Page 1: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Material Requirements Planning

Page 2: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

• Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product

• MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced

• Dependent demand drives MRP

Material Requirements PlanningDefined

Page 3: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Dependent Demand

The demand for one item is related The demand for one item is related to the demand for another itemto the demand for another item

Given a quantity for the end item, Given a quantity for the end item, the demand for all parts and the demand for all parts and components can be calculatedcomponents can be calculated

In general, used whenever a In general, used whenever a schedule can be established for an schedule can be established for an itemitem

MRP is the common techniqueMRP is the common technique

Page 4: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Benefits of MRP

1.1. Better response to customer Better response to customer ordersorders

2.2. Faster response to market Faster response to market changeschanges

3.3. Improved utilization of facilities Improved utilization of facilities and laborand labor

4.4. Reduced inventory levelsReduced inventory levels

Page 5: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

• Based on a master production schedule, a material requirements planning system:– Creates schedules identifying the specific

parts and materials required to produce end items

– Determines exact unit numbers needed

– Determines the dates when orders for those materials should be released, based on lead times

Material Requirements PlanningSystem

Page 6: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

6

©The McGraw-Hill Companies, Inc., 2004

Firm orders from knowncustomers

Forecastsof demand

from randomcustomers

Aggregateproduct

plan

Bill ofmaterial

file

Engineeringdesign

changes

Inventoryrecord file

Inventorytransactions

Master productionSchedule (MPS)

Primary reportsSecondary reports

Planned order schedule for inventory and production control

Exception reportsPlanning reportsReports for performance control

Materialplanning(MRP

computer program)

Page 7: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Elemen MRP

1.1. Master production scheduleMaster production schedule

2.2. Specifications or bill of materialSpecifications or bill of material

3.3. Inventory availabilityInventory availability

4.4. Purchase orders outstandingPurchase orders outstanding

5.5. Lead timesLead times

Effective use of dependent demand Effective use of dependent demand inventory models requires the inventory models requires the followingfollowing

Page 8: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Master Production Schedule (MPS)

Specifies what is to be made and whenSpecifies what is to be made and when Must be in accordance with the aggregate Must be in accordance with the aggregate

production planproduction plan Aggregate production plan sets the Aggregate production plan sets the

overall level of output in broad termsoverall level of output in broad terms As the process moves from planning to As the process moves from planning to

execution, each step must be tested for execution, each step must be tested for feasibilityfeasibility

The MPS is the result of the production The MPS is the result of the production planning processplanning process

MPS is established in terms of specific MPS is established in terms of specific productsproducts

Page 9: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Master Production Schedule (MPS)

A customer order in a job shop (make-A customer order in a job shop (make-to-order) companyto-order) company

Modules in a repetitive (assemble-to-Modules in a repetitive (assemble-to-stock) companystock) company

An end item in a continuous (make-to-An end item in a continuous (make-to-stock) companystock) company

Can be expressed in any of the Can be expressed in any of the following terms:following terms:

Page 10: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

• Materials

• Parts

• Components

• Production sequence

• Modular BOM – Subassemblies

Bill of Materials (BOM) FileA Complete Product Description

Page 11: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

BOM (Table Example)

Top

Leg

Long Rail

Short Rail

Page 12: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

BOM (Product Structure)

Short Rails(2)

Table(End Item)

Long Rails(2)

Legs(4)

Top(1)

Leg Assembly(1)

Page 13: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Code

Level Code Component

0 Table (end-item)

1 Leg assembly (1)

2 Short rails (2)

2 Long rails (2)

2 Legs (4)

1 Top(1)

Page 14: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Attribute MRP Order Point

Demand Dependent Independent

Order philosophy

Requirements Replenishment

Forecast Based on master schedule

Based on past demand

Control concept

Control all items ABC

Objectives Meet manufacturing needs

Meet customer needs

Lot sizing Discrete EOQ

Types of inventory

Work in process and raw materials

Finished goods and spare parts

Attribute MRP Order Point

Demand Dependent Independent

Order philosophy

Requirements Replenishment

Forecast Based on master schedule

Based on past demand

Control concept

Control all items ABC

Objectives Meet manufacturing needs

Meet customer needs

Lot sizing Discrete EOQ

Types of inventory

Work in process and raw materials

Finished goods and spare parts

MRP versus Order-Point Systems

Page 15: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Elements of Success in MRP

• Implementation planning

• Adequate computer support

• Accurate data

• Management support

• User knowledge

Page 16: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed
Page 17: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Example of MRP Logic and Product Structure Tree

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Product Structure Tree for Assembly A Lead TimesA 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day

Total Unit DemandDay 10 50 A

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed

Page 18: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10.

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10.

Page 19: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50B Required 200

Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

SparesLT = 2

4x50=200

Page 20: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

LT=1 Order Placement 50B Required 200

LT=2 Order Placement 200C Required 100

LT=1 Order Placement 100D Required 400 300

LT=3 Order Placement 400 300E Required 200

LT=4 Order Placement 200F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Finally, repeating the process for all components, we have the final materials requirements plan:

Finally, repeating the process for all components, we have the final materials requirements plan:

20

Page 21: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

MRP Example

A(2) B(1)

D(5)C(2)

X

C(3)

Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

Page 22: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

A(2)

X

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 2 A’s for each X

It takes 2 A’s for each X

Page 23: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

B(1)A(2)

X

It takes 1 B for each X

It takes 1 B for each X

Page 24: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

A(2) B(1)

X

C(3)

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 3 C’s for each A

It takes 3 C’s for each A

Page 25: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

A(2) B(1)

C(2)

X

C(3)

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 2 C’s for each B

It takes 2 C’s for each B

Page 26: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

A(2) B(1)

D(5)C(2)

X

C(3)

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 5 D’s for each B

It takes 5 D’s for each B

Page 27: Material Requirements Planning. Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed

Closed Loop MRP

Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

Realistic?No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback