maritime romas remote operations of machinery and ... · blackout loss of ship-shore comms ecc...
TRANSCRIPT
DNV GL © 2018 06 February 2019 SAFER, SMARTER, GREENERDNV GL © 2018
Steinar Låg
06 February 2019
MARITIME
ROMAS – Remote Operations of Machinery and Automation Systems
1
Haugesundkonferansen 6.februar 2019
DNV GL © 2018 06 February 2019
Outline
▪ The ROMAS Project
▪ Some of the work done
– CONOPS – Concept of operations
– HaziD analysis
– IAS Data analysis
▪ Pilot testing
▪ Way forward
2
DNV GL © 2018 06 February 2019
The ROMAS project
▪ ROMAS: Remote Operation of
Machinery and Automation
Systems
–NFR application granted Dec 2016
– Research project 2017-2019
– Total budget 9,5 MNOK
– 50% support from NFR (Maroff)
4
▪ Partners:
▪ Reference partner:
DNV GL © 2018 06 February 2019
Remote machinery operation: Background and motivation
5
• Fleet wide control from an on-shore ECC• Reduced need for engineers on-board• Improved efficiency & safety• Not as “revolutionary” as remote/autonomous navigation
Idea: Move the Engine Control Room
(ECR) from the ship to a shore-
based Engine Control Centre (ECC)
▪ Shortage of machinery engineers to man ships
▪ Increasingly complex ships, new skills needed
▪ Increased digitalisation & improved ship-shore
connectivity
▪ Automation and remote operations is
increasingly adopted in other industries
DNV GL © 2018 06 February 2019
ROMAS Work packages
Business & user requirements
Risk & reliability
Operational data analysis
Rules & regulations
Verification & approval
Implementation Piloting & DemoPM &
dissemination
6
H1 H2 H3 H4
H5 H6 H7 H8
▪ Objective: To establish a framework of regulations, rules and
verification methods for remote (shore-based) operations of ship
machinery and automation systems, enabling improved operations
and cost-efficiency without compromising safety of ship operations.
DNV GL © 2018 06 February 2019
Some of the work done
- CONOPS – Concept of Operations- HazID analysis- IAS data analysis
7
DNV GL © 2018 06 February 2019
Concept qualification process as per CG-0264 (Class Guideline for Autonomous and remotely operated ships)
8
Decide on
operations and
automation
High-level
design
Detailed
design
Build and
integrate
Commissioning
and test
Review of overall concepts Plan approvalNewbuild
survey
Test
witnessing
DNV GL newbuild process
Operations
DNV GL fleet in service process
FiS
surveys
Test scope
approval
Analyse class
operations
data
CONOPS
Preliminaryrisk analysis
report
Designphilosophy
Detailedvessel design
Detailed riskanalysisreports
Testspecifications
Safetyphilosophy
Verificationand validation
strategy
Maintenance philosophy
TestReports
Configurationmanagement
reports
Off-shipsystems design
Submitter’s activities
DNV GL © 2018 06 February 2019
Pilot vessel MF Fannefjord
▪ Norwegian flagged Ro-ro ferry built for Fjord1 in 2010
▪ Yard: Gdanska Stocznia Remontowa, Gdansk Poland
