1/15
Method Statement
Task Approval
Contractor: Client maintenance department/safety representative
Approval ( Contractor’s Name):
Signed: Date:
Approval client:
Signed: Date:
Approval other:
Signed: Date:
Method Statement Number: N/A
Location: Enterprise Hub, Job Supervisor/Contact: Contractor Foreman: Proposed Start Date: Scheduled Finish Date: Proposed Working Hours: Prepared by: Reviewed by: Attachments:
3/15/
1.0 Introduction
This method statement outlines the sequence to complete the works safely, without impact to personnel, property, or the environment.
2.0 Scope
Method Statement for the following works:-
Render/Wall Cleaning
Slab Cleaning
3.0 Programme
Time estimated to complete the works.
4.0 Access to the Work Place
The following access requirements are needed for completion of the task:
Slabbed area
Wall
5.0 Permits and Documentation
The following is a list of the required permits/controls
Permits Fire hydrant access, General permit to work
Other controls N/A
6.0 Chemicals substances brought onto site
The following substances shall be used for the completion of the task:
Product Approved by client
Yes
Yes
N/A
Yes
Other (specify):
N/A
4/15/
7.0 Resources
Item Description/Details
PPE HI-VIZ/Hard hat/Steel top cap shoes/protective gloves/Face visor
RPE (RPE) – P3 Fall Protection n/a
MEWP n/a
Scaffolding n/a
Other
Labour Number Foreman Applicator
Applicator Ground man/hoseman
8.0 Work Site Set Up/Layout
Item Applicable Comment
Transport routes
Yes
Setdown and Laydown Area
Yes
Routing of hoses
Yes
Hazard signage
Yes
Waste disposal – skips
N/A
Other:
Yes No
9.0 Training and Information
The following are the training and requirements identified to complete the outlined task:
CSCS Contractor training N/A
Task specific training N/A
10.0 Supervision
5/15/
The works will be supervised by the Contractor’s foreman who has overall responsibility for the safe execution of the work on this project.
11.0 Environmental Impacts and Controls
Generated Waste Control Environmental Impact Product packaging.
Wash out container into contractor’s tank and dispose/recycle container off- site.
Acceptable
Chemical run-off
Run-off is to be kept to minimum or zero using good spray and brush control techniques. If run off to drains is unavoidable, block drains/gutters until application has been concluded.
Run-off to drains is to be kept to as near Acceptable
zero as possible using good spray and
brush control techniques. If run off to
drains is unavoidable, block
drains/gutters until application has been concluded.
Residue run-off from Due to the nature of Blackwash, any Acceptable diluted (5-10:1) BENZ Blackwash rinse water.
chlorine will disappear very rapidly. Oxidised molecules will be the dominant by-products of Blackwash. Chlorinated compounds have been viewed as the more important to assess from an environmental point of view because of the hazardous properties of certain types of chlorinated molecules.
Residue run-off of diluted BENZ Blackwash are relatively
biodegradable and are not
expected to bioacumulate.
Any residues entering water system are not expected to cause any harm to the environment.
Treated areas are to be left a minimum
of 30 minutes – and 60 minutes is
preferable – before rinsing to ensure no
chlorinated molecules remain.
6/15/
12.0 Emergency Provisions In the event of an incident the following people shall be notified: Site emergency tel: N/A Security: N/A Contractor H&S leader tel: 07773560582 Client H&S leader tel N/A
12.1 First Aid
In the event of any Contractor’s employee requiring medical emergency treatment they will notify the Contractor’s trained 1st Aid person.
13.0 Work Sequence ( Steps to Complete the Task)
13.1 Mobilise to Site.
1. Bring all equipment and materials on to the site.
2. Ensure standby attendant is in position. All hoses are rolled out to minimise trip hazards.
3. Signage should be in place.
13.2 Stain removal of surface
1. Using soft washing equipment with good flow control, spray or brush the area to be cleaned with BENZ Blackwash in a concentration not greater than 5:1 ensuring no run-off of chemical into local drains. Block drains/gutters during application if necessary.
7/15/
2. Wait at least 30-60 minutes before rinsing the surface with suitable rinsing equipment such as a low pressure/high flow power washer, booster pump, or WFP (water fed pole).
3. Repeat the process until clean, bearing in mind
staining will fade dramatically once dry. Two applications are typical, three on only the most severe of cases.
Red staining, once turned pink, will disappear within 1-24 hours.
Black staining will turn a light brown and will mostly disappear with 24 hours. Some staining may still be present in the very worst of cases. This is probably water staining from the heavy biological growth and may improve with weathering over time.
8/15/
13.3 Treatment of surfaces
Now the heavy soiling has been removed from the surface, it may be treated with BENZ
Biocidal Wash to kill any organic spores that may remain. The active ingredient in BENZ
Biocidal Wash also has a latent affect and is able to penetrate deeper into the pores of the
surface than BENZ Blackwash. The concentration of BENZ Biocidal Wash can be as low as
50:1 in summer and 40:1 in winter
1. Use appropriate spray equipment and spray
techniques (WFP and BENZ Nozzle) to spray all
elevations, paying particular attention to areas
where algae and mould like to breed. These
places include capping stones, cement mortar
joints. window sills, and so on.
2. Work methodically to ensure saturation of the
entire surface, whilst at the same time keeping
run-off to drains to a minimum. Block
drains/gutters during application if necessary.
