massdep approval process for nitrogen-reducing i/as

18
MassDEP Approval Process for Nitrogen-Reducing I/As Claire A. Golden Environmental Engineer IV MassDEP/BRP Buzzards Bay Coalition – March 5, 2014

Upload: buzzards-bay-coalition

Post on 07-May-2015

386 views

Category:

Education


1 download

DESCRIPTION

A presentation about the approval process in Massachusetts for nitrogen-removing technologies. Presented by Claire Golden, environmental engineer with the Massachusetts Dept. of Environmental Protection, during a Buzzards Bay Coalition 2014 Decision Makers mini-workshop on nitrogen-reducing septic systems. Learn more at www.savebuzzardsbay.org/DecisionMakers

TRANSCRIPT

Page 1: MassDEP Approval Process for Nitrogen-Reducing I/As

MassDEP Approval Process for Nitrogen-Reducing I/As

Claire A. GoldenEnvironmental Engineer IVMassDEP/BRP

Buzzards Bay Coalition – March 5, 2014

Page 2: MassDEP Approval Process for Nitrogen-Reducing I/As

SESSION OBJECTIVES & STRUCTURE

I/A Approval Process at MassDEPNitrogen-Reducing I/As and Conditions of ApprovalPath to General Use ApprovalOperation and MaintenanceUse of Shared Systems with I/As

Buzzards Bay Coalition – March 5, 2014

Page 3: MassDEP Approval Process for Nitrogen-Reducing I/As

I/A APPROVAL PROCESS HISTORYTitle 5 - 1995 Code (Oct 1994)

Nitrogen loading limitations (440 gpd/building acre)Nitrogen Sensitive Areas

Zone II of PWSIWPA of PWS

Areas served by on-site wells and on-site septicLimitations apply primarily to new construction or increase in flow but may be required for upgrades also under Maximum Feasible ComplianceCode did not go into full effect (March 31, 1995) until some I/As for N-reduction were approved.RSF established as standard (550 gpd/ac).

Buzzards Bay Coalition – March 5, 2014

Page 4: MassDEP Approval Process for Nitrogen-Reducing I/As

I/A APPROVAL PROCESS AT MassDEP

Established 4 Tiers of ApprovalRemedial Use ApprovalGeneral Use Approval Process

Piloting Use ApprovalProvisional Use ApprovalGeneral Use Approval

Approvals Design considerationsNitrogen-reductionPhosphorus-reduction

Buzzards Bay Coalition – March 5, 2014

Page 5: MassDEP Approval Process for Nitrogen-Reducing I/As

Types of I/A Approval

Remedial Useupgrades onlyno increase in design flow

Piloting Usepermitted installation at up to 15 locations

Provisional Usepermitted installation at up to 50 locations

General Use

Buzzards Bay Coalition – March 5, 2014

Page 6: MassDEP Approval Process for Nitrogen-Reducing I/As

NITROGEN-REDUCING I/As

General Use1 generic3 patented

Provisional Use9 patented

Piloting Use3 patented

Buzzards Bay Coalition – March 5, 2014

Page 7: MassDEP Approval Process for Nitrogen-Reducing I/As

General Use Approval I/As

Recirculating Sand Filter (RSF)RUCKMicroFAST & NitriFAST

TECHNOLOGY FLOW (gpd)

RESTRICTION N-LOADING EFFLUENT N

RSF < 10,000 None 550 gpd/ac 25 mg/l

RUCK < 2,000 None 660 gpd/ac 19 mg/l

MicroFASTNitriFAST

< 2,000 < 2,000

ResidentialResidential

550 gpd/ac660 gpd/ac

25 mg/l19 mg/l

Buzzards Bay Coalition – March 5, 2014

Page 8: MassDEP Approval Process for Nitrogen-Reducing I/As

Provisional Use Approval I/As

Advantex AX20 and AX100 (Advantex)Amphidrome Process (Amphidrome)Bioclere – 2 approvalsHighStrengthFAST, MicroFAST & NitriFAST (FAST)Modular FASTNitrexSeptiTechSingular 960 DNWaterloo Biofilter – 2 approvals (Waterloo)