▪ Built to DNV class (Vessel ID 28425/D28424)
– 1A1 Car ferry B Clean E0 Gas fuelled R4(nor)
▪ Double-ended ferry design with battery hybrid gas (and
diesel) electric propulsion
11
Highly redundant propulsion system:
▪ 2 azimuth thrusters
▪ Power: 2x Gas + Battery + Diesel
DNV GL © 2018 06 February 2019
Remote operations concept: ECC side
▪ ECC located in Fjord1’s office in Molde
– Manning: 24x7 by 1 operator (chief engineer)
– Arrangement for additional support (bakvakt)
▪ ECC designed to support 3 ferries
– Similar design & operational profile
– Pilot tests: Just one ferry (MF Fannefjord)
▪ Responsibilities
– Main responsibility for maintenance & operation
– Communication with ship and shore-parties
▪ Equipment
– 2 workstations (~ECR-like)
– Big screen with fleet view
12
DNV GL © 2018 06 February 2019
Remote operations concept: Ferry side
▪ Overall manning level (5) remains unchanged
– to comply with requirements for safety manning
▪ Chief engineer replaced by “combiman”
– Qualification: Able Seafarer Engine (“Motormann”)
– Responsibilities:
– Combination of deck- and machinery- work
– Emergency/safety duties acc.to safety plan
– Planned maintenance
– Assist ECC operator when required
– Visual inspections and routine work
– Take local command of technical systems (when required)
– Receive support and guidance from ECC
▪ ECR and Bridge workstations: Backup for ECC
13
DNV GL © 2018 06 February 2019
Remote operations concept: Monitoring & Control
▪Remote IAS (Integrated Automation
System)
– “hub” for monitoring & control of the machinery
and engineering systems
▪ IAS functional enhancements
– Communication system integration
– Transfer of Command
▪Remote connections from other relevant
ship systems such as:
– Fire / safety systems
– Shiplog – admin / operational
– CCTV
14
DNV GL © 2018 06 February 2019
Remote operations concept: Communications
▪ The IAS Network onboard is extended to
ECC over a reliable and redundant ship-
shore communication link
▪ Communications
– 2 x 4G modems (Telia and Telenor) + ICE
– “Always on” 2-way voice ECC-Bridge
– VHF at ECC
– Portable communication device to support
troubleshooting
15
Example: DAQRI’s smart helmet (www.daqri.com)
https://www.ice.no/dekning/
DNV GL © 2018 06 February 2019
CONOPS: Identification of abnormal conditions / scenarios
▪ Putting spare ferry into operations
▪ Simultaneous problems on two ferries
▪ ESD (Emergency Shutdown)
▪ Blackout
▪ Loss of ship-shore comms
▪ ECC unavailable
▪ Loss of propulsion
▪ Extreme weather
▪ Evacuation
▪ Etc.
18
DNV GL © 2018 06 February 2019
Hazid Analysis
▪ Workshop: DNV GL, Fjord1, Høglund, Sjøfartsdirektoratet and Rederiforbundet
▪ Goal: Identify and assess hazards associated with the concept
▪ Input: CONOPS
▪ Output: Hazid Report + Risk sheets
– serving as input for further work
▪ Two steps
– Jan 2018 (v1.0): MF Norangsfjord (workshop)
– Oct-Dec 2018 (v1.1) MF Fannefjord (@ DNV GL)
