of Hamilton County
• 7 major treatment plants, 120 pump stations
• 3,000 miles of sanitary and combined sewers
• 184 mgd ADF combined
OWEA Annual Conference | June 19, 2013
Muddy Creek WWTP Overview
• Built in 1958
• 15 mgd Design ADF
• Discharges to Ohio River
OWEA Annual Conference | June 19, 2013
Muddy Creek WWTP Secondary Process
• Constructed in 1972
• Two tanks
• 220’x78’x15’ each
• 1.9 MG each
• Plug flow
• Three passes per tank
OWEA Annual Conference | June 19, 2013
•Aeration Demand: 6,400 - 13,400 scfm
•Blowers (4)
•Positive Displacement
•200 hp
•Rated at 4,650 scfm each
•Age: Installed in 1972
•Fine Bubble Diffusers
•Sanitaire Ceramic Disc
•Age: Installed in 2008
Prior to Upgrade
OWEA Annual Conference | June 19, 2013
• New Blowers with Automatic DO Control
• Contractors: Dugan & Meyers, Lake Erie Electric
• Design Engineers: Brown and Caldwell
• Designed in 2010
• Construction Started in Spring 2011
• Substantial Completion in Spring 2013
• Construction Cost: $7,703,000 *
* Construction contract includes new blowers, diffusers, and automatic DO control at Little Miami WWTP. Muddy Creek construction cost ≈ $2,500,000
Aeration Upgrade Project
OWEA Annual Conference | June 19, 2013
• Existing positive displacement blowers were 40 years old
• Decreasing reliability
• Increasing maintenance
• Increasing risk of failure
• Potential for energy savings
Project Motivation
OWEA Annual Conference | June 19, 2013
Source: Energy Conservation in Water and Wastewater Facilities,
Manual of Practice No. 32 (WEF, 2009)
Upgrade Evaluation
• Equipment Reliability
• Age of existing equipment
• Capital Costs
• Equipment
• Installation
• Operational Costs
• Maintenance
• Energy
OWEA Annual Conference | June 19, 2013
OWEA Annual Conference | June 19, 2013
Blower Technologies
• Positive Displacement
• Centrifugal – Single Stage
• Centrifugal – Multistage
• High Speed Turbo
High Speed Turbo Blowers
• Developed in the aerospace industry based on gas turbine engines
• Single stage centrifugal, direct drive
• High speed (15,000-60,000 rpm)
• Air foil bearing
• Blower, motor, VFD, and PLC in single enclosure
OWEA Annual Conference | June 19, 2013
OWEA Annual Conference | June 19, 2013
High Speed Turbo Blowers
Advantages
• High efficiency
• Package design, small footprint, low installation labor
• Lowest maintenance
• Low vibration – isolators not required
• Lowest noise
• Air plenum not required
OWEA Annual Conference | June 19, 2013
High Speed Turbo Blowers
Disadvantages
• Only for lower flow rates (8,000 to 15,000 scfm max flow per unit)
• VFDs require harmonic filters for protection
• New technology with limited installation base
Business Case Evaluation
OWEA Annual Conference | June 19, 2013
Final Alternatives Capital Cost Net Present
Value
1. Positive Displacement Blowers $3,865,000 $7,925,000
2. High Speed Turbo Blowers $2,937,000 $6,096,000
* Replace Blowers – MSDGC Useful Life of Capital Assets Report
* 30 Year Analysis, Electricity Cost $0.073 KW/HR
* MSDGC NPV analysis
High Speed Turbo Blowers Selected
• Lower Capital Cost
• Lower O&M Cost
• Lower Energy Cost
• Lower NPV
• Four High-Speed Turbo Blowers
• HP: 250
• Rated Capacity: 4,770 scfm
• Harmonic Filters
• Electrically Actuated
Butterfly Air Control
Valves
• Startup Date: February, 2012
Equipment Installed
OWEA Annual Conference | June 19, 2013
• Each Blower was provided as a package by the manufacturer
• A Master Control Panel (MCP) was also provided by the manufacturer to act as a pressure controller.