Buzzards Bay Coalition – March 5, 2014

Page 9: MassDEP Approval Process for Nitrogen-Reducing I/As

TECHNOLOGY FLOW (gpd)

RESTRICTION N-LOADING EFFLUENT N

Advantex < 2,000 < 2,000> 2,000

NoneNoneNone

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

Amphidrome < 2,000 < 2,000> 2,000

NoneNoneNone

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

Bioclere* < 2,000< 2,000 > 2,000

NoneResidential

None

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

FAST < 2,000> 2,000

NonresidentialNone

550 gpd/ac550 gpd/ac

25 mg/l25 mg/l

Modular FAST > 2,000 None 550 gpd/ac 25 mg/l

Prov. Use N-Removal I/As Chart

Buzzards Bay Coalition – March 5, 2014

Page 10: MassDEP Approval Process for Nitrogen-Reducing I/As

TECHNOLOGY FLOW (gpd)

RESTRICTION N-LOADING EFFLUENT N

Nitrex < 2,000 < 2,000> 2,000

NoneResidential

None

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

SeptiTech < 2,000 < 2,000> 2,000

NoneNoneNone

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

Singular < 2,000< 2,000

NoneNone

550 gpd/ac660 gpd/ac

25 mg/l19 mg/l

Waterloo < 2,000 < 2,000> 2,000

NoneResidential

None

550 gpd/ac660 gpd/ac550 gpd/ac

25 mg/l19 mg/l25 mg/l

Prov. Use N-Removal I/As Chart (cont.)

Buzzards Bay Coalition – March 5, 2014

Page 11: MassDEP Approval Process for Nitrogen-Reducing I/As

Piloting Use Approval I/As

BioBarrier Wastewater Treatment System (BioBarrier)Hydro-Kinetic Wastewater Treatment System (Hydro-Kinetic)RUCK CFT System (RUCK CFT)

Buzzards Bay Coalition – March 5, 2014

Page 12: MassDEP Approval Process for Nitrogen-Reducing I/As

TECHNOLOGY FLOW (gpd)

RESTRICTION N-LOADING EFFLUENT N

BioBarrier < 2,000 < 2,000

NonresidentialResidential

550 gpd/ac660 gpd/ac

25 mg/l19 mg/l

Hydro-Kinetic < 600 < 600

NonresidentialResidential

550 gpd/ac660 gpd/ac

25 mg/l19 mg/l

RUCK CFT < 2,000 None 660 gpd/ac 19 mg/l

Piloting Use N-Removal I/As

Buzzards Bay Coalition – March 5, 2014

Page 13: MassDEP Approval Process for Nitrogen-Reducing I/As

Path to General Use Approval

Piloting – up to 15 systems state-wideOperationsDataApply for Provisional Use Approval

Provisional – up to 50 systems state-wideOperationsDataApply for General Use Approval

General

Page 14: MassDEP Approval Process for Nitrogen-Reducing I/As

OPERATION AND MAINTENANCE

Deed notificationOperations contractInspectionsSampling and reportingRelated electrical cost for operation of the I/A

Buzzards Bay Coalition – March 5, 2014

Page 15: MassDEP Approval Process for Nitrogen-Reducing I/As

SHARED SYSTEM USE WITH I/As

Approval process for shared system must be completedPotential cost savingsPotential more consistent treatmentSystems are fully inspected every three years (inspection at time of transfer not required)

Buzzards Bay Coalition – March 5, 2014

Page 16: MassDEP Approval Process for Nitrogen-Reducing I/As

Shared System Approvals

Shared components must be definedFinancial mechanisms put into place as needed

I/AsPump chambers

Establishment of ownership entityTrustsLLC

Easement for shared componentsDocuments provided in Title 5 regs

Buzzards Bay Coalition – March 5, 2014

Page 17: MassDEP Approval Process for Nitrogen-Reducing I/As

Buzzards Bay Coalition – March 5, 2014

Page 18: MassDEP Approval Process for Nitrogen-Reducing I/As

CONTACTS

Brett RoweMassDEP/BRP/SERO [email protected]

Claire A. GoldenMassDEP/[email protected]

Brian DudleyMassDEP/BRP/SEROCape [email protected]

Buzzards Bay Coalition – March 5, 2014