▪ Limitations: Relative exercise, no formal voting, CONOPS completeness
20
1 2 3 4
Minor Significant Severe Catastrophic
Effect on Human Safety Single or minor
injuries
Multiple or severe
injuries
Single fatality or
multiple severe
injuries
Multiple fatalities
Effect on Ship Local equipment
damage
Non-severe ship
damage
Severe damage Total loss
Frequency F\S 0,01 0,1 1 10
7 Frequent Likely to occur once per month on one ship 1E+1
6 Probable Likely to occur once per year on one ship 1E+0
5 Reasonably
probable
Likely to occur once per year in a fleet of 10 ships, i.e. likely
to occur a few times during the ship's life
1E-1
4 Seldom Likely to occur once per 10 years in a fleet of 10 ships 1E-2
3 Remote Likely to occur once per year in a fleet of 1,000 ships, i.e.
likely to occur in the total life of several similar ships
1E-3
2 Very remote Likely to occur once per 10 years in a fleet of 1000 ships 1E-4
1 Extremely
remote
Likely to occur once in the lifetime (20 years) of a world
fleet of 5,000 ships
1E-5
Severity
DNV GL © 2018 06 February 2019
Hazid Workshop – risk matrix
21
Risk matrix
Conventional ops Remote ops w/mitigations
Rempote ops
DNV GL © 2018 06 February 2019
30 mitigations identified
30 mitigations
Training (2)
Design (13)
Procedure (15)
22
DNV GL © 2018 06 February 2019
30 mitigations identified
Training(2)
• Machinery training (Combiman)
• Safety training (Combiman)
Design(13)
• UPS for IAS & Comms
• Descriptive Battery Alarm
• Alarm limits adjusted for remote operations
• Alarms with priority/criticality
• Sufficient IAS integration
• Additional ICE modem
• Comms outage alarm
• Walkthrough of all essential sensors
• Visual surveillance (CCTV) at ECC
• Redundancy of comms modems
• VHF at ECC
• Sufficient UPS, broadband and security at ECC
• Additional sensors or inspection tools for gas system
Procedures(15)
• Avoid simultaneous overhaul of two engines/generators
• Procedure for ECC-Bridge communication
• Procedure for handling comms loss
• Procedure for spare ferry to be put into operations
• Procedure for ECC handling for simultaneous problems on two ferries
• Procedures/criteria for taking the ferry out of service
• Procedure for transferring command from ECC to Bridge
• Procedure for ECC support in severe weather conditions
• Updated procedures for remote/ECC-operations
• Procedure for handling water ingress
• Procedure for fire handling
• Procedure for bilge handling
• CBM (Condition Based Maintenance)
• Updated procedure for gas system
• Updated procedure for battery system
23
DNV GL © 2018 06 February 2019
Hazid Results
Conventional ops ROMAS ops w/mitigations
24
Increased risk
• 6.6 Communication failure
• 6.7 ECR/ECC outage
Reduced risk
▪ 2.2.1 Battery (ESS) Alarm availability
▪ 2.3.2 Too many alarms for ECC operator
▪ 2.3.3 Alarm information not detailed enough
▪ 6.4 Unplanned Maintenance & Repair
▪ 6.13 Fire incident
▪ 6.14 Environmental emissions
DNV GL © 2018 06 February 2019
Could be
automated?
Analysis of historic IAS data – to understand the alarm picture and existing operations and practices
ALARM
Does it
trigger
work ?
Does it trigger
maintenance
or repairs?
Is safety
affected ?
Could be done
remotely?
On-board or in
port?
Skills & tools
needed ?
Countermeasures?
Affecting
manning levels?
DNV GL © 2018 06 February 2019
Data sources
▪ IAS logs – events and alarms
▪ AIS data – position, speed, operational mode
▪ Historic maintenance logs
▪ Chief engineer’s log book
27MF Fannefjord MF Norangsfjord
DNV GL © 2018 06 February 2019
IAS-log: Need for filtering..... (Norangsfjord 2016)
Alarmer + Eventer [126100]
Alarmer (alle statuser) [28166]
Nye alarmer (status 5) [1773]
Ex DG Stop/Start & THR Stop [1555]
Pivot System-Alarmer[661]
EkskludertMaintenance & Repair [540]
Ex Other [250]
28
Eventer: ikke
behov for
håndtering
Kun
hørbare alarmer
Overgangsalarmer
rel til DG start/stop
og THR stop
Oppfølgingsalarmer for
samme system (2 min)
Alarmer fra M&R 19.-23.
September
• Koble på landstrøm
• Tester og feilsøk
• REPEAT og FIRE Alarmer
~ 345 per dag
~ 0,7 per dag
DNV GL © 2018 06 February 2019
Handling of routine work (planned maintenance)
▪ 2017 : 1434 records
▪ Mapped into categories
– Currently carried out by Service Personell
(external)
– Could be carried out by Service Personell
(external)
– Requires local precence of Chief Engineer
– Could be carried out by other crew (e.g.