13.4 PPE ( Personal Protective Equipment) Required All spraying shall require the following PPE:
▪ Goggles ▪ Face visor that also covers the operators hair ▪ Chemical resistant gloves ▪ Respiratory Personal Equipment (RPE) – P3 ▪ Chemical spraying suit
9/15/
14.0 Task Specific Risk Assessment
Risk Categories
IV
High
Mitigate with hi priority
III
Significant
Mitigate with Pr
II
Medium
Controls Verif ALARP (As Lo
Reasonabl Practicable
I
Low
No Mitigatio Required
Risk Assessment Method
1. Identify a hazard. Note this in the
assessment table.
2. Note the risk-effect of the hazard.
3. Add proposed controls-mitigation.
4. Select the category of potential
consequence with controls in
place. Use the table to the right
and note under ‘C’
5. Select the likelihood of the
occurrence taking place with the
current controls in place. Note this
under ‘L’
6. Determine risk category from risk
matrix. This will be a Roman
numeral. Note this under ‘RC’
7. Do not proceed with task if risk is
Category III or IV – use further
controls-mitigation to reduce risk to
a category I or II.
CATEGORY CONSEQUENCE-
SEVERITY LIKELIHOOD
5 Fatality, Public Hospitalization, or
Severe Health Effects
Frequent
LIK
EL
IHO
OD
5 II II III IV IV
4 I II III III IV 4 Permanent
Disability, Multiple Hospitalizations, or Major Health Effects
Probable
3 I II II III III
2 I I II II II
3 One or more Lost
Time Workday Cases or Significant
Health Effects
Rare
1 I I I I II
1 2 3 4 5 2
Medical Treatment with Restricted Duty or Medium Health
Effects
Remote
CONSEQUENCEE
1 Medical Treatment,
Minor Health Effects, First Aid
Case, or Less
Improbable
10/15/
HAZARD
RISK- EFFECT CONTROLS- MITIGATION Assessment
FURTHER
CONTROLS-
MITIGATION
Secondary
Assessment COMMENT
C L RC C
L
RC
Use of hand tools
Hand injury, falling
object
Approved tools
Barrier off when working at height
Competent workers employed
2 3 II
ALARP ("As Low As
Reasonably
Practicable") - NO
FURTHER CONTROLS
NEEDED
Acceptable
Mobile plant and
equipment on site
Ignition of
flammable vapours.
Spill/drip of fuel
All plant to be turned off and
disconnected at breaks / lunch /
cease work.
Fire extinguisher (CO2) by plant.
All plant electrically and mechanically
tested and tagged.
Drip trays provided and used.
No unauthorised entry into work area
5 1 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
Movement around site
Uneven surfaces,
obstructions in and
around work area
Use only dedicated access routes.
Ensure lighting is adequate.
Due care and attention.
Walk around – do not step over.
Housekeeping - dedicated areas for
materials/plant and equipment.
Wind back all hose when not in use
3 3 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
11/15/
HAZARD
RISK- EFFECT CONTROLS- MITIGATION Assessment
FURTHER
CONTROLS-
MITIGATION
Secondary
Assessment COMMENT
C L RC C
L
RC
Manual handling
Lifting/carrying
materials and
equipment
Consider mechanical aid before
manual handling.
Due care and attention.
Manual handling training carried out
for all operatives.
Correct lifting technique.
Assess the task prior to
commencement.
1 3 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
Working at height
Injuries through
falls from
scaffolding
All temporary working at height will be
from a dedicated scaffold platform.
Access via certified ladder system.
Scaffold inspected daily by a
competent person.
Where required a “full body harness”
must be worn and attached to a
suitable anchor point via a fall arrest
or restraint lanyard.
5 2 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
BENZ Softwash Limited 2015
www
.benzsoftwash.com
12/15/
HAZARD
RISK- EFFECT CONTROLS- MITIGATION Assessment
FURTHER
CONTROLS-
MITIGATION
Secondary
Assessment COMMENT
C L RC C
L
RC
Use of MEWP's
Falls from Height
Falling materials
Collapse or
overturning of
MEWP's.
Failure of MEWP
Driven by competent and authorised
operatives.
All operatives to wear correct fall
prevention protection equipment.
A fall restraint lanyard shall be used in
MEWPs, adjusted correctly and fixed
to the correct anchor point.
All MEWPS are to be fully certified.
Check certification of MEWP's
Cordon off area below whilst MEWP's
are in operation.
Attendant to monitor activity and
escort/advise visitors.
All tools and equipment to be
maintained below the kick plate.
Tools and equipment to be kept in
boxes if possible.
Tool lanyards may be used.
Due care and attention.
Ensure MEWP is sited on suitable
hard standing ground.
Do not use MEWP as a materials lift.
Do not overload MEWP. Carry only
minimum tools.
MEWP's are to be driven only as per
the manufacturer’s instructions.
SWL not to be exceeded.
5 2 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
HAZARD
RISK- EFFECT CONTROLS- MITIGATION Assessment
FURTHER
CONTROLS-
MITIGATION
Secondary
Assessment COMMENT
C L RC C
L
RC
Overspray from
spraying operations
Injury to persons:
eye/skin irritations
Do not spray in high winds.
Barrier off area to members of the
public.
Use appropriate spraying techniques
and equipment
1 4 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
Chemical burns from
handling concentrated
product
Injury to persons,
eyes, skin burns
Wear appropriate recommended
Personal Protective Equipment (PPE)
when handling concentrated product.
3 3 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
Irritations from using
diluted product
Long exposure
times could
potentially lead to
irritation of the skin.
Wear appropriate recommended PPE.
Immediately wash any residues from
skin and remove any contaminated
clothing
5 2 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
Loss of control of
spray pole Pole breakage
and/or injury to
persons
Operatives in-house trained in the use
of telescopic WFPs. recovery
techniques, stance, etc
1 5 II
ALARP- NO FURTHER
CONTROLS NEEDED
Acceptable
13/15/