method statement - the wca€¦ · 3/15/ 1.0 introduction this method statement outlines the...

15
1/15 Method Statement Task Approval Contractor: Client maintenance department/safety representative Approval ( Contractor’s Name): Signed: Date: Approval client: Signed: Date: Approval other: Signed: Date: Method Statement Number: N/A Location: Enterprise Hub, Job Supervisor/Contact: Contractor Foreman: Proposed Start Date: Scheduled Finish Date: Proposed Working Hours: Prepared by: Reviewed by: Attachments:

Upload: doanque

Post on 10-May-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

1/15

Method Statement

Task Approval

Contractor: Client maintenance department/safety representative

Approval ( Contractor’s Name):

Signed: Date:

Approval client:

Signed: Date:

Approval other:

Signed: Date:

Method Statement Number: N/A

Location: Enterprise Hub, Job Supervisor/Contact: Contractor Foreman: Proposed Start Date: Scheduled Finish Date: Proposed Working Hours: Prepared by: Reviewed by: Attachments:

2/15/

Amendments and change control

No Comment Initial 1

2

3

4

5

6

7

8

9

10

3/15/

1.0 Introduction

This method statement outlines the sequence to complete the works safely, without impact to personnel, property, or the environment.

2.0 Scope

Method Statement for the following works:-

Render/Wall Cleaning

Slab Cleaning

3.0 Programme

Time estimated to complete the works.

4.0 Access to the Work Place

The following access requirements are needed for completion of the task:

Slabbed area

Wall

5.0 Permits and Documentation

The following is a list of the required permits/controls

Permits Fire hydrant access, General permit to work

Other controls N/A

6.0 Chemicals substances brought onto site

The following substances shall be used for the completion of the task:

Product Approved by client

Yes

Yes

N/A

Yes

Other (specify):

N/A

4/15/

7.0 Resources

Item Description/Details

PPE HI-VIZ/Hard hat/Steel top cap shoes/protective gloves/Face visor

RPE (RPE) – P3 Fall Protection n/a

MEWP n/a

Scaffolding n/a

Other

Labour Number Foreman Applicator

Applicator Ground man/hoseman

8.0 Work Site Set Up/Layout

Item Applicable Comment

Transport routes

Yes

Setdown and Laydown Area

Yes

Routing of hoses

Yes

Hazard signage

Yes

Waste disposal – skips

N/A

Other:

Yes No

9.0 Training and Information

The following are the training and requirements identified to complete the outlined task:

CSCS Contractor training N/A

Task specific training N/A

10.0 Supervision

5/15/

The works will be supervised by the Contractor’s foreman who has overall responsibility for the safe execution of the work on this project.

11.0 Environmental Impacts and Controls

Generated Waste Control Environmental Impact Product packaging.

Wash out container into contractor’s tank and dispose/recycle container off- site.

Acceptable

Chemical run-off

Run-off is to be kept to minimum or zero using good spray and brush control techniques. If run off to drains is unavoidable, block drains/gutters until application has been concluded.

Run-off to drains is to be kept to as near Acceptable

zero as possible using good spray and

brush control techniques. If run off to

drains is unavoidable, block

drains/gutters until application has been concluded.

Residue run-off from Due to the nature of Blackwash, any Acceptable diluted (5-10:1) BENZ Blackwash rinse water.

chlorine will disappear very rapidly. Oxidised molecules will be the dominant by-products of Blackwash. Chlorinated compounds have been viewed as the more important to assess from an environmental point of view because of the hazardous properties of certain types of chlorinated molecules.

Residue run-off of diluted BENZ Blackwash are relatively

biodegradable and are not

expected to bioacumulate.

Any residues entering water system are not expected to cause any harm to the environment.

Treated areas are to be left a minimum

of 30 minutes – and 60 minutes is

preferable – before rinsing to ensure no

chlorinated molecules remain.

6/15/

12.0 Emergency Provisions In the event of an incident the following people shall be notified: Site emergency tel: N/A Security: N/A Contractor H&S leader tel: 07773560582 Client H&S leader tel N/A

12.1 First Aid

In the event of any Contractor’s employee requiring medical emergency treatment they will notify the Contractor’s trained 1st Aid person.