Combiman)
– Could be remotely operated
– Could be automated/skipped
30
DNV GL © 2018 06 February 2019
IAS data analysis – key findings
▪ Better system integration needed
– Standalone systems, local panels, lack of operator-focus
▪ Alarm improvements are needed
– Too many «nuisance alarms» – need for cleaning up and reduce volume
– Context/mode awareness and suppression of non-essential alarms
– Descriptive alarm texts - get rid of “COMMON Alarms”
– Categorisation of alarm criticality – to enable prioritisation
▪ Increase automation – minimise manual operations
– However, automation will call for new alarms..
– Sensor quality and self-diagnostics
▪ Need for supporting offline analysis
– Historical IAS logs
– Digital engine log
31
Total
BILGEBLACKOUTBOILERBUS_COMMUNICATIONDEADDG1DG2DG3DG4FOFWHYD. AGGMBSMSBNODEPUBLIC ADDRESSSEWAGESLUDGESTART AIRTHR1THR2UPS
DNV GL © 2018 06 February 2019
Pilot test program 1Q 2019
▪ M/F Fannefjord as pilot vessel
▪ ECC in Molde (Fjord1’s premises)
▪ Based on previous work: CONOPS, Hazid and IAS data analysis
– NOTE: Subset implemented for Pilot testing
▪ In between test phases:
– Analysis of logs, documenting and assessing experiences. Making adjustment to equipment in ECC and
on-board the ship, as well as operational procedures.
33
DNV GL © 2018 06 February 2019
Hazid: 30 mitigations identified
Training(2)
• Machinery training (Combiman)
• Safety training (Combiman)
Design(13)
• UPS for IAS & Comms
• Descriptive Battery Alarm
• Alarm limits adjusted for remote operations
• Alarms with priority/criticality
• Sufficient IAS integration
• Additional ICE modem
• Comms outage alarm
• Walkthrough of all essential sensors
• Visual surveillance (CCTV) at ECC
• Redundancy of comms modems
• VHF at ECC
• Sufficient UPS, broadband and security at ECC
• Additional sensors or inspection tools for gas system
Procedures(15)
• Avoid simultaneous overhaul of two engines/generators
• Procedure for ECC-Bridge communication
• Procedure for handling comms loss
• Procedure for spare ferry to be put into operations
• Procedure for ECC handling for simultaneous problems on two ferries
• Procedures/criteria for taking the ferry out of service
• Procedure for transferring command from ECC to Bridge
• Procedure for ECC support in severe weather conditions
• Updated procedures for remote/ECC-operations
• Procedure for handling water ingress
• Procedure for fire handling
• Procedure for bilge handling
• CBM (Condition Based Maintenance)
• Updated procedure for gas system
• Updated procedure for battery system
34
DNV GL © 2018 06 February 2019
Mitigations implemented for pilot testing (implemented, partly implemented)
Training(2)
• Machinery training (Combiman)
• Safety training (Combiman)
Design(13)
• UPS for IAS & Comms
• Descriptive Battery Alarms
• Alarm limits adjusted for remote operations
• Alarms with priority/criticality
• Sufficient IAS integration
• Additional ICE modem
• Comms outage alarm
• Walkthrough of all essential sensors
• Visual surveillance (CCTV) at ECC
• Redundancy of comms modems
• VHF at ECC
• Sufficient UPS, broadband and security at ECC
• Additional sensors or inspection tools for gas system
Procedures(15)
• Avoid simultaneous overhaul of two engines/generators
• Procedure for ECC-Bridge communication
• Procedure for handling comms loss
• Procedure for spare ferry to be put into operations
• Procedure for ECC handling for simultaneous problems on two ferries
• Procedures/criteria for taking the ferry out of service
• Procedure for transferring command from ECC to Bridge
• Procedure for ECC support in severe weather conditions
• Updated procedures for remote/ECC-operations
