October 3, 2007 Lyme Properties purchases the former Bailey
Bros. site in West Lebanon comprising 38 acres with over mile ofConnecticut River frontage.
Winter/S rin 2008 L me invited a roximatel 200 of theclosest neighbors to meet at the site and discuss the future of WestLebanon and how the Bailey Bros. may be part of that future. Fivewell attended Neighborhood Meetings were held as a result.
May 13, 2008 At the 4th Neighborhood Meeting, Lymeintroduces the River Park Master Plan incor oratin the to
priorities voiced by neighbors for river access, neighborhood scaleretail, expanded job base, mixed-use, and protection for the existingcharacter of Crafts Ave via construction of single family homes as atransition zone with no vehicular access to River Park from Crafts
Ave. 2
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
3/25
Fall 2008/Winter 2009 The conceptual River Park Master
Plan was resented to the Plannin Board and Conservation
Commission pursuant to the zoning ordinance. Three publicmeetings and four site tours were conducted with positive input fromboth groups.
July 2009 Lyme held meetings with Old West Lebanon businessowners to discuss the im act of River Park on existin businesses.The River Park Master Plan was embraced by the business ownersas an important step in revitalizing West Lebanon.
July 19, 2009 Lyme held a neighborhood picnic. More than150 neighbors attended to experience the river frontage first handand view the scale model of River Park. L me announced thewould seek a rezoning to allow the River Park Master Plan to be
implemented. 3
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
4/25
October 26, 2009 A voter initiated petition, with over 135
signatures, was submitted to the City Clerk to place the River Parkrezoning on the spring ballot.
Jan/Feb 2010 L me conducts outreach and education on theRiver Park rezoning petition including four days of site tours.
,voters of Lebanon 1975 to 949 (725 to 236 in West Lebanon).
,preliminary subdivision and site plan review. This represents atremendous engineering effort by Lymes consultants compressed
Lebanon City Council, in defiance of the referendum vote.4
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
5/25
December 2010 Six months after our applications were formallysubmitted, the City Engineer has not fully reviewed the engineeringplans and insists that a third party water and sewer study beconducted. However, the proposals for these no-bid studies are notprovided to Lyme for more than a month. Lyme pays $2,500 for thewater study and $12,000 for the sewer study. Both reports are due
in January 2011 based upon the written scope documents prepared .
February 2011 Despite repeated requests, the City Engineer
re uses to a ow yme access to t e water an sewer stu y resu ts.In fact, during this same period, the City Engineer directed the peerreviewer to disregard the data from Lymes engineers and to
informing Lyme.5
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
6/25
April 11, 2011 After three months of stonewalling Lymes
efforts to obtain co ies of the water and sewer re orts the Cit
Engineer issues a memo to the City Council recommending that theCouncil require extensive infrastructure upgrades as part of theRiver Park approval, including rebuilding Crafts Avenue to full Citystandards. After repeated requests, the Council agrees to allowLyme and an independent engineer time to review the studies
before acting on City Engineers memo.
April 2011 The new City Manager convenes meetings to discussthe water and sewer studies. The City Engineers unilateral directive
to disregard Lymes projections is disclosed and a number ofmethodological errors by the City Engineers office and the Cityspeer reviewer are uncovered. The City Manager directs staff toreconsider the proposed conditions. Two of the original four
conditions are dropped. 6
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
7/25
May 18, 2011 City Council votes to allow water and sewer
connections for River Park, but still includes unrelated infrastructuremprovements as part o t e approva , suc as ou ng t e s ze o
the sewer main to accommodate other areas of the City andcompletely rebuilding Crafts Avenue.
October 11, 2011 Planning Board approves the River ParkSubdivision application with conditions.
,Plan application for all seven phases of River Park.
March 15, 2012 NH DOT conditionally approves the River Park
.with the City approvals. Lyme is seeking a meeting with the NH DOTCommissioner in June to resolve the outstanding issues.
7
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
8/25
Upsize the sewer line from our proposed 10 line to a 15 or 18 line.
Reconstruct the full length of Crafts Ave within the existing right ofway, including replacement of all sidewalks and curbing to theircurrent standard.
.required outside of the street right of way.
No work will be done on the existing water lines in Crafts Avenue.
existing water line in Crafts Avenue.
Council reserved the right to require granite curbs and concrete
sidewalks at municipal expense.
Total construction timeframe now estimated at 3 months unless theCit o ts for new curbs and sidewalks.
8
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
9/25
Potential Sidewalk Conflict
Owner - Cynthia Mansell
9
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
10/25
Potential Sidewalk Conflict
Owner Raymond & Iris Mok
10
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
11/25
Potential Sidewalk Conflict
Owner Benjamin & Terrill Salter
11
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
12/25
Potential Sidewalk Conflict
Owner Etienne & Kristin Houdegbe
12
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
13/25
Potential Sidewalk Conflict
Owner Edwin Pearce
13
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
14/25
Potential Sidewalk Conflict
Owner Mary Munn
14
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
15/25
Potential Sidewalk Conflict
Owner Jonathan & Lissa Jones
15
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
16/25
Potential Sidewalk Conflict
Owner Jonathan & Lissa Jones
16
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
17/25
Potential Sidewalk Conflict
Owner Matthew & Debra Malloy
17
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
18/25
Potential Sidewalk Conflict
Owner Greg & Beverly Taylor
18
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
19/25
Potential Roadway Conflict
Owner Schwaber Trust
19
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
20/25
Potential Roadway Conflict
Owner Kathleen Omalley
20
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
21/25
North Main Street from River Park to.
21
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
22/25
Location of New Sidewalk
Owner Donald & Debra Curtis
22
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
23/25
Location of New Sidewalk
Owner George Kraus
23
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
24/25
Location of New Sidewalk
Edson/Villaverde & Scearbo
24
-
7/31/2019 May 14, 2012 River Park Neighborhood Meeting
25/25
Lyme Properties will continue to advance the engineering and
design work necessary to accomplish the mandated work. Our goals to start construct on n ugust, assum ng t e ty s gns o
by July 1, 2012.
Lyme will update our website regularly with any new informationregarding the construction schedule.www.riverparkwestlebanon.com
,contractor to perform the work. The contractor will be required toprovide sufficient personnel to keep neighbors informed with a dailywebsite ostin and to monitor traffic im acts.
The work will be organized in phases to minimize daily impact to thefewest neighbors possible.
Please dont hesitate to contact us with questions or concerns.