metro transit police department facility update€¦ · design objectives support mission of the...
TRANSCRIPT
______________________________________
PROGRAM OF REQUIREMENTS
Office/Support spaces for 400 Staff
Tempered Parking for up to 100 fleet vehicles
DESIGN OBJECTIVES
Support Mission of the MTPD
Refreshed Presence and New Gateway to Campus
High Performance Building
Metro Transit Police Department Facility Update
1
Site
2
Massing of Building
3
Public Interface
4
Three Schemes
5
Hybrid Concept
6
Entry Plaza
7
MTPD – Project Schedule
8
2015 MTPD Award
Design Contract February
Heywood Campus Master plan and MTPD
update
FTH 2 Design RFP Issue
Month
Land Acquisition
Second Quarter
2016 MTPD Bid
Construction First Quarter
MTPD Construction Start Second
Quarter
2017 MTPD
Construction Completed November
2018 FTH 2
Construction Completed Summer
8