• Procedure for handling water ingress
• Procedure for fire handling
• Procedure for bilge handling
• CBM (Condition Based Maintenance)
• Updated procedure for gas system
• Updated procedure for battery system
35
DNV GL © 2018 06 February 2019
+ new features identified in pilot planning (implemented, partly implemented)
Training(2)
• Machinery training (Combiman)
• Safety training (Combiman)
Design(13)
• UPS for IAS & Comms
• Descriptive Battery Alarms
• Alarm limits adjusted for remote operations
• Alarms with priority/criticality
• Sufficient IAS integration
• Additional ICE modem
• Comms outage alarm
• Walkthrough of all essential sensors
• Visual surveillance (CCTV) at ECC
• Redundancy of comms modems
• VHF at ECC
• Sufficient UPS, broadband and security at ECC
• Additional sensors or inspection tools for gas system
Procedures(15)
• Avoid simultaneous overhaul of two engines/generators
• Procedure for ECC-Bridge communication
• Procedure for handling comms loss
• Procedure for spare ferry to be put into operations
• Procedure for ECC handling for simultaneous problems on two ferries
• Procedures/criteria for taking the ferry out of service
• Procedure for transferring command from ECC to Bridge
• Procedure for ECC support in severe weather conditions
• Updated procedures for remote/ECC-operations
• Procedure for handling water ingress
• Procedure for fire handling
• Procedure for bilge handling
• CBM (Condition Based Maintenance)
• Updated procedure for gas system
• Updated procedure for battery system
36
• IAS Command transfer functionality
• IAS alarm history “resynchronisation”
• Shiplog integration (ticket/adm system)
• Voice communication ECC-Bridge
• Comms system health monitoring
• Digital engine log book
• Big Screen Fleet view in ECC
• ESS/battery integration
• Fire system integration
DNV GL © 2018 06 February 2019
ECC BIG screen layout
AIS
Fleet Sta
tus
CCTV
ECC implementation by Høglund – Big Screen
DNV GL © 2018 06 February 2019
ECC Implementation by Høglund – Fleet Status
▪ Persons On Board:
– Automatically updated from
Shiplog.
– Can easily be expanded with
other info e.g. dangerous cargo
– Time saver during emergencies
DNV GL © 2018 06 February 2019
Pilot test scope
▪ Normal operations
▪ Test cases
– Abnormal cases & failures
– Functional tests
– Ship-to-shore comms failures
– IAS – Comms interworking
– New ECC & IAS functionality
39
Nr Test type Scenario
1 AbormalPutting spare ferry into
operation
2 AbormalOperational problems on two
ferries simultaneously
3 Abormal DG auto-stop
4 AbormalUnplanned Maintenance &
Repair.
5 Abormal Black-out.
6 AbormalLoss of ship-shore
communications
7 Abormal ECC unavailable.
8 AbormalLoss of propulsion or
manoeuvring capability.
9 Abormal Extreme weather
10 Abormal Evacuation
11 Abormal Mob boat operation
12 AbormalWater ingress / Loss of
stability.
13 Abormal Fire alarm / fire incident.
14 AbormalEquipment down for
maintenance
DNV GL © 2018 06 February 2019
Pilot test program 1Q 2019
Dry-run P0 Tønsberg 5/12 Test P1: Molde 23/1
40
DNV GL © 2018 06 February 2019
Way forward
▪ Continue and complete pilot campaign
▪ Document and share learnings
42
▪ Use learnings for future operations and development of new products & services
– “Remote Ready” IAS system [Høglund]
– Rules, RPs and TQ/AIP programs [DNV GL] and regulations [NMA]
– Consider commercial deployment for new ferries [Fjord1]
DNV GL © 2018 06 February 2019
SAFER, SMARTER, GREENER
www.dnvgl.com
Thank you for the attention!
43
Steinar Låg
Phone: +47 95236838
Read more about ROMAS in DNV GL’s Research Review 2018:https://www.dnvgl.com/research/review2018/featured-projects/romas-remote-operations-machinery-automation.html