• New Dissolved Oxygen Meters
• New Air Flow Meters
Controls Installed
OWEA Annual Conference | June 19, 2013
• Luminescent technology
• No membranes or solutions
• Factory calibrated
Dissolved Oxygen Probes
OWEA Annual Conference | June 19, 2013
• Thermal Mass Flow technology
• Flow conditioner upstream
• Low pressure loss
Air Flow Meters
OWEA Annual Conference | June 19, 2013
Overview of Secondary Aeration
OWEA Annual Conference | June 19, 2013
AERATION TANK 1
PASS 1
PASS 2
PASS 3
PASS 1
PASS 2
PASS 3
AERATION TANK 2
BLOWERS
AIR MODULATING
VALVES
AIR FLOW
METERS
D.O. MEASUREMENT
Most Open Valve (MOV) Pressure Control
OWEA Annual Conference | June 19, 2013
M
PIT
MOV %
SETPOINT
AIR HEADER
PLC
PID
SPEED % - + -
DRIVE
PLC
MOV
LOGIC
PRESS
SP
AIR VALVE
POSITIONS
M
AIT
D.O.
SETPOINT
PLC
PID
% OPEN - + -
DISSOLVED OXYGEN
PLC
PID
FIT
- + -
FLOW
SETPOINT
FLOW
% OPEN TO MOV
CONTROLLER
PRESSURE
Blower Operation – Communications
OWEA Annual Conference | June 19, 2013
Aeration
Master PLC
Blower MCP Master Control
Panel
Blower 1
PLC
• 6 PLCs are inter-connected with Ethernet
• Each Blower PLC and the MCP have PanelView
touch-screens
Blower 2
PLC
Blower 3
PLC
Blower 4
PLC
Pressure Set-point
Blower Operation – MCP Pressure Controls
OWEA Annual Conference | June 19, 2013
• The MCP is programmed to
maintain header pressure
by adjusting the blower
speeds.
• MCP determines:
• Which blower is lead
• Time delays for
starting/stopping
• Which pressure
transmitter to use for
feedback
• Dead-bands
Blower Operation – Local Controls
OWEA Annual Conference | June 19, 2013
• Blower is normally controlled
from the MCP via Ethernet.
• It can be placed in Local
Control to manually
start/stop and adjust speed.
• Displays speed, pressure,
estimated flow, temperature,
etc.
• Indicates when filter
changes are required based
on pressure differential
Aeration System – HMI Controls
OWEA Annual Conference | June 19, 2013
Trending
Blower Details
Overview
Pop-Ups
Energy Savings - Estimated
OWEA Annual Conference | June 19, 2013
• Original Positive Displacement Blowers
• Estimated usage of 270 kW
• High Speed Turbo Blowers
• Estimated usage of 212 kW
• Estimated Energy Savings
• $3,000/mo
• $36,000/yr
• ≈ 20%
Actual Energy Savings – First Year
OWEA Annual Conference | June 19, 2013
$0
$5,000
$10,000
$15,000
$20,000
$25,000
Ae
rati
on
Bu
ild
ing M
on
thly
Po
we
r C
osts
Month
2009-2011
2012-2013
Average Energy
Savings:
≈ 40%
Actual Energy Savings – First Year
OWEA Annual Conference | June 19, 2013
• Average Annual Energy Cost 2009-2011
• $220,000
• Average Annual Energy Cost 2012
• $135,000
• Energy Savings
• $85,000/yr
• ≈ 40%
Lessons Learned
OWEA Annual Conference | June 19, 2013
• New Technology
• New manufacturers
• Purchase extended warranty
• Base bid manufacturer
• Performance Testing is Critical
• ASME Performance Test Codes
• PTC-10 – Compressors and Exhausters
• PTC-13 – Blowers – under development
Lessons Learned
OWEA Annual Conference | June 19, 2013
• Turndown
• Be weary of manufacturer claims
• Blower controls protect against surge – reduces operating range
• Muddy Creek HMI programming was modified to avoid LCP warnings and keep blow-off valves from opening
Lessons Learned
OWEA Annual Conference | June 19, 2013
• Programming System Controls is Critical
• Controls can contribute to energy savings as much as the blowers
• Startup adjustments will be necessary - flexibility in programming is required
• Muddy Creek HMI control was modified to maintain mixing airflow