13.0 Work Sequence ( Steps to Complete the Task)

13.1 Mobilise to Site.

1. Bring all equipment and materials on to the site.

2. Ensure standby attendant is in position. All hoses are rolled out to minimise trip hazards.

3. Signage should be in place.

13.2 Stain removal of surface

1. Using soft washing equipment with good flow control, spray or brush the area to be cleaned with BENZ Blackwash in a concentration not greater than 5:1 ensuring no run-off of chemical into local drains. Block drains/gutters during application if necessary.

7/15/

2. Wait at least 30-60 minutes before rinsing the surface with suitable rinsing equipment such as a low pressure/high flow power washer, booster pump, or WFP (water fed pole).

3. Repeat the process until clean, bearing in mind

staining will fade dramatically once dry. Two applications are typical, three on only the most severe of cases.

Red staining, once turned pink, will disappear within 1-24 hours.

Black staining will turn a light brown and will mostly disappear with 24 hours. Some staining may still be present in the very worst of cases. This is probably water staining from the heavy biological growth and may improve with weathering over time.

8/15/

13.3 Treatment of surfaces

Now the heavy soiling has been removed from the surface, it may be treated with BENZ

Biocidal Wash to kill any organic spores that may remain. The active ingredient in BENZ

Biocidal Wash also has a latent affect and is able to penetrate deeper into the pores of the

surface than BENZ Blackwash. The concentration of BENZ Biocidal Wash can be as low as

50:1 in summer and 40:1 in winter

1. Use appropriate spray equipment and spray

techniques (WFP and BENZ Nozzle) to spray all

elevations, paying particular attention to areas

where algae and mould like to breed. These

places include capping stones, cement mortar

joints. window sills, and so on.

2. Work methodically to ensure saturation of the

entire surface, whilst at the same time keeping

run-off to drains to a minimum. Block

drains/gutters during application if necessary.

13.4 PPE ( Personal Protective Equipment) Required All spraying shall require the following PPE:

▪ Goggles ▪ Face visor that also covers the operators hair ▪ Chemical resistant gloves ▪ Respiratory Personal Equipment (RPE) – P3 ▪ Chemical spraying suit

9/15/

14.0 Task Specific Risk Assessment

Risk Categories

IV

High

Mitigate with hi priority

III

Significant

Mitigate with Pr

II

Medium

Controls Verif ALARP (As Lo

Reasonabl Practicable

I

Low

No Mitigatio Required

Risk Assessment Method

1. Identify a hazard. Note this in the

assessment table.

2. Note the risk-effect of the hazard.

3. Add proposed controls-mitigation.

4. Select the category of potential

consequence with controls in

place. Use the table to the right

and note under ‘C’

5. Select the likelihood of the

occurrence taking place with the

current controls in place. Note this

under ‘L’

6. Determine risk category from risk

matrix. This will be a Roman

numeral. Note this under ‘RC’

7. Do not proceed with task if risk is

Category III or IV – use further

controls-mitigation to reduce risk to

a category I or II.

CATEGORY CONSEQUENCE-

SEVERITY LIKELIHOOD

5 Fatality, Public Hospitalization, or

Severe Health Effects

Frequent

LIK

EL

IHO

OD

5 II II III IV IV

4 I II III III IV 4 Permanent

Disability, Multiple Hospitalizations, or Major Health Effects

Probable

3 I II II III III

2 I I II II II

3 One or more Lost

Time Workday Cases or Significant

Health Effects

Rare

1 I I I I II

1 2 3 4 5 2

Medical Treatment with Restricted Duty or Medium Health

Effects

Remote

CONSEQUENCEE

1 Medical Treatment,

Minor Health Effects, First Aid

Case, or Less

Improbable

10/15/

HAZARD

RISK- EFFECT CONTROLS- MITIGATION Assessment

FURTHER

CONTROLS-

MITIGATION

Secondary

Assessment COMMENT

C L RC C

L

RC

Use of hand tools

Hand injury, falling

object

Approved tools

Barrier off when working at height

Competent workers employed

2 3 II

ALARP ("As Low As

Reasonably

Practicable") - NO

FURTHER CONTROLS

NEEDED

Acceptable

Mobile plant and

equipment on site

Ignition of

flammable vapours.

Spill/drip of fuel

All plant to be turned off and

disconnected at breaks / lunch /

cease work.

Fire extinguisher (CO2) by plant.

All plant electrically and mechanically

tested and tagged.

Drip trays provided and used.

No unauthorised entry into work area

5 1 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

Movement around site

Uneven surfaces,

obstructions in and

around work area

Use only dedicated access routes.

Ensure lighting is adequate.

Due care and attention.

Walk around – do not step over.

Housekeeping - dedicated areas for

materials/plant and equipment.

Wind back all hose when not in use

3 3 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

11/15/

HAZARD

RISK- EFFECT CONTROLS- MITIGATION Assessment

FURTHER

CONTROLS-

MITIGATION

Secondary

Assessment COMMENT

C L RC C

L

RC

Manual handling

Lifting/carrying

materials and

equipment

Consider mechanical aid before

manual handling.

Due care and attention.

Manual handling training carried out

for all operatives.

Correct lifting technique.

Assess the task prior to

commencement.

1 3 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

Working at height

Injuries through

falls from

scaffolding

All temporary working at height will be

from a dedicated scaffold platform.

Access via certified ladder system.

Scaffold inspected daily by a

competent person.

Where required a “full body harness”

must be worn and attached to a

suitable anchor point via a fall arrest

or restraint lanyard.

5 2 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

BENZ Softwash Limited 2015

www

.benzsoftwash.com

12/15/

HAZARD

RISK- EFFECT CONTROLS- MITIGATION Assessment

FURTHER

CONTROLS-

MITIGATION

Secondary

Assessment COMMENT

C L RC C

L

RC

Use of MEWP's

Falls from Height

Falling materials

Collapse or

overturning of

MEWP's.

Failure of MEWP

Driven by competent and authorised

operatives.

All operatives to wear correct fall

prevention protection equipment.

A fall restraint lanyard shall be used in

MEWPs, adjusted correctly and fixed

to the correct anchor point.

All MEWPS are to be fully certified.

Check certification of MEWP's

Cordon off area below whilst MEWP's

are in operation.

Attendant to monitor activity and

escort/advise visitors.

All tools and equipment to be

maintained below the kick plate.

Tools and equipment to be kept in

boxes if possible.

Tool lanyards may be used.

Due care and attention.

Ensure MEWP is sited on suitable

hard standing ground.

Do not use MEWP as a materials lift.

Do not overload MEWP. Carry only

minimum tools.

MEWP's are to be driven only as per

the manufacturer’s instructions.

SWL not to be exceeded.

5 2 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

HAZARD

RISK- EFFECT CONTROLS- MITIGATION Assessment

FURTHER

CONTROLS-

MITIGATION

Secondary

Assessment COMMENT

C L RC C

L

RC

Overspray from

spraying operations

Injury to persons:

eye/skin irritations

Do not spray in high winds.

Barrier off area to members of the

public.

Use appropriate spraying techniques

and equipment

1 4 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

Chemical burns from

handling concentrated

product

Injury to persons,

eyes, skin burns

Wear appropriate recommended

Personal Protective Equipment (PPE)

when handling concentrated product.

3 3 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

Irritations from using

diluted product

Long exposure

times could

potentially lead to

irritation of the skin.

Wear appropriate recommended PPE.

Immediately wash any residues from

skin and remove any contaminated

clothing

5 2 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

Loss of control of

spray pole Pole breakage

and/or injury to

persons

Operatives in-house trained in the use

of telescopic WFPs. recovery

techniques, stance, etc

1 5 II

ALARP- NO FURTHER

CONTROLS NEEDED

Acceptable

13/15/

13 Work Area Sketch

14/15

Method Statement

14 Employee Acknowledgement

I the undersigned, have read and understand the method statement, and agree to work as set above.

Print name Signature

End of Document

15 Rev 0